Planning_ Design _ Construction -- Project Status Report - Capital

Document Sample
Planning_ Design _ Construction -- Project Status Report - Capital Powered By Docstoc
					Sep 2011 Planning, Design & Construction -- Project Status Report - Capital Improvements                                                             Page 1 of 17
Environmental and Natural Resources Phase II                                                                                                                 03-8526
DESCRIPTION                                                                                                   Project Status:                            D - Design
This addition on the east side of the existing Dennis DeConcini Environment and Natural Resources             Project Delivery Method:                        CMR
Building will further interdisciplinary research in earth, environmental, natural resources, atmospheric,
                                                                                                              PDC Design Project Manager:                      Carr
mathematical, and related sciences. The building will primarily provide faculty offices, conferencing and
support spaces with some related research and instructional dry laboratory and work space. A large            PDC Fac Project Manager:                         TBD
classroom addition will meet the UA's critical need to teach an increasing number of students with            User Representative:                   Andrew Comrie
decreasing State funding for faculty support.
                                                                                                              AE:         G L H N Architects And Engineers
                                                                                                              CM:         Hensel Phelps Construction Company
                                                                                                              Contractor:
STATUS
The project is on hold awaiting funding and approvals by the UA Administration and ABOR to proceed.           NASF:                77,940         GSF:         130,000
Funded by a DOE grant, the Schematic Design is complete.                                                                                                    $2,315,047
                                                                                                              Current Budget:
                                                                                                              Projected Budget:                            $75,000,000
                                                                                                              Bldg:


Residence Life Building Renewal Phase III                                                                                                                    04-8537
DESCRIPTION                                                                                                   Project Status:                        C - Construction
This project will extend the useful life of aging residential facilities and reduce the risk of potentially   Project Delivery Method:                          CMR
disruptive system failures that would affect both the health and safety of the occupants at Cochise
                                                                                                              PDC Design Project Manager:                 Helentjaris
Residence Hall by replacing the fire sprinkler systems, and Coronado Residence Hall by replacing
mechanical, electrical and plumbing systems, and renovating bathrooms.                                        PDC Fac Project Manager:                          Kraft
                                                                                                              User Representative:                             Corral

                                                                                                              AE:         G L H N Architects And Engineers
                                                                                                              CM:         Lloyd Construction Co Inc
                                                                                                              Contractor: Lloyd Construction Co Inc
STATUS
The contractor has mobilized on site and is well into the demolition phase. The contractor has completed NASF:                    131,652         GSF:         191,070
approximately 5% the project.                                                                                                                              $27,865,215
                                                                                                              Current Budget:
                                                                                                              Projected Budget:                            $27,865,215
                                                                                                              Bldg:   31           85


Residence Life Building Renewal Phase IV                                                                                                                     04-8538
DESCRIPTION                                                                                                   Project Status:                            O - Occupancy
Extend the useful life of aging residential facilities and reduce the risk of potentially disruptive system   Project Delivery Method:                            CMR
failures that would affect both the health and safety of the occupants at Apache-Santa Cruz and Colonia
                                                                                                              PDC Design Project Manager:                    Helentjaris
De La Paz Residence Halls by replacing mechanical, electrical and plumbing systems, and renovating
bathrooms.                                                                                                    PDC Fac Project Manager:                            Kraft
                                                                                                              User Representative:                               Corral

                                                                                                              AE:         G L H N Architects And Engineers
                                                                                                              CM:         Lloyd Construction Co Inc
                                                                                                              Contractor: Lloyd Construction Co Inc
STATUS
Construction performed the Summer 2010 at La Paz Hall is substantially complete. All of the intended          NASF:               101,890         GSF:         170,584
scope of work included in Phase 4 has been completed. Follow-up corrective work is required in both                                                        $10,134,785
Apache-Santa Cruz and La Paz.                                                                                 Current Budget:
                                                                                                              Projected Budget:                            $10,134,785
                                                                                                              Bldg:   118          50       50.01


Sixth Street Residence Halls / Likins Hall & Arbol de la Vida                                                                                                07-8770
DESCRIPTION                                                                                                   Project Status:                        C - Construction
This project will provide new on-campus housing for 1,088 undergraduate students. The buildings are           Project Delivery Method:                          CMR
being constructed on two sites along 6th Street; one at Tyndall Avenue, and one at Highland Avenue.
                                                                                                              PDC Design Project Manager:                   Johnson
These new residence halls will be organized into learning communities to promote academic success
and self-development. Four to six story buildings of brick, metal and stucco, are designed around interior    PDC Fac Project Manager:                         Marsh
courtyards to create secure private space for student circulation and gathering.                              User Representative:                    Jim Van Arsdel

                                                                                                              AE:         AR7 Architects P C
                                                                                                              CM:         Core Construction
                                                                                                              Contractor: Core Construction
STATUS
Tyndall site: Substantial Completion was granted on May 20th. Punchlist items are being completed.            NASF:               212,025         GSF:         328,365
Owner supplied furnishings have been delivered and installed.                                                                                             $156,700,000
Highland Site:Substantial Completion was granted on May 31st. Punchlist items are being completed.            Current Budget:
Owner supplied furnishings have been delivered and installed.                                                 Projected Budget:                           $159,300,000
                                                                                                              Bldg:   131          132      133
Sep 2011 Planning, Design & Construction -- Project Status Report - Capital Improvements                                                             Page 2 of 17
Bryant Bannister Tree-Ring Building                                                                                                                          08-8826
DESCRIPTION                                                                                                    Project Status:                            D - Design
The Laboratory of Tree-Ring Research (LTRR) has been housed in the West Stadium for more than 70               Project Delivery Method:                        CMR
years, with minimal improvements to their facilities. This project will provide new laboratories and offices
                                                                                                                                                           Gajdorus
to house the LTRR's diverse array of research programs, as well as public outreach and support spaces. PDC Design Project Manager:
The project is the first phase of a long-term effort to relocate the entire LTRR into contemporary facilities. PDC Fac Project Manager:                         Kraft
Minor renovations of space at the Math East building is included in the project.                               User Representative:                    Tom Swetnam

                                                                                                             AE:         Richard & Bauer Architecture
                                                                                                             CM:         Martin Lang Construction LLC dba Lang Wya
                                                                                                             Contractor:
STATUS
The Architect is finalizing the Construction Documents, and the CMR is finalizing the Guaranteed             NASF:                17,300        GSF:            28,200
Maximum Price, simultaneously.                                                                                                                             $12,039,000
                                                                                                             Current Budget:
                                                                                                             Projected Budget:                             $12,039,000
                                                                                                             Bldg:   45B          TBD


Health Sciences Education Building                                                                                                                           09-8900
DESCRIPTION                                                                                                  Project Status:                         C - Construction
Addition of a new building, named the Health Sciences Education Building, on the Phoenix Biomedical          Project Delivery Method:                           CMR
Campus (PBC) is to include flexible classrooms and state-of-the-art educational facilities, such as,
                                                                                                             PDC Design Project Manager:                     Mackey
simulation laboratories, gross anatomy facilities, preclinical training, learning resource center, student
services and faculty office administrative space.                                                            PDC Fac Project Manager:                      Bagnoche
                                                                                                             User Representative:                            Tierney

                                                                                                             AE:         CO Architects
                                                                                                             CM:         D P R / Sundt (A Joint Venture)
                                                                                                             Contractor: D P R / Sundt (A Joint Venture)
STATUS
Construction Documents are complete. The GMP has been accepted and the construction of the                   NASF:               151,000        GSF:        265,000
superstructure has begun.                                                                                                                              $135,998,801
                                                                                                             Current Budget:
                                                                                                             Projected Budget:                         $135,998,801
                                                                                                             Bldg:


Arizona Stadium, North End Zone Expansion                                                                                                                    09-8902
DESCRIPTION                                                                                                  Project Status:                                D - Design
Construction of the new north end-zone facility at Arizona Stadium will provide upgraded premium             Project Delivery Method:                            CMR
seating and fan amenities, relocate and provide new facilities for the football program and provide new
                                                                                                             PDC Design Project Manager:                          Vos
concourses cross connecting access to the east and west stadium seating section.
                                                                                                             PDC Fac Project Manager:                            Dolan
                                                                                                             User Representative:

                                                                                                             AE:         Heery International Inc
                                                                                                             CM:         Mortenson Construction
                                                                                                             Contractor:
STATUS
Design Phase services underway with Budget Assessment, Programming, Conceptual, and Schematic                NASF:               140,589        GSF:           183,683
Design Phase services complete. ABOR PIA Approval secured with Design Development services are                                                              $4,115,000
underway. Proceeding with CMR Pre-Construction Phase services with intent to secure GMP at end of            Current Budget:
Design Development Phase to support bond issuance requirements.                                              Projected Budget:                             $72,300,000
                                                                                                             Bldg:   58


Vivarium Phase I - Phoenix                                                                                                                                   10-8988
DESCRIPTION                                                                                                  Project Status:                                D - Design
The new facility, funded from a Federal Stimulus grant awarded by the National Institute of Health (NIH),    Project Delivery Method:                            CMR
is essential for the advancement of the biomedical research at the Phoenix Biomedical Campus (PBC).
                                                                                                             PDC Design Project Manager:                       Mackey
The Vivarium and research core will support research activities currently being performed at the first
Arizona Biomedical Collaborative (ABC1) building.                                                            PDC Fac Project Manager:                       Bagnoche
                                                                                                             User Representative:                              Tierney

                                                                                                             AE:         CO Architects
                                                                                                             CM:         D P R / Sundt (A Joint Venture)
                                                                                                             Contractor:
STATUS
The project is currently in the Design Development phase.                                                    NASF:                12,100        GSF:            22,000
                                                                                                             Current Budget:                               $18,996,000
                                                                                                             Projected Budget:                             $18,996,000
                                                                                                             Bldg:
Sep 2011 Planning, Design & Construction -- Project Status Report - Capital Improvements                                                             Page 3 of 17
Arizona Cancer Center - Phoenix                                                                                                                          10-9001
DESCRIPTION                                                                                                 Project Status:                             D - Design
This new facility will provide the highest quality cancer research and care with an evidence-based,         Project Delivery Method:                   Design/Build
multi-disciplinary model, along with the modern technologies, and a compassionate patient-centered
                                                                                                            PDC Design Project Manager:                        Carr
approach. The building will be located near the northeast corner of Fillmore and Seventh Streets on the
downtown Phoenix Biomedical Campus.                                                                         PDC Fac Project Manager:                     Bagnoche
                                                                                                            User Representative:                            Tierney

                                                                                                            AE:         Hensel Phelps Const Co / Zimmer Gunsul Fr
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Schematic design is underway.                                                                               NASF:               142,500        GSF:        250,000
                                                                                                            Current Budget:                             $6,507,500
                                                                                                            Projected Budget:                         $135,000,000
                                                                                                            Bldg:


Wm J Parker Agricultural Research Complex, Finish Shell Space Phase II                                                                                   12-9095
DESCRIPTION                                                                                                 Project Status:                             D - Design
The William J. Parker Agricultural Research Complex was constructed with a significant amount of shell      Project Delivery Method:                          CMR
space, so the facility could be quickly adapted to evolving future research demands. Some of that shell
                                                                                                            PDC Design Project Manager:                  Gajdorus
space was completed several years ago. This project will finish the remainder of the available space, as
well as develop new exterior dairy facilities, to address the current needs of the College of Agriculture   PDC Fac Project Manager:                          TBD
and Life Sciences.                                                                                          User Representative:                      Robert Collier

                                                                                                            AE:         Merry Carnell Schlecht Inc
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
PDC is assisting the Department of Animal Sciences in identifying the required improvements, and            NASF:                55,700        GSF:         55,700
developing a forecast of anticipated project costs for University administrative and financial approvals.                                                  $30,000
                                                                                                            Current Budget:
                                                                                                            Projected Budget:
                                                                                                            Bldg:   2019
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                                  Page 4 of 17
Tyndall Avenue Enhancement                                                                                                                                       01-8316
DESCRIPTION                                                                                               Project Status:                                 O - Occupancy
Tyndall Avenue Enhancements is a joint project with the City of Tucson to improve multi-modal circulation Project Delivery Method:                       Design/Bid/Build
on the street. Extent of the project is from 6th Street to University Boulevard. Reconstruction of the
                                                                                                          PDC Design Project Manager:                             Novak
campus street will include new pavement, curbs, bicycle lanes, sidewalks, pedestrian crossings, and
landscape. The Tucson Dept. of Transportation is managing this project. The project is funded by a        PDC Fac Project Manager:                                  Kraft
federal transportation grant. The University budget is for matching funds.                                User Representative:

                                                                                                                AE:
                                                                                                                CM:
                                                                                                                Contractor: Borderland Construction Co Inc
STATUS
This project is completed and open to traffic.                                                                  NASF:                               GSF:
                                                                                                                Current Budget:                                  $136,100
                                                                                                                Projected Budget:                                $543,291
                                                                                                                Bldg:


Solar Energy Initiatives                                                                                                                                         08-8847
DESCRIPTION                                                                                                     Project Status:                          C - Construction
A solar energy initiative is underway that is being facilitated through the University's partnership with APS   Project Delivery Method:                          P/DBF
Energy Services to advance solar technology awareness on campus and throughout the community.
                                                                                                                PDC Design Project Manager:                        Banks
Through this initiative solar installations are planned for Second Street Garage, Student Recreation
Center, McClelland Hall, McClelland Park, and Hillenbrand Aquatic Center. In addition a PV/Solar                PDC Fac Project Manager:                           Banks
Thermal System will be installed at Villa del Puente and funded through a Tucson Electric Power/Federal         User Representative:
agreement.
                                                                                                                AE:
                                                                                                                CM:
                                                                                                                Contractor:
STATUS
Contractor is finalizing installations at Student Recreation Center, McClelland Hall, McClelland Park and       NASF:                               GSF:
Mary Roby Gymnastics buildings. System commissioning is in progress. Design is underway for the                                                                   $73,500
Ville Del Puente solar project.                                                                                 Current Budget:
                                                                                                                Projected Budget:                                 $73,500
                                                                                                                Bldg:


Student Recreation Center, Renovate Lobby/Weight Room                                                                                                            09-8938
DESCRIPTION                                                                                                     Project Status:                              O - Occupancy
Renovation and upgrade of lobby entrance and adjacent weightroom into new lobby, SRC registration,              Project Delivery Method:                              CMR
academic services, retail and cafe as a result of vacated space due to Expansion project 05-8634.
                                                                                                                PDC Design Project Manager:                        Johnson
                                                                                                                PDC Fac Project Manager:                             Dolan
                                                                                                                User Representative:

                                                                                                                AE:         AAD: Fitch Inc. dba Fitch Inc.
                                                                                                                CM:         Lloyd Construction Co Inc
                                                                                                                Contractor: Lloyd Construction Co Inc
STATUS
Main Lobby and Cafe completed and occupied. Additional patio extension is complete and the                      NASF:               13,000          GSF:            13,000
associated fencing will be completed shortly.                                                                                                                   $3,500,000
                                                                                                                Current Budget:
                                                                                                                Projected Budget:                               $3,500,000
                                                                                                                Bldg:   117


Jefferson Gymnasium, Weight/Cardio Training Renovations                                                                                                          09-8946
DESCRIPTION                                                                                                     Project Status:                          O - Occupancy
Enclose approximately 1,200 gsf at the east end of the Richard Jefferson Gymnasium to create a weight           Project Delivery Method:             Job Order Contract
and cardiovascular training center in support of coaching staff's training objectives for student athletes.
                                                                                                                PDC Design Project Manager:                        Vos
                                                                                                                PDC Fac Project Manager:                         Dolan
                                                                                                                User Representative:

                                                                                                                AE:         NTD Architecture
                                                                                                                CM:         R W Burkel Contracting Inc
                                                                                                                Contractor: R W Burkel Contracting Inc
STATUS
Weight/Cardio project is complete and closed out.                                                      NASF:                                        GSF:             1,200
Graphics package and storage closets are being accomoplished separately in conjunction with project                                                             $1,500,000
10-8991. Storage closetes are complete and occupied. Graphics are installed but ICA is asking for some Current Budget:
addtional painting.                                                                                    Projected Budget:                                        $1,500,000
                                                                                                                Bldg:   140
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                                 Page 5 of 17
Arizona Bioscience Park Infrastructure Phases I & II                                                                                                            10-8958
DESCRIPTION                                                                                                      Project Status:                        C - Construction
Grant funded project for on-site infrastructure improvements at the new Arizona Bioscience Park                  Project Delivery Method:                        P/DBF
including roads; water systems; dry utilities for gas, electricity and telecommunications; and perimeter
                                                                                                                 PDC Design Project Manager:                      Banks
landscaping.
                                                                                                                 PDC Fac Project Manager:                         Banks
                                                                                                                 User Representative:                      Bruce Wright

                                                                                                                 AE:         Wood, Patel & Associates Inc
                                                                                                                 CM:
                                                                                                                 Contractor: SunWestern Contractors Inc
STATUS
Phase II has been bid. Contract award is in progress.                                                            NASF:                             GSF:
                                                                                                                 Current Budget:                              $8,580,000
                                                                                                                 Projected Budget:                            $8,580,000
                                                                                                                 Bldg:   INFRA


Highland District Housing, Window Investigation                                                                                                                 10-8964
DESCRIPTION                                                                                                      Project Status:                               D - Design
Investigation to determine the cause of problems with the casement windows at the Highland District              Project Delivery Method:
Housing facilities: Villa del Puente, Posada San Pedro, Pueblo de la Cienega and El Portal (Buildings
                                                                                                                 PDC Design Project Manager:                      McCarthy
A/B), and Residence Life Administrative Offices located at the Highland Residential Community.
                                                                                                                 PDC Fac Project Manager:                         McCarthy
                                                                                                                 User Representative:

                                                                                                                 AE:
                                                                                                                 CM:
                                                                                                                 Contractor:
STATUS
                                                                                                                 NASF:                             GSF:
                                                                                                                 Current Budget:                                   $10,000
                                                                                                                 Projected Budget:                                 $10,000
                                                                                                                 Bldg:   121         121.01    121.02       122         12
                                                                                                                         182

Campus Enterprise GIS                                                                                                                                           10-8983
DESCRIPTION                                                                                                      Project Status:                               D - Design
Create a cross-departmental, state-of-the-art Enterprise Geographic Information System (GIS) for                 Project Delivery Method:
managing shared spatial data about the University of Arizona campus.
                                                                                                                 PDC Design Project Manager:                  McCormick
                                                                                                                 PDC Fac Project Manager:                     McCormick
                                                                                                                 User Representative:

                                                                                                                 AE:
                                                                                                                 CM:
                                                                                                                 Contractor:
STATUS
Draft GeoDatabase completed and work is underway on revised version; data elements from                          NASF:                             GSF:
collaborating departments being integrated. Design for internal Interactive Web Map is underway,                                                                   $60,000
building on prototyping for a public web map. CAD integration tasks have begun.                                  Current Budget:
                                                                                                                 Projected Budget:                                 $60,000
                                                                                                                 Bldg:


Park Student Union                                                                                                                                              10-8990
DESCRIPTION                                                                                                      Project Status:                               D - Design
The Park Student Union has been serving the southwest quadrant of campus since the mid-1960s. The Project Delivery Method:
on-campus residential population of this area is continuing to increase and evolve. A recent expansion of
                                                                                                          PDC Design Project Manager:                            Gajdorus
the Park Union provided additional space, but was not successful in re-positioning the PSU within the
market. Additionally, the original 1960s facility remains in need of significant improvements.            PDC Fac Project Manager:                                   TBD
                                                                                                                 User Representative:                       Joe Sottosanti

                                                                                                                 AE:         Line and Space LLC Architects
                                                                                                                 CM:
                                                                                                                 Contractor:
STATUS
The University Division of Student Affairs has developed a broad vision of what the Park Student Union           NASF:                             GSF:                  0
wants to be, as well as potential University units which might participate in bringing that vision to reality.                                                     $90,000
An initial facility program is being developed to quantify the project's space needs.                            Current Budget:
                                                                                                                 Projected Budget:
                                                                                                                 Bldg:   87
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                             Page 6 of 17
McKale Memorial Center, Renovate Locker Room/Corridor                                                                                                      10-8991
DESCRIPTION                                                                                              Project Status:                             O - Occupancy
To facilitate recruitment, renovate approximately 2,000 gsf of obsolete locker rooms and showers         Project Delivery Method:                Job Order Contract
facilities, and provide upgraded corridors with graphic displays to showcase the historical achievements
                                                                                                         PDC Design Project Manager:                           Vos
of the basketball program at McKale Memorial Center.
                                                                                                         PDC Fac Project Manager:                            Dolan
                                                                                                         User Representative:

                                                                                                            AE:         NTD Architecture
                                                                                                            CM:
                                                                                                            Contractor: Division II Construction Co Inc
STATUS
Locker room project is complete and occupied. Corridor upgrades phase is nearly complete including the NASF:                                    GSF:           2,000
graphics package. May need to implement some wall protection measures to minimize damage to                                                               $1,500,000
graphics.                                                                                              Current Budget:
                                                                                                            Projected Budget:                             $1,500,000
                                                                                                            Bldg:   96


Aerospace & Mechanical Engineering, Install Fume Exhaust System                                                                                            10-8996
DESCRIPTION                                                                                                 Project Status:                          O - Occupancy
Provide the infrastructure for a fume hood exhaust system in Labs N213, N217, N319B and N417B               Project Delivery Method:             Job Order Contract
located in the Aerospace and Mechanical Engineering building.
                                                                                                            PDC Design Project Manager:                   Helentjaris
                                                                                                            PDC Fac Project Manager:                      Helentjaris
                                                                                                            User Representative:                         Jeff Jacobs

                                                                                                            AE:         G L H N Architects And Engineers
                                                                                                            CM:
                                                                                                            Contractor: Sun Mechanical Contracting Inc
STATUS
The initial construction phase is substantially complete.                                                   NASF:                               GSF:
                                                                                                            Current Budget:                                 $200,000
                                                                                                            Projected Budget:                               $200,000
                                                                                                            Bldg:   119


1st and 2nd Streets, Traffic Conversion                                                                                                                    10-9016
DESCRIPTION                                                                                                 Project Status:                                D - Design
Provide an analysis of the impact of converting 1st & 2nd Streets from their current one-way                Project Delivery Method:
configurations to a two-way configuration to accommodate the planned modern street car route
                                                                                                            PDC Design Project Manager:                      Mackey
                                                                                                            PDC Fac Project Manager:                            TBD
                                                                                                            User Representative:                           Heineking

                                                                                                            AE:         Kimley-Horn and Associates, Inc.
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
The analysis is complete and construction is pending.                                                       NASF:                               GSF:
                                                                                                            Current Budget:                                  $31,625
                                                                                                            Projected Budget:                                     $0
                                                                                                            Bldg:


Old Main, Building Condition Assessment                                                                                                                    11-9023
DESCRIPTION                                                                                                 Project Status:                                D - Design
Old Main is the University's historic icon. Over the years the building has received incremental remedial   Project Delivery Method:
improvements and continues to require signficant attention as it ages. This building condition
                                                                                                            PDC Design Project Manager:                        Galda
assessment will provide an indepth analysis of Old Main's condition, as well as a comprehensive and
prioritized program for future preservation-sensitive improvements.                                         PDC Fac Project Manager:                            TBD
                                                                                                            User Representative:

                                                                                                            AE:         Turner Structural Engineering Co
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Consultant has submitted the first draft of the report, which includes assessment of current conditions,    NASF:                               GSF:
prioritization of building needs, development of rehabilitiation proposals, and probable cost estimates.                                                     $43,000
Initial correspondence with State Historic Preservation Office (SHPO) is being prepared.                    Current Budget:
                                                                                                            Projected Budget:                                $43,000
                                                                                                            Bldg:   21
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                      Page 7 of 17
Martin Avenue Surface Water Analysis                                                                                                              11-9024
DESCRIPTION                                                                                                 Project Status:                      D - Design
Preliminary study to define in detail the facilities and features recommended for storm drainage flow       Project Delivery Method:
reductions and water storage and reuse along Martin Avenue north of Sixth Street between the newly
                                                                                                            PDC Design Project Manager:          McCormick
refurbished Jimenez Practice Field and Sancet Field.
                                                                                                            PDC Fac Project Manager:                  TBD
                                                                                                            User Representative:

                                                                                                            AE:
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
A project consultant has been selected and a project scope is being refined.                                NASF:                         GSF:
                                                                                                            Current Budget:                        $12,000
                                                                                                            Projected Budget:                      $12,000
                                                                                                            Bldg:


Mathematics Facility, Planning Analysis                                                                                                           11-9025
DESCRIPTION                                                                                                 Project Status:                      D - Design
Planning study to review the space requirements and explore alternatives for accommodating the              Project Delivery Method:
Department of Mathematics and related departments. The review will include campus planning and
                                                                                                            PDC Design Project Manager:              Galda
growth options within the context of the University's Comprehensive Campus Plan.
                                                                                                            PDC Fac Project Manager:                  TBD
                                                                                                            User Representative:

                                                                                                            AE:
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Program is substantially complete, with accompanying narrative pending.                                     NASF:                         GSF:
                                                                                                            Current Budget:                        $25,000
                                                                                                            Projected Budget:                      $25,000
                                                                                                            Bldg:


South Campus Edge Enhancement                                                                                                                     11-9028
DESCRIPTION                                                                                                 Project Status:                      D - Design
Landscape improvements to vacant lots along the campus planning boundary on the south side of               Project Delivery Method:
campus.
                                                                                                            PDC Design Project Manager:             Novak
                                                                                                            PDC Fac Project Manager:                Novak
                                                                                                            User Representative:

                                                                                                            AE:
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Developing landscape treatment options.                                                                     NASF:                         GSF:
                                                                                                            Current Budget:                        $45,000
                                                                                                            Projected Budget:                      $45,000
                                                                                                            Bldg:


CALS Campus Agricultural Center Development Plan                                                                                                  11-9030
DESCRIPTION                                                                                                 Project Status:                      D - Design
Provide a study for the University of Arizona Campus Agricultural Center that revisions and rearticulates   Project Delivery Method:
the existing vision for the Center. Identify uses to be maintained, disposed or further developed on the
                                                                                                            PDC Design Project Manager:                Fey
east side of the Campus. Provide market analysis of excess property. Develop disposition process and
provide offering documents for initial offering. Develop long-term recommendations and design               PDC Fac Project Manager:                   Fey
guidelines for property development and disposition.                                                        User Representative:

                                                                                                            AE:
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Consultant has been selected.                                                                               NASF:                         GSF:
                                                                                                            Current Budget:                        $46,000
                                                                                                            Projected Budget:
                                                                                                            Bldg:
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                          Page 8 of 17
La Aldea, Code Assessment / Improvements                                                                                                               11-9031
DESCRIPTION                                                                                             Project Status:                          C - Construction
Conduct an accessibility assessment of the La Aldea Complex and implement ADA improvements.             Project Delivery Method:               Job Order Contract
                                                                                                        PDC Design Project Manager:                   Helentjaris
                                                                                                        PDC Fac Project Manager:                            Kraft
                                                                                                        User Representative:

                                                                                                        AE:         Burns Wald-Hopkins Shambach Architects
                                                                                                        CM:
                                                                                                        Contractor: Lang Wyatt Construction (see Martin Lang C
STATUS
The pricing from the JOC contractor has been approved. Notice to Proceed has been granted to the JOC NASF:                                 GSF:
contractor.                                                                                                                                              $57,000
                                                                                                        Current Budget:
                                                                                                        Projected Budget:                                $57,000
                                                                                                        Bldg:   85.01


Steward Observatory, IT Closet Upgrades                                                                                                                11-9032
DESCRIPTION                                                                                             Project Status:                            O - Occupancy
Project will upgrade the existing IT Closets Iin rooms 251, 353A, 453 and 551. Consideration is under   Project Delivery Method:               Job Order Contract
investigation to add rooms 208, 314 and 420. This work will include Cooling, Outlets and Grounding.
                                                                                                        PDC Design Project Manager:                        Cousy
                                                                                                        PDC Fac Project Manager:                           Cousy
                                                                                                        User Representative:                           David Lane

                                                                                                        AE:
                                                                                                        CM:
                                                                                                        Contractor: Sturgeon Electric Co Inc
STATUS
The project is near completion.                                                                         NASF:                              GSF:              300
                                                                                                        Current Budget:                                 $178,000
                                                                                                        Projected Budget:                               $178,000
                                                                                                        Bldg:   65


Highland Housing, Install PV Panel System                                                                                                              11-9033
DESCRIPTION                                                                                             Project Status:                          C - Construction
Provide a Photovoltaic Panel System at the Highland Housing Complex on the Posada San Pedro             Project Delivery Method:               Job Order Contract
Residence Hall.
                                                                                                        PDC Design Project Manager:                        Banks
                                                                                                        PDC Fac Project Manager:                           Banks
                                                                                                        User Representative:                         Blandeburgo

                                                                                                        AE:
                                                                                                        CM:
                                                                                                        Contractor:
STATUS
Infrastructure construction is underway.                                                                NASF:                              GSF:
                                                                                                        Current Budget:                                  $94,000
                                                                                                        Projected Budget:                                $94,000
                                                                                                        Bldg:   I122


Engineering, Equipment Removal                                                                                                                         11-9034
DESCRIPTION                                                                                             Project Status:                          C - Construction
Removal of equipment at the Engineering building.                                                       Project Delivery Method:                 Design/Bid/Build
                                                                                                        PDC Design Project Manager:                        Banks
                                                                                                        PDC Fac Project Manager:                           Banks
                                                                                                        User Representative:

                                                                                                        AE:         Turner Structural Engineering Co
                                                                                                        CM:
                                                                                                        Contractor: LVI Environmental Services Inc
STATUS
Equipment removal is in progress.                                                                       NASF:                              GSF:
                                                                                                        Current Budget:                               $1,654,894
                                                                                                        Projected Budget:                             $1,990,686
                                                                                                        Bldg:   20
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                               Page 9 of 17
UA Downtown, 44 N Stone Avenue Tenant Improvements                                                                                                           11-9036
DESCRIPTION                                                                                                     Project Status:                        O - Occupancy
Tenant Improvements to the County-owned historic downtown 2-story building designed by Roy Place,               Project Delivery Method:           Job Order Contract
also known as the Walgreen's Building located at Stone & Pennington. This project initiates a downtown
                                                                                                                PDC Design Project Manager:                     Carr
presence with new community-minded graduate level programs. The first phase of improvements
primarily located on the first floor include 2 classrooms, CALA graduate studios, MPA Honors, misc.             PDC Fac Project Manager:                        Carr
office & office support space, student spaces and UA Bookstore/retail space                                     User Representative:

                                                                                                                AE:         Burns Wald-Hopkins Shambach Architects
                                                                                                                CM:
                                                                                                                Contractor: Hickam Arnold and Associates LLC dba Hick
STATUS
Substantial completed and Pima County Temporary CofO received on Aug 16. Cosntruction of Bookstore NASF:                                          GSF:            9,350
millwork partitions (off site) is in progress.                                                                                                                 $491,000
                                                                                                                Current Budget:
                                                                                                                Projected Budget:                              $506,720
                                                                                                                Bldg:   336


AzRISE Solar House Relocation                                                                                                                                11-9037
DESCRIPTION                                                                                                     Project Status:                          O - Occupancy
The re-location of the University of Arizona Solar House entry in 2009 DOE Solar Decathlon to the open          Project Delivery Method:
mall south of the Gould-Simpson Building. Address: 1050 E. 4th Street. The Solar House is intended to
                                                                                                                PDC Design Project Manager:                     Mackey
be used as a Conference Center and a demonstration center for the Campus solar initiatives.
                                                                                                                PDC Fac Project Manager:                        Mackey
                                                                                                                User Representative:                           Simmons

                                                                                                                AE:
                                                                                                                CM:
                                                                                                                Contractor:
STATUS
The building has been re-located to the designated site and awaiting permitting.                                NASF:                             GSF:              700
                                                                                                                Current Budget:                                 $17,000
                                                                                                                Projected Budget:                               $22,000
                                                                                                                Bldg:   347


Cannon-Douglass House, Rehabilitation                                                                                                                        11-9038
DESCRIPTION                                                                                              Project Status:                               O - Occupancy
Historic preservation of the Cannon-Douglass House located at 1189 E Speedway Boulevard. The             Project Delivery Method:                  Job Order Contract
Cannon-Douglass House is on the National Register of Historic Buildings and will be restored for use for
                                                                                                         PDC Design Project Manager:                            Carr
CALA. Offices, student and program space.
                                                                                                         PDC Fac Project Manager:                               Carr
                                                                                                         User Representative:

                                                                                                                AE:         Burns Wald-Hopkins Shambach Architects
                                                                                                                CM:         Division II Construction Co Inc
                                                                                                                Contractor: Division II Construction Co Inc
STATUS
Project is 98% completed. Floor is installed, final plumbing fixture door install and final landscaping is in   NASF:               1,545         GSF:            1,545
progress.                                                                                                                                                      $420,000
                                                                                                                Current Budget:
                                                                                                                Projected Budget:                              $450,000
                                                                                                                Bldg:   199


Arizona Stadium, Scoreboard Structural System                                                                                                                11-9039
DESCRIPTION                                                                                                     Project Status:                        O - Occupancy
This project is limited to the new foundation system, structural columns, primary structural steel system,      Project Delivery Method:           Job Order Contract
and replacement of concrete sidewalk. The new video board, scoreboard enclosure, electrical and
                                                                                                                PDC Design Project Manager:                      Vos
mechanical systems, signage, audio systems, and controls will be developed by ICA/AJP under a
separate funded project(s).                                                                                     PDC Fac Project Manager:                       Dolan
                                                                                                                User Representative:                        Kozachik

                                                                                                                AE:
                                                                                                                CM:
                                                                                                                Contractor: Tucson Building & Remodeling Inc
STATUS
Structure is complete, accepted and turned over to the separate video board vendor.                             NASF:                             GSF:
                                                                                                                Current Budget:                             $3,021,829
                                                                                                                Projected Budget:                           $3,021,829
                                                                                                                Bldg:   58
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                               Page 10 of 17
Meinel Optical Science West Building, Structrural Investigation                                                                                              11-9043
DESCRIPTION                                                                                                   Project Status:                                D - Design
Investigate wall cracking issues.                                                                             Project Delivery Method:
                                                                                                              PDC Design Project Manager:                     McCarthy
                                                                                                              PDC Fac Project Manager:                        McCarthy
                                                                                                              User Representative:

                                                                                                              AE:
                                                                                                              CM:
                                                                                                              Contractor:
STATUS
                                                                                                              NASF:                                GSF:
                                                                                                              Current Budget:                                   $2,000
                                                                                                              Projected Budget:
                                                                                                              Bldg:   94.04


Arizona Stadium, Scoreboard Electrical Infrastructure                                                                                                        11-9047
DESCRIPTION                                                                                                   Project Status:                            O - Occupancy
Upgrade a portion of the electrical infrastructure serving Arizona Stadium to provide the necessary           Project Delivery Method:               Job Order Contract
electrical services to support development of the new scoreboard (See Project 11-9039 for Structural
                                                                                                              PDC Design Project Manager:                          Vos
Systems).
                                                                                                              PDC Fac Project Manager:                           Dolan
                                                                                                              User Representative:                            Kozachik

                                                                                                              AE:         Dave Diebold Architect
                                                                                                              CM:
                                                                                                              Contractor: Sturgeon Electric Co Inc
STATUS
Majority of primary electrical work is complete and transformer has been energized. Minor interface work NASF:                                     GSF:
with video board vendor remains.                                                                                                                              $475,000
                                                                                                              Current Budget:
                                                                                                              Projected Budget:                               $475,000
                                                                                                              Bldg:   58


Police Department, Renovate Communications Room                                                                                                              11-9049
DESCRIPTION                                                                                                 Project Status:                                  D - Design
The University of Arizona Police Department will be installing new radio equipment as part of an initiative Project Delivery Method:                 Job Order Contract
to provide inter-operability of communications among law enforcement entities throughout Pima County.
                                                                                                            PDC Design Project Manager:                       Gajdorus
Future upgrades will include enhanced 911 service as well as computer-assisted dispatch capabilities.
The existing UAPD communications room will require modifications to provide adequate support for the        PDC Fac Project Manager:                               TBD
new equipment.                                                                                              User Representative:                     Robert Sommerfeld

                                                                                                              AE:         Burns Wald-Hopkins Shambach Architects
                                                                                                              CM:
                                                                                                              Contractor:
STATUS
The project has been authorized and funded by the University administration. Conceptual Design is in          NASF:                   0            GSF:              0
progress.                                                                                                                                                     $235,000
                                                                                                              Current Budget:
                                                                                                              Projected Budget:                               $235,000
                                                                                                              Bldg:   100


AHSC, Surgery Offices 4th Floor Phases 3 & 4                                                                                                                 11-9051
DESCRIPTION                                                                                                   Project Status:                               D - Design
Conversion of old lab and office space into offices on the 4th floor of Clinical Sciences at Arizona Health   Project Delivery Method:               Job Order Contract
Sciences Center (AHSC) for the Department of Surgery Transplant, ENT and Plastic Surgery sections
                                                                                                              PDC Design Project Manager:                         Carr
will improve space efficiency, provide much needed space for recently hired researchers
and faculty, and consolidate office and support for several surgery programs.                                 PDC Fac Project Manager:                            TBD
                                                                                                              User Representative:                              Souza

                                                                                                              AE:         Dave Diebold Architect
                                                                                                              CM:
                                                                                                              Contractor:
STATUS
Schematic Design Submission is in review.                                                                     NASF:                                GSF:          5,520
                                                                                                              Current Budget:                               $1,531,000
                                                                                                              Projected Budget:                             $1,680,000
                                                                                                              Bldg:   201
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                       Page 11 of 17
Computer Center, High Performance Computing Utility Upgrades                                                                                         11-9054
DESCRIPTION                                                                                       Project Status:                              C - Construction
Upgrade power and HVAC in the Computer Center, Rooms 122, 126, 126A and 126B, to support existing Project Delivery Method:                   Job Order Contract
and future, centrally supported High Performance Computing (HPC) systems. Also, new 30-ton data
                                                                                                  PDC Design Project Manager:                            Banks
center air conditioners are to be installed in Rooms 214 and 215.
                                                                                                  PDC Fac Project Manager:                               Banks
                                                                                                  User Representative:                                  Bowles

                                                                                                      AE:         G L H N Architects And Engineers
                                                                                                      CM:
                                                                                                      Contractor: R W Burkel Contracting Inc
STATUS
Constuction is in progress.                                                                           NASF:                              GSF:            1,500
                                                                                                      Current Budget:                               $2,700,000
                                                                                                      Projected Budget:                             $2,800,000
                                                                                                      Bldg:   73          73.01


Pharmacy, IT Closet Upgrade                                                                                                                          11-9056
DESCRIPTION                                                                                           Project Status:                            O - Occupancy
Upgrades to the Pharmacy building will offer increased telecommunications capabilities. Rooms 221 and Project Delivery Method:               Job Order Contract
319B will be converted from storage and office space to dedicated telecommunications rooms. Work will
                                                                                                      PDC Design Project Manager:                        Cousy
include electrical and HVAC upgrades, and replacement of a moveable partition wall with a permanent
wall.                                                                                                 PDC Fac Project Manager:                           Cousy
                                                                                                      User Representative:                             D. Lane

                                                                                                      AE:
                                                                                                      CM:
                                                                                                      Contractor: Sturgeon Electric Co Inc
STATUS
Construction is nearing completion pending final inspection punch list items soon to be completed.    NASF:                  298         GSF:              298
                                                                                                      Current Budget:                                 $101,000
                                                                                                      Projected Budget:                               $101,000
                                                                                                      Bldg:   207


Biosphere 2, Landscape Evolution Observatory                                                                                                         11-9057
DESCRIPTION                                                                                                Project Status:                     C - Construction
Biosphere 2 serves as a center for research, outreach, teaching, and life-long learning about Earth, its   Project Delivery Method:                       CMR
living systems, and its place in the Universe. The former Habitat provides an opportunity for the
                                                                                                           PDC Design Project Manager:                Gajdorus
development of large scale specialized experimental systems. The Landscape Evolution Observatory
(LEO) will provide a controlled environment to investigate how water is utilized in natural ecosystems and PDC Fac Project Manager:                      Dolan
the role of life on landscapes.                                                                            User Representative:                Stephen DeLong

                                                                                                      AE:         M3 Engineering & Technology Corp
                                                                                                      CM:         Lloyd Construction Co Inc
                                                                                                      Contractor: Lloyd Construction Co Inc
STATUS
Project recently started. Fabrication of tray 1 is underway.                                          NASF:                              GSF:
                                                                                                      Current Budget:                               $4,845,000
                                                                                                      Projected Budget:                             $4,845,000
                                                                                                      Bldg:   4000


Student Union Memorial Center, Upgrade Spaces                                                                                                        11-9058
DESCRIPTION                                                                                           Project Status:                          C - Construction
Upgrade SUMC to improve outdoor dining.                                                               Project Delivery Method:               Job Order Contract
                                                                                                      PDC Design Project Manager:                      Johnson
                                                                                                      PDC Fac Project Manager:                           Dolan
                                                                                                      User Representative:

                                                                                                      AE:         AAD: Fitch Inc. dba Fitch Inc.
                                                                                                      CM:         Lang Wyatt Construction (see Martin Lang C
                                                                                                      Contractor:
STATUS
Improvements to the outdoor patio has been but on hold pending redesign. Information Office remodel   NASF:                              GSF:
has recently been completed.                                                                                                                          $685,000
                                                                                                      Current Budget:
                                                                                                      Projected Budget:                             $3,825,000
                                                                                                      Bldg:   19
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                            Page 12 of 17
Sixth Street Garage, Long-Term Maintenance                                                                                                                 11-9061
DESCRIPTION                                                                                                 Project Status:                             D - Design
The Sixth Street Garage has been in service for several years and is in need of periodic long-term          Project Delivery Method:             Job Order Contract
maintenance to correct any deficiences and protect the functionality and serviceability of the structure.
                                                                                                            PDC Design Project Manager:                   Gajdorus
                                                                                                            PDC Fac Project Manager:                          TBD
                                                                                                            User Representative:                    Mike Delahanty

                                                                                                            AE:         Desman Associates
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Field investigations of the garage have been completed. An evaluation report with maintenance               NASF:               228,803         GSF:        576,962
recommendations and a forecast of anticipated construction costs, has been submitted, and is being                                                          $13,000
reviewed by the University.                                                                                 Current Budget:
                                                                                                            Projected Budget:
                                                                                                            Bldg:   180


Park Student Union, Parkmart Tenant Improvements                                                                                                           11-9062
DESCRIPTION                                                                                                 Project Status:                          O - Occupancy
ParkMart convenience store tenant improvement at Park Student Union.                                        Project Delivery Method:             Job Order Contract
                                                                                                            PDC Design Project Manager:                    Johnson
                                                                                                            PDC Fac Project Manager:                         Dolan
                                                                                                            User Representative:

                                                                                                            AE:         Merry Carnell Schlecht Inc
                                                                                                            CM:
                                                                                                            Contractor: R W Burkel Contracting Inc
STATUS
Construction is scheduled to begin in June and be completed prior to start of fall semester 2011.           NASF:                               GSF:
                                                                                                            Current Budget:                                $330,000
                                                                                                            Projected Budget:                              $770,000
                                                                                                            Bldg:   87


Main Library, Bookends Cafe Renovations                                                                                                                    11-9063
DESCRIPTION                                                                                                    Project Status:                           D - Design
The proposed project is in the Main Library, Building 55, 1510 E. University Boulevard. The scope of           Project Delivery Method:
work is to upgrade and expand the Bookends Café to create exterior dining space on the east side of the
                                                                                                                                                            Johnson
café, enclose a portion of the west patio dining to expand the interior footprint of the café, add a grill and PDC Design Project Manager:
re-organize the food prep and product layout.                                                                  PDC Fac Project Manager:                       Dolan
                                                                                                               User Representative:

                                                                                                            AE:         AAD: Fitch Inc. dba Fitch Inc.
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Concept design is under review.                                                                             NASF:                               GSF:
                                                                                                            Current Budget:                                 $35,000
                                                                                                            Projected Budget:                              $975,000
                                                                                                            Bldg:   55


AHSC, Plastination Science Lab Renovation                                                                                                                  11-9065
DESCRIPTION                                                                                                 Project Status:                              D - Design
Feasibility study to determine suitable space at AHSC to locate a Plastination Science Laboratory for the Project Delivery Method:
AHSC Anatomical Services Department.
                                                                                                            PDC Design Project Manager:                      Banks
                                                                                                            PDC Fac Project Manager:                         Banks
                                                                                                            User Representative:

                                                                                                            AE:         G L H N Architects And Engineers
                                                                                                            CM:
                                                                                                            Contractor:
STATUS
Feasibilty study is in progress.                                                                            NASF:                               GSF:
                                                                                                            Current Budget:                                  $5,500
                                                                                                            Projected Budget:
                                                                                                            Bldg:   201
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                              Page 13 of 17
1420 N Vine Avenue, Construct Parking Lot                                                                                                                   11-9067
DESCRIPTION                                                                                                  Project Status:                          C - Construction
Construct a new parking lot at 1420 N Vine Avenue for Facilities Management State Vehicle parking.           Project Delivery Method:               Job Order Contract
PD&C and FM are collaborating with P&TS to install this parking lot. PD&C will complete the design of
                                                                                                             PDC Design Project Manager:                         Kraft
the civil, landscaping and electrical work, and install the civil and electrical work. FM will install the
landscaping work.                                                                                            PDC Fac Project Manager:                            Kraft
                                                                                                             User Representative:

                                                                                                             AE:
                                                                                                             CM:
                                                                                                             Contractor: Sturgeon Electric Co Inc
STATUS
Paving is completed. Installation of the screen wall is completed. Installation of the light poles is in     NASF:                                 GSF:
progress. FM is installing a fence around the perimeter and landscaping.                                                                                     $160,000
                                                                                                             Current Budget:
                                                                                                             Projected Budget:                               $225,000
                                                                                                             Bldg:   PARK


AHSC, Renovate BME Lab Space                                                                                                                                11-9069
DESCRIPTION                                                                                                  Project Status:                               D - Design
Renovate space (1250 complex) to relocate Biomedical Engineering, and a hallway and two laboratory           Project Delivery Method:
rooms to become the new surgery suite for training and research.
                                                                                                             PDC Design Project Manager:                       Banks
                                                                                                             PDC Fac Project Manager:                          Banks
                                                                                                             User Representative:                      Wilson-Sanders

                                                                                                             AE:
                                                                                                             CM:
                                                                                                             Contractor:
STATUS
Promotional material is being prepared to facilitate fund raising efforts.                                   NASF:                  900            GSF:         1,100
                                                                                                             Current Budget:                                   $5,500
                                                                                                             Projected Budget:                               $320,000
                                                                                                             Bldg:   201


Arizona Stadium, Student Union Food Service Tenant Improvements                                                                                             11-9071
DESCRIPTION                                                                                                  Project Status:                               D - Design
Tenant improvements for the development of the Cafe/Kitchen, Concessions and Loge/Club to be                 Project Delivery Method:
located in the Arizona Stadium North End-Zone Expansion. The food services will be owned and
                                                                                                             PDC Design Project Manager:                          Vos
operated by the Student Union
                                                                                                             PDC Fac Project Manager:                            TBD
                                                                                                             User Representative:                            Sotosanti

                                                                                                             AE:         Heery International Inc
                                                                                                             CM:
                                                                                                             Contractor:
STATUS
The project status and schedule mirrors the status and schedule of the Project 09-8902 Arizona Stadium NASF:                                       GSF:
North End-Zone Expansion. SU Food Service tenant improvements will be designed and constructed to                                                            $110,000
support the larger stadium expansion project.                                                          Current Budget:
                                                                                                             Projected Budget:                               $750,000
                                                                                                             Bldg:   58


Arizona State Museum, Renovate Basket Collection Space                                                                                                      11-9073
DESCRIPTION                                                                                                  Project Status:                               D - Design
Create display and storage space for the Arizona State Museum's Basket Collection in Room 110 located Project Delivery Method:
in the north building. Upgrades will accommodate fragile and valuable collections in a secure, improved,
                                                                                                                                                                  Vos
visible storage facility. The project is based on Save America's Treasures Award and is a highest priority PDC Design Project Manager:
collection need for the museum.                                                                            PDC Fac Project Manager:                              Kraft
                                                                                                             User Representative:

                                                                                                             AE:
                                                                                                             CM:
                                                                                                             Contractor:
STATUS
Evaluation of existing structural systems is in progress.                                                    NASF:                1,776            GSF:         1,776
                                                                                                             Current Budget:                                  $52,000
                                                                                                             Projected Budget:                               $680,000
                                                                                                             Bldg:   26
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                                Page 14 of 17
Parking Lot Improvements 2011                                                                                                                                 11-9074
DESCRIPTION                                                                                                    Project Status:                          C - Construction
Install two new parking lots on the north side of Campus including landscaping and lighting. Resurface         Project Delivery Method:               Job Order Contract
six existing parking lots and repave the entrances to the Sixth Street Garage and the Park Avenue
                                                                                                               PDC Design Project Manager:                         Kraft
Garage.
                                                                                                               PDC Fac Project Manager:                            Kraft
                                                                                                               User Representative:

                                                                                                               AE:
                                                                                                               CM:
                                                                                                               Contractor: Sturgeon Electric Co Inc
STATUS
The two new parking lots on the north side of Campus are paved and open. Lighting and landscaping            NASF:                                 GSF:
installations are in progress. Resurfacing of six existing parking lots and the repaving of the entrances to                                                   $392,000
the Sixth Street and Park Avenue Garages are completed.                                                      Current Budget:
                                                                                                               Projected Budget:                               $442,000
                                                                                                               Bldg:


Modern Streetcar, Relocate UITS Fiber Optic Cable                                                                                                             11-9075
DESCRIPTION                                                                                                    Project Status:                               D - Design
Relocate UITS fiber optic cable in preparation for the development of the Modern Streetcar route.              Project Delivery Method:
                                                                                                               PDC Design Project Manager:                        Banks
                                                                                                               PDC Fac Project Manager:                            TBD
                                                                                                               User Representative:

                                                                                                               AE:         G L H N Architects And Engineers
                                                                                                               CM:
                                                                                                               Contractor:
STATUS
The Architect is proceeding with design and impact assessment of Downtown Links.                               NASF:                               GSF:
                                                                                                               Current Budget:                                  $34,400
                                                                                                               Projected Budget:
                                                                                                               Bldg:


Arizona Stadium, Renovate Suites 224,325B,325C                                                                                                                11-9087
DESCRIPTION                                                                                                    Project Status:                            O - Occupancy
Install electric operable windows and shades in three skybox seating areas at the Arizona Stadium,             Project Delivery Method:               Job Order Contract
including the President's Suite 325B, Rodgers' Suite 224 and Alumni Suite 325C.
                                                                                                               PDC Design Project Manager:                        Dolan
                                                                                                               PDC Fac Project Manager:                           Dolan
                                                                                                               User Representative:

                                                                                                               AE:         Dave Diebold Architect
                                                                                                               CM:
                                                                                                               Contractor: Division II Construction Co Inc
STATUS
All windows have been installed and project will be complete for the first home game.                          NASF:                               GSF:           6,000
                                                                                                               Current Budget:                                 $350,000
                                                                                                               Projected Budget:                               $350,000
                                                                                                               Bldg:   58


Hi Corbett Field, Modify Facility                                                                                                                             11-9089
DESCRIPTION                                                                                                    Project Status:                               D - Design
Investigate the viability of relocating the Arizona Wildcat Baseball home events to Hi Corbett Field and       Project Delivery Method:
finding alternate uses for the Frank Sancet Field site. Included in this study will be recommendations
                                                                                                               PDC Design Project Manager:                      Mackey
and cost estimates for modifications to Hi Corbett Field identifying it as a University of Arizona facility.
                                                                                                               PDC Fac Project Manager:                           TBD
                                                                                                               User Representative:

                                                                                                               AE:         Breckenridge Group
                                                                                                               CM:
                                                                                                               Contractor:
STATUS
Proceeding with a cost estimate to determine the financial implications of the Wildcat Baseball Team           NASF:                               GSF:
practicing and playing at Hi Corbett field.                                                                                                                      $8,700
                                                                                                               Current Budget:
                                                                                                               Projected Budget:
                                                                                                               Bldg:
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                        Page 15 of 17
Enviromental Research Laboratory-West Center                                                                                                           12-9091
DESCRIPTION                                                                                               Project Status:                             D - Design
Relocation of the U of A's Environmental Research Laboratory (ERL)-West Center to Pima County's           Project Delivery Method:
ROMP Central Regional Laboratory Complex.
                                                                                                          PDC Design Project Manager:                        Vos
                                                                                                          PDC Fac Project Manager:                          TBD
                                                                                                          User Representative:

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
                                                                                                          NASF:                             GSF:          15,000
                                                                                                          Current Budget:                                $10,000
                                                                                                          Projected Budget:
                                                                                                          Bldg:   CLC


Lunar and Planetary Laboratory, Renovate Room 104                                                                                                      12-9094
DESCRIPTION                                                                                               Project Status:                             D - Design
This facility has most recently hosted the Team whcih led the Phoenix Mars mission. The facility is now   Project Delivery Method:
being readied to host the Team which will lead the OSIRIS-REx mission. Room No. 104 will be
                                                                                                          PDC Design Project Manager:                      Banks
renovated to provide space for the Principal Investigators and Senior Staff.
                                                                                                          PDC Fac Project Manager:                          TBD
                                                                                                          User Representative:                     Dante Lauretta

                                                                                                          AE:         A B A Architects P.C.
                                                                                                          CM:
                                                                                                          Contractor: Lang Wyatt Construction (see Martin Lang C
STATUS
The Conceptual Design and Budget Verification phase has been completed. Design documentation and          NASF:                   0         GSF:               0
cost estimates have been provided to the Lunar & Planetary Laboratory, for their use in determining                                                     $150,000
which elements of the project should move forward.                                                        Current Budget:
                                                                                                          Projected Budget:
                                                                                                          Bldg:   500


Student Union Memorial Center, Renovate Panda Express                                                                                                  12-9096
DESCRIPTION                                                                                               Project Status:                             D - Design
Renovate the Panda Express outlet space in the Student Union Memorial Center (SUMC) Food Court.           Project Delivery Method:
The Panda Express corporate architect and contractor will be used for the renovation work, with PDC
                                                                                                          PDC Design Project Manager:                       Kraft
and FM providing plan review, permitting, inspection and project coordination services and support.
                                                                                                          PDC Fac Project Manager:                          Kraft
                                                                                                          User Representative:

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
Project will begin with minor cosmetic work around the Food court side of the front counter. Mechanical   NASF:                             GSF:
and plumbing upgrades will begin on or about September 12.                                                                                               $10,000
                                                                                                          Current Budget:
                                                                                                          Projected Budget:
                                                                                                          Bldg:   17


Student Union Memorial Center, Einstein Bros Bagels Tenant Improvements                                                                                12-9098
DESCRIPTION                                                                                               Project Status:                             D - Design
Tenant improvements for existing space at the Student Union Memorial Center for Einstein Bros Bagels      Project Delivery Method:
store front.
                                                                                                          PDC Design Project Manager:                   Johnson
                                                                                                          PDC Fac Project Manager:                         TBD
                                                                                                          User Representative:

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
                                                                                                          NASF:               1,000         GSF:           1,000
                                                                                                          Current Budget:                                     $0
                                                                                                          Projected Budget:                             $522,000
                                                                                                          Bldg:   19
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                  Page 16 of 17
Hillenbrand Softball Stadium, Renovate Dugouts                                                                                                 12-9099
DESCRIPTION                                                                                             Project Status:                        D - Design
First utilized during the 1993 season, Hillenbrand Softball Stadium has hosted eight NCAA National      Project Delivery Method:
Championship Softball Teams. Renovation of the dugouts will provide enhanced player facilities, as well
                                                                                                        PDC Design Project Manager:              Gajdorus
as improved safety from foul balls.
                                                                                                        PDC Fac Project Manager:                     TBD
                                                                                                        User Representative:               Steve Kozachik

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
PDC is assisting the Department of Intercollegiate Athletics in identifying the required improvements, and NASF:                        GSF:
developing a forecast of anticipated project costs, for University administrative and financial approvals.                                      $200,000
                                                                                                          Current Budget:
                                                                                                          Projected Budget:
                                                                                                          Bldg:    93.03


Student Union Memorial Center, Pinkberry Tenant Improvements                                                                                   12-9100
DESCRIPTION                                                                                               Project Status:                      D - Design
Outlet space tenant Improvements at the Student Union Memorial Center for the Pinkberry yogurt shop.      Project Delivery Method:
                                                                                                          PDC Design Project Manager:            Johnson
                                                                                                          PDC Fac Project Manager:                 Dolan
                                                                                                          User Representative:

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
Construction documents are in progress.                                                                   NASF:               960       GSF:         960
                                                                                                          Current Budget:                             $0
                                                                                                          Projected Budget:                     $565,000
                                                                                                          Bldg:    19


Biomedical Research Laboratory, MRI Equipment Installation                                                                                     12-9121
DESCRIPTION                                                                                               Project Status:                      D - Design
Renovation of space at the Biomedical Research Laboratory for installation of MRI equipment for the       Project Delivery Method:
Department of Radiology.
                                                                                                          PDC Design Project Manager:              Banks
                                                                                                          PDC Fac Project Manager:                  TBD
                                                                                                          User Representative:

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
PDC is supporting the department in the preparation of an NIH Grant submittal.                            NASF:                         GSF:
                                                                                                          Current Budget:                             $0
                                                                                                          Projected Budget:                     $800,000
                                                                                                          Bldg:    209


McKale Memorial Center, Renovations and Additions                                                                                              12-9122
DESCRIPTION                                                                                               Project Status:                      D - Design
Feasibility study is to be prepared addressing the refurbishment and expansion of the McKale Memorial     Project Delivery Method:
Center including improved offices, lockers, academic areas, fan amenitites and services within an aging
                                                                                                          PDC Design Project Manager:                Vos
facility. Site infrastructure and building access improvements may also be included.
                                                                                                          PDC Fac Project Manager:                  TBD
                                                                                                          User Representative:

                                                                                                          AE:
                                                                                                          CM:
                                                                                                          Contractor:
STATUS
                                                                                                          NASF:                         GSF:
                                                                                                          Current Budget:                             $0
                                                                                                          Projected Budget:
                                                                                                          Bldg:
Sep 2011 Planning, Design & Construction -- Project Status Report - CDP                                                                    Page 17 of 17
Mount Lemmon Sky Center Renovations                                                                                                                12-9123
DESCRIPTION                                                                                             Project Status:                          D - Design
The Mount Lemmon Sky Center hosts numerous visitors throughout the year for general tours and           Project Delivery Method:          Job Order Contract
specialized observation opoportunities. Improvements are required to provide additional space, an
                                                                                                        PDC Design Project Manager:                Gajdorus
enhanced visitor experience, as well as convenient access for individuals with disabilities.
                                                                                                        PDC Fac Project Manager:                       TBD
                                                                                                        User Representative:                   Alan Strauss

                                                                                                        AE:
                                                                                                        CM:
                                                                                                        Contractor:
STATUS
PDC is assisting the Steward Observatory in identifying the required improvements, and developing a     NASF:                            GSF:
forecast of anticipated project costs, for University administrative and financial approvals.                                                             $0
                                                                                                        Current Budget:
                                                                                                        Projected Budget:
                                                                                                        Bldg:


Steward Obs Mirror Lab, Install HVAC System                                                                                                        12-9125
DESCRIPTION                                                                                             Project Status:                            D - Design
Installation of HVAC system to replace the existing evaporative coolers at the Steward Observatory      Project Delivery Method:
Mirror Laboratory (SOML) in support of the Giant Magellan Telescope (GMT) Segment #2.
                                                                                                        PDC Design Project Manager:                    Banks
                                                                                                        PDC Fac Project Manager:                        TBD
                                                                                                        User Representative:

                                                                                                        AE:
                                                                                                        CM:
                                                                                                        Contractor:
STATUS
                                                                                                        NASF:                            GSF:
                                                                                                        Current Budget:                             $285,000
                                                                                                        Projected Budget:                           $285,000
                                                                                                        Bldg:   61.06


Red Rock / Campus Agricultural Centers, Install PV Arrays                                                                                          66-9673
DESCRIPTION                                                                                             Project Status:                     C - Construction
The department of Planning, Design & Construction will provide design, engineering and inspection       Project Delivery Method:
services for the installation of photovoltaic arrays at the Red Rock and Campus Agricultural Centers.
                                                                                                        PDC Design Project Manager:                    Banks
                                                                                                        PDC Fac Project Manager:                       Banks
                                                                                                        User Representative:                            Ryan

                                                                                                        AE:
                                                                                                        CM:
                                                                                                        Contractor:
STATUS
Installation of Red Rock PV systems is complete. PV systems for West Campus Agricultural Centers are NASF:                               GSF:
in design. Construction is underway on PV system at Campus Agricultural Center.                                                                      $30,000
                                                                                                        Current Budget:
                                                                                                        Projected Budget:                                 $0
                                                                                                        Bldg:   1000        2000


Campbell Farm, CEAC Greenhouse Installation                                                                                                        68-3842
DESCRIPTION                                                                                             Project Status:                            D - Design
The department of Planning, Design & Construction will facilitate the provision of design, engineering and Project Delivery Method:
inspection services for the installation of two high tunnel research greenhouses that have been donated
                                                                                                           PDC Design Project Manager:                 Banks
to the Controlled Environment Agricultural Center (CEAC).
                                                                                                        PDC Fac Project Manager:                       Banks
                                                                                                        User Representative:                    Steve Husman

                                                                                                        AE:
                                                                                                        CM:
                                                                                                        Contractor:
STATUS
Infrastructure design is in progress.                                                                   NASF:                            GSF:
                                                                                                        Current Budget:                               $1,500
                                                                                                        Projected Budget:
                                                                                                        Bldg:

				