					                             SEI CMMI Quick Assessment Process

This process can be used to quickly assess the SEI CMMI Maturity Level (Staged
Representation) of an Organization. A typical meeting with Project Managers and Their
Managers to answer the Level 2 Questions would take between 2 to 4 hours depending on
the amount of discussion between the Managers in determining the "score" for each
Activity.

The Rating Guide uses a combination of the Common Features translated into a scoring
method that enables the selection of a score of 0 to 10 for each Specific Practice (Activity)
within each Process Area of the CMMI. The Method for scoring is designed to be simple
to understand for Managers trained or not trained in the CMMI. The moderator/scorer
must have knowledge of the CMMI.

The specific practices within the CMMI describe the activities expected to result in
achievement of the specific goals of a process area. The Rating Guide, combined with
the Process Area Specific Practices Questions in each Sheet of this Workbook can be
used to produce a quick "score" showing organizational process maturity.

During a typical meeting with several project managers, there is a lot of discussion on
how to score the first few questions. Once the scoring is understood by the managers
the pace quickens and it usually takes less than 3 hours to complete the Level 2
Questions.


The process is applicable to each level of the CMMI, although its value is greatest in the
CMM Level 2 and Level 3 Project Management KPAs.

Each spreadsheet is filled out with an example of the answers from a group of Managers.
The results spreadsheet shows the summary and gives a visual picture (radar chart) of
the results. The visual provides an overall "gap" view and the each process area sheet
contains a specific roadmap to specific practices that comprise the gap.


A score of 8 for all specific practices in a process area would indicate that the process
area would be likely to pass an assessment. An overall level score 1.8 for the level 2




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls        1                                10/5/2011 3:22 AM
SEI CMMI Level 2 Quick AssessmentScoring Guide                                                                Date:


                               Key Activitity Evaluation Guideline
     Score                  APPROACH                            DEPLOYMENT                           RESULTS
                 No management                          No part of the organization       Ineffective.
                 recognition of need.                   uses practice.
     POOR        No organizational ability.             No part of the organization
       0         No organizational                      shows interest.
                 commitment.
                 The practice is not evident.

                 Management has begun to                Fragmented use.                   Spotty results.
                 recognize the need.                    Inconsistent use.                 Inconsistent results.
     WEAK        Support items for the practice         Deployed in some parts of         Some evidence of effective-
      2          start to be created.                   the organization.                 effectiveness for some parts
                 A few parts of the organization        Limited monitoring/verification   of the organization.
                 are able to implement the              of use.
                 practice.

                 Wide but not complete                  Less fragmented use.              Consistent and positive
                 commitment by management.              Some consistency in use.          results for several parts of
      FAIR       Roadmap for practice                   Deployed in some major parts      the organization.
       4         implementation defined.                of the organization.              Inconsistent results for other
                 Several supporting items for           Monitoring/verification of use    parts of the organization.
                 the practice in place.                 for many parts of the
                                                        organization.
                 Strong management commit-              Deployed in almost all parts      Positive measurable results
                 ment; some management                  of the organization.              in most parts of the
 MARGINALLY      becomes proactive.                     Mostly consistent use across      organization.
  QUALIFIED      Practice implementation well           many parts of the organization.   Consistently positive results
     6           under way across parts of              Monitoring/verification of use    over time across many parts
                 the organization.                      for almost all parts of the       of the organization.
                 Supporting items in place.             organization.
                 Total management commitment.           Deployed in almost all parts      Positive measurable results
                 Majority of management is              of the organization.              in almost all parts of the
   QUALIFIED     proactive.                             Consistent use across almost      organization.
      8          Practice established as an             all parts of the organization.    Consistently positive results
                 integral part of the process.          Monitoring/verification of use    over time across almost all
                 Supporting items encourage and         for almost all parts of the       parts of the organization.
                 facilitate the use of the practice.    organization.
                 Management provides zealous            Pervasive and consistent          Requirements exceeded.
                 leadership and commitment.             deployment across all parts       Consistently world class
   WORLD         Organizational excellence of the       of the organization.              results.
  STANDARD       practice is recognized even            Consistent use over time          Counsel sought by others.
     10          outside of the company.                across all parts of the
                                                        organization.
                                                        Monitoring/verification for all
                                                        parts of the organization.




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls               Page 2                                     10/5/20113:22 AM
                      Requirements
SEI CMMI Level 2 Quick Assessment Management Process Area                              Date: 09/13/04


Requirements Management (REQM) Process
 SG1 Manage Requirements
     List of Specifice Practices                               0 1 2 3 4 5 6 7 8 9 10
SP 1.1   Obtain an Understanding of Requirements                               x
SP 1.2   Obtain Commitment to Requirements                                 x
SP 1.3   Manage Requirements Changes                                       x
SP 1.4   Maintain Bidirectional Traceability of Requirements                   x
SP 1.5   Identify Inconsistencies between Project Work and             x
         Requirements
Score                                                          0   0   2   6   8   0   0   0   0   0   0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls              Page 3                           10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                                                       Date: 09/13/04


Project Planning (PP) Process
 SG1 Establish Estimates
 SG 2 Develop a Project Plan
 SG 3 Obtain Commitment to the Plan
      List of Specifice Practices                                   0 1 2 3 4 5 6 7 8 9 10
 SP 1.1   Estimate the Scope of the Project                                 x
 SP 1.2   Establish Estimates of Work Product and Task Attributes           x
 SP 1.3   Define Project Life Cycle                                                 x
 SP 1.4   Determine Estimates of Effort and Cost                            x
 SP 2.1   Establish the Budget and Schedule                                 x
 SP 2.2   Identify Project Risks                                                    x
 SP 2.3   Plan for Data Management                                          x
 SP 2.4   Plan for Project Resources                                            x
 SP 2.5   Plan for Needed Knowledge and Skills                              x
 SP 2.6   Plan Stakeholder Involvement                                              x
 SP 2.7   Establish the Project Plan                                                        x
 SP 3.1   Review Plans that Affect the Project                          x
 SP 3.2   Reconcile Work and Resource Levels                               x
 SP 3.3   Obtain Plan Commitment                                           x
Score                                                               0   1 16 3 12 0         6   0   0   0   0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls             Page 4                             10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                                                Date: 09/13/04


Project Monitoring & Control (PMC) Process
SG1 Monitor Project Against Plan
SG 2 Manage Corrective Action to Closure
     List of Specifice Practices                        0 1 2 3 4 5 6 7 8 9 10
SP 1.1   Monitor Project Planning Parameters                               x
SP 1.2   Monitor Commitments                                               x
SP 1.3   Monitor Project Risks                                             x
SP 1.4   Monitor Data Management                                           x
SP 1.5   Monitor Stakeholder Involvement                                   x
SP 1.6   Conduct Progress Reviews                                          x
SP 1.7   Conduct Milestone Reviews                                         x
SP 2.1   Analyze Issues                                                    x
SP 2.2   Take Corrective Action                                            x
SP 2.3   Manage Corrective Action                                          x
Score                                                   0   0   0   0   0 50 0   0   0   0   0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls       Page 5                            10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                                     Date: 09/13/04


Supplier Agreement Management (SAM) Process
 SG1 Establish Supplier Agreements
 SG 2 Satisfy Supplier Agreements
        List of Specifice Practices                 0 1 2 3 4 5 6 7 8 9 10
 SP 1.1 Determine Acquisition Type                                      x
 SP 1.2 Select Suppliers                                                x
 SP 1.3 Establish Supplier Agreements                      x
 SP 2.1   Review COTS Products                             x
 SP 2.2   Execute the Supplier Agreement                   x
 SP 2.3   Accept the Acquired Product                      x
 SP 2.4   Transition Products                              x
Score                                               0   0 10 0   0   0 12 0    0   0     0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls   Page 6                     10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                                             Date: 09/13/04


Measurement & Analysis (M&A) Process
 SG1 Align Measurement and Analysis
 SG 2 Provide Measurement Results
        List of Specifice Practices                      0 1 2 3 4 5 6 7 8 9 10
 SP 1.1 Establish Measurement Objectives                        x
 SP 1.2 Specify Measures                                        x
 SP 1.3 Specify Data Collection and Storage Procedures          x
 SP 1.4   Specify Analysis Procedures                           x
 SP 2.1   Collect Measurement Data                              x
 SP 2.2   Analyze Measurement Data                              x
 SP 2.3   Store Data and Results                                x
 SP 2.4   Communicate Results                                   x
Score                                                    0   0 16 0   0   0   0   0   0   0   0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls       Page 7                         10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                                                  Date: 09/13/04


Process & Product Quality Assurance (PPQA) Process
 SG1 Objectively Evaluate Processes and Work Products
 SG 2 Provide Objective Insight
      List of Specifice Practices                                     0 1 2 3 4 5 6 7 8 9
 SP 1.1   Objectively Evaluate Processes                                            x
 SP 1.2   Objectively Evaluate Work Products and Services                           x
 SP 2.1   Communicate and Ensure Resolution of Noncompliance Issues                 x
 SP 2.2   Establish Records                                                   x
Score                                                                 0   0   2   0 12 0   0   0   0   0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls          Page 8                           10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                   Date: 09/13/04




10




 0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls   Page 9   10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment                                             Date: 09/13/04


Process & Product Quality Assurance (PPQA) Process
 SG1 Establish Baselines
 SG 2 Track and Control Changes
 SG 3 Establish Integrity
      List of Specifice Practices                           0 1 2 3 4 5 6 7 8 9 10
 SP 1.1   Identify Configuration Items                                    x
 SP 1.2   Establish a Configuration Management System                             x
 SP 1.3   Create or Release Baselines                                      x
 SP 2.1   Track Change Requests                                            x
 SP 2.2   Control Configuration Items                                      x
 SP 3.1   Establish Configuration Management Records                       x
 SP 3.2   Perform Configuration Audits                                     x
Score                                                       0   0   0   0 24 0    6   0   0   0   0




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls          Page 10                     10/5/20113:22 AM
SEI CMMI Level 2 Quick Assessment          Project Management Processes                                                Date: 09/13/04


                                               World Standard        Certification           Score           Level Score vs Cert
Requirements Management                              10                   8.0                 4.0                   1.40
Project Planning                                     10                   8.0                 3.4                   1.34
Project Monitoring & Control                         10                   8.0                 6.3                   1.63
Supplier Agreement Management                        10                   8.0                 3.9                   1.39
Measurement & Analysis                               10                   8.0                 2.5                   1.25
Process & Product QA                                 10                   8.0                 4.4                   1.44
Configuration Management                             10                   8.0                 5.4                   1.54
Total Points and Level Rating                       550                  440                  186                   1.42

                                                                                                            World Standard
                                             Requirements Management
                                                      10                                                    Certification
                                                       9                                                    Score
                                                       8
                                                       7
               Configuration Management                6
                                                                               Project Planning
                                                       5
                                                       4
                                                       3
                                                       2
                                                       1
                                                       0


               Process & Product QA                                                  Project Monitoring & Control




                                                                      Supplier Agreement
                          Measurement & Analysis
                                                                         Management




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls                   Page 11                                                  10/5/2011 3:22 AM
SEI CMMI Level 2 Quick Assessment          Project Management Processes     Date: 09/13/04




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls              Page 12             10/5/2011 3:22 AM
SEI CMMI Level 2 Quick Assessment
                     Project Management                       Processes              Date: 09/13/04


                                           Process Area Totals
Process Area                                  KPA      Total     Total   Certification   Level    World
                                             Score   Questions   Score      Score                Standard
                                                                                                  Score
Requirements Management                       4.00        5       16          40         1.40        50
Project Planning                              3.39       14       38         112         1.34       140
Project Monitoring & Control                  6.25       10       50          80         1.63       100
Supplier Agreement Management                 3.93        7       22          56         1.39        70
Measurement & Analysis                        2.50        8       16          64         1.25        80
Process & Product QA                          4.38        4       14          32         1.44        40
Configuration Management                      5.36        7       30          56         1.54        70

Total                                         4.23       55       186        440         1.42       550




32f2bbff-f706-4ab5-8959-48f7d98306d4.xls       Page 13                               10/5/20113:22 AM

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:4
posted:10/5/2011
language:English
pages:13