Demolition Specifications

Document Sample
Demolition Specifications Powered By Docstoc
					Demolition Specifications
KONA VOR DEMOLITION



                  TABLE OF CONTENTS


DIVISION 1            GENERAL REQUIREMENTS

SECTION 01300         SUBMITTALS

SECTION 01500         TEMPORARY FACILITIES AND CONTROLS

SECTION 02051         REMOVAL OF FUEL STORAGE TANKS

SECTION 02080         ASBESTOS ABATEMENT

SECTION 02090         LEAD PAINT ABATEMENT

SECTION 02221         BUILDING DEMOLITION

SECTION 02222         SITE DEMOLITION

SECTION 02230         SITE CLEARING

SECTION 02311         ROUGH GRADING

SECTION 02745         ASPHALT SURFACE REPAIR
KONA VOR Demolition


                                         DIVISION 1

                               GENERAL REQUIREMENTS


1-1.1 Scope of Work:
 The Contractor shall provide labor, equipment, transportation, services, and materials (unless
specifically identified as Government Furnished Material-GFM list) required or necessary to
perform the work as specified in the contract documents. All services, work, materials and
equipment shall be subject to approval of the Government. The scope of work includes, but not
limited to:

   Scope of Work

   1.   EMPTY EXISTING 1000 GAL DIESEL FUEL. REMOVE CONVALT FUEL TANK, CRATE AND
        TRANSPORT TO A LOCATION DESINGATED BY THE FAA SSC MANAGER. DEMOLISH
        EXISTING CONCRETE PAD TO EXISTING GRADE LEVEL.

   2.   REMOVE AND DISPOSE EXISTING BATTERIES AND RETURN THE BATTERY RACK TO
        LOCAL SSC.

   3.   DEMOLISH EXISTING CONCRETE FILLED VECHICLE GUARD POLES

   4.   ABATE ASBESTOS AND LEAD PAINT PER PLANS AND SPECS.

   5.   DEMOLISH EXISITNG MASONARY VORTAC BUILDING AND COUNTERPOSE ROOF TO
        GRADE LEVEL. HAUL AWAY RUBBISH FROM THE SITE AND RE-GRADE TO EXISTING
        CONDITION.

   6.   REMOVE EXISTING POWER AND TELCO CABLES, CONDUITS. AND PULL BOXES TO THE
        LAST POWER POLE ABOUT 1000’ AWAY FROM THE SITE.

   7.   REMOVE EXISTING PULL BOX.INSIDE THE FENCE AREA

   8.   REMOVE EXISTING MESSENGER CABLE

   9.   REMOVE EXISTING TACAN MONITOR ANTENNA PLOE AND FOUNDATION.

   10. REMOVE EXISTING BOARD FENCE AND SWING GATE

   11. REMOVE EXISTING CONCRETE REFERENCE MARKER.

   12. REMOVE AND DISPOSE TWO (2) CONTAINERS AS SHOWN IN DRAWING.

   13. REMOVE EXSITING TOILET ENCLOSURE AND CESSPOOL LOCATED OUTSIDE THE BOARD
       FENCE

   14. REMOVE EXISTING ENGINE GENERATOR, TRANSFER SWITCH, DAY TANK, MUFFER,
       BATTERY RACK, LOAD BANK AND OTHER ASSOCIATED HARDWARE. CONTRACTOR
       SHALL CRATE THE UNIT AND TRANSPORT TO A DESIGNATED LOCATION IDENTIFIED BY
       LOCAL SSC MANGER.




Date: 11/17/2010
                                               1
KONA VOR Demolition


   15. RESTORE AREA BY BACKFILLING THE EXCAVATED UNDERGROUND CONFUIT AREA. FILL
       MATERIAL SHALL BE COMPACTED TO APPROXIMATELY THE SAME DENSITY OF THE
       ADJACENT SOIL.

   16. HAUL AWAY ALL DEBRIS AND CLEAN UP PREMISES TO GOOD CONDITION AND TO
       SATISFACTION OF RESIDENT ENGINEER.




REFERENCE DOCUMENTS                        TITLE
KONA-D-VOR-GOOR                            Index of Drawings and Vicinity map
                                           Building Demolition Plan

                                           BUILDING, ASBESTOS AND LEAD PAINT
KONA-D-VOR-COO3
                                           REMOVAL PLAN




1-1.2 Contractor Furnished Material: The Contractor shall supply all materials not
specifically listed on the Government Furnished Property List. This includes but not limited to
the following:

Not required

1-1.3 Government-Furnished Material (GFM):

   None


1-1.4 Existing ILS Shutdown Date: Not required

1-1.5 Codes, Standards, Ordinances and Applicable Documents: All work including
materials shall comply with the latest applicable codes, standards, ordinances, rules, and
regulations requirements, as they may have referenced in herein.

   •   National Electrical Code (NEC) 2009 Code
   •   FAA-C-1391b Installation & Splicing of Underground Cable
   •   FAA-C-1217f Electrical Work, Interior.

If there is a conflict between any requirements in the referenced codes, standards, federal, state
or local regulations, the most stringent requirement shall govern

1-1.6 Advisory Circular 150/5370-2E “Operational Safety on Airport during Construction.


Date: 11/17/2010
                                                 2
KONA VOR Demolition


The contractor will be expected to comply in detail to all of the applicable requirements of this
Advisory Circular (AC).

1-1.7 Local Permits: The Contractor shall apply, pay fees, etc., to obtain applicable local
permits and inspections as required. The Contractor shall obtain the required permits in
sufficient time to prevent delaying the project completion. All work shall comply with the latest
editions of the International Building Code (IBC), the National Electric Code, and all other
applicable local codes. Copies of all permits and other inspection reports required by local
agencies shall be submitted to the COTR. The contractor is responsible for preparing the
necessary documents and submittals to obtain the permits.

1-1.8 Work Schedule:
Unless noted otherwise, the Contractor shall schedule his work to be performed during a normal
8-hour workday (i.e., 7:00 AM to 4:00 PM). No work shall be scheduled or performed on
Saturdays, Sundays or Federal Holidays without prior approval of the COTR. Approval by the
COTR for overtime work shall not be construed as an agreement for payment of overtime work.

Night work: Some work must be performed at night. Night work shall be performed between the
hours of 11:00 pm – 5:00 am. The following areas and activities shall be performed at night:

   NO NIGHT WORK FOR THIS PROJECT


Only one (1) COTR will be assigned to this project as a result night work shall be scheduled and
performed so that the COTR does not work in excess of 8 hours each day nor shall the COTR
work continuously in excess of 8 hours.

1-1.9 Pre Bid Conference/Inspection: It shall be the Contractor’s responsibility to inspect the
job site and become familiar with the conditions under which the work will be performed. The
CO shall designate the inspection date and time. A pre-bid meeting will be held to familiarize
prospective Contractors with the project. Failure to attend the pre-bid meeting may be considered
cause for rejection of the Contractor’s bid.

1-1.10 Project Schedule:
The Contractor shall, within ten (10) working days after the award of the contract, prepare and
submit to the Contracting Officer for approval three copies of a schedule showing the order in
which the Contractor proposes to perform the work, and the dates on which the Contractor
contemplates starting and completing the principal features of the work (including acquiring
materials and equipment).

a. Identify all work scheduled to be performed after normal working hours. The schedule shall be
   in the form of a progress chart of suitable scale and detail to indicate appropriately the
   percentage of work scheduled for completion by any given date during the period.

b. Show sequence, duration, and interdependence of activities required for complete performance
  of all items of work. Include following, as appropriate:
      • Mobilization.

Date: 11/17/2010
                                                 3
KONA VOR Demolition


     •    Major construction activities.
     •    Shutdown period (for any reason), or limited access.
     •    Performance and acceptance tests and supervisory service activities.
     •    Milestone dates and final completion date.
     •    Identify and activity that requires unusual shift work, such as two shifts, six day work
           weeks, involvement in cab, etc.

c. The chart shall be updated if the schedule slips more than five days and copies of the revised
   schedule shall be submitted to the Contracting Officer or COTR.

1-1.11 Airport Requirements: Not required

1-1.12 Pre-Construction Meeting: Prior to the start of construction, a pre-construction meeting
will be conducted with all applicable parties - ATO-W, ATO-T, and the contractor. The purpose
of the meeting will be to ensure that special conditions and other related requirements will be
met, to review construction schedule and a work plan, discuss ingress and egress into/from the
work area, and review elements contained in FAA Order 3900.57, FAA Pre-Construction and
Maintenance Project Safety and Health Checklist.

1-1.13 Submittals: Submittal" is used to refer to shop drawings, samples, manufacturer's catalog
cuts, technical data, specifications, installation instructions, material lists, test reports,
certificates, guaranties, operation and maintenance manuals, used in the work shall be inspected,
tested, and approved by the COTR before installation.

a. Submit four (4) copies of all submittals.

b. Submit Material Safety Data Sheets (MSDS) for all materials and/or products utilized in this
  contract.

c. The following submittals are required for this contract: (1) Health and Safety Plan; (2) Haz
   Com Plan; (3) Injury and Illness Prevention Program (IIPP); (4) Construction Schedule; (5)
   Local permits (if applicable); and (6) materials.

1-1.14 Existing Utilities: Prior to any excavation or trenching, where cable or utility lines are
   shown or otherwise made known to the contractor, the contractor shall locate them precisely,
   with equipment especially designed for this purpose, and be operated by personnel who are
   knowledgeable and experience in its use. In addition, the contractor shall make contact and
   coordinate with local utilities and the Underground Service Alert, to ensure underground
   services are properly located and staked. The contractor shall then hand excavated and
   exposes these cables or utility lines in these areas and shall protect them from any possible
   damage prior to any excavations. If a utility is damaged by the contractor, the contractor shall
   immediately notify the VO or resident engineer. Any damage caused by the contractor shall
   be immediately repaired, at no cost to the government, with materials and methods approved
   by the resident engineer. The reference drawings are provided as an aid to assist in the
   identification and location of underground utilities. It shall be the responsibility of the
   contractor to locate and protect from harm all underground utilities where trenching or
   excavation work is being performed.

Date: 11/17/2010
                                                 4
KONA VOR Demolition


Demolition work shall not start until HECO secures the power to the facility.

1-1.15 Coordination, Construction Permits, Licenses, Vehicles Permits, ID Badges,
   Insurance and Construction Notices:

1-1.15.1 Project Coordination: The contractor shall maintain a schedule of work and work
   layout to resolve conflicts and to ensure coordination of the work by different trades. It shall
   be the contactor’s responsibility to resolve all coordination conflicts between subcontractor’s
   and other trades.

1-1.16 Temporary Facilities: The Contractor shall provide and pay for all temporary services
and facilities necessary for the proper and expeditious execution of the work. The Contractor
shall remove all such temporary installations and connections when no longer necessary for the
project work.

a. Temporary Electric Lighting and Power: The contractor shall make all necessary
  arrangements for temporary electrical power. The contractor will not be permitted to use FAA
  electric service.

b. Temporary Water: The contractor shall make arrangements to transport all necessary water
  for construction and drinking.

c. Temporary Toilets and Sanitation: The Contractor shall provide ample and suitable on-site
  sanitary conveniences with proper enclosures for the use of the workers employed on the
  contract. Such conveniences shall be kept clean, be properly ventilated and shall be installed
  and maintained in conformity with requirements of all laws and ordinances governing such
  installations. Locations shall be subject to approval by the COTR.

1-1.17 Surveying: Not required

1-1.18 As-Built Drawings: The contractor shall correct and maintain at least two (2) sets of
       red-line drawings and one set of specifications on project site. The contractor shall
       submit a complete set of red-line drawings prior to the final inspection. .These drawings
       shall include all changes whether initiated by contract modifications, change conditions,
       mutual consent, shop drawings, or submittal data. Work will not be recognized as
       complete until the “As-Built” drawings are approved by the resident engineer.

1-1.19 Temporary Electric Lighting and Power: Contractor shall provide and maintain a
temporary lighting and power system for construction and inspection purposes. Contractor shall
make all necessary arrangements for temporary electrical services with the local power company
to provide and pay for all temporary work or, at contractor’s option; contractor shall provide an
approved temporary engine generator at the project site for construction support.


1-1.15 Final Acceptance of Work: The Contractor shall correct discrepancies noted during the
initial inspection, clean the premises and notify the FAA that the work is ready for acceptance.


Date: 11/17/2010
                                                 5
KONA VOR Demolition


The FAA will verify that all discrepancies have been corrected. The Contracting Officer makes
final acceptance. Intermittence acceptance of work as it gets accomplished will not be given.

                                      ***************




Date: 11/17/2010
                                              6
KONA VOR DEMOLITION



SECTION 01300 – SUBMITTALS


PART 1 - GENERAL

1.1    RELATED DOCUMENTS:

  A.   Drawings and general provisions of the Contract, including General and Supplementary
       Conditions and other Division 1 Specification Sections, apply to this Section.

1.2    SUMMARY:

  A.   Furnish submittals as required by the individual sections of the specifications in
       accordance with this Section.

1.3    QUALITY ASSURANCE:

  A.   Submittals, including shop drawings, are the Contractor's sole responsibility. Carefully
       examine submittals to ascertain that all provisions of the specifications have been
       complied with.

  B.   Submit descriptive data, certificates, performance data, test results and other
       information necessary to ascertain the quality of the component and its suitability for the
       purpose intended. The Contractor shall make, without cost to the Contracting Officer’s
       Representative (COR), any change or adjustment in correcting work resulting from the
       use of such optional material or construction in conformity with the contract
       requirements.

1.4    DEFINITIONS:

  A.   For the purpose of defining the meaning of scheduled submittals, the following
       descriptions shall apply:
       1.    Certification of Applicator/Subcontractor (CSQ) - A certified letter stating that the
             applicator or subcontractor proposed to perform a specified function is duly
             designated as factory authorized and trained for the application of the specified
             product.
                    1)    Compliance with recognized testing agency standards
                    2)    Application of testing agency labels and seals.
                    3)    Notation of dimensions verified by field measurement.
                    4)    Notation of coordination requirements.
       2.    Operational and Maintenance Manuals - Refer to Section 01730 “Operation and
             Maintenance Data.”
       3.    Equipment Installation Report - A report by the manufacturer's representative or
             installer, stating that equipment has been installed in accordance with
             manufacturer's requirements and has been operated or otherwise tested and



SUBMITTALS                                                                                01300-1
KONA VOR DEMOLITION


             functions properly, fulfills the requirements of the Documents. Include copies of
             Test Report Forms as required by the COR.

1.5    SUBMITTALS:

  A.   Submittals shall be accompanied by an original and one copy of transmittal letter that
       identifies the content of the submittals.

1.6    SUBMITTALS PRIOR TO NOTICE TO PROCEED:

  A.   Submit the following information to the COR within fifteen (15) days after award of
       contract. Notice to Proceed (NTP) will not be issued until these submittals are
       approved.
       1.    Shop Drawings required prior to NTP are identified by an asterisk (*) in the
             Schedule of Submittals located at the end of this Section.
       2.    Provide construction/demolition schedule and project safety plan for approval
             prior to NTP.

1.7    SAMPLES: NOT REQUIRED

1.8    JOB CONDITIONS:

  A.   Contractor is responsible to coordinate the submittals between the various trades. When
       a proposed component requires modification to some other part of the project, the
       Contractor shall also include the revision or modifications necessary to incorporate the
       proposed item.

  B.   The COR will indicate approval or disapproval of the shop drawings, and if not
       approved as submitted, shall indicate the reasons for disapproval. Work done before
       such approval shall be at the Contractor's risk. Approval by the COR shall not relieve
       the Contractor from responsibility for any errors or omissions in such submittals, nor
       from responsibility for complying with the requirements of this contract.

1.9    SCHEDULES:

  A.   All submittals, including samples, certificates, test reports, and shop drawings shall be
       submitted in ample time for the COR to make a determination of compliance with the
       Contract Documents before fabrication and deliver to the site. Make submittals in
       advance of first need in ample time to allow for COR's review (15 calendar days
       maximum).

  B.   After a submission has been approved, substitutions will not be permitted without
       written approval by the COR.

END OF SECTION 01300



SUBMITTALS                                                                              01300-2
KONA VOR DEMOLITION



SECTION 01500 - TEMPORARY FACILITIES AND CONTROLS


PART 1 - GENERAL

1.1    RELATED DOCUMENTS

  A.   Drawings and general provisions of the Contract, including General and Supplementary
       Conditions and other Division 1 Specification Sections, apply to this Section.

1.2    SUMMARY

  A.   This Section includes requirements for temporary facilities and controls, including tem-
       porary utilities, support facilities, and security and protection facilities.

  B.   Temporary utilities include, but are not limited to, the following:
       1.  Sewers and drainage.
       2.  Water service and distribution.
       3.  Sanitary facilities, including toilets, wash facilities, and drinking-water facilities.
       4.  Ventilation.
       5.  Electric power service.
       6.  Lighting.
       7.  Telephone service.

  C.   Support facilities include, but are not limited to, the following:
       1.   Temporary roads and paving.
       2.   Project identification and temporary signs.
       3.   Waste disposal facilities.
       4.   Field offices.
       5.   Storage sheds.
       6.   Lifts and hoists.
       7.   Construction aids and miscellaneous services and facilities.

  D.   Security and protection facilities include, but are not limited to, the following:
       1.   Environmental protection.
       2.   Stormwater control.
       3.   Tree and plant protection.
       4.   Pest control.
       5.   Site enclosure fence.
       6.   Barricades, warning signs, and lights.
       7.   Temporary enclosures.
       8.   Temporary partitions.
       9.   Fire protection.




TEMPORARY FACILITIES AND CONTROLS                                                           01500 - 1
KONA VOR DEMOLITION


  E.   Related Sections include the following:
       1.    Division 1 Section 01300 "Submittals" for procedures for submitting copies of
             implementation and termination schedule and utility reports.
       2.    Division 2 Section 02745 "Asphalt Surface Repair" for construction and mainte-
             nance of asphalt paving for temporary roads and paved areas.

1.3    USE CHARGES

  A.   General: Cost or use charges for temporary facilities are not chargeable to Owner or Ar-
       chitect and shall be included in the Contract Sum. Allow other entities to use temporary
       services and facilities without cost, including, but not limited to, the following:
       1.    Owner's construction forces.
       2.    Occupants of Project.
       3.    Architect.
       4.    Testing agencies.
       5.    Personnel of authorities having jurisdiction.

  B.   Water Service: Use water from Owner's existing water system with metering and with-
       out payment of use charges.

  C.   Electric Power Service: Use electric power from Owner's existing system without me-
       tering and with payment of use charges to power company.

1.4    SUBMITTALS

  A.   Implementation and Termination Schedule: Within 15 days of date established for sub-
       mittal of Contractor's Construction Schedule, submit a schedule indicating implementa-
       tion and termination of each temporary utility.

1.5    QUALITY ASSURANCE

  A.   Standards: Comply with ANSI A10.6, NECA's "Temporary Electrical Facilities," and
       NFPA 241.
       1.   Trade Jurisdictions: Assigned responsibilities for installation and operation of
            temporary utilities are not intended to interfere with trade regulations and union
            jurisdictions.
       2.   Electric Service: Comply with NECA, NEMA, and UL standards and regulations
            for temporary electric service. Install service to comply with NFPA 70.

  B.   Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect
       each temporary utility before use. Obtain required certifications and permits.




TEMPORARY FACILITIES AND CONTROLS                                                     01500 - 2
KONA VOR DEMOLITION


1.6    PROJECT CONDITIONS NOT APPLICABLE


PART 2 - PRODUCTS

2.1    MATERIALS

  A.   Water: Potable.

2.2    EQUIPMENT

  A.   General: Provide equipment suitable for use intended.

  B.   Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing
       agent as indicated or a combination of extinguishers of NFPA-recommended classes for
       exposures.
       1.    Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and
             size required by location and class of fire exposure.

  C.   Self-Contained Toilet Units: Single-occupant units of chemical, aerated recirculation, or
       combustion type; vented; fully enclosed with a glass-fiber-reinforced polyester shell or
       similar nonabsorbent material.

  D.   Drinking-Water Fixtures: Containerized, tap-dispenser, bottled-water drinking-water
       units, including paper cup supply.

  E.   Electrical Outlets: Properly configured, NEMA-polarized outlets to prevent insertion of
       110- to 120-V plugs into higher-voltage outlets; equipped with ground-fault circuit in-
       terrupters, reset button, and pilot light.

  F.   Power Distribution System Circuits: Where permitted and overhead and exposed for
       surveillance, wiring circuits, not exceeding 125-V ac, 20-A rating, and lighting circuits
       may be nonmetallic sheathed cable.


PART 3 - EXECUTION

3.1    INSTALLATION, GENERAL- NOT APPLICABLE

3.2    TEMPORARY UTILITY INSTALLATION

  A.   General: Engage appropriate local utility company to install temporary service or con-
       nect to existing service. Where utility company provides only part of the service, pro-
       vide the remainder with matching, compatible materials and equipment. Comply with
       utility company recommendations.
       1.     Arrange with utility company, Owner, and existing users for time when service
              can be interrupted, if necessary, to make connections for temporary services.

TEMPORARY FACILITIES AND CONTROLS                                                      01500 - 3
KONA VOR DEMOLITION


       2.    Provide adequate capacity at each stage of construction. Before temporary utility
             is available, provide trucked-in services.
       3.    Obtain easements to bring temporary utilities to Project site where Owner's ease-
             ments cannot be used for that purpose.

  B.   Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking-water fix-
       tures. Comply with regulations and health codes for type, number, location, operation,
       and maintenance of fixtures and facilities.
       1.     Disposable Supplies: Provide toilet tissue, paper towels, paper cups, and similar
              disposable materials for each facility. Maintain adequate supply. Provide covered
              waste containers for disposal of used material.
       2.     Toilets: Install self-contained toilet units. Shield toilets to ensure privacy. Provide
              separate facilities for male and female personnel.
       3.     Wash Facilities: Install wash facilities supplied with potable water at convenient
              locations for personnel who handle materials that require wash up. Dispose of
              drainage properly. Supply cleaning compounds appropriate for each type of mate-
              rial handled.
       4.     Drinking-Water Facilities: Provide bottled-water, drinking-water units.

  C.   Ventilation and Humidity Control: Provide temporary ventilation required by construc-
       tion activities. Select equipment that will not have a harmful effect on abatement activi-
       ties or elements being demolished. Coordinate ventilation requirements to produce am-
       bient condition required and minimize energy consumption.

  D.   Electric Power Service: Use of Owner's existing electric power service will be permit-
       ted, as long as equipment is maintained in a condition acceptable to Owner.

  E.   Electric Distribution: Provide receptacle outlets adequate for connection of power tools
       and equipment.
       1.    Provide waterproof connectors to connect separate lengths of electrical power
             cords if single lengths will not reach areas where construction activities are in
             progress. Do not exceed safe length-voltage ratio.
       2.    Provide warning signs at power outlets other than 110 to 120 V.
       3.    Provide 4-gang outlets, spaced so 100-foot extension cord can reach each area for
             power hand tools and task lighting. Provide a separate 125-V ac, 20-A circuit for
             each outlet.

  F.   Lighting: Provide temporary lighting with local switching that provides adequate illu-
       mination for construction operations and traffic conditions.
       1.    Install and operate temporary lighting that fulfills security and protection re-
             quirements without operating entire system.

  G.   Telephone Service: Provide temporary telephone service throughout construction period
       for common-use facilities used by all personnel engaged in construction activities. In-
       stall separate telephone line for each field office and first-aid station.
       1.     At each telephone, post a list of important telephone numbers.
              a.    Police and fire departments.

TEMPORARY FACILITIES AND CONTROLS                                                          01500 - 4
KONA VOR DEMOLITION


             b.    Ambulance service.
             c.    Contractor's home office.

3.3    SUPPORT FACILITIES INSTALLATION

  A.   General: Comply with the following:
       1.   Locate field offices, storage sheds, sanitary facilities, and other temporary con-
            struction and support facilities for easy access.
       2.   Provide incombustible construction for offices, shops, and sheds located within
            construction area or within 30 feet of building lines. Comply with NFPA 241.
       3.   Maintain support facilities until near Substantial Completion. Remove before
            Substantial Completion. Personnel remaining after Substantial Completion will be
            permitted to use permanent facilities, under conditions acceptable to Owner.

  B.   Traffic Controls:
       1.    Provide temporary traffic controls at junction of construction site accesses and
             temporary roads with public roads. Include warning signs for public traffic and
             "STOP" signs for entrance onto public roads. Comply with requirements of au-
             thorities having jurisdiction.
       2.    Provide temporary traffic control and traffic control staff at each end of the en-
             trance tunnel to the Diamond Head crater during the transportation of debris from
             the construction site to off-site locations. Maintain existing tunnel access and
             minimize impact on tunnel traffic.

  C.   Dewatering Facilities and Drains: Comply with requirements in applicable Division 2
       Sections for temporary drainage and dewatering facilities and operations not directly as-
       sociated with construction activities included in individual Sections. Where feasible, use
       same facilities. Maintain Project site, excavations, and construction free of water.
       1.    Dispose of rainwater in a lawful manner that will not result in flooding Project or
             adjoining property nor endanger permanent Work or temporary facilities.

  D.   Project Identification and Temporary Signs: Prepare Project identification and other
       signs in sizes indicated. Install signs where indicated to inform public and persons seek-
       ing entrance to Project. Do not permit installation of unauthorized signs.

  E.   Revise subparagraphs below to suit Project. Delete if not required. If required, insert a
       list of necessary signs and add Project-specific provisions, such as special graphics and
       special lighting. See Evaluations.
       1.     Engage an experienced sign painter to apply graphics for Project identification
              signs. Comply with details indicated.
       2.     Prepare temporary signs to provide directional information to construction per-
              sonnel and visitors.
       3.     Construct signs of exterior-type plywood in sizes and thicknesses indicated. Sup-
              port on posts or framing of preservative-treated wood or steel.
       4.     Paint sign panel and applied graphics with exterior-grade alkyd gloss enamel over
              exterior primer.


TEMPORARY FACILITIES AND CONTROLS                                                       01500 - 5
KONA VOR DEMOLITION


  F.   Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to han-
       dle waste from construction operations. Containerize and clearly label hazardous, dan-
       gerous, or unsanitary waste materials separately from other waste.
       1.   If required by authorities having jurisdiction, provide separate containers, clearly
            labeled, for each type of waste material to be deposited.

  G.   Janitorial Services: Provide janitorial services on a daily basis for temporary offices,
       first-aid stations, toilets, wash facilities, and similar areas.

  H.   Common-Use Field Office: Provide an insulated, weathertight, air-conditioned field of-
       fice for use as a common facility by all personnel engaged in construction activities; of
       sufficient size to accommodate required office personnel and meetings of 10 persons at
       Project site. Keep office clean and orderly.

  I.   Storage Sheds: Provide sheds sized, furnished, and equipped to accommodate materials
       and equipment involved, including temporary utility services. Sheds may be open shel-
       ters or fully enclosed spaces within building or elsewhere on-site.

3.4    SECURITY AND PROTECTION FACILITIES INSTALLATION

  A.   Environmental Protection: Provide protection, operate temporary facilities, and conduct
       construction in ways and by methods that comply with environmental regulations and
       that minimize possible air, waterway, and subsoil contamination or pollution or other
       undesirable effects. Avoid using tools and equipment that produce harmful noise. Re-
       strict use of noisemaking tools and equipment to hours that will minimize complaints
       from persons or firms near Project site.

  B.   Stormwater Control: Provide earthen embankments and similar barriers in and around
       excavations and subgrade construction, sufficient to prevent flooding by runoff of
       stormwater from heavy rains.

  C.   Tree and Plant Protection: Install temporary fencing located outside the drip line of
       trees to protect vegetation from construction damage. Protect tree root systems from
       damage, flooding, and erosion.

  D.   Barricades, Warning Signs, and Lights: Comply with standards and code requirements
       for erecting structurally adequate barricades. Paint with appropriate colors, graphics,
       and warning signs to inform personnel and public of possible hazard. Where appropriate
       and needed, provide lighting, including flashing red or amber lights.

  E.   Temporary Enclosures: Provide temporary enclosures for protection of construction, in
       progress and completed, from exposure, foul weather, other construction operations,
       and similar activities. Provide temporary weathertight enclosure for building exterior.
       1.    Vertical Openings: Close openings of 25 sq. ft. or less with plywood or similar
             materials.
       2.    Horizontal Openings: Close openings in floor or roof decks and horizontal sur-
             faces with load-bearing, wood-framed construction.

TEMPORARY FACILITIES AND CONTROLS                                                      01500 - 6
KONA VOR DEMOLITION


       3.    Install tarpaulins securely using fire-retardant-treated wood framing and other ma-
             terials.

  F.   Temporary Partitions: Erect and maintain dustproof partitions and temporary enclosures
       to limit dust and dirt migration and to separate areas from fumes and noise.

  G.   Temporary Fire Protection: Install and maintain existing and temporary fire-protection
       facilities of types needed to protect against reasonably predictable and controllable fire
       losses. Comply with NFPA 241.
       1.     Provide fire extinguishers, installed on walls on mounting brackets, visible and
              accessible from space being served, with sign mounted above.
              a.     Field Offices: Class A stored-pressure water-type extinguishers.
              b.     Other Locations: Class ABC dry-chemical extinguishers or a combination
                     of extinguishers of NFPA-recommended classes for exposures.
              c.     Locate fire extinguishers where convenient and effective for their intended
                     purpose; provide not less than one extinguisher on each floor at or near each
                     usable stairwell.
       2.     Store combustible materials in containers in fire-safe locations.
       3.     Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire-
              protection facilities, stairways, and other access routes for firefighting. Prohibit
              smoking in hazardous fire-exposure areas.
       4.     Supervise welding operations, combustion-type temporary heating units, and
              similar sources of fire ignition.
       5.     Permanent Fire Protection: At earliest feasible date in each area of Project, com-
              plete installation of permanent fire-protection facility, including connected ser-
              vices, and place into operation and use. Instruct key personnel on use of facilities.
       6.     Develop and supervise an overall fire-prevention and first-aid fire-protection pro-
              gram for personnel at Project site. Review needs with local fire department and
              establish procedures to be followed. Instruct personnel in methods and proce-
              dures. Post warnings and information.
       7.     Provide hoses for fire protection of sufficient length to reach construction areas.
              Hang hoses with a warning sign stating that hoses are for fire-protection purposes
              only and are not to be removed. Match hose size with outlet size and equip with
              suitable nozzles.
       8.     Limit smoking to designated areas.

3.5    OPERATION, TERMINATION, AND REMOVAL

  A.   Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste
       and abuse, limit availability of temporary facilities to essential and intended uses.


END OF SECTION 01500




TEMPORARY FACILITIES AND CONTROLS                                                        01500 - 7
KONA VOR DEMOLITION




SECTION 02051 - REMOVAL OF FUEL STORAGE TANKS

GENERAL

1.1    SUMMARY

  A.   Applicable provisions of Division 1 – General Requirements, Drawings, and other
       provisions and requirements of the Contract Documents apply to work of this Section.

  B.   This section includes labor, materials, services, and equipment necessary for the safe
       removal and disposal of one 1,000-gallon, co vault, diesel above ground storage tank
       (AST). The bid for the project shall include conforming to Hawaii Administrative
       Rules, Title 11, Department of Health, Chapter 281 and performing the following
       removal activities: site preparation which is to include excavation of the UST;
       permanent removal of the UST; excavation de-watering utilizing a trash pump (or
       similar), if necessary; and the disposal of the UST and any evacuated
       water/decontamination water; stockpiling of excavated backfill material on site for
       characterization; and disposal, if necessary, of contaminated soil. The Work for the
       project shall also include: performing all required State of Hawaii’s Department of
       Health (DOH) Closure soil/water sampling; conducting the required on-site closure site
       assessment activities; and submitting the UST Closure Report, if necessary. Work is to
       be accomplished in compliance with removal activities as specified in individual
       sections of these contract documents. In the event contamination is encountered, the
       Contracting Officer’s Representative (COR) shall be contacted immediately.

  C.   The Work also includes the removal of a 1000-gallon diesel above ground containment
       tank. The contractor shall comply with hauling and disposal regulations of the USEPA
       and SOH DOH. The contractor shall provide FAA the proof of compliance.

  D.
       1.   The bid for the project shall include the removal and disposal of all related piping
            and appurtenances to these tanks, including concrete pads, the emptying of the
            tanks, rinsing of the tank that is to be disposed of and the disposal of all
            rinse/decontamination water.
       2.   The tanks that are to be removed shall be transported to the SSC designed storage:

       3.   The actual storage location is to be coordinated with the FAA.

1.2    REFERENCE STANDARDS

  A.   API 1604, "Removal and Disposal of Used Underground Storage Tanks"

  B.   API 2003, "Protection Against Ignitions Arising Out of Static Lightning and Stray
       Currents"



REMOVAL OF FUEL STORAGE TANKS                                                          02051 - 1
KONA VOR DEMOLITION


  C.   API 2015, "Cleaning Petroleum Storage Tanks"

  D.   API 2217, "Guideline for Confined Space Work in the Petroleum Industry"

  E.   API 2219, "Safe Operating Guidelines for Vacuum Trucks in Petroleum Service"

  F.   OSHA, "Occupational Safety and Health Regulations for General Industry"
       (29 CFR 1910)

  G.   OSHA, "Occupational Safety and Health Regulations for Construction" (29 CFR 1926)

  H.   EPA, "General Regulations for Hazardous Waste Management (40 CFR 260)"

  I.   EPA, "Regulations for Identifying Hazardous Waste (40 CFR 261)"

  J.   EPA, "Underground Storage Tanks Regulations (40 CFR 280)"

  K.   Hawaii Administrative Rules, Title 11, Department of Health, Chapter 281.
       “Underground Storage Tanks”

1.3    SUBMITTALS (TO CONTRACTING OFFICER’S REPRESENTATIVE)

  A.   Before mobilization, submit necessary permits and certifications of waste haulers and
       disposal facilities with plans for disposing of the tank.

  B.   Submit copies of any permits required to be obtained by the Contractor to do the Work
       stated in this Section at the Project location.

  C.   Submit analytical laboratory name, address, and copy of State certification (if required)
       to analyze UST site assessment samples.

  D.   Submit certification outlined in Article 1.05 – Certifications.

  E.   Submit a copy of all hazardous waste manifests, bills of lading, disposal receipts,
       construction permits, material receipts, and quality control and analytical test reports.

1.4    CERTIFICATIONS

  A.   The Contractor shall certify the underground storage tank is properly destroyed.

1.5    REGULATORY REQUIREMENTS

  A.   All work must be accomplished in accordance with federal, state, and local
       requirements as well as accepted industry and safety standards. Before initiating work,
       the appropriate government agencies should be consulted concerning applicable
       regulatory and permit requirements. Provide the Hawaii DOH with written notification
       of intent to remove the AST 30 days prior to commencement of work.


REMOVAL OF FUEL STORAGE TANKS                                                             02051 - 2
KONA VOR DEMOLITION


  B.   29 CFR 1910.120 – Hazardous Waste Operations and Emergency Response.

  C.   Hawaii Administrative Rules, Title 11, Department of Health, Chapter 281 UST closure
       regulations and requirements.

  D.   City of Honolulu, Honolulu Fire Department (Fire Marshall), as appropriate. Each
       respective fire department must be notified, as required, by Contractor concerning the
       UST removal work.

  E.   Other State, County, and City regulations related to this Section.

1.6    PROJECT/SITE CONDITIONS

  A.   Conduct removal activities to minimize interference with facility operations.

  B.   Conduct operations with minimum interference to public or private thoroughfares.
       Maintain protected egress and access at all times.

  C.   Do not close or obstruct roadways and sidewalks without permits or permits from the
       Owner.

  D.   Protect improvements on adjoining properties and on Owner’s property.

  E.   Restore damaged improvements to their original condition, as acceptable to COR.

  F.   Protect existing trees and other vegetation indicated to remain in place, against
       unnecessary cutting, breaking or skinning of roots, skinning or bruising of bark,
       smothering of trees by stockpiling construction materials or excavated materials or
       grading equipment within drip line, excess foot or vehicular traffic, or parking of
       vehicles within drip line. Provide temporary guards to protect trees and vegetation to be
       left standing.

1.7    SEQUENCING AND SCHEDULING

  A.   All work activities shall be coordinated with other site activities. All subcontracted
       work shall be coordinated by Contractor, so as to provide a minimum delay to work
       activities.

1.8    HEALTH AND SAFETY

  A.   The Contractor shall develop a health and safety program to be implemented during the
       excavation, removal, decommissioning and related activities.

  B.   The Health and Safety Plan shall be in compliance with the applicable requirements in
       OSHA Regulations 29 CFR 1910 and 1926




REMOVAL OF FUEL STORAGE TANKS                                                          02051 - 3
KONA VOR DEMOLITION


PART 2 - PRODUCTS (NOT USED)


PART 3 - EXECUTION

3.1    EXAMINATION

  A.   Prior to the initiation of work, contingency plans should be prepared to address
       unanticipated conditions which may consist of, but are not limited to the following:
       contaminated soils and water, and hidden pavement profiles such as asphalt overlying
       concrete. Notify COR immediately upon discovery of any of these conditions.

3.2    AST PREPARATION

  A.   Prior to removal of the ASTs, locate and mark utilities.

  B.   Drain product piping into the tank, being careful to avoid any spillage. Remove product
       piping and appurtenances.

  C.   Remove liquids and residues from the tank using explosion-proof or air-driven pumps.
       Pump motors and suction hoses must be bonded to the tank or otherwise grounded to
       prevent electrostatic ignition hazards. It may be necessary to use a hand pump to
       remove the last few inches of liquid from the bottom of the tank. If a vacuum truck is
       used for removal, the area of operation for the vacuum truck must be vapor-free. The
       truck shall be located upwind from the tank and outside the path of probable vapor
       travel. The vacuum pump exhaust gases shall be discharged through a hose of adequate
       size and length downwind of the truck and work area.

3.3    AST REMOVAL

  A.   Prior to removal of the tank that is to be disposed of, clean the tank by opening all
       accessible tank inlets and rinsing with a high-pressure water sprayer using water or a
       water and detergent mixture, if necessary. Collect rinsate in appropriate containers and
       dispose in accordance with applicable regulations.

  B.   Estimate the dimensions and approximate weight of the tanks in order to verify that the
       hoisting equipment is adequate to safely lift the tank, including but not limited to, the
       crane or trackhoe, hoisting, slings, or cables. Select the equipment to satisfy the safety
       factors for load limits and rated capacity established in OSHA Regulations 29 CFR
       1926.550 (Subpart N).

  C.   As applicable, the operator shall verify the location of overhead utilities and provide
       sufficient clearance to minimize the risk of damaging the wire and subsequent
       electrocution of the operator. Any overhead wire shall be considered to be energized
       until a qualified agent has locked out and tagged the distribution system. Verify that
       applicable overhead lines have been de-energized before work begins.


REMOVAL OF FUEL STORAGE TANKS                                                           02051 - 4
KONA VOR DEMOLITION


  D.   The ASTs that are to be relocated shall be rendered non-explosive by purging the tank
       by one of the following methods: inert gas (such as carbon dioxide or nitrogen), dry ice
       using approximately 1.5 pounds per 100 gallons of tank capacity or combination of the
       above.

  E.   After the tanks have been rendered non-explosive and before it is moved, temporarily
       plug or cap all accessible holes. One plug shall have a 1/8-inch vent hole to prevent the
       tanks from being subjected to excessive differential pressure caused by temperature
       changes. The tanks shall always be positioned with this vent plug on top of the during
       subsequent transport and storage.

  F.   Pipe trench excavations shall be backfilled and regraded in accordance with the final
       grading plans.

3.4    DISPOSAL

  A.   Obtain approval from COR prior to disposal of all waste generated such as the tank,
       contaminated soil and water in accordance with applicable federal, state, and local
       regulations. Obtain required permits and manifests for transportation and disposal of the
       tanks and any impacted soil and water.

  B.   It shall be the responsibility of the Contractor to perform any sampling and analyses
       required to characterize any free liquids or solids in conformance with all applicable
       state and county waste disposal regulations, prior to disposal. The tank may be taken to
       a scrap metal dealer, if permissible under state and local regulations.

  C.   Additional cost for the disposal of contaminated materials (i.e., soil and groundwater)
       shall be in accordance with the provisions of the BID FORM, Unit Rate Prices for Extra
       Work.

3.5    SITE ENVIRONMENTAL ASSESSMENT

  A.   Kona, HI Project Site:
       1.   Notify the Hawaii Dept. of Health at least ten (10) days prior to UST permanent
            closure to schedule an on-site closure inspection.


END OF SECTION 02051




REMOVAL OF FUEL STORAGE TANKS                                                          02051 - 5
KONA VOR DEMOLITION




SECTION 02080 - ASBESTOS ABATEMENT


PART 1 - GENERAL

1.1    SUMMARY

  A.   Applicable provisions of Division 1 - General Requirements, Drawings, and other
       provisions and requirements of the Contract Documents apply to work of this Section.
       This specification is being included as part of the bid package to be followed for the
       removal of asbestos that would be disturbed during the course of the project.

  B.   This Section includes the removal, control and disposal of friable and nonfriable
       asbestos containing materials (ACM) which will be encountered during the KONA
       VOR building demolition located at the VOR facility in KONA, Hawaii. The work
       includes, but is not limited to: the construction of temporary enclosures to isolate the
       work area, the establishment of negative-air pressure within the isolated work area, the
       removal of ACM from the isolated work area, and the legal disposal of the removed
       ACM from FAA property. This specification covers ACM located in the VOR facility,
       exterior buildings located on FAA property, and the metal container located next to the
       VOR building.
         1.    Observe all existing conditions prior to submitting a bid. The Contractor is
               expected to have considered, and included in their bid, all aspects and liability
               of the existing conditions and their impact, particularly to cost and health and
               safety of workers and occupants, and proper function and operation of the
               facility. Additionally, the Contractor shall be aware of other work being
               performed. Failure to visit the site shall in no way relieve the Contractor from
               the necessity of furnishing materials or performing any work that may be
               required to complete the work in accordance with the Contract Documents
               without additional cost to the FAA. Additional site visits required by the
               Contractor shall be scheduled with the FAA.
        2.     The quantities and locations of ACM and the extent of work indicated are only
               best estimates that are limited by the physical constraints imposed by occupancy
               of the facility. Material information and quantities were obtained from previous
               site surveys performed by others. Accordingly, minor variations (plus or minus
               10 percent) in quantities of ACM within the limits of containment for each
               abatement area are considered as having no impact on contract sum and contract
               performance period. Locations of ACM different than indicated on drawings
               but within the limits of containment are considered as having no impact on
               contract sum and contract performance period. Where additional asbestos
               abatement work is required beyond the above variations, the contract sum and
               contract performance period will be adjusted under provisions of Division One
               of the Specifications.




ASBESTOS ABATEMENT                                                                     02080 - 1
KONA VOR DEMOLITION



  C.   ACM Locations - The following asbestos containing materials will be encountered in
       the KONA VOR demolition. Refer to the hazardous material survey report prepared by
       RMCI dated May 1997 for ACM locations.

  Asbestos Material:
        1.   Equipment room – 26 sq ft of non-friable 9”x9” green floor tile (under
             equipment rack.
        2.   Equipment room – 26 sq ft of non-friable 9”x9” green floor tile mastic (under
              equipment racks)1’
        3.    Equipment room – 517 sq ft of non-friable floor tile mastic (under tan patterned
              floor tile)
        4.    Exterior – non-friable penetration caulk
        5.    Exterior – non-friable vent frame caulk
        6.    Lavatory – 16 sq ft of non-friable 1’ x 1’ light brown streaked floor tile
        7.    Lavatory – 16 sq ft of non-friable 1’ x 1’ light brown streaked floor tile mastic
        8.    Pull box – 3 insulators
        9.    Roof 803 sq ft of roofing materials
        10. VOR Non-friable floor leveler

1.2    REFERENCE STANDARDS

  A.   The current issues of the following documents in effect on the date of Invitation For
       Bids form a part of this specification and are applicable to the extent specified herein.
       Work shall conform to applicable federal, state and local government regulations and
       to the requirements specified in these Contract Documents. Whenever inconsistencies
       occur between the referenced materials, the more stringent shall apply. The intent of
       these documents is to verify the Work is conducted at the highest level of safety.

  B.   American National Standards Institute (ANSI)
       1.    ANSI Z9.2 (1979; R 1991) Fundamentals Governing the Design and
                                            Operation of Local Exhaust Systems
       2.    ANSI (1989; Errata; Z87.1a) Occupational and Educational Eye and Face
                                            Protection
       3.    ANSI Z88.2 (1992)              Respiratory Protection
       4.    ANSI Z41.1 (1967)              Safety Shoes
       5.    ANSI Z89.1 (1981)              Hard Hats

  C.   American Society for Testing and Materials (ASTM)
       1.    ASTM C 732 (1995)            Aging Effects of Artificial Weathering on Latex
                                          Sealants
       2.    ASTM D 522 (1993a)           Mandrel Bend Test of Attached Organic Coatings
       3.    ASTM D 1331 (1989)           Surface and Interfacial Tension of Solutions of
                                          Surface-Active Agents
       4.    ASTM D 2794 (1993)           Resistance of Organic Coatings to the Effects of
                                          Rapid Deformation (Impact)



ASBESTOS ABATEMENT                                                                      02080 - 2
KONA VOR DEMOLITION



       5.    ASTM D 4397 (1996)        Polyethylene     Sheeting     for    Construction,
                                       Industrial, and Agricultural Applications
       6.    ASTM E 84 (1996a)         Surface Burning Characteristics of Building
                                       Materials ASTM E 96 (1995), Water Vapor
                                       Transmission of Materials
       7.    ASTM E 119 (1998)         Fire Tests of Building Construction and
                                       Materials
       8.    ASTM E 736 (1992)         Cohesion/Adhesion of Sprayed Fire-Resistive
                                       Materials Applied to Structural Members
       9.    ASTM E 1368 (1997)        Visual Inspection of Asbestos Abatement
                                       Projects
       10.   ASTM D 2986 (1995a)       Evaluation of Air Assay Media by the
                                       Monodisperse DOP (Dioctyl Phthalate) Smoke
                                       Test

  D.   Code of Federal Regulations (CFR)
       1.    29 CFR
              Part 1910 Occupational Safety and Health Regulations.
              Subpart G Occupational Health and Environmental Control.
              1910.132    Personal Protective Equipment.
              1910.134    Respiratory Protection.
              Subpart J   General Environmental Controls
              1910.141    Sanitation.
              1910.145    Specifications for Accident Prevention Signs and Tags.
              Subpart S Electrical.
              Subpart Z Toxic and Hazardous Substances
              1910.1000 Air Contaminants.
              1910.1001 Asbestos
              1910.1020 Access to Employee Exposure and Medical Records.
              1910.1200 Hazard Communication.
       2.    Part 1926 Safety and Health Regulations for Construction.
              Subpart C General Safety and Health Provisions.
              Subpart D Occupational Health and Environmental Controls.
              1926.59     Hazard Communication For Construction.
              Subpart E Personal Protective and Life Saving Equipment.
              Subpart Z Toxic and Hazardous Substances.
              1926.1101 Asbestos.
              Appendix F Work Practices and Engineering Controls for Major Asbestos
                          Removal, Renovation, and Demolition Operations.
              Appendix H Substance Technical Information for Asbestos.
              Appendix I Medical Surveillance Guidelines for Asbestos.
        3.   40 CFR
              Part 61     National Emission Standards for Hazardous Air Pollutants.
              Subpart A General Provisions.

ASBESTOS ABATEMENT                                                               02080 - 3
KONA VOR DEMOLITION



              Subpart M    National Emission Standard for Asbestos.
              Part 261     Identification and Listing of Hazardous Waste.
                           (Resource Conservation and Recovery Act, RCRA)
              Part 262     Standards Applicable to Generators of Hazardous Waste.
              Part 302.4   Designation of Hazardous Substances.
              Part 763     Asbestos-Containing Materials in Schools; Final Rule and Notice
                           (10/30/87).
        4.    49 CFR
              Part 172     Use of Hazardous Materials Tables & For Communication.
              Part 172.01 Hazardous Materials Table (Part 172, Subpart B, Appendix A).
              Part 173     Shippers - General Requirements for Shipments and Packaging.
              Part 173.24 General Requirements for Packaging and Packages.
              Part 173.216 Asbestos, Blue, Brown or White.
              Part 176     Carriage by Vessel.
              Part 178     Packaging.

  E.   National Institute for Occupational Safety and Health (NIOSH). Department of Health
       and Human Services
        1.   Method 7400 Fibers.
        2.   Method 7402 Asbestos Fibers

  F.   National Fire Protection Association (NFPA)
       1.    70             National Electrical Code
       2.    701            Standard Method of Fire Tests for Flame-Resistant Textiles and
                            Films.

  G.   Compressed Gas Association (CGA)
        1.  CGA G-7      Compressed Air for Human Respirators
        2.  CGA G-7      Commodity Specifications for Air

  H.   Underwriters Laboratories (UL)
        1.   UL 586       High-Efficiency Particulate Air Filter Units

  I.   Other Standards
        1.    National Sanitation Foundation Class II (Laminar Flow) Biohazard Cabinetry

  J.   Federal Aviation Administration (FAA) Documents
       1.     Article 77 Agreement Between DOT/FAA and the National Air Traffic
                           Controllers Association.
       2.     Article 52      Agreement Between DOT/FAA and the Professional Airway
                              System Specialists (PASS).
       3.     Order 1050.20 Airway Facilities Asbestos Control.
       4.     Order 3910.5    Asbestos Control.
       5.     PASS MOU        Memorandum of Understanding Between PASS and the FAA.



ASBESTOS ABATEMENT                                                                 02080 - 4
KONA VOR DEMOLITION



       6.     NATCA MOU Memorandum of Understanding Between NATCA and the
                        FAA.

1.3    DEFINITIONS

  A.   The following terms used in the text shall be defined as follows:
        1.    ACRP:        Abatement, Containment, and Removal Plan, submitted by the
              Contractor and subject to COR approval, clearly stating and scheduling the
              Work, identifying the Levels of Work required at each area, and identifying the
              safety, removal and disposal requirements for Work at each area. ACRP shall
              include signs, labels and related warning devices for identifying hazardous
              surfaces, areas and conditions to workers, occupants, and the general public.
        2.    Adequately Wet. A term as defined in 40 CFR 61, Subpart M and EPA 340/1-
              90-019 that means to sufficiently mix or penetrate with liquid to prevent the
              release of particulates. If visible emissions are observed coming from asbestos-
              containing material (ACM), then that material has not been adequately wetted.
              However, the absence of visible emissions is not sufficient evidence of being
              adequately wetted.
        3.    Amended Water. Water containing a wetting agent or surfactant with a
              maximum surface tension of 29 dynes per square centimeter when tested in
              accordance with ASTM D 1331.
        4.    APM: Asbestos Project Manager, contracted as a third party to the FAA, to
              perform inspections and air monitoring.
        5.    Asbestos Containing Material. Any material containing more than one percent
              asbestos by volume. For purposes of these specifications, ACM includes
              presumed asbestos-containing material (PACM) as defined by 29 CFR
              1926.1101.
        6.    Asbestos Regulated Work Area. An area established to demarcate areas where
              Class I, II, and III asbestos work is conducted, and any adjoining area where
              debris and waste from such asbestos work accumulates; and a work area where
              the airborne concentration of asbestos fibers exceeds, or has a possibility to
              exceed, the permissible exposure limit.
        7.    Category I Non-friable ACM. Asbestos-containing packings, gaskets, resilient
              floor coverings, and asphalt roofing products containing more than 1 percent
              asbestos by volume as determined using the method specified in appendix A,
              subpart F, 40 CFR 763, that cannot be crumbled pulverized or reduced to
              powder by hand pressure, when dry.
        8.    Category II Non-friable ACM. Any material, excluding Category I non-friable
              ACM, containing more than 1 percent asbestos by volume as determined using
              the methods specified in appendix A, subpart F, 40 CFR 763, section 1,
              Polarized Light Microscopy that, when dry, cannot be crumbled, pulverized, or
              reduced to powder by hand pressure.
        9.    Certified Industrial Hygienist (CIH). An Industrial Hygienist certified in the
              comprehensive practice of industrial hygiene by the American Board of
              Industrial Hygiene.


ASBESTOS ABATEMENT                                                                    02080 - 5
KONA VOR DEMOLITION



        10.   Class I Asbestos Work. Activities involving the removal of thermal system
              insulation (TSI) and surfacing ACM.
        11.   Class II Asbestos Work. Activities involving the removal of ACM that is not
              thermal system insulation or surfacing material. This includes, but is not
              limited to, the removal of asbestos-containing wallboard, floor tile and sheeting,
              siding shingles, and construction mastic.
        12.   Class III Asbestos Work. Repair and maintenance operations where ACM,
              including TSI and surfacing ACM, is likely to be disturbed. Operations may
              include drilling, abrading, cutting a hole, cable pulling, crawling through
              tunnels or attics and spaces above the ceiling, where asbestos or asbestos-
              containing debris is actively disturbed. Removal of small amounts of ACM that
              would fit into a single 60x60-inch glove bag or disposal bag may be classified
              as a Class III job.
        13.   Class IV Asbestos Work. Maintenance and custodial construction activities
              during which employees contact but do not disturb ACM and activities to clean
              up dust, waste and debris resulting from Class I, II, and III activities. This may
              include dusting surfaces where ACM waste and debris and accompanying dust
              exists and cleaning up loose ACM debris from TSI or surfacing ACM following
              construction.
        14.   Competent Person. On all construction worksites the contractor shall designate
              a competent person having the qualifications and authority for ensuring worker
              safety and health as required by 29 CFR 1926.20 and for overseeing asbestos-
              related work as required by 29 CFR 1926.1101. The duties of the competent
              person include, but are not limited to, the following: establishing the negative
              pressure enclosure, ensuring its integrity, controlling entry into and exit from
              the enclosure, and ensuring workers wear required personal protective
              equipment and are trained in the use of hygiene facilities, work practices, and
              decontamination procedures specified in this specification and applicable
              regulations.
        15.   COR: Contracting Officer’s Representative
        16.   Friable ACM. A term as defined in 40 CFR 61, Subpart M and EPA 340/1-90-
              018 that means any material containing more than 1 percent asbestos by volume
              as determined using the method specified in 40 CFR 763, Appendix A, Subpart
              F, Section 1, Polarized Light Microscopy, that when dry, can be crumbled,
              pulverized, or reduced to powder by hand pressure.
        17.   High Efficiency Particulate Air (HEPA) filter. A filter capable of trapping and
              retaining at least 99.97 percent of all mono-dispersed particles of 0.3
              micrometers in diameter.
        18.   Immediately: In this Section, the definition of this term shall be as follows:
              When the contractor is on-site, immediately refers actions required to take place
              within 15 minutes of being notified. When the contractor is off-site,
              immediately refers to actions required to take place within 2 hours of being
              notified.
        19.   Presumed Asbestos-Containing Material (PACM). Thermal system insulation
              and surfacing material found in buildings constructed no later than 1980.


ASBESTOS ABATEMENT                                                                     02080 - 6
KONA VOR DEMOLITION



        20.   Permissible Exposure Limit (PEL). OSHA PELs are worker exposure limits
              regulating the amount or concentration of a substance in air that shall not be
              exceeded. (1) An airborne concentration of asbestos of 0.1 fibers per cubic
              centimeter of air (f/cc) as an eight- (8) hour time weighted average (TWA). (2)
              An airborne concentration of asbestos of 1.0 f/cc as averaged over a sampling
              period of thirty (30) minutes (Excursion Limit).
        21.   Time-Weighted Average (TWA). The TWA is an 8-hour time weighted
              average concentration of airborne asbestos fibers (longer than 5 micrometers)
              per cubic centimeter of air that represents the employee's 8-hour workday as
              determined by Appendix A of 29 CFR 1926.1101.

1.4    SUBMITTALS

  A.   Contractor Identification: The Asbestos Abatement Contractor shall be licensed by the
       State of Hawaii for the purpose of removal, encapsulation, enclosure, demolition, and
       maintenance of structures of components covered by or composed of asbestos
       containing materials.
        1.    Company name and address (street and mailing if different).
        2.    Name of individual supplying information.
        3.    Name of parent company, if any.
        4.    Address of office responsible for this project.
        5.    Telephone number.

  B.   Insurance:
        1.    Insurance carrier and coverage.
        2.    Surety company.
        3.    Special coverage specifically regarding asbestos.
        4.    Contractor shall have at a minimum the following insurance amounts.
             General Liability                 $5 million per occurrence
             Contractual Liability             $1 million per occurrence
             Automobile Liability              $1 million per occurrence for bodily injury
                                               $50,000 per occurrence for property damage
             Property Damage Liability         $1 million per occurrence
             Worker’s Compensation             $1 million per occurrence
             Pollution Liability                    $1 million per occurrence
        5.    The policies evidencing required insurance shall be written on a comprehensive
              form of policy listing the FAA as the certificate holder and shall not contain
              pollution exclusions. The policies shall also contain an endorsement to the
              effect that any cancellation or any material change adversely affecting the
              FAA’s interest shall not be effective for such period as the laws allow or until
              30 days after the insurer or the Contractor gives written notice to the CO,
              whichever period is longer. Each policy shall include a provision that the FAA
              will be notified at least 30 days in advance of the effective date of any reduction
              in coverage or cancellation.


ASBESTOS ABATEMENT                                                                      02080 - 7
KONA VOR DEMOLITION



  C.   Staff:
        1.    Number of full-time company employees.
        2.    Names of full-time field supervisory personnel, and years of asbestos removal
              experience.
        3.    Names of part-time field supervisory personnel, and years of asbestos removal
              experience.
        4.    Number of full-time laborers.
        5.    Number of part-time laborers.
        6.    Name of employees union, if any.
        7.    Usual ratio of supervisory to labor personnel used.

  D.   Experience:
        1.    Briefly describe company history.
        2.    Provide evidence verifying that the company has a minimum of three (3) years
              of successful abatement experience working in the State of Hawaii.
        3.    Provide a representative list (at least three projects) of successful asbestos
              abatement projects working in occupied environments, such as in hospitals or
              computer centers. List project name, date, size, duration, removal cost,
              references and telephone numbers for each project.
        4.    State average yearly dollar volume of asbestos removal work over the past two
              years.

  E.   Regulatory:
        1.   List and explain warnings or citations received from Federal, State or Local
             Regulatory Agencies related to asbestos abatement activities. Include project
             name, date and resolution.
        2.   List assessed penalties, liquidated damages or schedule overruns and resolutions
             which occurred. Include contract terminations.
        3.   List projects where removal activities were halted by the owner, architect or
             consultant. State project name, date, reason for shutdown and resolutions.
        4.   List asbestos-related legal proceedings/claims in which the company (or
             employees scheduled to participate in this project) have participated or are
             currently involved. Include descriptions of role, issue and resolution to date.

  F.   Medical Requirements (29 CFR 1926.1101):
        1.   Provide a copy of the company's Medical Surveillance Program.
        2.   Provide documentation from a physician that employees or agents who may be
             exposed to airborne asbestos in excess of background levels have been
             medically monitored to determine whether they are physically capable of
             working while wearing the respirator required without suffering adverse health
             effects. In addition, the Contractor shall document that personnel have received
             medical monitoring as required in OSHA 29 CFR 1926.1101.                    This
             documentation shall be submitted for each employee entering the regulated
             (removal) area.

  G.   Asbestos Training:


ASBESTOS ABATEMENT                                                                   02080 - 8
KONA VOR DEMOLITION



        1.    Provide a copy of the company's training program for supervisors and laborers.
              The program shall include, but is not limited to, how often training is
              conducted, who conducts the training, when it is conducted, what the duration
              of the program is and how documentation of training is accomplished.
        2.    The Contractor shall submit signed certificates for each employee stating that
              each employee has:
             a.    Received training in the proper handling of materials that contain asbestos.
             b.    Understands the health implications and risks involved (including the
                   illnesses possible from exposure to airborne asbestos fibers).
             c.    Understands the use and limits of the respiratory equipment to be used.
             d.    Understands the results of monitoring of airborne quantities of asbestos as
                   related to health and respiratory equipment.
             e.    Understands the project scope and has been given project specific training.

  H.   Respiratory Protection:
        1.    Provide a copy of the company's respiratory protection training program.
        2.    Provide a copy of a passing and current (within the last 12 months) fit test for
              the employees with the respirator that will be used for the abatement.

  I.   Health and Safety Program: Provide a copy of the company's health and safety
       program.

  J.   Project Personnel
        1.    Provide number of full-time laborers that will be assigned to this project.
        2.    Provide number of crews and shifts for this project.

  K.   Asbestos Abatement Plan: Submit three (3) copies of a detailed plan and schedule of
       the work procedures to be used in the removal of asbestos containing materials to the
       COR within thirty (30) days from award of contract. The abatement plan shall be
       completed and signed by a CIH with at least two (2) years of asbestos experience and
       that is thoroughly knowledgeable in Class I asbestos abatements and is a Certified
       Asbestos Project Designer and a licensed Project Supervisor. The plan shall include:
         1.    A physical description of the work area;
         2.    A detailed work area layout plan showing the location of all containment walls
               to be erected, dust partitions, buffer zones, decontamination/bag-out units,
               placement of negative air machines, temporary scaffolding, decking, access
               ladders, stairways, and elevators (interior & exterior), as needed;
         3.    A description of the material to be removed and approximate quantity;
         4.    A description of the local exhaust ventilation systems to be used and air change
               calculations, including evidence that the negative air machines have an
               automatic restart feature;
         5.    A schedule for shutting down and locking out electrical power, heating and
               ventilation;
         6.    Interface of trades involved in the construction and sequencing of asbestos
               related work;
         7.    Personal hygiene procedures;
         8.    Labeling procedures;
ASBESTOS ABATEMENT                                                                      02080 - 9
KONA VOR DEMOLITION



        9.    A description of personal protective equipment and clothing to be worn by
              employees;
        10.   A description of the local exhaust ventilation systems to be used;
        11.   A description of work practices to be observed by employees;
        12.   A description of the method to be used to remove the asbestos containing
              material;
        13.   A description of the wetting and lockdown agents to be used;
        14.   Material Safety Data Sheets (MSDS) for all hazardous chemicals, including the
              wetting and lockdown agents, mastic removers, spray adhesives, etc.;
        15.   A description of the decontamination and bag out procedures;
        16.   A detail of the decon/bag-out chamber units with the “Z-flap” construction;
        17.   A description of the mode of transport and legal disposal of waste material.
              Provide the FAA with the proper Names, Addresses, Primary Contacts,
              Telephone numbers, all-applicable Federal, State and local licenses and
              operating permits, and insurance certificates;
        18.   A list of employees, including the Abatement Superintendent, who will
              participate in the project, including delineation of experience, training and
              assigned responsibilities during the abatement;
        19.   A contingency plan and emergency procedures for unexpected conditions,
              including local emergency phone numbers;
        20.   Provide a time line for the asbestos abatement;
        21.   Description of hazard sign text;
        22.   A sample copy of the waste manifest to be utilized for the project.

  L.   Laboratories: Submit documentation that the laboratory to be used by the Abatement
       Contractor for Personnel Samples on this contract is accredited, and will remain
       accredited for the duration of the project, by the American Industrial Hygiene
       Association (AIHA) for Phase Contrast Microscopy and has successful completion in
       the last four rounds in the American Industrial Hygiene Association (AIHA)
       Proficiency Analytical Testing (PAT) Program. All technicians analyzing asbestos
       samples shall be a current member in the Asbestos Analyst Registry (AAR).

  M.   Certifications:      Submit manufacturer’s certification that vacuums, ventilation
       equipment and other equipment required to contain airborne asbestos fibers conform
       with ANSI Z9.2 and NSF 49. All equipment shall be certified onsite by the APM prior
       to the initiation of abatement activities.

  N.   Miscellaneous: Submit copies of the Notification to the EPA, Asbestos Abatement
       Contractor's State License for Asbestos Removal, Hazardous Waste Manifest Form,
       and manufacturer’s data on materials used at the site.

  O.   Submittal Notarization: Sign and date submittal, indicating name and title of person
       signing.

  P.   Title to Materials: Provide all required Federal, State and Local documentation
       regarding the transportation and disposal of ACM and asbestos contaminated materials
       at the earliest possible time.

ASBESTOS ABATEMENT                                                                02080 - 10
KONA VOR DEMOLITION



  Q.   Industrial Hygienist.
        1.    Provide the name, address, telephone number, and copies of the CIH’s current
              ABIH and Asbestos Project Designer certifications and resume documenting at
              least two years of asbestos abatement experience.
        2.    Provide the names, addresses, telephone numbers, resumes and current
              certifications of additional IHs and IHTs who will be assisting the CIH in
              performing on-site tasks.

1.5    SYSTEM DESCRIPTION

  A.   The work consists of the containment and removal of asbestos containing materials.
       Asbestos is a material which can cause a serious health risk to humans. The work is
       governed by a body of local, state and federal rules, regulations and laws. The
       Contractor agrees by accepting the contract that their company is fully knowledgeable
       of this information and will bear full responsibility for the health and safety of his
       workers, provide protection to FAA's employees and invitees, and third parties, who
       come in contact with the work site.

  B.   The FAA will employ an independent Asbestos Project Manager (APM). The APM
       will be responsible for monitoring the Contractor in conformance of the Contract
       Documents, and for conducting area air sampling.

  C.   The Contractor shall cooperate with the COR and the APM. This cooperation shall
       include allowing access to the work areas to allow for visual and air monitoring,
       collecting samples, providing requested data on personnel, equipment, scheduling and
       facilitating FAA's monitoring of the work.

  D.   The Contractor shall not allow anyone access to the site who is not authorized by FAA
       to enter the regulated area.

  E.   The Contractor shall provide personal protective equipment for three (3) authorized
       persons including full protective clothing without charge. Protective clothing supplied
       by Contractor shall be identical to or of better quality than the Contractor provides for
       his/her own employees. The Contractor shall allow full use of facilities by the APM.

  F.   The Contractor is responsible for maintaining a log of all personnel who enter the work
       place. A copy of logs shall be submitted to the APM on a weekly basis. Contractor
       shall have logs available for review by the COR/APM.

  G.   The Contractor shall install warning labels in prominent locations adjacent to asbestos
       containing material identified in this specification to remain. The labels shall be
       installed before demolition or construction starts under this contract. The labels will
       remain in place, after completion of abatement work, as the property of the FAA. The
       labels shall be printed in large, bold letters on a contrasting background and conform to
       the requirements of 29 CFR 1926.1101 and contain the following information:

                                         DANGER

ASBESTOS ABATEMENT                                                                    02080 - 11
KONA VOR DEMOLITION




                            CONTAINS ASBESTOS FIBERS

                               AVOID CREATING DUST

                      CANCER AND LUNG DISEASE HAZARD

1.6    PROJECT CONDITIONS

  A.   The VOR and surrounding buildings will be unoccupied and are scheduled for
       demolition.

1.7    WORK BY FAA

  A.   Environmental monitoring and sample analysis (by separate contract).

1.8    NOTIFICATION

  A.   The Contractor is responsible for filing the necessary asbestos related
       notifications and permits prior to and following abatement. The Contractor shall
       notify the COR ten (10) working days prior to the start of the asbestos removal
       operation.


1.9    HOURS OF WORK

  A.   The Contractor shall strictly adhere to work hours as specified in Division One.
       Deviations shall be pre-approved, in writing, by the COR 48 hours in advance.

  B.   Request to change work hours or overtime proposed by the Contractor shall require
       COR’s written approval prior to implementing changes. The COR’s rejection of
       request for change shall not result in changing contract sum or extending contract time.

1.10   SCHEDULE OVERRUNS

  A.   If the work is behind the agreed time of completion, the COR shall deduct extra costs,
       including expenses, for APM services due to the overrun, from the final payment to the
       Contractor, in addition to compensation for damages identified in other parts of the
       contract documents.

1.11   PRECONSTRUCTION MEETING - ASBESTOS ABATEMENT

  A.   The FAA will schedule a preconstruction meeting after the Notice to Proceed. The
       minimum agenda will consist of the following:


ASBESTOS ABATEMENT                                                                   02080 - 12
KONA VOR DEMOLITION



        1.    Designation of responsible personnel and name the Asbestos Project Manager
              (APM). The APM will be retained as a third party, by the FAA, and shall have
              the authority and responsibility defined by the FAA.
        2.    Establishing chain of authority for routing and emergency communication.
              (The direction will be from the FAA, including the COR, Regional Office,
              safety personnel, FAA Certified Industrial Hygienist and the Facility Asbestos
              Coordinator and the Systems Management Office, in continual consultation
              with the APM.)
        3.    Tentative abatement schedule, as identified by the Contractor.
        4.    Critical work sequencing, scheduling.
        5.    Processing of field decisions and change orders.
        6.    Adequacy of distribution of Contract Documents.
        7.    Discuss procedures to be followed for Application for Payment.
        8.    Submittals: schedules, shop drawings, product data and samples, manufacturer's
              certifications of products, manpower reports, major equipment deliveries and
              priorities, procedures for maintaining record documents, use of FAA facilities
              by contractor (access, parking, office area, storage area, and waste load-outs),
              safety and first aid procedures, security procedures and housekeeping
              procedures.
        9.    Review emergency planning and procedures, as specified in Section 3.1.

1.12   PROJECT CLOSEOUT

  A.   Closeout Submittal: Upon completion of the work, the Contractor shall provide to the
       FAA, through the APM, a closeout submittal. The closeout submittal will consist of
       the following documents:
         1.    Written certification on final completion of the Work that Work complies with
               Contract Documents.
         2.    Certification that items on punch list issued at substantial completion have been
               completed or corrected and that tools, construction equipment and surplus
               materials have been removed from the site.
         3.    Contractor daily logs for abatement work.
         4.    Contractor entry/exit logs for each containment.
         5.    Copy of asbestos Waste Manifests for the project.
         6.    Copies of personal air monitoring results.
         7.    Copies of HEPA filter change logs for all HEPA equipment utilized during the
               project.

  B.   Application for Final Payment: In addition to the closeout submittal, the Contractor
       shall submit Application for Final Payment. FAA will process final statement for
       payment in accordance with Conditions of the Contract.




ASBESTOS ABATEMENT                                                                    02080 - 13
KONA VOR DEMOLITION



PART 2 - PRODUCTS

2.1    MATERIALS AND EQUIPMENT

  A.   Materials and products shall comply with the requirements of 29 CFR 1910.134 and 29
       CFR 1926.1101.

  B.   Polyethylene Sheeting: ASTM D2l03, 6 mils thick, flame-retardant. Sheeting shall
       meet flammability requirements of NFPA 701, and flame spread and smoke density
       requirements of ASTM E84.

  C.   Duct Tape: Pressure-sensitive adhesive tape, 3 mils (min.) thick by 2 or 3 inches wide,
       waterproof.

  D.   High Efficiency Particulate Air (HEPA) Filtered Vacuum: Vacuum(s) shall:
        1.   Be capable of removing 99.97% of the asbestos particles (0.3 microns or greater
             in diameter) from the air.
        2.   Be portable.
        3.   Be equipped with hoses of sufficient length to reach areas behind pipes, ducts
             and other obstacles.
        4.   Have new filters installed at the beginning of the project. The filters will be
             changed on a regular basis for the duration of the project.
        5.   Be tested and certified onsite by the APM in accordance with NSF-49.
        6.   Be removed from the FAA property immediately if they are found to be non-
             conforming.

  E.   HEPA Filtered Ventilation System: Portable ventilation system designed to exhaust
       and clean the air inside the enclosure prior to exhausting to the outside of the building.
       The units shall have at least three (3) filter stages, including readily accessible pre- and
       secondary filters, and a final filter which shall be a High Efficiency Particulate Air
       (HEPA) filter. The units shall:
        1.    Be capable of capturing particles having a diameter of 0.3 micrometers or
              greater in size with an efficiency of 99.97%.
        2.    Be equipped with the automatic restart feature.
        3.    Have new filters installed prior to the onset of abatement activities. The filters
              will be changed on a regular basis for the duration of the project.
        4.    Be located as far away from the fresh air intakes as possible.
        5.    Be tested and certified onsite by the APM prior to the onset of any abatement
              activities, in accordance with NSF 49.
        6.    Be removed from FAA property immediately if they are found to be non-
              conforming.

  F.   Redundant Negative Air Machines: The Contractor shall furnish and install at least
       one redundant negative air machine in EACH containment. The extra machine(s) shall
       serve as a back up in case one machine should happen to fail at any time during the
       asbestos abatement. The Contractor shall also have access to additional negative air
       machines in case the redundant machine(s) are not sufficient.

ASBESTOS ABATEMENT                                                                       02080 - 14
KONA VOR DEMOLITION



  G.   Ducts: All HEPA ventilation ducts from the negative air machines shall be constructed
       of new and unused reinforced tubing. The tubing shall consist of two sleeves, one
       sleeve may be plain polyethylene tubing and the other a wire reinforced tubing. The
       attachment of the ducts shall be spliced by means of sheet metal connectors in order to
       insure an adequate seal. The attachment of the ducts shall withstand the force from the
       machines for the entire duration of the project. The construction shall be inspected and
       approved by the APM prior to the start of abatement activities. The Contractors
       Superintendent will have the responsibility of inspecting the integrity of the exhaust
       ducts on a regular basis throughout the duration of the abatement activities.

  H.   Wetting Agent: Provide water to which a surfactant has been added. Use a mixture of
       surfactant and water which results in wetting of the asbestos-containing material and in
       retardation of fiber release during disturbance of the material, equal to or greater than
       that provided by the use of one ounce of a surfactant consisting of 50 percent
       polyoxyethylene ester and 50 percent polyoxyethylene ether mixed with five gallons of
       water.

  I.   Encapsulant: Provide an encapsulant/sealant which will be compatible with the existing
       surfaces, and one which will act as a suitable substrate for future sprayed-on
       fireproofing. Taint (or tint) the encapsulant with a contrasting color, to be approved by
       the COR, so as to identify coverage.

  J.   Airless Sprayer: Hand-pump type, pressure-can sprayer fabricated of non-conductive
       plastic, equipped with a wand at the end of a hose capable of delivering a stream or
       spray of liquid under pressure.

  K.   Respirators: Personal protective breathing equipment shall be in accordance with 29
       CFR 1910.134, and 29 CFR 1926.1101.

  L.   Signs and Labels: Signs and labels shall be provided in accordance with 29 CFR
       1910.145, 29 CFR 1910.1200, 29 CFR 1926.1101 and 40 CFR 61 subpart M.

  M.   Disposal Bags: Leak-tight, 6 mil thick clear polyethylene bags with appropriate hazard
       warning, per EPA regulations 40 CFR 61.150 (a) (1) (v) or OSHA requirement 29 CFR
       1926.1101.

  N.   Radios: The Contractor shall furnish and maintain at least three (3) sets of two-way
       radios for communication. The Contractor’s Abatement Superintendent shall use the
       radios to maintain constant contact with the COR. And adequacy test of the radios
       shall be conducted to verify clear, static free communications throughout the building.
       The purpose of the adequacy tests is to verify compatibility of the radios with existing
       FAA equipment so that there is no interference with FAA equipment or the control of
       air traffic. The radios shall maintain project control and immediately communicate
       information relating to air monitoring results and pressure differential readings.

  O.   Framing Lumber: Two inch by four-inch utility grade softwood, any commercially
       available specie. All framing lumber shall be fire treated per NFPA.

ASBESTOS ABATEMENT                                                                    02080 - 15
KONA VOR DEMOLITION



  P.   Miscellaneous Materials: Provide tangible supplies (such as coveralls, duct tape, soap,
       shampoo, towels, etc.), for persons entering the removal area. This includes FAA
       personnel, the APM and other persons approved for entry.

  Q.   Air Monitoring Equipment. The Contractor's CIH shall select and approve the personal
       air monitoring equipment to be provided and used by the contractor for evaluation of
       airborne asbestos fiber concentrations. The equipment shall include, but not be limited
       to:
         1.   Low-volume, battery powered, body-attachable, portable personal pumps with a
              power pack capable of sustaining the calibrated flow rate for a minimum of 10
              hours.
        2.    Standard 25-millimeter diameter, 0.8 micron pore size filters and cassettes in
              accordance with 29 CFR 1926, for personal air sampling.
        3.    A flow calibrator capable of calibration to within plus or minus 2 percent of
              reading over a temperature range of minus 20 degrees C (minus 4 degrees F) to
              plus 60 degrees C (140 degrees F) and traceable to a National Institute of
              Standards and Technology (NIST) primary standard.


PART 3 - EXECUTION

3.1    EMERGENCY PLANNING AND PROCEDURES

  A.   Emergency planning shall be developed by the Contractor and agreed to by the COR
       prior to abatement initiation. The emergency planning shall be coordinated with the
       facility’s contingency plan requirements. Upon approval, the emergency plan and
       procedures shall be reviewed with all responsible personnel in a meeting prior to
       abatement initiation.

  B.   Emergency procedures shall be in written form and prominently posted in the clean
       change area and equipment room of the worker decontamination area. Everyone, prior
       to entering the work area, shall be required to read and sign these procedures to
       acknowledge receipt and understanding of work site layout, location of emergency
       exits and emergency procedures. The Contractor shall review and designate
       containment area emergency exits in adequate number and location to safely exit
       workers in the event of the need to do so. Consideration shall be given to the resultant
       contamination, but as a second priority to life safety. The Contractor shall be
       responsible for required decontamination.

  C.   Emergency planning shall include written notification sent to police, fire and
       emergency medical personnel of planned abatement activities, work schedule, and
       layout of work area, particularly barriers that may affect response capabilities.

  D.   Emergency planning shall include considerations of fire, explosion, toxic atmospheres,
       electrical hazards, slips, trips and falls, confined spaces and heat related injury.
       Written procedures shall be developed and employee training in procedures shall be
       provided.

ASBESTOS ABATEMENT                                                                   02080 - 16
KONA VOR DEMOLITION



  E.   Emergency planning shall include a Hazard Communication Program (HAZCOM). A
       written HAZCOM program shall be established and implemented according to 29 CFR
       1926.59. Copies of Material Data Sheets (MSDS) for chemicals brought on-site by the
       Contractor shall be attached to the written HAZCOM Program.

  F.   Employees shall be trained in evacuation procedures in the event of work place
       emergencies:
        1.   For non-life threatening situations, employees injured or otherwise
             incapacitated shall be decontaminated following normal procedures, with
             assistance from fellow workers if necessary, before exiting the work place to
             obtain proper medical treatment.
        2.   For life-threatening injury or illness, worker decontamination shall be secondary
             after measures stabilize the injured worker. Remove workers from the work
             place and secure proper medical treatment prior to decontamination.

  G.   Telephone numbers of emergency response personnel shall be prominently posted in
       the clean change area and equipment room, along with the location of the nearest
       telephone.

  H.   Upon coordination with the COR, the Contractor shall clearly mark the exit paths
       within the enclosure for emergency egress. The Contractor shall use a fluorescent paint
       or tape and apply the markings no more than 24" above the floor surface.

  I.   Inspection by the COR: During asbestos work, the work will be subject to on-site
       inspection by the COR, who may be assisted by the APM, safety personnel or a
       Certified Industrial Hygienist.

  J.   Work Stoppage: If the Contractor encounters any problem conditions identified below,
       the Contractor shall cease all work and immediately notify the COR. The COR will
       immediately issue a "stop work" order to the Contractor for any of the reasons listed
       below. No work will be allowed to resume until the conditions stabilize and upon
       approval from the COR. Standby time required to identify and resolve the problem
       will be at the expense of the Contractor and may include the costs incurred by the
       extended efforts of the FAA's Monitoring Contractor.
         1.   If asbestos air monitoring results indicate the presence of airborne fibers to be
              greater than 0.02 f/cc above baseline outside the containment.
        2.    If the pressure differential inside the containment falls below 0.02 inches of
              water or above 0.05 inches of water beyond the design pressure differentials
              established in Section 2080.3.5 (B). The change in pressure differentials shall
              not exceed one (1) minute.
        3.    If excessive water accumulations appear or if water leakage is detected in areas
              adjacent to the removal area.
        4.    If the work is found to violate specified requirements.




ASBESTOS ABATEMENT                                                                   02080 - 17
KONA VOR DEMOLITION



3.2    GENERAL DESCRIPTION OF WORK

  A.   Comply with the requirements of these Specifications and ANSI Z9.2, 29 CFR
       1910.145, 29 CFR 1926.1101 and 40 CFR 61 and 763. The most stringent of codes
       shall apply. The following will be considered as the typical sequence to the asbestos
       abatement work. Refer to the following sections for specific procedures for the
       asbestos removal project.
        1.     Establishing Baseline TWA. Area monitoring, sufficient to establish a
               reference or baseline time-weighted average (TWA) for each abatement area,
               shall be accomplished by the FAA at least 10 days prior to the start of any
               construction activity.
        2.     Preparing the Work Area. Prepare the work area in accordance with Section
               2080.3.7 of these specifications. In addition, the containment must be able to
               withstand the project design pressure differentials of Section 2080.3.5 (B).
        3.     Establish a worker decontamination system and a waste and equipment
               decontamination system in accordance with Section 2080.3.6 of these
               Specifications.
        4.     Upon approval from the COR, initiate removal activities, cleaning and waste
               load-out.
        5.     Perform final cleaning, pass inspection from COR and initiate clearance testing.
        6.     Upon passing final clearance testing, restore work area to original conditions.

  B.   Daily Commencement of Work: The Contractor shall receive approval from the COR
       prior to initiating ANY work activities for the day, for the entire duration of the
       abatement project. The overnight samples need to be analyzed by the APM and
       approved by the FAA prior to any work activities commencing. The COR shall be
       onsite at all times that abatement activities are taking place. If the COR is not onsite,
       all abatement activities shall not commence or immediately cease.

  C.   Environmental Monitoring: Environmental monitoring for airborne fiber
       concentrations and pressure differential, and third party inspections will be
       accomplished by the APM, who will be under a separate contract with the FAA. This
       individual will respond directly to the COR.

  D.   Wet Removal: All ACM will be removed using an amended water wet removal method
       as recommended by the EPA and OSHA. The Contractor shall provide for the
       continual prevention of excessive water accumulation throughout the duration of the
       project.

  E.   Housekeeping: Essential parts of asbestos dust control are housekeeping and clean up
       procedures. Maintain surfaces of the asbestos control area free of accumulations of
       asbestos fibers. Give meticulous attention to restricting the spread of dust and debris.
       Keep waste from being distributed over the general area. Do not blow down the space
       with compressed air. The COR and/or APM will inspect the removal area daily for
       residual asbestos material on the floors and decks, and for the accumulation of dust.
       The Contractor will be required to re-clean all areas noted having visible emissions by
       the inspection.

ASBESTOS ABATEMENT                                                                    02080 - 18
KONA VOR DEMOLITION



  F.   Asbestos Abatement Superintendent: The Contractor shall designate a qualified
       employee as the Competent Person and Superintendent. This person MUST be onsite
       at all times before any abatement activities can be started. This person shall have direct
       supervisory experience for Class I asbestos abatement projects. A Competent Person is
       defined as an individual who is capable of identifying existing asbestos hazards in the
       workplace and selecting the appropriate control strategy for asbestos exposure, take
       prompt corrective measures to eliminate them and who is properly trained per 40 CFR
       763 and 29 CFR 1926.1101. The Competent Person shall have, at a minimum, three
       years of supervisory experience for asbestos abatements. The Superintendent shall
       perform the following:
        1.      Oversee all Contractor personnel performing any asbestos related work,
                including:
               a.    Licensed carpenters
               b.    Licensed electricians
               c.    Licensed mechanical workers
        2.      Oversee construction of all enclosures, including the worker decontamination
                chamber and the waste load-out chamber.
        3.      Verify the integrity of the enclosures and exhaust ducts on a daily basis.
        4.      Control entry to and exit from the removal area.
        5.      Supervise all employee exposure monitoring required by OSHA.
        6.      Verify the proper use of protective clothing and equipment.
        7.      Verify that all occupants of the removal area are properly trained and certified.
        8.      Verify the proper use of hygiene facilities and decontamination procedures.
        9.      Verify that all engineering controls are functioning per design.

  G.   Disposal Supervisor: The Contractor shall designate a qualified individual to oversee
       the following "clean-up", "housekeeping" and disposal tasks in accordance with these
       Specifications, specifically:
         1.    Continuous floor and horizontal surface clean up.
         2.    Continuous clean up of ACM debris.
         3.    Continuous collection and disposal of water build-up. No puddling or ponding
               of water will be tolerated.
         4.    Regular inspection of disposal procedures to verify conformance with this
               specification as well as all Federal, State and Local Laws.
         5.    This individual shall have no other duties and shall be responsible for the daily
               removal of ACM from the regulated area.

3.3    PERSONAL PROTECTIVE EQUIPMENT

  A.   Personal Protective Equipment (PPE): The Contractor shall provide PPE for workers,
       FAA representatives, APM and authorized visitors and shall include, at a minimum,
       full body and head coverings (i.e. Tyvek coveralls) as well as full face PAPR.
       Respiratory protection shall comply with 29 CFR 1910.134 and 29 CFR 1926.1101.




ASBESTOS ABATEMENT                                                                     02080 - 19
KONA VOR DEMOLITION



3.4    TEMPORARY FACILITIES AND UTILITIES

  A.   Field Office: The Contractor shall furnish the contractor's own temporary office space.
        The office shall be made available for use by FAA representatives, APM or authorized
       visitors.


  B.   Temporary Electric: The Contractor shall provide and maintain a specified secondary
       electrical power center for asbestos removal operations throughout the abatement
       period. The Contractor shall provide:
        1.     Main distribution panel with a capacity of 110-120 volts, 60 amperes, single
               phase and 60 hertz.
        2.     Circuit protection for each circuit.
        3.     Ground fault interruption protection for all circuits.
        4.     Grounded, UL listed extension cords from power centers to the point of
               operation.
        5.     Emergency back-up power source (i.e. battery or engine generator).

  C.   Temporary Lighting: The Contractor shall provide temporary lighting for construction
       needs, safe working conditions, public safety and security lighting. Lamps shall be
       covered with safety guards or deeply recessed in reflector. The lamps shall not be
       suspended by their electric cords unless cord and fixture is designed for that purpose.

  D.   Temporary Water: The Contractor shall provide and maintain temporary water service
       connection throughout the abatement period. The Contractor shall install valves at tie-
       in locations that shall be turned off and locked-out and tagged out when the contractor
       is not present on-site.

  E.   Monitor Temporary Utilities: The Contractor shall be responsible for all damage to the
       work and the facility caused by a defect in such utilities.

  F.   Existing Systems: The Contractor may make written arrangements with the FAA to
       modify, supplement and extend an existing system to meet temporary requirements for
       the project, subject to approval by the COR.

3.5    ISOLATION OF THE WORK AREA

  A.   Prepare the work areas in accordance with 29 CFR 1926.1101, Appendix F, and as
       detailed in section 2080.3.7 for each work area.

  B.   Establishing Negative Pressure: Establish negative pressure in accordance with the
       recommendations of 29 CFR 1926.1101 Appendix F, and to the extent stated below.
       Each system for each Phase shall maintain negative pressure, without failure, for a 24-
       hour period and be approved by the COR (in coordination with the APM) prior to the
       start of asbestos-related activity. Pressure differentials throughout the asbestos removal
       phases will be monitored continuously by the APM or an independent Monitoring
       Contractor hired by, and under the direction of the FAA.

ASBESTOS ABATEMENT                                                                     02080 - 20
KONA VOR DEMOLITION




        1.    In the event of a loss of pressure to less than 0.02 inches of water or an increase
              in pressure to more that 0.05 inches of water at any time of the day or night, for
              any reason, the Contractor will immediately be called to the site to remedy the
              situation. Contractors shall be "on call" throughout the duration of the removal
              project, 24-hours a day, 7-days a week. Failure to remedy the situation may
              result in back charges to the Contractor for the services rendered from an
              outside source.
        2.    The negative-air pressure shall be adjusted to meet the Design Pressure
              Differential as indicated below and shall run continuously until final clearance
              is achieved. Once the Contractor has satisfied the pressure differential
              requirements, at least one redundant unit for every 4 units in use (minimum one
              redundant unit) shall be on-site, to be utilized in the event of equipment failure.
        3.    Definition of Zones: To verify the safety of the non-abatement environments
              inside and outside the ARTCC, the following Zones shall be established:
                     ZONE I - Areas outside the asbestos removal area.
                     ZONE II - The Asbestos Removal Area.
        4.    Design Pressure Differential Concept.-
                     PZONE I > PZONE II
                     The intent of this Design Concept is to prevent the contamination of non-
                     abatement areas.
        5.    Design Pressure Differentials                     Inches of water
                     P ZONE I - ZONE II.............................0.02 to 0.05
        6.    Negative air units shall exhaust to the building exterior. The Asbestos
              Abatement Contractor shall be responsible for the restoration of the buildings to
              the preabatement condition after the completion of abatement.

  C.   Pre-Abatement Inspection: Upon completion of the work area containment and the
       establishment of negative pressure, the Contractor shall receive notification from the
       COR (in coordination with the APM) before removal work is initiated.

  D.   Work Place Entry and Exit: Enforcement is the responsibility of the Contractor's
       Abatement Superintendent. Entry shall be controlled to prevent unauthorized,
       accidental access into the containment area.

  E.   Maintenance of Enclosure System: The COR shall be immediately notified of problems
       that have developed such as a puncture of the barrier system, electrical power loss,
       GFCI failure, equipment failure, accidental discharge into occupied areas, and partial
       collapse of the critical barrier (plastic sheet fails to remain in place), etc.




ASBESTOS ABATEMENT                                                                     02080 - 21
KONA VOR DEMOLITION



3.6    DECONTAMINATION UNITS

  A.   Worker Decontamination Unit: The Contractor shall provide a detailed plan of the
       decon chamber and location to the COR (in coordination with the APM) for approval
       prior to beginning construction. Seal vertical and horizontal surfaces similar to Section
       2080.3.7 of these Specifications. The chamber shall be water-tight, the Contractor
       shall be liable and responsible to the FAA for any leaks/damages occurring during the
       abatement activities. The worker decontamination chamber shall consist of, at a
       minimum, a clean room, an airlock, a shower area, a second airlock and a dirty room.
       Provide lockers for each asbestos worker. Keep street clothing and street shoes in
       locker. While in removal area, only disposable protective clothing may be worn, reuse
       will not be allowed nor will laundering be acceptable. Shoes and undergarments worn
       in the removal area shall not be removed without being thoroughly cleaned in the
       shower first and then properly bagged. Locate showers between the decontamination
       room and the clean room. The shower shall be equipped with hot (Contractor
       furnished) and cold running water. Prefabricated units shall not be used without prior
       acceptance by the COR. Each person entering the removal area shall shower upon
       exiting. Do not use the worker decontamination unit for equipment or waste
       decontamination. The door to the decontamination unit, on the clean side, shall be
       lockable. The Contractor shall provide the COR with two (2) keys to the lock, or the
       combination. The door will be locked during hours when abatement work is not being
       performed.

  B.   Equipment and Waste Decontamination Unit: Provide a detailed plan of the proposed
       equipment and waste decontamination unit and location to the COR (in coordination
       with the APM) for approval prior to the beginning of construction. Seal vertical and
       horizontal surfaces similar to Section 2080.3.7 of these Specifications. The unit shall
       be maintained water-tight, the Contractor will be liable and responsible to the FAA for
       leaks/damages occurring during the abatement activities. The equipment and waste
       decontamination unit shall consist of, at a minimum, a clean room, an airlock, a wash
       station, a second airlock and an equipment room.

       The door to the bag-out chamber, on the clean side, shall be lockable. The Contractor
       shall provide the COR with two (2) keys to the lock, or the combination. The door will
       be locked during hours when abatement work is not being performed.

  C.   Wastewater: Water produced from the decontamination of persons, equipment or
       waste shall be collected and filtered through a system capable of trapping particles 5
       microns or larger (unless local regulations are more stringent), specifically designed to
       remove asbestos fibers and approved by EPA. The used filters shall be disposed of as
       asbestos-contaminated waste. Comply with any local wastewater systems regulations
       regarding the disposal of wastewater from asbestos abatement activities.




ASBESTOS ABATEMENT                                                                    02080 - 22
KONA VOR DEMOLITION



3.7    ABATEMENT PROCEDURES

  A.   Linoleum, acoustical wall panel, and cementicious walls. The following procedures
       shall be followed for the removal of these materials at the Honolulu CERAP facility
       demolition.
        1.    Seal all openings in the floor, walls or ceilings due to electrical, mechanical and
              telephone penetrations.
        2.    Prepare the work area. Erect Critical Barriers with duct tape and two (2) layers
              of 6-mil plastic sheeting to prevent air movement out of the area. Cover
              surfaces which are not contaminated or scheduled for abatement with 2 layers of
              6-mil plastic sheeting. Install a minimum of one clear 1/8-inch thick acrylic
              sheet 18 inches by 24 inches, as a viewing inspection window at eye level on a
              wall in each containment enclosure. All such windows shall be sealed leak-
              tight with duct tape. Do not cover the floor or walls identified for removal.
              Access shall be limited to authorized personnel. Install OSHA/EPA approved
              ASBESTOS WARNING signs at the entrances to the work area. Materials that
              may be damaged from water contact shall be sealed water tight with 6-mil
              plastic sheeting to prevent water contact.
        3.    Establish respiratory protection for workers.
        4.    Construct a worker decontamination chamber and equipment and waste
              decontamination chamber according to Section 2080.3.6.
        5.    Establish negative pressure with HEPA negative pressure exhaust units
              according to Section 2080.3.5 (B).
        6.    Conduct a smoke test of all enclosure(s) in conjunction with the APM. No
              work will commence until the enclosure(s) have successfully passed the smoke
              test.
        7.    After written certification by the COR, initiate gross removal of the asbestos
              containing materials identified in Section 2080.1.1 (C) and 2080.1.1 (D).
        8.    Pass periodic inspections and air monitoring by the COR (in coordination with
              the APM) to verify removal progress.
        9.    Upon completion of gross removal, double bag in clear 6 mil plastic disposal
              bags. Initiate final cleaning of the work area according to section 2080.3.7 (B).
        10. Upon passing clearance testing, remove containment and conduct additional
              cleaning as directed by the COR.
        11. Final Clean-up: The following sequence of events shall strictly follow AHERA
              protocol and will apply:
             a.     Remove and containerize visible accumulations of asbestos-containing
                    material and asbestos-contaminated debris utilizing rubber dust pans and
                    rubber squeegees to move material around. Do not use metal shovels to
                    pick up or move accumulated waste.
             b.     Wet clean surfaces in the work area using rags, mops and sponges as
                    appropriate. Be certain not to create any excess water build-up.
             c.     Doors, HVAC system vents and other openings shall remain sealed. The
                    negative pressure ventilation units shall remain in continuous operation.
                    Decontamination enclosure systems shall remain in place and be utilized.


ASBESTOS ABATEMENT                                                                     02080 - 23
KONA VOR DEMOLITION



             d.    Remove containerized waste from the work area and waste container bag-
                   out airlock
             e.    Decontaminate tools and equipment, and remove at the appropriate time in
                   the cleaning sequence
             f.    After cleaning the work area, wait at least 24 hours to allow fibers to settle,
                   and HEPA vacuum and wipe clean objects and surfaces in the work area
                   again.
             g.    Inspect the work area for visible residue. If any accumulation of residue is
                   observed, it will be assumed to be asbestos, and the 24-hour settling
                   period/cleaning cycle repeated.
             h.    Once the area passes the visual inspection by the COR (in coordination
                   with the APM), equipment not going to be used should be recleaned and
                   removed from the work area.
             i.    Apply encapsulant on surfaces and wait 8-24 hours before continuing.
             j.    Allow area to dry and then conduct visual inspection, reclean if required.
             k.    Conduct final air clearance tests according to Section 2080.3.9 (B) (3).
                   Negative-air machines will operate continuously until test results verify a
                   "clean" environment.
             l.    This process shall be repeated, at no expense to the FAA, until clearance is
                   achieved. Repeated clearance testing due to unacceptable results shall be
                   charged to the Contractor.
             m.    Remove enclosure, all ACM debris and waste and Contractor equipment
                   from FAA property.

  B.   The following procedures shall be followed for the removal of floor tile and mastic.
        1.    Prepare the work area. Erect Critical Barriers with duct tape and two (2) layers
              of 6 mil plastic sheeting to prevent air movement out of the area. Where floor
              tile and mastic removal occurs, cover the walls with a 6 a mil plastic splash
              guard sheeting beginning from the floor and .at least 3 foot high up the wall
              surface. Access shall be limited to authorized personnel. Install OSHA/EPA
              approved ASBESTOS WARNING signs at the entrances to the work area.
              Materials that may be damaged from water contact shall be sealed water tight
              with 6 mil plastic sheeting to prevent water contact.
        2.    Establish respiratory protection for workers.
        3.    Construct a worker decontamination chamber and equipment and waste
              decontamination chamber according to Section 2080.3.6.
        4.    Establish negative pressure with HEPA negative pressure exhaust units
              according to Section 2080.3.5 (B).
        5.    Pass COR's (in coordination with the APM) inspection of containment area set-
              up.
        6.    After written certification by the COR, initiate gross removal of the asbestos
              containing materials identified in Section 2080.1.1 (C) and 2080.1.1 (D).
        7.    Pass periodic inspections and air monitoring by the COR (in coordination with
              the APM) to verify removal progress.
        8.    Upon completion of gross removal, double bag in clear 6 mil plastic disposal
              bags. Initiate final cleaning of the work area according to section 2080.3.7 (B).

ASBESTOS ABATEMENT                                                                      02080 - 24
KONA VOR DEMOLITION



        9.    Upon passing clearance testing, remove containment and conduct additional
              cleaning as directed by the COR.
        10. Final Clean-up: The following sequence of events shall strictly follow AHERA
               protocol and will apply:
            a.      Remove and containerize visible accumulations of asbestos-containing
                    material and asbestos-contaminated debris utilizing rubber dust pans and
                    rubber squeegees to move material around. Do not use metal shovels to
                    pick up or move accumulated waste.
            b.      Wet clean surfaces in the work area using rags, mops and sponges as
                    appropriate. Be certain not to create any excess water build-up.
            c.      Doors, HVAC system vents and other openings shall remain sealed. The
                    negative pressure ventilation units shall remain in continuous operation.
                    Decontamination enclosure systems shall remain in place and be utilized.
            d.      Remove containerized waste from the work area and waste container bag-
                    out airlock
            e.      Decontaminate tools and equipment, and remove at the appropriate time in
                    the cleaning sequence
            f.      After cleaning the work area, wait at least 24 hours to allow fibers to settle,
                    and HEPA vacuum and wipe clean objects and surfaces in the work area
                    again.
            g.      Inspect the work area for visible residue. If any accumulation of residue is
                    observed, it will be assumed to be asbestos, and the 24-hour settling
                    period/cleaning cycle repeated.
            h.      Once the area passes the visual inspection by the COR (in coordination
                    with the APM), equipment not going to be used should be recleaned and
                    removed from the work area.
            i.      Apply encapsulant on surfaces and wait 8-24 hours before continuing.
            j.      Allow area to dry and then conduct visual inspection, reclean if required.
            k.      Conduct final air clearance tests according to Section 2080.3.9 (B) (3).
                    Negative-air machines will operate continuously until test results verify a
                    "clean" environment.
            l.      This process shall be repeated, at no expense to the FAA, until clearance is
                    achieved. Repeated clearance testing due to unacceptable results shall be
                    charged to the Contractor.
            m. Remove enclosure, all ACM debris and waste and Contractor equipment
                    from FAA property.

  C.   Transite Piping. Located aboveground and underground, the following procedures
       shall be followed for the removal of the transite piping at the Honolulu CERAP facility
       demolition.
        1.     Transite piping shall be cut into lengths appropriate for transport and disposal.
               Workers performing this work shall have asbestos training appropriate for
               OSHA Class II asbestos work.
        2.     Wet methods shall be utilized to minimize migration of asbestos fibers.
        3.     Each worker shall be donned in appropriate personal protection equipment.


ASBESTOS ABATEMENT                                                                       02080 - 25
KONA VOR DEMOLITION



  D.    Fire Doors. The following procedures shall be followed for asbestos removal of
        asbestos fire doors in the basement.
         1.    Remove the hinges from the door jamb (or remove the hinge pins) so the hinge
               leaf attached to the door remains attached to the door. Cover wrap the door
               (with the hinge leaf, door closer, locksets, etc. attached) with two (2) layers of 6
               mil plastic sheeting. Tape the layers separately one after the other.
         2.    Dispose of the wrapped door as asbestos containing material.

3.8     PROCEDURE FOR DISPOSAL

       A.        Collect asbestos waste, scrap, debris, bags, containers, equipment, and asbestos-
                 contaminated clothing which may produce airborne concentrations of asbestos
                 fibers, and place in sealed impermeable asbestos bags. Each bag shall be pre-
                 printed with an asbestos warning label. Double bag debris. Identify all waste
                 bags and containers as follows:
                                           FAA – KONA VOR
                                             KONA, HAWAII
                                          (Name of Contractor)
            1.      Dispose of waste asbestos material at an Environmental Protection Agency
                    (EPA) or state-approved landfill off Government property. For temporary
                    storage, store sealed, impermeable bags in asbestos waste drums or waste
                    storage containers. The FAA will assign an area for interim storage of asbestos
                    waste-containing drums or containers. Procedure for hauling and disposal shall
                    comply with 40 CFR 61 (Subpart B), state, regional, and local standards.
                    Workers unloading the ACM waste shall wear appropriate respirators and
                    personal protective equipment when handling asbestos materials at the disposal
                    site. A fully sealed and plastic lined dumpster will be used for transportation of
                    all ACM wastes. The Waste Manifests will be prepared by the contractor and
                    signed by an FAA representative.
            2.      Minimum requirements for a waste manifest are as follows:
                 a.      Contain a unique number, proper DOT markings, and shipping name of
                         waste material.
                 b.      Be signed by an FAA representative when shipping.
                 c.      Be signed by transporter when material is picked-up.
                 d.      Be signed by disposal facility when received.
                 e.      Name and address of pick-up site.
                 f.      Estimated quantity of waste.
                 g.      Specific location within the building where waste was generated.
                 h.      Type and number of bags and drums used at each specific location within
                         the building.
                 i.      Name of Transporter.
                 j.      Disposal site name, location and EPA identification number.
                 k.      Copies of the manifest signed by an FAA representative; transporter and
                         disposal site shall be maintained by each entity.


ASBESTOS ABATEMENT                                                                          02080 - 26
KONA VOR DEMOLITION



        3.    The ACM waste shipment shall be transported directly from the job site to the
              EPA approved landfill. The Contractor shall notify the landfill of the date and
              time the ACM waste will arrive at the landfill. The landfill shall have a hole
              excavated to receive the ACM waste upon arrival. The waste containers shall
              be hand-placed into the hole, not tossed or thrown, and immediately covered
              with 6 inches of soil. Cost due to delay to the FAA caused by the ACM waste
              transporter, landfill operator or Contractor failure to coordinate ACM debris
              landfilling will be charged to the Contractor and deducted from payments to the
              Contractor. Provide asbestos waste shipment records to the COR within three
              (3) days after delivery of the ACM to the landfill.

3.9    ABATEMENT AIR MONITORING

  A.   Personal Monitoring: Personal monitoring shall be performed on a representative
       number of employees engaged in asbestos abatement in the regulated area. The
       Contractor is responsible for Personal Samples that are related to his employees, as
       required in accordance with Section 2080.1.2 of these Specifications. Personal air
       sampling and training shall be conducted under the direction of a CIH possessing at
       least two years experience in asbestos abatement. An independent American Industrial
       Hygiene Association accredited laboratory shall be used to analyze air samples in
       accordance with OSHA Regulation 29 CFR 1926.1101. Copies of the results of the air
       samples shall be furnished to the APM within 48 hours following the day in which they
       were collected.

  B.   Environmental Monitoring: Environmental monitoring for airborne fiber count and
       pressure differential, and third party inspections, under contract to the FAA, will be
       accomplished by a Certified Industrial Hygienist (CIH) or an air sampling technician
       supervised by a CIH and be referred to as the Asbestos Project Manager (APM). An
       independent accredited industrial hygiene laboratory and technician shall be used to
       analyze air samples in accordance with OSHA Regulation 29 CFR 1926.1101.
         1.   Background Monitoring: Background samples will be collected at least 10 days
              prior to the isolation of the work area. Background samples will be conducted
              by the FAA or the APM and will consist of a minimum of two (2) samples per
              work area and an additional sample for each 25,000 cubic feet of air space in
              excess of 50,000 cubic feet of air space.
         2.   Clearance Monitoring: The Contractor shall notify the COR who in turn will
              notify the APM when the work areas are ready for clearance air monitoring.
              The APM shall arrange to sample the air in the work area for airborne fiber
              concentrations in accordance with 40 CFR 763.
             a.     A minimum of five samples will be taken in the abatement work area and
                    analyzed by Phase Contrast Microscopy (PCM). Air volumes will be
                    sufficient to provide reliable results down to a fiber concentration of 0.01
                    f/cc or lower. If any of the five samples, in each containment area, show
                    asbestos fiber concentrations greater than 0.01 f/cc, or above baseline, the
                    area shall be recleaned and reanalyzed. The Contractor shall be required to
                    bear the extra expense of recleaning and of additional APM monitoring

ASBESTOS ABATEMENT                                                                    02080 - 27
KONA VOR DEMOLITION



                  fees as well as other FAA delay expenses incurred due to the Contractor's
                  failure to pass clearance.
            b.    Clearance sampling shall be done under aggressive conditions as follows:
                  1)     The Contractor shall provide at least one portable 20" diameter fan
                         per 10,000 cubic feet (ft3) of containment volume. The fans shall be
                         positioned in the center of the space and the airflow directed towards
                         the ceiling and operated on the "slow" speed setting. The fans shall
                         operate throughout the duration of the final clearance air-sampling
                         period. Negative pressure ventilation units shall not be utilized for
                         this purpose.
                  2)     The APM shall blow down surfaces with a portable electric leaf
                         blower. The APM shall operate the leaf blower for a minimum of 5
                         minutes per 1,000 square feet (ft2) of containment area.

  C.   Accreditation of Laboratories: Proof shall be provided of the qualifications of the
       testing laboratory and personnel used by the Abatement Contractor for Personnel
       Samples and the APM Environmental Monitoring. Accreditation by the American
       Industrial Hygiene Association (AIHA) for Phase Contrast Microscopy and
       certifications that persons analyzing the samples have been judged proficient by
       successful participation in the American Industrial Hygiene Association (AIHA)
       Proficiency Analytical Testing (PAT) Program, shall be considered sufficient proof of
       compliance. In addition, all analysts must be currently registered in the Asbestos
       Analyst Registry (AAR). Submittal shall be approved by the COR prior to beginning
       work.


END OF SECTION 02080




ASBESTOS ABATEMENT                                                                   02080 - 28
KONA VOR DEMOLITION



SECTION 02090 LEAD PAINT ABATEMENT


1.1         STATEMENT OF WORK


1.1.1       Scope of Work

This section covers the Scope of Work (SOW) at the FAA identified in the specific task order
requirement regarding the abatement of intact and/or delaminating lead-based paint (LBP) coatings
from existing building components, or the complete removal and replacement of existing building
component containing LBP. All paint/coatings identified for removal will be referred within this
specification as LBP. Specification references to the Contracting Officer's Representative (COR) /
Resident Engineer (RE) shall include the COR/RE's technical representative(s), as applicable.

To complete the specified SOW, the contractor is required to furnish all labor, materials, services,
equipment, insurance, bonds, security, etc., in accordance with applicable federal, state and local
regulatory requirements.

The quantities of materials listed for removal are to be considered estimates and are presented to
assist the contractor in evaluating the total scope of work. All areas and quantities given wuthin this
specification are to be verified by the contractor prior to bid submittal since its counting and sizing
methods may differ from those used to prepare this document.

Drawings have been attached to assist the contractor in identifying LBP locations.

1.1.1.3 Abatement of Lead-Based Paint Chips

The contractor shall furnish all labor, materials, services, trained personnel, insurance and
equipment as needed to complete the removal of LBP as indicated in the project-specific task order
requirements. The contractor shall follow all federal, state and local ordinances, regulations and
requirements pertaining to LBP removal, storage, transportation and disposal.

LBP abatement work areas include the following locations:
        Lead Paint:
EG Room           LBP/LCC on ceiling and I-beams                                                     intact         1.67 wt
                                                                                                                    %
Storage Shed      LBP/LCC on walls (red) (paint is peeling)                                          delaminated    12.1 wt
Exterior                                                                                                            %
Storage Shed      LBP/LCC on ceiling, walls and floor (gray) (this paint is also on roof under rolled delaminated   17.7 wt
Interior          roofing material)                                                                                 %
Storage Trailer   LBP/LCC on walls (red) (paint is peeling)                                           delaminated   11.1 wt
Exterior                                                                                                            %
Storage Trailer   LBP/LCC on ceiling, walls and floor (gray)                                         intact         2.82 wt
Interior                                                                                                            %
VOR Exterior      LBP/LCC on EG exhaust (silver) (also on interior EG exhaust)                       delaminated    .974 wt
KONA VOR DEMOLITION
                                                                                                        %
VOR Exterior     LBP/LCC on doors and door frames (gray) (on EG and Equipment Room doors)   delaminated 1.25 wt
                                                                                                        %
VOR Exterior     LBP/LCC on gate (red) (also on 8 ft. section of fence)                     delaminated 11.4 wt
                                                                                                        %
VOR Exterior     LBP/LCC on pull box located near gate (orange)




1.1.2      Regulatory Compliance

All project activities, including pre-cleaning, set-up, LBP removal, final clean-up, air monitoring,
transportation, and waste disposal shall be in accordance with this specification and current federal
and state regulations, including local laws, ordinances, rules, regulations, orders and codes (all to be
referred to as "applicable law"). The contractor shall be responsible for the proper handling, storage
and disposal of all waste generated from this project, including any material classified by the
Environmental Protection Agency (EPA) as Resource Conservation and Recovery Act (RCRA) or
Toxic Substances Control Act (TSCA) regulated waste. In cases where regulations and/or contract
documents are conflicting, or discrepancies occur, the more stringent requirement shall be followed
and enforced.

1.1.3     Contractor's Responsibilities

The contractor's responsibilities include, but are not limited to, providing:

          A) All necessary safeguards, including safe work practices and engineering controls, to
             ensure the health and safety of FAA employees and other persons in and around the
             work areas.
          B) Isolation and/or containment of work areas in accordance with applicable law and this
             specification.
          C) Air monitoring of employee lead exposure levels as required by applicable law and
             this specification.
          D) Coordination/procurement of all permits, approvals and authorizations required to
             perform site work ; this includes notification as required by applicable law.
          E) Supplying all material, services, labor, equipment, instrumentation and Personal
             Protective Equipment (PPE) required to perform the required SOW.
          F) Removal and disposal of all designated LBP relative to project activities, including
             any material contaminated by LBP, unless otherwise stated in the contract.
          G) Final clean-up and restoration of all work area(s) to their original condition.
          H) All shipping documents, manifests and disposal receipts within 10 days of
             removal/transport of waste from the project site.
          I) All licenses and certifications required by applicable law for the purpose of removal,
             encapsulation or enclosure needed to complete this project.
          J) A qualified supervisor, with current lead-related construction supervisor certification,
             to be present during all project activities.
          K) Prior to commencing work, the contractor shall investigate the work area and agree on
             pre-abatement conditions with the COR/RE. A space-by-space pre-work damage
             report shall be completed by the COR/RE and reviewed/signed by the contractor. Any
KONA VOR DEMOLITION
           discrepancies between the COR/RE's pre-work damage report and the contractor, shall
           be resolved prior to the contractor commencing site work..
        L) Submittals as required by this specification and/or task order requirements.


1.2     SUBMITTALS

1.2.1   Pre-Construction Conference Submission Requirements

After contract award, and 15 days prior to the pre-construction conference, the following
information shall be submitted to the COR/RE:

        A) Final list of all contractor personnel to be used in any work area for set-up, pre-
           cleaning, removal, final cleaning, dismantling of the work area and waste disposal,
           including:
           - Copies of current training certificates from an EPA-accredited training provider
               for Lead-Related Construction Supervisor or Worker.
           - Current copies of workers blood lead testing results.
           - Copies of attending physician medical opinions regarding respirator usage.
           - Copies of current respirator fit test records.
           - Copies of photo identifications and social security numbers.
           - Verification that the project superintendent has supervised project(s) of similar
               size and nature of that to be performed at this site.
        B) For proposed subcontractors (if applicable); include the following information:
           - Supervisor's resume.
           - List of proposed workers, including training certifications, medical opinions and
               fit tests, as subcontractor tasks dictate.
           - Copies of all certifications required to complete assigned tasks.
           - Description of subcontractor job functions and percent of project activities to be
               performed.
           - Applicable licenses.
        C) Final project schedule.
           - Start and completion dates for each work area, including project milestones.
           - Number of workers on-site each day, per work area.
           - Schedule of hours to be worked each day, per work area.
        D) Description and drawings.
           - Placement and design of containments, mini-containments, and decontamination
               facilities, as required.
           - Placement of barriers and engineering controls for each work area, when
               applicable.
           - Utilities requirements, when applicable.
           - Emergency and fire escape/response procedures.
        E) Respiratory Protection Plan.
        F) Site specific Written Hazard Communication Program (29 CFR 1910.1200 and/or 29
           CFR 1926.59).
KONA VOR DEMOLITION
          -   Include Material Safety Data Sheet (MSDS) submissions as required by applicable
              standards.
KONA VOR DEMOLITION
         G) Written Standard Operating Procedure (SOP) for each type of removal used on this
            project.
            - A written SOP specific to this project delineating how the contractor proposes to
                protect workmen, visitors and FAA employees from potential lead exposure and
                how spaces outside the work areas will be protected from contamination for the
                duration of the work. The SOP shall also specify the exact removal method the
                contractor shall utilize on this project, along with associated equipment.
            - Include all pertinent information on patented abatement systems or equipment that
                are utilized by the contractor. Signed licensing agreements will be required for
                any patented system or equipment used by the contractor. False information or
                illegal use of patented systems by the contractor will not be the liability of the
                FAA or its representatives.
         H) Applicable business licenses, insurance certificates, permits, and notifications.
         I) Analytical laboratory for air sample analysis; the laboratory must be a successful and
            current participant in the EPA’s Environmental Lead Proficiency Analytical Testing
            Program (ELPAT).
         J) Overview of all air sampling procedures to be utilized.
         K) Disposal arrangements.
            - Provide specific information regarding LBP waste and construction debris
                disposal site(s).
            - Provide letter of acceptance, blank copies of a waste manifest and bill of lading,
                and specific disposal requirements.

1.2.2    Submittals During Work

The contractor may be required to provide submittals at various times throughout the project. All
items required for submission during work shall be submitted in such time to allow the COR/RE
sufficient time to review the documents prior to the commencement of work. All delay costs
associated with the failure of timely submittals shall be at the contractor's expense.

1.2.2.1 Daily Submittals

The items below shall be provided to the COR/RE by the contractor's site supervisor prior to leaving
the site each work shift. The contractor shall submit the daily information to the COR/RE at a time
agreed upon by the COR/RE and the contractor during the pre-construction conference.

         A) One copy of the daily entrance/exit log.
         B) One copy of the site supervisor's daily report; the report shall record all milestones
            achieved, pertinent events or agreements, health & safety concerns/corrections and an
            estimate of project completion percentage.
         C) Hard copy of any air monitoring results from the previous workday and copies of the
            day's air monitoring field data sheets and calculations. All daily air sampling results
            shall be prominently displayed at a location designated by the COR/RE.
         D) One copy of the next day's proposed schedule and work areas. Include forecasts for
            the COR/RE's inspections, background sampling and work hours.
KONA VOR DEMOLITION
1.2.2.2 Periodic Submittals

The contractor shall submit copies of the following items to the COR/RE immediately following
each occurrence:

         A) Records of any accident, emergency evacuation and any other safety and/or health
            incident occurring on-site or related to the project, including corrective actions taken.
         B) Worker Compensation Forms or physician's diagnosis for each accident occurring on-
            site which requires medical attention.
         C) Disposal certificates issued by landfill officials with regard to where waste was buried
            or construction debris disposed.
         D) Changes to the project schedule.

1.3      NOTIFICATIONS, PERMITS, WARNING SIGNS, LABELS AND POSTERS

The contractor shall:

         A) Provide required notifications to the EPA and any other regional, state and/or local
            authority having jurisdiction over the project. Copies of such notifications shall be
            furnished to the COR/RE prior to the commencement of any work. All permits
            required for the work shall be displayed in an approved location as determined by the
            COR/RE.
         B) Erect Occupational Safety and Health Administration (OSHA) required danger sign(s)
            around the work space at every point of potential entry from the outside. The danger
            signs shall meet all applicable OSHA guidelines, including shape, size, color, and
            statement.
         C) Provide and use appropriate OSHA and NESHAP labels for all containers utilized to
            transport waste materials to the landfill.
         D) Provide and use appropriate Department of Transportation (DOT) placarding required
            for the transport of materials to the landfill.

1.4      TEMPORARY UTILITY AND SERVICE ARRANGEMENTS

The contractor shall use qualified tradesmen for the installation of temporary utility and service
facilities. Temporary utility and service facilities shall be located where they will serve the project
adequately and result in minimum interference to the performance of the contractor and FAA. The
contractor shall employ licensed tradesmen to accomplish this work, as required by applicable law.
KONA VOR DEMOLITION
1.4.1    Water Service

All connections to the water system shall be coordinated with the COR/RE and shall include back
flow protection. Valves shall be temperature and pressure rated for operation at the temperatures
and pressures encountered. After completion of use, connections and fittings shall be removed
without damage or alteration to existing water piping and equipment. Leaking or dripping valves
shall not be allowed and, upon discovery, shall be immediately replaced.

The contractor shall employ heavy-duty abrasion-resistant hoses, with a pressure rating greater than
the maximum pressure of the water distribution system, to provide water into each work area and to
each decontamination enclosure system. The contractor shall provide fittings, as required, to allow
connection to existing wall hydrants or spouts, as well as temporary water heating equipment,
branch piping, showers, shut-off nozzles, and equipment.

A decision concerning water service will be made during the pre-construction meeting. Hot water
service may not be available from the facility, therefore, the contractor shall be required to provide
an Underwriters Laboratories (UL) rated 40 gallon or greater electric hot water heater to supply hot
water for the decontamination enclosure system shower. The heater shall be provided with a relief
valve compatible with water heater operation. The pipe relief valve shall extend down to a drip pan
on the floor with type "L" copper.

1.4.2    Electrical Service

The contractor shall comply with applicable National Electrical Manufacturers Association
(NEMA), National Electrical Contractors Association (NECA), Underwriter Laboratories (UL)
standards, and governing regulations for materials and layout of temporary electric service.

All power panels deemed necessary by the COR/RE shall be totally accessible to FAA personnel
during all phases of construction. The contractor shall provide service to a temporary subpanel or
ground fault circuit-interrupter with a minimum 60 amp, 2 pole circuit breaker or fused disconnect
connected to the building's main distribution panel. Temporary electrical service shall be sized and
equipped to accommodate all electrical equipment required for completion of the work. The
electrical equipment shall be located as directed by the COR/RE.

All temporary wiring in the work area shall be an Underground Feeder (UF) type, non-metallic
sheathed cable located overhead and exposed for surveillance. The contractor shall not wire
temporary lighting with plain, exposed (un-insulated) electrical conductors. Liquid tight enclosures
or boxes for wiring devices shall be used.

The contractor shall provide sufficient branch circuits as required for the work. All branch circuits
are to originate at the temporary electrical service equipment.

It is the contractor's responsibility to arrange and coordinate electrical service for the abatement with
the COR/RE. Identification warning signs shall be affixed at power outlets which are other than
110-120 volt power. Polarized outlets shall be provided for twist-type outlets to prevent insertion of
KONA VOR DEMOLITION
110-120 volt plugs into higher voltage outlets. Dry-type transformers shall be used, where required,
to provide voltages necessary for work operations.

The contractor shall equip all circuits entering the work area with ground fault circuit interrupters
(GFCI) and locate GFCI's exterior to the work area so that all circuits are protected prior to entry to
the work area. Also, each GFCI shall be equipped with a test button and reset switch.

1.4.3    Power Lockout

Existing power and lighting in the work area shall not be used during abatement activities unless
specifically approved in advance by the COR/RE. All power and lighting to the work area and
decontamination enclosure systems are to be provided from a temporary electrical panel (as
described previously).

The contractor shall coordinate comprehensive lockout procedures regarding power to the work
area, with the COR/RE.

1.4.4    Self-Contained Toilets

The contractor shall provide a single-occupant, self-contained toilet unit of the chemical type,
properly vented and fully enclosed with a glass fiber reinforced polyester or similar non-absorbent
material for each gender of worker as per 29 CFR 1910.140.

1.4.5    Fire Protection

The contractor shall provide "ABC" dry chemical extinguishers or a combination of several
extinguishers, of National Fire Protection Association (NFPA) recommended types, for the
exposures in each case. Fire extinguishers shall be of sufficient size and number for each location
as described within the NFPA guidelines and 29 CFR 1910.57. Extinguishers must be located
within useful distance of all work areas both inside and outside the barriers.

1.5      CONTRACTOR PERSONNEL REQUIREMENTS

The contractor shall ensure each employee scheduled to accomplish set-up, pre-cleaning, removal,
tear-down and disposal shall meet the following requirements:

         A) Employee Right-to-Know training.
         B) Physician's medical opinion approving employee to wear a negative pressure
            respirator.
         C) Current respirator fit test record.
         D) Current EPA approved, state* and local* lead worker certificates. *(when applicable)
         E) Current/acceptable blood lead levels, as required by 29 CFR 1926.62 and CCR Title 8,
            1532.1.
         F) Positive form of photo identification (driver’s license, lead worker certification card,
            etc.)
KONA VOR DEMOLITION
The contractor shall provide the above information, relative to any new employees, to the COR/RE
for review at least 24 hours prior to bringing a new employee onto the job site. Original copies of
any certificate of identification, or any required employee documentation, shall be shown to the
COR/RE upon request. Anyone unable to produce an original copy of any required document
within 24 hours of its request by the COR/RE, shall be directed to leave the job site immediately.
The COR/RE reserves the right to verify all certificates and identification produced.

While work is in progress, the contractor shall maintain on-site at all times a project supervisor
which meets the requirements of a certified lead-related construction supervisor. Additionally this
supervisor shall hold a current Cardiopulmonary Resuscitation (CPR)/first aid certificate.

1.6      PERSONAL PROTECTIVE EQUIPMENT

The contractor shall provide employees with respiratory protection in accordance with applicable
law. Protective clothing and respiratory protection shall be worn at all times when workers may be
exposed to lead dust during any phase of the project.

1.6.1    Respiratory Protection

Workers shall use air purifying respirators (APR) or powered air purifying respirators (PAPR), with
the appropriate HEPA cartridge type, as necessary for the specific tasks being performed, in
accordance with OSHA 29 CFR 1926.62 and CCR Title 8, Part 1532.1. The contractor shall
provide all workers, foremen, superintendents, authorized visitors and inspectors with clean,
individually issued and marked APRs and or PAPRs, as appropriate for the specific task(s) being
performed. All equipment shall be NIOSH-approved. Dual cartridges (e.g., HEPA with organic,
charcoal, etc.) shall be utilized for abatement activities requiring that cartridge type, such as heat
guns, burning, torch cutting, etc.

1.6.1.1 Negative Pressure Full-Face and Half-Face Respirators (APR)

Negative pressured APR full-face and half-face respirators with HEPA cartridges shall be used, at a
minimum, for the following:

         A) Pre-construction sealing of walls, floors and openings with polyethylene sheeting if
            LBP dust may be encountered.
         B) Decontamination of any removable or fixed objects.
         C) Abatement execution, as approved by the RE with advice from the GCIH.
         D) Final cleaning.
         E) Plastic sheeting removal.
         F) Loading bags/containers from the work area.
         G) Cleaning bags/containers prior to loading them on trucks.
         H) Loading bags/containers onto a truck for transportation.
         I) Unloading bags/containers at the landfill.

1.6.1.2 Powered Air Purifying Respirators (PAPRs)
KONA VOR DEMOLITION
PAPRs shall be required for all abatement activities, unless otherwise stated by the RE/GCIH.

1.6.2    Protective Clothing

The contractor shall provide workers, foremen, superintendents, authorized visitors and inspectors
with necessary disposable protective clothing, including disposable coveralls with attached hood
and footings No tennis shoes, standard work boots or other miscellaneous footwear deemed
unacceptable by the COR/RE, shall be worn in the containment area.

Additionally, the contractor shall provide workers with hard hats, as well as eye and hand
protection, as required by job conditions and personnel safety requirements. Reusable footwear,
hard hats and eye protection shall be left in the contaminated equipment room until the end of the
abatement work. Items which cannot be properly decontaminated to the COR/RE’s satisfaction,
shall be disposed as lead waste.

1.7      MONITORING, TESTING, AND INSPECTION

1.7.1    Pre-clean and Work Area Inspection

Prior to the commencement of any abatement work, the COR/RE shall inspect and approve the
work area. The purpose of this inspection is to determine specification compliance and assess
overall site conditions.

The contractor shall post outside the work area, at a central location, a list of phone numbers where
individuals from the contractor's firm may be reached 24 hours a day, 7 days a week.
Commencement of abatement work in any work area shall not occur until:

         A) The COR/RE and the contractor's supervisor inspect the work areas to ensure
            conformance with this specification.
         B) Barriers and decontamination facilities construction is complete and operational.
            (Barrier, Personal Decontamination Facilities [PDF] and Equipment Decontamination
            Facilities [EDF], as required, shall be specific to those stated in this specification for
            each project task)
         C) All pre-abatement submissions, notifications, posting and permits have been provided
            and deemed satisfactory by the COR/RE.
         D) Personnel and area air monitoring (as required) is in progress and background area
            samples (as required) have been collected by the GCIH.
         E) Written permission to proceed has been issued by the RE.

Any activities conducted by the contractor that are in violation of the air monitoring requirements
outlined in this specification, shall result in a stop work order for the affected work area. In these
instances the entire work area and/or affected surrounding areas shall be wet wiped and cleaned by
the contractor at no expense to the government or COR/RE.

1.7.2    Contractor's Air Sampling Requirements
KONA VOR DEMOLITION
As required, the contractor shall be required to conduct personal and area sampling for all
abatement phases of the project. The COR/RE will employ the services of a Government's
Consulting Industrial Hygienist (GCIH) for the duration of the project. The COR/RE, with advice
from the GCIH, shall have the final opinion on all air sampling matters.

The contractor shall provide the services of a financially independent qualified air monitoring
professional referred to as the Contractor's Air Sampling Professional (CASP), unless otherwise
specified by the COTR. This individual shall meet the following qualifications:

         A) At least an associate's degree, or equivalent field experience, in one of the sciences
            such as chemistry, biology, geology, earth science, engineering or meteorology.
         B) A minimum of one year's experience under the direct supervision of a Certified
            Industrial Hygienist (CIH) performing similar work.
         C) A current certificate of completion from an EPA-approved course for Lead Related
            Construction Supervision/Project Monitor.
         D) Current state and/or local certification to perform IH services/project monitoring for
            lead-related abatement projects, if applicable.

On a daily basis, the contractor shall collect the following samples, at a minimum, for each
individual work area during pre-cleaning, set-up, removal, disposal and other miscellaneous work
area operations that require air monitoring:

         1) Personal Samples
            - All personal air samples required by OSHA regulations, in accordance with the
                NIOSH Method 7402.
            - 25% of the work force for each activity shall be monitored.

         2) Area Samples (as required):
            - At all work areas during removal operations, unless stated otherwise. (If sampling
               is required, the quantity of samples collected shall be at the discretion of the
               GCIH.)

All sampling schemes shall be approved by the COR/RE, with advice from the GCIH. All area
sample locations utilized by the contractor, including the quantity of samples collected, shall be
approved by the COR/RE, with advice from the GCIH.

Results for each day's air samples shall be provided to the COR/RE within 24 hours of the sample
collection completion time. A copy of the laboratory report and field sheets shall be provided to the
COR/RE for posting at the facility. The analytical laboratory shall be a successful and current
participant in the EPA’s ELPAT.

1.7.3    Work Area Clearance

Upon completion of all required abatement and final cleanup by the contractor, the COR/RE shall
visually inspect each work area to ensure that all designated LBP has been removed and the areas
properly decontaminated. Any area not deemed acceptable by the COR/RE shall be re-cleaned to
KONA VOR DEMOLITION
the COR/RE's satisfaction at no additional expense to the Government. Final clearance will be
conducted by the GCIH following the conclusion of all abatement activities. Final clearance will
include a visual inspection of the work area and, when dictated by project requirements, area dust
wipe sample and/or soil sample collection.

1.8      MATERIALS

1.8.1    Material Requirements

The contractor shall not use any materials or solvents with pungent odor or toxicity, and these
requirements must be addressed on all MSDS required for each individual product. The contractor
shall provide a physical sample of any product approaching these restrictions for the COR/RE's
approval.

         A) All materials and equipment shall be Underwriters Laboratory (UL)-listed, and in
            adherence to all federal, state, and local regulatory requirements for the intended
            application.
         B) Adhesives, polyethylene sheeting and encapsulants shall be compatible with materials
            to which they are applied. These materials shall be suitable for application in
            accordance with manufacturer's recommendations and the most current NEPA and
            American Society of Testing and Materials (ASTM) regulations.
         C) Polyethylene sheeting shall have a thickness of 6 millimeters, ASTM D 2103, unless
            otherwise specified in writing by the COR/RE.
         D) Organic solvents having a flash point of 140 degrees Fahrenheit or less, as indicated in
            the MSDS, shall not be permitted for project use. No organic solvent, or mixture
            containing an organic solvent, may be released into any drainage system at the site.

1.9      TOOLS AND EQUIPMENT

Any equipment or tools brought onto the site which are suspected of being contaminated with LBP
shall be removed from the work area and cleaned by contractor personnel at the direction of the
COR/RE. Potential equipment requirements that may be necessary to complete the project scope of
work include:

Airless Sprayer: An airless sprayer suitable for application of encapsulant coatings shall be
furnished and used by the contractor. This sprayer shall also be used to apply a continuous mist
throughout the removal phase to adequately wet all LBP, as required.

Building Materials: All building materials required for the construction of elevated platform
barriers, semi-permanent barrier walls, and dust partitions shall conform with this specification and
the associated drawings. This requirement is also relative to any building materials utilized during
remove & replace abatement methods.

Negative Pressure Monitoring Equipment: A combination sensing alarm and recording pressure
differential monitor shall be approved by the COR/RE, when indicated in project requirements. The
owner/operator manual shall be included with this unit and remain on-site throughout the project.
KONA VOR DEMOLITION
In addition, a current calibration record for the unit, using a primary calibration standard, shall be
provided to the COR/RE for review. This record will verify that the unit has been properly
calibrated for the project prior to commencement of any removal operation.

Scaffolding: Scaffolding, as required to accomplish the specified work, shall meet all applicable
law requirements. All scaffolding shall be clean with no evidence of LBP contamination on the
unit. Any scaffolding with contaminated or soiled exteriors shall not be permitted onto the project
site. All lumber used as scaffolding inside the barrier shall be wrapped in two layers of 6 mil
polyethylene prior to use.

Transportation Equipment: Transportation equipment, as required, shall be suitable for loading,
temporary storage, transporting and unloading contaminated waste without causing lead exposure to
persons or property. All vehicles used to transport LBP waste shall meet all applicable regulations
regarding labeling and signs.

Vacuum Equipment: All vacuum equipment used in the work area shall utilize High Efficiency
Particulate Air (HEPA) filtration systems. Approval by the COR/RE is required for all HEPA
systems. A written statement regarding the most recent HEPA filter change for each individual
filtration unit must be submitted for COTR/RE approval.

Water Filtration: All water to be discharged shall be filtered through a multi-part filter system with
a final pore size of 5.0 micron, nominal. The proposed filtration system shall be submitted to the
COR/RE for approval. A filtering system not meeting the above requirement shall not be approved.

Other Tools and Equipment: The contractor shall provide other suitable tools for stripping,
removal, encapsulation, disposal and other abatement activities including, but not limited to: heavy
equipment (demolition projects only), fiberglass ladders, hand-held scrapers, stiff nylon brushes,
sponges, cleaning cloths, rounded edge shovels (usually plastic), squeegees and carts.

The materials, tools and equipment lists described above are general, and shall not be considered
all-inclusive.

1.10     ABATEMENT EXECUTION

1.10.1   Removal Of Movable Objects

The FAA is responsible for removal of all movable objects within the work areas, unless otherwise
specified by the CO. The COR/RE shall determine if moveable objects need to be pre-cleaned by
the contractor prior to removal. Storage space of movable objects will be coordinated through the
COR/RE.

1.10.2   Set-Up of Work Area

Prior to any work activities, the contractor shall erect a temporary barrier around the work area. The
barrier shall be adequate for restricting unauthorized personnel from the area, relative to site
requirements and the SOW being performed.
KONA VOR DEMOLITION

Prior to abatement activities, the contractor shall have an operational decontamination unit in place
for workers' use. The decontamination unit shall require RE/GCIH inspection and approval prior to
being used.

The contractor shall be responsible for ensuring that FAA equipment and electronic instruments,
when present, are protected from dust, water and heat damage during abatement operations.

1.10.3   Personnel Decontamination Facilities

Personnel decontamination facilities shall be required for any abatement area. The extent of the
required decontamination facilities will be indicated in each project task order. All decontamination
facilities shall comply with 29 CFR 1926.62 requirements. Personnel decontamination facilities
constructed at the work site shall utilize 6 mil opaque fire-retardant polyethylene sheeting for
privacy. All walls, ceilings, and floors will be constructed with a minimum of two layers of
polyethylene sheeting. Entry and exit from all decontamination facility system chambers shall be
through curtained doorways consisting of three sheets of overlapping polyethylene sheeting (triple
flap). Sheets shall be secured alternately at the top left and right sides and weighted at the bottom to
ensure they hang straight. Arrows shall be either painted on or taped on each individual curtain to
indicate which direction the curtain opens. Doorway designs which provide equivalent protection,
and are acceptable to the COR/RE, may also be utilized.

The PDF shall consist of a Clean Room, Shower Room and Equipment Room, each separated from
each other and the work area by air locks. Deviations from these requirements will only be
permitted due to site specific conditions that would restrict specified dimensions, or the issue of a
variance from the COR/RE.

The Clean Room shall be sized to adequately accommodate the work crew. Benches shall be
provided as well as hangers or appropriate storage for the workers' and visitors' street clothes.
Storage for respirators shall also be provided in this area. Clean protective clothing, disposable
towels, replacement filters for respirators, and other necessary items shall be provided in adequate
supply at the Clean Room. Whenever possible, a lockable door shall be used to restrict access into
the Clean Room during non-abatement working hours. Lighting, heat, and electricity shall be
provided as necessary for comfort. No smoking shall be allowed in the clean room.

The Shower Room shall contain one or more showers as necessary to accommodate personnel.
There shall be one shower per six “full shift” abatement persons, calculated on the basis of the
largest shift. Each shower shall be supplied with hot and cold water that is adjustable at the shower
fixture. The contractor shall take all necessary precautions to prevent any run-off from the Shower
Room. All water discharged shall be filtered through a multi-part filter system with a final nominal
pore size of 5.0 microns. The shower stall(s) shall be maintained in a clean, sanitary state and in
accordance with the GCIH's recommendations. The contractor shall supply soap, shampoo and
disposable towels to employees and authorized visitors. A towel rack and hanging soap dispenser
shall be available.
KONA VOR DEMOLITION
The Equipment Room shall be used for the storage of equipment and tools after they have been
partially decontaminated in the work area using a HEPA vacuum and/or wet cleaning techniques, as
appropriate. Workers and authorized visitors shall dispose of their protective clothing in the
Equipment Room, except for the respirator which will be worn into the shower. The disposable
protective clothing shall be placed into labeled 6 mil polyethylene disposal bags located in the
Equipment Room. Contaminated footwear (e.g. rubber boots and other reusable footwear) shall be
stored in the Equipment Room for reuse the following work shift. Any items clothing worn into the
work area shall be disposed of as lead-contaminated.

1.10.4   Equipment Decontamination Facilities

The EDF, also referred to as the Waste Load-out Area, is required for removing and
decontaminating double-bagged LBP waste from the work area, and decontaminating non-
disposable equipment. The EDF will be separate from the PDF and will be required for any
abatement areas. The EDF will consist of two chambers, serving as air locks, providing a system
for ingress and egress which only allows air movement from the clean outside areas into the
contaminated work area. The installation requirements for the EDF are consistent with those
required for PDF construction, as specified in section 1.10.3.

The first chamber from the contaminated work area, the Wash Room, shall be equipped with an in-
place drainage and filtration system, separate from that of the PDF shower system. The multi-part
filtration system shall have a nominal pore size of 5.0 microns. The second chamber, the Holding
Room, will be attached to the Wash Room. This chamber will be the final room of the EDF leading
to uncontrolled space where waste bags and/or equipment will be transported to storage trailers or
trucks.
KONA VOR DEMOLITION

1.10.5   Auxiliary Lighting

If necessary, halogen stand lighting fixtures shall be available to provide temporary lighting.
Electrical current for all temporary lighting inside the work areas shall be through a GFCI. All
lighting systems within each work area shall meet the approval of the COR/RE before abatement
will be allowed to proceed.

1.10.6   Abatement Operations

Upon a satisfactory inspection of the work area by the COR/RE, and written approval regarding the
contractor's removal and fiber control methods, the contractor may commence abatement
operations. All abatement shall be conducted in accordance with the contractor's approved
abatement plan and procedures and all requirements of this specification. Required types of PPE for
the different materials being abated are listed in Section 1.6.

1.10.9   LBP Abatement

This section details all areas where LBP abatement work is to be performed and lists areas requiring
special protection during the abatement work.

1.10.9.1 Work Area Preparation for LBP Abatement

All containment construction shall adhere to this specification and the requirements set forth in 29
CFR 1926.62 and applicable state and local regulations. The contractor shall comply with the
following procedures for preparation of the work area prior to any removal of LBP chips:

         A) Provide a physical boundary around the lead control area by installing appropriate
            barriers around the area in a manner that will prevent entry by unauthorized personnel.
         B) Signs reading "WARNING - LEAD WORK AREA - POISON - NO SMOKING OR
            EATING" shall be posted around the lead control area.
         C) Set up personnel and equipment decontamination areas, as described in Sections
            1.10.3 and 1.10.4.
         D) Coordinate all electrical service connections, requirements and equipment with the
            COR/RE. Service connections and electrical equipment shutdowns shall be
            coordinated with the COR/RE at least 10 days prior to commencement of work in
            each work area.
         E) Adequate portable fire extinguishing equipment shall be maintained within the work
            area, meeting the requirements of 29 CFR 1910.157 and the NFPA, including
            state/local fire safety regulations, as applicable.
         F) Pick up all visible loose paint chips/dust around the work area manually, and/or using
            a HEPA filter equipped vacuum.
         G) Place polyethylene sheeting on the floor or ground at the interior/exterior wall areas
            where loose LBP is to be abated. The polyethylene sheeting shall be sealed to the
            foundation and extend away from the foundation a minimum of six feet. The
KONA VOR DEMOLITION
            polyethylene sheeting shall be weighted down and the edges shall be raised to prevent
            runoff.
         H) For removal of LBP from ceiling surfaces, the application of polyethylene sheeting on
            the floor (two layers) will be required, with continuous 18-inch splash guards
            extending up the walls. The tops of all splash guards shall be continuously sealed with
            duct tape.
         I) For removal of LBP from floor surfaces, polyethylene splash guards shall be installed
            up walls to a minimum distance of 18 inches from the floor. The tops of the splash
            guards shall be continuously sealed with duct tape.

1.10.9.2 Standard Requirements During Removal of LBP

         A) If water is utilized during any abatement operation, it shall be continuously sprayed on
            the area being abated to minimize dust generation. Caution should be used when
            spraying the water. If an excessive amount of water is used and standing water is
            observed, the contractor shall collect and containerize the water. The water shall be
            passed through a filtration system prior to it being disposed of; upon project
            completion, the filter shall be included with the lead waste.
         B) The LBP that has been removed double-bagged into 6 mil polyethylene disposal
            containers. The disposal containers shall not be overloaded, be securely sealed, and
            be stored in a designated area until disposal at an appropriate facility.
         C) Any polyethylene sheeting utilized shall be wiped down or HEPA vacuumed at the
            end of each work shift. The sheeting shall be inspected for rips and tears and replaced
            as necessary. The work site shall be kept clean on a regular basis throughout the
            duration of the project.
         D) All tools and equipment shall be cleaned regularly and prior to removal from the work
            area by high-phosphate washing or use of an approved lead-cleaning agent, then
            completely HEPA vacuumed.
         E) Upon exiting the work area, the workers shall remove all PPE and properly
            decontaminate themselves at the approved PDF.

1.10.9.3 Specific Task Order Requirements

  INSERT PROJECT SOW AND APPLICABLE STANDARD OPERATING
                  PROCEDURES (SOPs) HERE
1.10.9.4 Encapsulation of Lead Painted Components

After the facility has been abated of LBP at the specified areas, and final visual clearance granted by
the COR/RE, the following procedures shall be adhered to, if encapsulation is specified:

The encapsulation coating shall be applied in accordance with the manufacturer's recommendations.
The encapsulation coatings shall be applied to the substrate in a continuous system as to seal the
surface being coated. All surfaces shall be inspected by the COR/RE.
KONA VOR DEMOLITION
Workers shall wear coveralls and a negative pressure respirator, equipped with HEPA filter
cartridges. Specific respirator cartridges may be required based on the MSDS for the encapsulant.
Workers shall decontaminate before leaving the work site.


1.11     DISPOSAL PROCEDURES

The contractor shall dispose of all LBP waste in an EPA approved waste disposal facility. It shall
be the responsibility of the contractor to determine current waste handling, transportation and
disposal regulations for the work site and each waste disposal landfill it intends to use. The
contractor shall comply fully with these regulations and all applicable laws. Prior to any waste
being transported off- site, the contractor shall provide a list to the COR/RE for review that includes
the following: 1) applicable regulations regarding waste requirements relative to the project; 2) the
chosen disposal site's requirements; and 3) a blank waste manifest.

The contractor shall document actual disposal of the waste at the designated landfill by completing a
disposal certificate and forwarding the original and a copy to the COR/RE.

1.11.1   Removal of Waste From the Work Area

Removal of LBP waste from the work area shall take place in the following manner. From inside
the work area, a worker in PPE will transfer a sealed, wet-wiped waste container to the EDF. A
second worker, also in PPE, will wash down the container over the drainage/filtration system and
transfer the decontaminated container into the holding area. A third worker, in PPE, will place the
decontaminated container into a clean, labeled 6 mil container. The outer container shall then be
sealed. The worker will then wet-wipe the exterior of the exterior of the outer container. The
required waste generator information labeling will be applied at this stage.

The container can now be transferred outside the holding area to a storage trailer or truck until it is
transported to the approved disposal facility. The storage containers, or storage areas, shall be
secured with a suitable lock when not being accessed for waste storage purposes. Hazard signs are
required on the exteriors of all storage containers or storage areas.

The decontamination procedure for contaminated equipment being passed out from inside the work
area will be consistent with that of the waste load-out. All equipment will be thoroughly
decontaminated in the wash area before being passed into the holding area.

Non-disposable equipment that cannot be adequately decontaminated will be HEPA vacuumed
and/or wet wiped in the EDF. The contaminated equipment will then be packaged in a sealed,
labeled 6 mil bag or appropriate container. The bagged/containerized equipment can then be passed
into the EDF for wet wiping.            At the completion of the wet decontamination, the
bagged/containerized equipment will be prepared for transportation from the work area.

1.11.4   LBP Disposal

1.11.4.1 Transport and Disposal of LBP Waste
KONA VOR DEMOLITION

The contractor shall contact the regional EPA, state and local authorities to determine LBP disposal
requirements. The requirements of the RCRA and applicable state solid waste plan requirements
shall be adhered to. A DOT certified waste transporter shall be required for the transport of lead-
containing or lead-contaminated materials considered to be hazardous materials.

The contractor may perform a waste characterization test on representative lead abatement wastes to
determine if the materials are regulated under RCRA, or may presume the lead abatement wastes
are RCRA regulated and dispose of accordingly. For Hawaii a sites, if the Toxicity Characteristic
Leaching Procedure (TCLP) analysis indicates that the lead concentration exceeds 5 parts per
million (ppm) or greater, the waste is regulated by Hawaii as a hazardous waste and shall be
disposed of accordingly. Landfills in Hawaii do not accept hazardous wastes.

The following materials shall be tested to evaluate their hazard classification, or shall be presumed
to be hazardous waste:

         -   Removed paint and/or paint chips
         -   HEPA and waste water filters
         -   Dust from HEPA vacuums, HEPA filters and damp sweeping
         -   Plastic sheets, duct tape and other materials used during the LBP removal
         -   cleaning cloths, sponges, mops, respirator cartridges, disposable suits/gloves and other
             materials used for testing, abatement and cleanup

NOTE:        State of Hawaii Department of Health Solid and Hazardous Waste Branch Office of
             Solid Waste Management does not consider intact painted building materials to be
             hazardous wastes and does not require the debris to be disposed of as hazardous waste.
             Components that have been scraped free of loose paint chips and encapsulated will be
             demolished with the building and sent to the landfill as general construction debris
             only if the paint remains intact and firmly adhered to the painted building material. If
             the paint becomes loose or dislodged from the painted building material then the waste
             characterization shall be performed and the painted debris shall be disposed of
             accordingly. This protocol shall apply in all cases, except for projects where more
             stringent requirements are included in the project-specific task order requirements.
KONA VOR DEMOLITION

1.12     RE-ESTABLISHMENT OF THE WORK AREAS

Re-establishment of the work area shall only occur following completion of clean-up and
encapsulation (if appropriate) procedures, and after a final project clearance inspection has been
performed, accepted and documented by the COR/RE.

1.13     RESTORATION AND REPAIRS

The contractor shall repair all damage that occurred as a result of abatement activities, and restore
the work space in accordance with the final inspection list.

1.14     DEMOBILIZATION FROM THE SITE

The contractor shall participate in a demobilization walk-through with the COR/RE to ensure
conformity to this specification. The contractor shall correct all deficiencies prior to completing
demobilization from the site.
KONA VOR DEMOLITION


                                      ATTACHMENT 1


   APPLICABLE PUBLICATIONS, REGULATIONS AND REFERENCE MATERIAL


       The publications and or agencies listed below form a part of this specification to
       the extent referenced. The publications/agencies are referenced in the text by basic
       designation only.


       A) State of Hawaii Department of Health Solid and Hazardous Waste Branch
          Office of Solid Waste Management


       B) American National Standards Institute (ANSI):
          - Z88.2-1980 .... Practices for Respiratory Protection.
          - Z9.2-79 .... Design and Operation of Local Exhaust Systems.

       C) American Society for Testing and Materials (ASTM):
          - D 2103 .... Polyethylene Film and Sheeting.

       D) Applicable state and local rules, regulations, orders, and codes.

       E) General Safety and Health Provisions, 29 CFR 1910.20, Subpart C. (OSHA)

       F) General Industry Lead, 29 CFR 1910.1025. (OSHA)

       G) Lead in Construction, 29 CFR 1926.62. (OSHA)

       H) National Electrical Code, latest edition.

       I) National Emission Standards for Hazardous Air Pollutants (NESHAP) -
          General Provisions, 40 CFR 61, Subpart A. (EPA)

       J) National Fire Prevention Association, latest edition.

       K) Occupational Safety and Health Act of 1970 (Public Law 91-596) Standards,
          Vol. I-V.

       L) Regulations Implementing the Resource Conservation and Recovery Act
          (RCRA), Title 42 U.S. Code, Section 6901.

       M) Uniform Building Code, latest edition.

       N) National Air Traffic Controllers Association (NATCA) Agreement, Article 77
KONA VOR DEMOLITION




       O) California Department of Toxic Substance Control (DTSC)

       P) HUD 1990a. U.S. Department of Housing and Urban Affairs; Office of Public
          and Indian Housing, Lead-Based Paint: Interim Guidelines for Hazard
          Identification and Abatement in Public and Indian Housing, Washington, D.C.,
          April 01, 1990; revised September 01, 1990.

       Q) HUD 1991. Department of Housing and Urban Development, (1991), the
          HUD Lead-Based Paint Abatement Demonstration (FHA), prepared by
          Dewberry & Davis HC-5831, Washington, D.C.

       R) California 1993. Lead Painted Construction Debris, Waste Evaluation
          Guidance, California Environmental Protection Agency, Department of Toxic
          Substances Control, Office of Scientific Affairs, Waste Evaluation Unit, RG
          Document #33, Revision 1, August 19, 1993.

       S) EPA 1997.       Environmental Protection Agency, Testing Methods for
          Evaluating Solid Waste, Physical/Chemical Methods. EPA\SW-846

       T) EPA 1992a.       Environmental Protection Agency (1992) Solid Waste.
          Applicability of RCRA Disposal Requirements to Lead-Based Paint Wastes.
          Office of Solid Wastes, Washington, D.C.

       U) EPA 1994a. Environmental Protection Agency, Draft EPA Model Lead Paint
          Abatement Worker Manual. Office of Pollution Prevention Toxics,
          Washington, D.C. Alice Hamilton Occupational Health Center, Landover,
          MD.

       V) NIOSH 1992a. Preventing Lead Poising in Construction Workers, NIOSH
          Alert, DHHS (NIOSH) Publication 91-116a, April 1992 (Revised Edition), 1-
          21.

       The Contractor shall be solely responsible for compliance with the publications
       used above and any other applicable regulations, ordinances, and codes.
KONA VOR DEMOLITION




SECTION 02221 - BUILDING DEMOLITION


PART 1 - GENERAL

1.1    RELATED DOCUMENTS

  A.   Drawings and general provisions of the Contract, including General and Supplementary
       Conditions and Division 1 Specification Sections, apply to this Section.

1.2    SUMMARY

  A.   Section includes demolition of designated structures; demolition of foundations and
       slabs-on-grade; disconnecting and capping and demolition of identified utilities;
       removing demolished materials from the site; protection of items to remain as indicated.

  B.   Hazardous materials removal plans and permits. Related sections:
       1.   Division 2 Section 02230 “Site Clearing”: Clearing outside periphery of
            structures.

  C.   Noise and dust abatement.

  D.   Related Sections include the following:
       1.    Division 1 Section 01322 "Photographic Documentation" for photographs taken
             before demolition.
       2.    Division 1 Section 01500 "Temporary Facilities and Controls" for temporary
             construction, protection facilities, and environmental-protection measures for
             demolition operations.

1.3    SITE CONDITIONS

  A.   Drawings indicate the general character, scope and extent of the demolition work to be
       performed. However, the drawings do not indicate in minute detail all portions of the
       demolition work to be done. The Contractor shall carefully examine the existing work
       to determine the full extent of the demolition work that will be required to make the
       completed work conform to the intent of the Contract Documents.

  B.   Contractor shall promptly notify the Owner when he encounters the following at the site
       during the course of construction. Owner will investigate the condition encountered and
       will instruct Contractors on how to proceed.
       1.     Subsurface or otherwise concealed conditions that differ materially from those
              indicated in the Contract Documents.
       2.     Unknown conditions of an unusual nature which differ materially from those
              ordinarily found to exist and generally recognized as inherent in construction
              activities of the type required by the Contract Documents.

BUILDING DEMOLITION                                                                   02221 - 1
KONA VOR DEMOLITION


1.4    SUBMITTALS

  A.   Division 1 Section 01300 “Submittals”: Submittal procedures.

  B.   Shop Drawings: Indicate demolition and removal sequence; location and construction
       of barricades, fences and temporary work.

1.5    CLOSEOUT SUBMITTALS

  A.   Division 1 Section 01703 “Contract Closeout”: Closeout procedures.

  B.   Project Record Documents: Accurately record actual locations of capped utilities, and
       subsurface obstructions.

1.6    QUALIFICATIONS

  A.   Demolition Firm: Company specializing in performing the Work of this section with
       minimum five years documented experience and with service facilities within 100 miles
       of Project.

1.7    SEQUENCING

  A.   Summary: work sequence. Provide COR with proposed sequence of work for review
       and approval, prior to commencing work.

  B.   Sequence activities to demolish the Work in the following stages:
       1.   Hazardous materials.
       2.   Structures and site improvements.

1.8    SCHEDULING

  A.   Describe demolition removal procedures and schedule. Provide COR with complete
       description of demolition removal procedures and schedule of work for review and
       approval, prior to commencing the work.


PART 2 - PRODUCTS – NOT USED.


PART 3 - EXECUTION

3.1    PREPARATION

  A.   Provide, erect, and maintain temporary barriers and security devices, including warning
       signs and lights, and similar measures, for protection of the public, Owner, Contractor’s
       employees and existing improvements to remain. Comply with OSHA regulations.

BUILDING DEMOLITION                                                                    02221 - 2
KONA VOR DEMOLITION


  B.   Protect existing landscaping materials, trees, appurtenances that are not to be
       demolished.

  C.   Mark location of utilities.

  D.   Conduct all demolition operations in such a manner to insure the safety of all persons
       and minimize property damage.

  E.   Removed and Salvaged Items: Comply with the following:
       1.  Clean salvaged items of dirt and demolition debris.
       2.  Pack or crate items after cleaning. Identify contents of containers.
       3.  Store items in a secure area until delivery to Owner.
       4.  Transport items to Owner’s off-site storage area designated by Owner.
       5.  Protect items from damage during transport and storage.

3.2    DEMOLITION REQUIREMENTS

  A.   Conduct demolition to minimize interference with adjacent structures and occupancies.

  B.   Cease operations immediately if adjacent structures appear to be in danger. Notify
       Contracting Officer’s Representative (COR). Do not resume operations until directed.

  C.   Conduct operations with minimum interference to private accesses.

  D.   Coordinate with F.A.A. to obtain written permission from adjacent property owners
       when demolition equipment will traverse, infringe upon or limit access to their property.

  E.   Sprinkle work with water to minimize dust. Provide hoses and water connections for
       this purpose.

  F.   Maintain fire suppression systems per local requirements.

3.3    DEMOLITION

  A.   Disconnect, remove, and identify designated utilities within demolition areas.

  B.   Remove foundation walls and footings.

  C.   Remove concrete slabs on grade.

  D.   Grade and compact areas affected by demolition to maintain site grades and contours.

  E.   Continuous clean-up and remove demolished materials from site.            Do not allow
       materials to accumulate in the building or on the site.

  F.   Do not burn or bury materials on site. Leave site in clean condition.


BUILDING DEMOLITION                                                                     02221 - 3
KONA VOR DEMOLITION


  G.   No explosives shall be allowed for the purposes of demolition.

3.4    NOISE AND DUST ABATEMENT

  A.   Exercise all possible precautions to keep noise to a minimum. Selection and disposition
       of power equipment shall be made with consideration of the least possible interference
       due to structure-borne and airborne noise. Air compressors shall be located with
       consideration of existing facilities in mind. Muffle equipment to every extent possible.

  B.   All demolition or other operations generating substantial noise shall be coordinated with
       the Owner. Excessive structural or airborne noise may be required to be scheduled on
       off-hours or weekends. Contractor shall include cost of scheduling work during such
       hours in his contract amount.

  C.   Exercise all possible precautions to keep dust from circulating and contaminating site,
       building and adjacent buildings and areas.

  D.   During entire period of work and during loading of excess material and debris, sprinkle
       area and material being loaded to reduce dust in air.


END OF SECTION 02221




BUILDING DEMOLITION                                                                    02221 - 4
KONA VOR DEMOLITION




SECTION 02230 - SITE CLEARING


PART 1 - GENERAL

1.1    RELATED DOCUMENTS

  A.   Drawings and general provisions of the Contract, including General and Supplementary
       Conditions and Division 1 Specification Sections, apply to this Section.

1.2    SUMMARY

  A.   Section includes removal of surface debris; removal of paving, curbs, driveways and
       sidewalks; removal of trees, shrubs, and other plant life; removal of active underground
       plants; removal of abandoned utilities; removal of above ground features including
       power poles, light poles, fences and topsoil excavation.

  B.   Related Sections:
       1.    Division 2 Section 02221 “Building Demolition.”
       2.    Division 2 Section 02222 “Site Demolition.”
       3.    Division 2 Section 02311 “Rough Grading.”


PART 2 - PRODUCTS (NOT USED)


PART 3 - EXECUTION

3.1    PREPARATION

  A.   Verify that existing plant life designated to remain is tagged or identified.

3.2    PROTECTION

  A.   Locate, identify, and protect utilities that remain from damage.

  B.   Protect trees, plant growth, and features designated to remain, as final landscaping.

  C.   Protect bench marks, survey control points, and existing structures from damage or
       displacement.

3.3    CLEARING

  A.   Clear areas required for access to site and execution of work.




SITE CLEARING                                                                           02230 - 1
KONA VOR DEMOLITION


  B.   Remove trees and shrubs within limits of work as indicated. Remove stumps and main
       root ball.

  C.   Clear undergrowth and deadwood, without disturbing subsoil.

3.4    REMOVAL

  A.   Remove debris and extracted plant life from site.

  B.   Remove paving, curbs, driveways, and sidewalks as indicated. Neatly saw cut edges at
       right angle to surface.

3.5    TOPSOIL EXCAVATION

  A.   Excavate soil from areas to be further excavated, relandscaped, or regraded, without
       mixing with foreign materials for use in finish grading.

  B.   Do not excavate wet soil.

  C.   Stockpile in area designated on site by Contracting Officer’s Representative (COR) to
       depth not exceeding 5 feet and protect from erosion. Material shall be stockpiled on
       impervious material on 36 mil Hypalon material and covered over with the same
       material, until disposal. No overnight stockpiling will be permitted unless approved by
       COR.


END OF SECTION 02230




SITE CLEARING                                                                        02230 - 2
KONA VOR DEMOLITION




SECTION 02311 - ROUGH GRADING


PART 1 - GENERAL

1.1    SUMMARY

  A.   Section includes removal of topsoil and subsoil; and cutting, grading, filling, rough
       contouring and compacting, the site for future site structures.

  B.   Related Sections:
       1.    Division 2 Section 02221 “Building Demolition.”
       2.    Division 2 Section 02230 “Site Clearing.”

1.2    REFERENCES

  A.   The latest edition of the publications listed below form a part of this specification to the
       extent referenced. The publications are referred to within the text by the basic
       designation only.
       1.    Standard Specifications for Public Works Construction (SSPWC), Latest Edition.
       2.    ASTM C136           Method For Sieve Analysis of Fine and Coarse Aggregates.
       3.    ASTM D698           Test Methods for Moisture-Density Relations of Soils and
                                 Soil-Aggregate Mixtures, Using 5.5 lb. Rammer and 12 inch
                                 Drop.
       4.    ASTM D1556          Test Method for Density of Soil in Place by the Sand-Cone
                                 Method.
       5.    ASTM D1557          Test Methods for Moisture-Density Relations of Soils and
                                 Soil-Aggregate Mixtures Using 10 lb. Rammer and 18 inch
                                 Drop.
       6.    ASTM D2167          Test Method for Density and Unit Weight of Soil in Place by
                                 the Rubber Balloon Method.
       7.    ASTM D2419          Test Method For Sand Equivalent Value of Soils and Fine
                                 Aggregate.
       8.    ASTM D2434          Test Method For Permeability of Granular Soils (Constant
                                 Head).
       9.    ASTM D2922          Test Methods for Density of Soil and Soil-Aggregate in Place
                                 by Nuclear Methods (Shallow Depth).
       10. ASTM D3017            Test Methods for Moisture Content of Soil and Soil-Aggregate
                                 Mixtures.

1.3    CLOSEOUT SUBMITTALS

  A.   Division 1 Section 01703 “Contract Closeout”: Closeout procedures.



ROUGH GRADING                                                                            02311 - 1
KONA VOR DEMOLITION


  B.   Project Record Documents: Accurately record actual locations of utilities remaining by
       horizontal dimensions, elevations or inverts, and slope gradients.

1.4    QUALITY ASSURANCE

  A.   Perform Work in accordance with the Standard Specifications.

  B.   Maintain one copy on site.


PART 2 - PRODUCTS (NOT USED)


PART 3 - EXECUTION

3.1    EXAMINATION

  A.   Verify site conditions.

  B.   Verify that survey bench mark and intended elevations for the Work are as indicated.

3.2    PREPARATION

  A.   Identify required lines, levels, contours, and datum.

  B.   Stake and flag locations of known utilities.

  C.   Locate, identify, and protect utilities that remain from damage.

  D.   Notify utility company regarding removal and relocation of their utilities.

  E.   Protect above and below grade utilities that remain.

  F.   Protect plant life and other features indicated to remain.

  G.   Protect benchmarks, survey control point, existing structures, fences, paving, and curbs
       from excavating equipment and vehicular traffic.

3.3    SUBSOIL EXCAVATION

  A.   Excavate subsoil from areas to be further regraded.

  B.   Do not excavate wet subsoil.

  C.   When excavating through roots, perform Work by hand and cut roots with sharp axe.

  D.   Remove subsoil from site.

ROUGH GRADING                                                                         02311 - 2
KONA VOR DEMOLITION


  E.   Stability: Replace damaged or displaced subsoil to same requirements as for specified
       fill.

3.4    FILLING

  A.   Install Work in accordance with the Standard Specifications.

  B.   Fill areas to contours and elevations with suitable soil materials.

  C.   Place fill material on continuous layers and compact in accordance with the schedule at
       end of this section.

  D.   Maintain optimum moisture content of fill materials to attain required compaction
       density.

  E.   Make grade changes gradual. Blend slope into level areas.

  F.   Remove surplus fill materials from site.

3.5    TOLERANCES

  A.   Top Surface of Subgrade: Plus or minus 1/10 foot from required elevation.

3.6    FIELD QUALITY CONTROL

  A.   Testing: In accordance with referenced standards.

  B.   If tests indicate Work does not meet specified requirements, remove Work, replace and
       retest.


END OF SECTION 02311




ROUGH GRADING                                                                        02311 - 3
KONA VOR DEMOLITION




SECTION 02745 - ASPHALT SURFACE REPAIR


PART 1 - GENERAL

1.1    RELATED DOCUMENTS

  A.   Drawings and general provisions of the Contract, including General and
       Supplementary Conditions and Division 1 Specification Sections, apply to this
       Section.

1.2    SUMMARY

  A.   This section includes repair of roadway asphalt pavement surfaces cut and removed
       for the demolition of buried utility services below roadbed.

  B.   This section includes the repair of asphalt surfaces weakened or damaged due to
       mechanical demolition equipment or dump truck traffic.

  C.   The limits of such repairs shall be the vicinity of the existing demolition project
       site, contractors parking and storage areas, the roadways access routes utilized by
       the contractor, and the access routes outside of the facility leading to a public
       roadway.

  D.   The contractor shall photograph and document the pre-construction conditions of
       the access road routes from the project site to the public road.


PART 2 - PRODUCTS

2.1    MATERIALS

  A.   Base Course: Base course shall be native material free of organic matter and trash.

  B.   Asphalt Concrete: Asphalt concrete shall be Class C2-AR4000.


PART 3 - EXECUTION

3.1    SURFACE RESTORATION TYPE

  A.   Type and details of surface restoration shall be as shown on the drawings or as
       specified. Where not shown or specified, surfaces shall be restored with the type
       that matches the existing surfaces or that is the most appropriate for adjacent
       surfaces.


ASPHALT SURFACE REPAIR                                                            02745 - 1
KONA VOR DEMOLITION


3.2    ASPHALT CONCRETE PAVEMENT REPLACEMENT

  A.   Subgrade: The subgrade shall be compacted to 95% relative compaction.

  B.   Base Course
       1.   The base course thickness shall match or exceed the adjacent existing base
            course thickness.
       2.   Edges of existing pavement that are damaged or broken shall be trimmed to a
            straight line. Trimming shall provide a smooth, sound, vertical edge for the
            new pavement to join.

  C.   Asphalt Concrete
       1.   Asphalt concrete for surface restoration shall be placed in accordance with
            Standard Specifications for Public Works Construction (SSPWC) Sections
            302-5.5 through 302-5.7 and as specified.
       2.   On prepared base course or existing pavement, the depth of asphalt concrete
            shall be the depth of the adjacent existing pavement plus 1 inch, but not less
            than 2 inches.
       3.   Asphalt paving may be placed in a single lift, providing the required
            thickness is not greater than 3 inches. Where the thickness is greater than 3
            inches, the surfacing shall be placed in 2 or more lifts. Each lift shall be 3
            inches maximum.
       4.   Asphalt concrete shall be spread and leveled by machine if possible. Hand
            tools or a mechanical spreader may be used only if the area is too confined for
            machine spreading.
       5.   Compaction
            a.    Compaction shall be performed with powered rollers capable of
                  providing compression of 200 to 300 pounds per linear inch of roller.
            b.    Rolling shall begin from the outside edge of the pavement replacement
                  and shall progress towards the existing surfacing. The rolling shall lap
                  the existing surface by at least half the width of the roller.
            c.    Where the existing surfacing bounds both edges of the pavement
                  replacement, rolling shall begin at the edges of the replacement, lapping
                  the existing surface at least half the width of the roller, and shall
                  progress towards the center of the replacement area. Each track shall
                  overlap the preceding track by at least half the width of the roller, and
                  sufficient passes shall be made over the entire area to produce the
                  required compaction and to remove roller marks.
            d.    Hand tampers shall be used where rolling is impossible or impractical.
       6.   The finished surface of the new compacted paving shall be flush with the
            existing surface and shall conform with the grade and crown of the adjacent
            pavement.




ASPHALT SURFACE REPAIR                                                            02745 - 2
KONA VOR DEMOLITION


3.3    FIELD QUALITY CONTROL

  A.   The Engineer will determine when atmospheric conditions, surface conditions, and
       material conditions are appropriate to proceed with surface restoration construction.


END OF SECTION 02745




ASPHALT SURFACE REPAIR                                                            02745 - 3

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:31
posted:10/1/2011
language:English
pages:84