ROAD CONSTRUCTION DEPARTMENT, BIHAR PROGRESS REPORT OF ONGOING
Document Sample


South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
1 Banka Dhaka More Banka Path Plan 280.07 18.09.06 Yes 17.04.07 17.04.07 171.22 219.82 31.03.08 280.07 219.82 28.00 6.50 6.50 6.50 6.50 5.00 0.80
Part-A (Km 0-8) 25.03.07
6.50
+1.40
3411(s)
320.46 24.05.07
28.03.06
2 Banka Dhaka More Banka Path Plan 77.50 05.04.07 Yes 31.10.07 31.10.07 62.81 31.03.08 51.00 62.81 - 1.00 1.00 0.80 0.85 18
Part-B (Bridge) 1.50
3 Banka Banka Belhar Path Plan 6.50 244.78 3412(s) 230.54 18.09.06 Yes 17.04.07 14.07.07 69.27 94.84 31.03.08 230.54 94.84 23.00 6.00 6.00 6.00 0.64 1
(Km 0-8) 28.3.06 25.03.07
+1.40
24.05.07
4 Banka Amarpur Shambhuganj Rd Plan (P) 24.00 837.20 6850(s) 911.68 08.01.07 Yes 30.04.08 07.09.08 122.32 391.21 31.03.08 541.46 391.21 4.55 22.00 22.00 8.00
(Km 0-24) 1.07.06 31.05.07
5 Banka Barahat Panjwara Rd Plan (P) 12.00 495.44 6204(s) 536.46 08.01.07 Yes 07.09.08 07.09.08 93.26 524.08 31.03.08 536.46 524.08 2.68 12.00 12.00 11.00 11.00 1.25
(Km 0-12) 14.06.06 09.03.07
6 Banka Pandeydih-Lahawan-Simultala Plan (P) 13.70 1002.12 6645(s) 621.79 08.01.07 Yes 31.05.08 07.09.08 69.22 353.62 31.03.08 438.15 333.62 6.20 11.40 11.00 7.00
Rd 27.06.06 23.05.07
(Km 0-13.7) 3.10
14.06.07
7 Banka Simutalla Katoria Rd Plan (P) 18.00 521.52 6794(s) 566.41 08.01.07 Yes 30.06.08 07.09.08 66.19 226.35 31.03.08 270.16 226.35 2.83 17.00 15.00 10.00
(Km 0-18) 30.06.06 09.03.07
+2.83
23.05.07
8 Banka Panjwara Dhoraiya Rd Plan (P) 14.88 644.61 6412(s) 696.13 08.01.07 Yes 30.04.08 07.09.08 111.48 652.06 31.03.08 660.00 652.06 3.48 15.00 15.00 14.00 11.00
(Km 0-15) 21.06.06 31.05.07
9 Banka Asarganj Shambhuganj Rd Plan (P) 2.00 69.95 6205(s) 77.89 08.01.07 Yes 31.07.07 07.09.08 46.41 62.76 31.03.08 77.89 62.76 0.38 2.00 2.00 2.00 2.00
(Km 0-2) 14.06.06 09.03.07
10 Banka Banka Belhar Purana Rd Plan (P) 24.00 767.47 6577 840.77 08.01.07 Yes 31.07.08 07.09.08 72.63 224.17 31.03.08 440.04 224.17 4.20 18.00 17.00 5.00
(Km 9-32) 24.06.06 31.05.07
11 Banka Akbarnagar Shahkund 12 FC 9.65 222.80 5995(s) 243.20 18.12.06 Yes 17.12.07 17.12.07 135.50 141.09 31.03.03 283.00 276.59 Nil 9.00 9.00 9.00 5.35 5.35 5.35 0.77 8
Amarpur Banka Rd 10.06.06
(Km )
11 Banka Total <<>> 132.73 5126.35 0.00 5082.44 0.00 0.00 0.00 0.00 957.50 2952.81 0.00 3808.77 3068.31 0.00 119.90 116.50 79.30 13.85 32.35 6.60 3.06 27
12 Bhagalpur Trimohan Ekachari Dhanaura Plan 20.20 716.28 10851(s) 863.49 06.03.07 Yes 31.03.08 05.03.08 29.20 382.29 31.03.08 863.49 411.50 8.60 18.00 18.00 6.00 4.00 4.00 0.80 9
Manhgama Road 13.09.06 21.06.07
(Km 0-20.20) +4.30
06.07.07
13 Bhagalpur Jagdishpur Sanhaula Road Plan 18.75 606.83 6994(s) 691.31 27.03.07 No 20.03.08 26.03.08 32.46 14.87 20.03.08 691.31 47.33 24.15 10.00 5
(Km 0-18.75) 5.07.06 29.06.07
+3.45
06.07.07
14 Bhagalpur Akbarnagar Shahkund Road Plan 13.30 523.81 8946(s) 546.39 22.01.07 Yes 21.01.08 05.03.08 0.36 30.17 20.03.08 546.39 30.53 16.32 10.00 0.36 0.36 7
(Km 4-18) 31.07.06 21.06.07
2.73
28.06.07
15 Bhagalpur Tilkamanjhi Champanagar Plan (P) 8.00 500.34 9791(s) 24.01.07 Yes 23.01.08 23.01.08 - 3.50 3.50 3.50 2.20 1.00 1.00 0.40 5
144.50
Road (Km 0-8) 21.08.06
16 Bhagalpur Tower Tatarpur Road Plan (P) 1.60 84.88 6398(s) 24.01.07 Yes 23.01.08 23.01.08 - 1.60 1.60 1.60 0.49
(Km ) 21.06.06 35.77
28.47
17 Bhagalpur Mahila College Mirjan Hat Plan (P) 3.00 148.16 6396(s) 948.28 24.01.07 Yes 23.01.08 23.01.08 94.27 165.53 948.28 14.06.07 0.80 0.80 0.80 1.15 1
Road (Km 0-3) 21.06.06 20.03.08
18.77 +4.74
28.06.07
18 Bhagalpur Tilkamanjhi Barari Road Plan (P) 3.00 106.06 7991(s) 24.01.07 Yes 23.01.08 23.01.08 - 3.00 3.00 3.00 2.70 2.70 4
(Km 0-3) 7.07.06 60.75
19 Bhagalpur Shambhuganj Ashargunj Road Plan 6.00 194.24 6397(s) 224.98 23.03.07 Yes 22.12.07 22.12.07 0.12 44.91 31.03.08 224.98 45.03 1.20 6.00 6.00 3.60
(Km 3-8) 21.06.06 14.06.07
1.20
21.06.07
20 Bhagalpur Bhagalpur Baikalpik Byepass Plan 10.55 434.84 8866(s) 315.05 08.01.07 Yes 07.10.08 07.10.08 40.69 149.79 31.03.08 315.05 190.49 6.30 5.49 7.10 5.59 4.80 0.09 1
Rd (Km 1.3-11.85) 1.12.05 21.06.07
+1.57
06.07.07
21 Bhagalpur Shahkund Asarganj Road Plan 7.50 323.16 13144(S) 346.03 26.04.07 No 09.01.08 0.15 - 31.03.08 346.03 78.29 1.72 7.50 7.50 0.30 3
(Km 7p-14) 24.11.06 21.06.07
22 Bhagalpur Construction of Rly Level Plan 0.30 40.16 4313(S) 41.41 04.07.07 03.12.07 - - 31.03.08 41.41 93.37 0.30 2
Crossing in place of Rly Under 26.03.07
Bridge in 1st Km of Bhagalpur
Yes
Amarpur via Kajraili to
Bhagalpur Muslim High School
(Km 7p-14)
23 Bhagalpur Bhikhanpur Barahpura IRQP 0.60 40.87 12146(S) 34.66 07.12.07 Yes 06.03.08 - 34.66 14.03.08 34.66 15.00
Road (1p) 16.10.07
Page 1 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
24 Bhagalpur Godda Pipaiti W&S 5.00 124.75 11258(S) 158.13 19.03.08 No 23.09.08 - 0.28 0.28
Road(Towards Thora) 25.09.07
(Km 1-5)
24 Bhagalpur <<>> 97.80 3844.38 0.00 4169.73 0.00 0.00 0.00 0.00 197.25 822.50 0.00 4011.60 1171.62 0.00 66.19 47.86 24.45 10.85 7.70 5.00 2.08 37
Total
25 Jamui Kharagar Amarth Shiv-Sona Plan (P) 20.00 769.70 6523(s) Yes 03.10.08 03.10.08 - 165.09 31.07.07 818.28 175.00 42.27 17.00 16.00 2.50
Manjway Road (Km 0-20) 23.06.06 05.07.07
3.50
03.03.08
04.01.07
26 Jamui Sono Khaira Rd Plan (P) 20.50 944.36 6755(s) Yes 03.10.08 03.10.08 411.39 269.38 31.07.07 884.03 275.00 18.76 17.00 16.50 1.70 1.50 1
04.01.07
(Km 0-20.50) 29.06.06 03.05.07
27 Jamui Jamui Kawakole Road Plan (P) 24.30 796.03 6676(s) 3752.77 04.01.07 Yes 03.10.08 03.10.08 228.87 31.07.07 774.16 236.00 9.37 22.00 20.50 3.75 1
(Km 0-24.30) 27.06.06 07.03.07
28 Jamui Sarwan Baksila Road Plan (P) 23.00 684.59 6751(s) Yes 03.10.07 03.10.08 - 322.16 31.07.07 763.50 340.00 7.65 22.00 22.00 11.00 3.50 6
04.01.07
(Km 0-23) 29.06.06 08.02.07
29 Jamui Sarwan-Chakai-Jasidih-Chopa Plan 15.77 528.33 13521(s) 529.00 20.03.07 Yes 19.01.08 19.03.08 53.56 - 31.07.07 475.31 230.00 - 15.00 15.00 15.00 15.00 2.00
Road (Km 59-75) dt.02.12.06
30 Jamui Kesopur Barwa Road Plan 16.00 382.35 8940(s) 393.20 08.01.07 Yes 05/2007 07.01.08 154.43 193.36 31.07.07 393.20 357.00 14.50 13.20 13.20 1.84
(Km 0-18) 31.07.06
31 Jamui Malaypur Barhat Lalmatia IRQP 3.00 36.45 11102(S) 35.16 13.11.07 No 12.01.08 - 36.06 3.20 36.00 3.00 2.80 2.80 0.20
Kadigram Road 20.09.07
(Km 1 to 3)
32 Jamui Amin Khaira Road IRQP 4.00 53.43 9490(S) 55.00 13.11.07 No 12.01.08 - 53.29 39.00 53.30 4.00 4.00 4.00
(km 2,3,4,5p & 6p) 10.08.07
33 Jamui Kenuhat Ratanpur Road IRQP 5.41 70.58 9492(S) 70.80 18.12.07 No 17.03.08 - 70.83 70.82 5.50 5.50 5.50
(km 7p,8,9,10,13 & 14) 10.08.07
34 Jamui Sikandra Lachhuar Dhadhur W&S 13.00 826.65 8479(S) 704.89 13.12.07 No 12.12.08 - 121.49 45.00 4.00 3.00
Road (5 km+ 8 km) 18.07.07
35 Jamui Keshopur Borwa Road (Km 5 IRQP 2.00 43.23 12672(S) 45.45 10.12.07 No 09.02.08 - 50.36 45.00 2.00 1.73 1.73 0.28
& 6) 01.11.07
35 Jamui Total <<>> 146.98 5135.70 0.00 5586.27 0.00 0.00 0.00 0.00 619.38 1510.90 0.00 4150.68 1863.12 0.00 126.00 93.00 33.95 18.50 30.73 27.23 2.32 8
36 Lakhisarai Kiul Station Approach Road Plan (P) 2.00 108.58 6411(s) 123.00 04.01.07 Yes 03.10.08 30.06.08 0.51 109.30 31.03.08 80.98 80.00 2.00 2.00 2.00 2.00 1.80 0.95 1
(Km 0-2) 21.06.06
24.018
37 Lakhisarai Surajgarha Kajra Road Plan (P) 7.50 274.12 7951(s) 319.00 04.01.07 Yes 03.10.08 30.06.08 10.24 21.91 31.03.08 210.24 31.85 2.30 3
31.05.07
(Km 1-8) 6.07.06
4.00
38 Lakhisarai Suryagarha Khaira Mehsauni Plan (P) 13.00 710.89 6521(s) 801.00 04.01.07 Yes 03.10.08 30.06.08 0.44 80.35 31.03.08 526.83 86.00 3.40 1.11 1.11 5
11.07.07
Road (Km0-12.50) 23.06.06
39 Lakhisarai Barahia Mini Byepass IRQP 0.80 35.60 10216(S) 36.10 24.01.08 No 25.03.08 - 34.32 0.80
24.08.07
39 Lakhisarai <<>> 23.30 1129.19 0.00 1279.10 0.00 0.00 0.00 0.00 11.19 245.87 0.00 818.04 197.85 0.00 5.40 2.00 3.11 2.00 4.10 0.00 2.86 9
Total
40 Munger Munger Bariyarpur Link Road Plan (P) 6.00 95.99 6404(s) 112.59 08.01.07 Yes 31.12.07 07.10.08 29.98 81.53 31.03.08 112.59 81.53 5.10 3.62
(Km 1-6) 21.06.06 13.828
41 Munger Gayghat Sangrampur Road Plan (P) 10.00 296.17 6848(s) 356.22 08.01.07 Yes 31.10.08 07.10.08 15.19 65.80 31.03.08 157.30 65.80 04.05.07 6.10 6.10 1.08
(Km 1-10) 01.07.06 2.57
42 Munger Munger Jamalpur Road Plan (P) 4.50 75.14 7990(s) 86.60 08.01.07 Yes 31.01.08 07.10.08 0.20 82.65 31.03.08 86.60 82.65 03.03.08 4.50 4.00
(Km 1,2,3p,4,6) 07.07.06
43 Munger Kharagpur Tarapur Road (Km W&S 12.10 859.07 6928(S) 859.07 20.08.07 Yes 31.07.08 - 110.09 31.03.08 446.35 110.89 11.80 2.90 0.00
0-12.30) 06.06.07
43 Munger Total <<>> 32.60 1326.37 0.00 1414.48 0.00 0.00 0.00 0.00 45.37 340.07 0.00 802.84 340.87 0.00 17.90 9.00 1.08 0.00 9.60 7.62 0.00 0
44 Shekhpura Sheikhpura Sahara Rd via Plan 9.00 465.40 9855(s) 473.29 28.03.07 Yes 28.08.08 27.09.08 0.18 60.93 31.03.08 294.79 60.03 1.36 9.00 8.00 2
Mehus 23.08.06 01.06.07
(Km 2-10) 2.36
14.02.08
45 Shekhpura Sheikhpura Sahara Rd via Plan (P) 9.40 507.00 6516(s) 812.86 04.01.07 Yes 03.10.08 03.10.08 62.24 194.87 31.03.08 437.84 207.09 5.29 8.50 6.50 2.00 1.60 0.42 12
Mehus(Km 1,11-19p) 23.06.06 27.04.07
+2.90
04.05.07
46 Shekhpura Mokama Barbigha Warsaliganj Plan (P) 14.26 530.30 6671(s) 816.78 04.01.07 Yes 03.10.08 03.10.08 63.68 471.32 31.03.08 441.20 480.21 8.59 13.00 13.00 11.00 10.00 3.70 1.30 5
Road 27.06.06 27.04.07
(Km 7.74-22) +3.08
04.05.07
47 Shekhpura Shekhpura Purainia Road Plan (P) 7.75 337.45 6581(s) 392.59 04.01.07 Yes 03.10.08 03.10.08 39.26 187.48 31.03.08 290.78 191.40 2.41 5.50 6.00 6.00 19
(Km 0-7.75) 24.06.06 27.04.07
+1.90
19.04.07
48 Shekhpura Puraina Ghat Kusumbha Road Plan (P) 6.00 642.36 6515(s) 642.36 04.01.07 Yes 03.10.08 03.10.08 56.72 129.29 31.03.08 401.95 137.85 5.37 5.50 3.50 0.80 12
(Km 0-6) 23.06.06 27.04.07
+2.61
04.05.07
Page 2 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
49 Shekhpura Belauni- Ghat Kusumbha Road Plan (P) 5.00 310.53 8939(s) 358.58 04.01.07 Yes 03.09.08 03.10.08 35.86 27.01 31.03.08 252.00 32.00 4.31 4.50
(Km 0-5) 31.07.06 27.04.07
+1.06
04.05.07
50 Shekhpura Shekhpura Arha Road Plan 19.80 534.66 11053(s) 618.00 28.03.07 Yes 27.11.08 27.09.08 0.52 152.61 31.03.08 332.20 127.81 Nil 14.00 12.50 6.00 0.20 4
(Km 0-20p) 18.09.06
51 Shekhpura Katara Bazar Road Plan 2.00 80.18 6670(s) 87.00 28.03.07 Yes 27.09.07 27.09.07 0.12 81.70 31.03.08 87.00 82.00 0.435 1.50 1.00 1.00 1.00 1.00
(Km 0-2) 27.06.06 27.04.07
+0.435
04.05.07
52 Shekhpura Shekhopur Sarai to Sheikhpura Plan 14.26 592.86 11289(s) 599.07 28.03.07 Yes 27.11.08 27.09.08 0.45 226.22 31.03.08 322.50 214.80 Nil 10.00 5.00 4.00 2.20 8
Road 25.09.06
(Km 0-14.26)
53 Shekhpura Shekhpura Shahpur Road Plan 14.20 516.74 868(s) 534.46 01.08.07 Yes 30.11.08 0.38 81.09 31.03.08 242.50 97.56 2.64 12.00
(Km 0-14.2) 22.01.07 14.02.08
54 Shekhpura Shekhpura Station Road (Km W&S 2.58 199.21 9871(S) 192.40 09.02.08 Yes 08.10.08 - 9.07 31.03.08 36.05 18.00 0.60
1P, 2 & 3P) 21.08.07
54 Shekhpura <<>> 104.25 4716.69 0.00 5527.39 0.00 0.00 0.00 0.00 259.41 1621.59 0.00 3138.81 1648.75 0.00 84.10 55.50 30.80 2.80 10.00 3.70 4.92 62
Total
55 Arrah Sakaddi-Chandi Rd Plan (P) 5.00 295.65 6882(s) 21.12.06 Yes 11/2007 20.09.07 23.91 229.03 31.03.08 337.23 300.00 5.00 5.00 4.50 4.50 4.50 3.00 0.10
(Km 0-5) 3.07.06
56 Arrah Bihiya-Tier Rd Plan (P) 13.00 624.29 6883(s) 21.12.06 Yes 11/2007 20.09.07 21.11 298.57 31.03.08 611.61 340.00 13.00 11.00 11.00 6.50 6.50
(Km 0-13) 3.07.06
57 Arrah Bihiya-Chaurasta-Karja-Barja Plan (P) 7.00 625.01 7956(s) 21.12.06 Yes 06/2008 20.09.07 0.06 104.16 31.03.08 472.94 150.00 3.50 2.80 2.50 1.50 1.20 1
Rd (Km 0-7p) 6.07.06
58 Arrah Chandi-Sandesh Rd Plan (P) 7.00 340.99 6402(s) 21.12.06 Yes 11/2007 20.09.07 123.90 338.22 31.03.08 375.05 330.00 7.00 7.00 7.00 6.00 6.00 6.00 0.60
(Km 0-7) 21.06.06
59 Arrah Shahpur-Bharauli Rd Plan (P) 6.00 200.62 6847(s) 21.12.06 Yes 10/2007 20.09.07 1.13 150.82 31.03.08 218.58 180.00 6.00 6.00 6.00 6.00 6.00
(Km 0-6) 01.07.06
60 Arrah Bharauli-Karnamapur Rd Plan (P) 7.00 323.54 8941(s) 21.12.06 Yes 10/2007 20.09.07 3.38 233.12 31.03.08 361.68 250.00 7.00 7.00 7.00 6.00 4.50 3.50
6435.18
(Km 0-7) 31.07.06
61 Arrah Saraiya-Balua Salempur Rd Plan (P) 10.40 746.09 6844(s) 21.12.06 Yes 07/2008 20.09.07 0.07 421.75 31.03.08 550.32 480.00 40.00 10.40 10.40 6.00 1.00 0.50 2
(Km 0-10.4) 1.07.06 07.05.07
62 Arrah Garhani-Agiaon Rd Plan (P) 6.80 399.97 6010(s) 21.12.06 Yes 08/2008 20.09.07 0.05 72.80 31.03.08 242.66 120.00 +32.17 6.00 3.50
(Km 0-6.8) 12.06.06 05.06.07
63 Arrah Piro-Sikarhatta Bihta Rd Plan (P) 22.40 960.90 6672(s) 21.12.06 Yes 06/2008 20.09.07 40.99 282.84 31.03.08 605.04 350.00 21.00 16.30 13.00 6
(Km 0-22.4) 27.06.06
64 Arrah Keshopur-Gundi-Saraiya Road Plan (P) 13.20 709.72 6754(s) 21.12.06 Yes 08/2008 20.09.07 0.06 73.36 31.03.08 513.34 130.00 7.00 5.50 0.00 6
(Km 0-13.25) 29.06.06
65 Arrah Pawna-Kori-Sandesh Rd Plan (P) 14.00 464.78 6401(s) 21.12.06 Yes 08/2008 20.09.07 0.15 28.15 31.03.08 278.07 80.00 14.00 5.00 14
(Km 0-14) 21.06.06
66 Arrah Veer Kuanwar Singh Link Plan 3.15 190.52 4802(s) 184.24 17.08.06 Yes 30.06.07 16.08.07 10.97 158.57 31.03.08 184.24 170.00 3.06 3.15 3.15 3.15 1.25 1.25 1.25 2.00
Rd (Km 0-3.15) 10.05.06 26.04.07
+0.0425
07.05.07
67 Arrah Bihiya Jagdishpur Piro Plan 10.00 206.02 2892(S) 176.24 19.09.06 Yes 30.06.07 18.09.07 43.13 176.90 31.03.08 176.24 213.00 1.00 9.25 13.00 10.00 10.00 10.00
Road (Km 0-10) 17.03.06 13.04.07
+0.88
19.04.07
68 Arrah Koilwar-Babura Rd 12 FC 12.53 253.64 6201(S) 273.36 18.11.06 No 25.03.07 129.08 103.44 08.02.08 274.00 219.00 1.36 7.00 7.00
(Km 0-13) 14.06.06 06.06.07
69 Arrah Sandesh-Sahar Rd (km 1,2 & IRQP 2.65 37.46 8477(S) 37.46 14.01.08 No 20.03.08 - - 08.02.08
3p) 18.07.07
70 Arrah Piro-Agion Rd IRQP 3.00 46.71 8946(S) 44.00 20.12.07 No 25.03.08 - 46.80 08.02.08 23.00 3.00 3.00
(km 7,8 & 9) 27.07.07
71 Arrah Arrah Barhara-Ekauna Rd (km PR 5.00 83.05 8945(S) 83.05 14.01.08 No 20.03.08 - - 08.02.08
0to 5) 27.07.07
72 Arrah Arrah-Sinha Rd W&S 16.00 957.59 8880(S) 915.50 14.12.07 Yes 13.06.09 - 121.17 31.03.08 122.64 130.00 15.00 1.00
(km 0 to 16) 26.07.07
73 Arrah Arrah-Ekauna Khaira-Sahar Rd W&S 18.00 987.52 13465(S) 981.22 12.02.08 No 11.08.09 - 43.68 31.03.08 27.90 22.00 13.00
(Km 0 to 18) 23.11.07
74 Arrah Arrah-Ekauna Khaira-Sahar Rd W&S 17.00 1188.21 13029(S) 1235.93 12.02.08 No 11.08.09 - 21.34 31.03.08 45.00 33.00 11.00
(Km 19 to 35) 12.11.07
75 Arrah Bihiya Chaurasta Barja via IRQP 6.25 159.85 9872(S) 174.24 12.02.08 No 11.08.09 - 4.53
Karja Road 21.08.07
(Km 8 to 13)
76 Arrah Chandi Sandesh Road (Km 8 W&S 8.62 594.77 12144(S) 536.32 14.01.08 No 13.01.09 - 25.00 14.03.08 19.72 12.00 4.00
to 15.62) 16.10.07
77 Arrah Arrah-Salempur Road CRF 14.00 337.47 1045(S) 160.41 - 6.00 5.60 5.60 5.60 5.60
16.02.04
77 Arrah Total <<>> 228.00 10734.37 0.00 11076.74 0.00 0.00 0.00 0.00 558.39 2934.25 0.00 5416.26 3532.00 0.00 168.30 102.25 75.75 48.35 33.45 39.35 2.70 29
78 Bhabhua Kudra Parsathua Road Plan 16.65 650.86 13522(s) 619.16 16.03.07 Yes 15.03.08 15.03.08 42.10 447.76 28.03.08 619.52 480.00 3.19 16.20 16.20 16.20 13.50 11.00 4.50 0.90
(Km 1p-19p) dt.02.12.06 19.04.07
+3.19
27.04.07
Page 3 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
79 Bhabhua Siswara Mukhraon Road Plan 9.70 147.59 2893(s) 175.41 31.07.06 No 30.07.07 30.07.07 16.00 221.59 28.03.08 237.52 237.52 Nil 7.60 7.60 9.30 9.25 9.25 0.30
(Km 1,2, 12-18.7) 17.03.06
80 Bhabhua Siswara Mukhraon Road Plan 9.00 431.31 1268(s) 447.91 09.03.07 Yes 15.11.07 08.08.07 63.07 378.74 28.03.08 447.91 445.91 Nil 9.00 9.00 9.00 9.00 9.00 9.00
(Km 3-11) 05.02.07
81 Bhabhua Chainpur -Bieur Rd Plan (P) 22.00 857.94 5997(s) 994.58 06.01.07 Yes 05.09.08 05.10.08 59.00 28.38 28.03.08 487.89 86.66 36.80 10.50 7.00 7.00 11
(Km 0-22.4) 12.06.06 01.06.07
+4.60
08.06.07
82 Bhabhua Hata-Mahdaich Rd Plan (P) 15.40 604.41 5988(s) 711.66 06.01.07 Yes 05.09.08 05.10.08 66.32 95.57 28.03.08 370.17 161.42 29.51 10.00 13.50 10.00 5.50
(Km 0-15) 10.06.06 08.06.07
3.55
14.03.08
83 Bhabhua Bhabhua-Adhaura Rd Plan (P) 40.00 646.22 6578(s) 760.24 06.01.07 Yes 05.09.08 05.10.08 11.38 200.12 28.03.08 402.08 210.01 15.00 14.50 7.30 0.35 6
(Km 0-27, 41-53) 24.06.06 28.08
08.06.07
+3.51
28.06.07
84 Bhabhua Chand Pawara Kharati Rd 12 FC 8.00 178.32 6473(s) 193.94 11.11.06 Yes 10.11.07 10.11.07 32.83 122.54 28.03.08 193.94 122.54 8.28 7.30 1.20 7.30 7.30 7.30 0.60
(Km 1p,9p-16) 22.06.06 08.06.07
+0.92
28.06.07
85 Bhabhua Chand Pawara Kharanti Road IRQP 1.00 19.73 11624(S) 19.72 06.11.07 Yes 05.01.08 - 8.20 28.03.08 19.70 8.70 1.00 1.00
(17 Km ) 03.10.07
86 Bhabhua Bhabhua Kudra Road W&S 9.00 523.18 9577(S) 553.79 25.01.08 No 24.01.09 - 117.15 28.03.08 81.36 85.18 5.50 3.50 0.00
(Km to 12 to 20) 14.08.07
87 Bhabhua Bhabhua Chainpur Chand Rd PR 11.00 84.31 387(S) 83.46 01.02.08 No 31.03.08 - -
(Km 0 to 11) 09.01.08
88 Bhabhua Chand Pawara Kharanti Road IRQP 7.60 175.28 12498(S) 181.67 25.01.08 No 24.06.08 - 29.56 28.03.08 15.00 29.56 1.50
(Km 2P to 9P) 29.10.07
89 Bhabhua Ramgarh-Durgawati Road Plan 10.70 217.35 798(S) 214.53 31.07.06 No 30.07.07 208.80 20.04 28.03.08 229.00 228.75 10.00 10.75 10.70 10.70 10.70
24.10.06
90 Bhabhua Ramgarh-Durgawati Road Plan 10.00 124.01 1561(S) 144.74 31.07.06 No 30.07.07 135.87 7.57 28.03.08 144.68 143.45 10.00 10.00 10.00
15.02.06
91 Bhabhua Kudra Bhabhua Road Plan 11.00 201.88 1632(S) 177.47 31.07.06 No 30.07.07 132.09 4.18 28.03.08 132.09 135.17 11.00 11.00 11.00
17.02.06
91 Bhabhua Total <<>> 181.05 4862.39 0.00 5278.27 0.00 0.00 0.00 0.00 767.46 1681.40 0.00 3380.87 2374.87 0.00 76.10 69.75 108.00 68.95 41.80 69.05 2.15 17
92 Buxar Dumaraon-Bikramganj Rd Plan (P) 26.00 1613.89 6645(s) 1630.18 06.01.07 Yes 31.12.07 05.10.08 43.77 159.38 27.02.08 1533.35 203.99 8.19 15.00 11.00 10.00
(Km 0-26) 27.06.06 26.03.07
+8.19
04.05.07
93 Buxar Buxar-Itarhi Rd Plan (P) 10.00 435.85 6203(s) 477.06 06.01.07 Yes 31.12.07 05.10.08 44.10 18.33 20.06.07 391.47 63.47 2.98 5.50 5.50 5
(Km 0-10) 14.06.06 26.03.07
+2.98
04.05.07
94 Buxar Dhansoi-Dinara Rd Plan (P) 14.00 423.38 6758(s) 476.02 06.01.07 Yes 30.06.07 05.10.08 Nil 103.39 25.02.08 415.04 103.54 2.98 10.00 11.00
(Km 0-14) 29.06.06 26.03.07
+2.98
04.05.07
95 Buxar Parari-Sonbarsa Rd Plan (P) 7.00 174.23 5595(s) 189.87 06.01.07 Yes 30.06.07 05.10.08 2.34 24.34 25.06.07 168.06 26.89 0.999 4.00 3.00 1.50
(Km 0-7) 30.05.06 26.03.07
+0.999
04.05.07
96 Buxar Karmnasha Approach Rd Plan (P) 0.74 32.31 6405(s) 40.37 06.01.07 Yes 30.11.07 05.10.08 9.86 25.74 18.12.07 40.36 35.62 0.20 0.74 0.74 0.74 0.74 0.74 0.74
(Km 0-.9) 21.06.06 26.03.07
+0.20
04.05.07
97 Buxar Bhojpur Simri Road Plan (P) 6.30 334.34 4314(S) 261.00 16.08.07 Yes 16.11.07 - 168.35 16.02.08 251.39 154.98 5.00 6.30 6.30 5.60 2.20
(Km 0-9) 26.03.07
98 Buxar Dewalghat Approach Road Plan 0.98 167.00 161.00 06.08.07 Yes 06.11.07 - 38.44 22.12.07 161.91 38.44 0.98
99 Buxar Dumarapm Railway PR 0.37 15.67 11261(S) 14.10 13.11.07 Yes 16.02.08 - 12.21
Station Apporoach Rd 25.09.07
(km1p)
100 Buxar Buxar Central Jail IRQP 1.40 12.78 9907(S) 12.40 13.11.07 No 20.01.08 - 11.33 0.40 0.40
Approach Rd (Km 0 to 2p) 21.08.07
101 Buxar Station Ramrekha Ghat Rd IRQP 0.50 30.18 10756(S) 29.54 13.11.07 No 12.01.08 - 20.41 0.50 0.50
(2 Km ) 12.09.07
102 Buxar Station New Bazar Rd (Km IRQP 2.30 48.86 12499(S) 48.11 13.11.07 No 12.01.08 - 44.33 1.50 1.50
1,2 & 3p) 29.10.07
103 Buxar Buxar New Byepass Rd IRQP 2.20 23.29 11561(S) 22.79 13.11.07 No 12.01.08 - 22.03 0.50 0.50
(Km 2p & Soling in Flat- 1.10.07
km 0 to 2.2 )
Page 4 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
104 Buxar Bhojpur Dumri Rd PR 0.50 19.97 10754(S) 15.89 30.11.07 No 29.01.08 - 0.28
(Km 1p ) 12.09.07
105 Buxar Itarhi Dhansoi Road IRQP 5.50 130.59 11739(S) 130.82 09.02.08 No 31.03.08 - 98.85 2.75 5.50 5.50
05.10.07
105 Buxar Total <<>> 77.78 3462.33 0.00 3509.15 0.00 0.00 0.00 0.00 100.07 747.41 0.00 2961.58 626.93 0.00 43.97 34.54 17.04 0.74 17.74 12.84 0.00 5
106 Dehri-On-Sone Dumra Agrer Arohi Rd Plan 10.00 224.26 1559(s) 236.52 31.08.06 Yes 30.08.07 78.04 33.20 25.03.08 220.53 111.19 1.18 8.00 9.50 9.00 6.25
(Km 0-11) 15.02.06 30.07.07
1.18
18.03.08
107 Dehri-On-Sone Vedadih Darshnadih Raipur Plan (P) 12.80 360.28 6990(s) 14.12.06 Yes 31.12.07 60.69 84.88 25.03.08 248.76 144.77 10.00 10.00 10.00 4.50 4.50
Chorbadi Rd 5.07.06
(Km 0-12.8)
1.715
03.07.07
108 Dehri-On-Sone Sasaram Tomb Rd Plan (P) 2.50 101.21 7992(s) 14.12.06 Yes 13.09.08 12.32 52.33 25.03.08 78.09 64.59 1.80 1.80 1.80 1.00 1.00 1.00 1.35
(Km 0-2.5) 7.07.06
109 Dehri-On-Sone Rajpur-Nokha Rd Plan (P) 21.00 1054.46 6645(s) 14.12.06 Yes 28.02.08 22.55 171.44 25.03.08 481.50 193.75 5.12 16.00 9.00 6.00 0.80
(Km 0-21) 27.06.06 31.03.07
110 Dehri-On-Sone Old G.T.Rd Plan (P) 1.50 119.26 7954(s) 14.12.06 Yes 31.12.07 12.07 54.30 25.03.08 59.22 66.32 0.62 1.50 1.50 1.50 1.15
(Km 0-1.5) 6.07.06 03.03.07
111 Dehri-On-Sone Nokha-Noonsari Rd Plan (P) 9.50 537.46 6793(s) 4578.52 14.12.06 Yes 31.01.08 22.20 118.59 25.03.08 251.20 140.54 2.27 7.00 8.50 6.50
(Km 2p-11) 30.06.06 01.06.07
112 Dehri-On-Sone Nokha Nasirganj Plan (P) 22.40 1030.95 8950(s) 14.12.06 Yes 28.02.08 129.88 343.99 25.03.08 680.90 439.42 Nil 20.00 20.00 20.00 16.50
31.07.06
(Km 0-22.4)
113 Dehri-On-Sone Akorigola Bagain Amra Talab Plan (P) 17.80 394.26 6846(s) 14.12.06 Yes 31.12.07 0.0970 54.3200 25.03.08 381.90 54.33 1.88 14.00 3.00
(Km 0-17.8) 1.07.06 31.03.07
1.80
18.03.08
114 Dehri-On-Sone Dehri Tetrarh Rajpur Rd Plan (P) 21.40 586.37 6792(s) 14.12.06 Yes 31.01.08 29.40 86.09 25.03.08 255.50 114.77 3.11 11.00 10.00 1.50 1.90
(Km 0-19) 30.06.06 01.06.07
115 Dehri-On-Sone Itimha Sakala Rd Plan (P) 6.00 358.16 6796(s) 14.12.06 Yes 31.01.08 - 61.77 25.03.08 218.33 61.78 3.48 4.50 2.70 7
(Km 12-17) 30.06.06 03.07.07
1.74
18.03.08
116 Dehri-On-Sone G.T. Rd to Gagauli Rd Plan 4.00 74.81 12111(s) 79.59 08.11.07 Yes 08.05.08 - 20.59 25.03.08 20.44 3.50 3.50
(Km 2-7.5) 25.10.06
117 Dehri-On-Sone Sasaram-Darigaon Rd Plan 12.80 557.52 13080(S) 531.05 12.12.07 Yes 11.09.08 0.36 40.41 25.03.08 39.87 4.50 3.00 1.75
(Km 0-12.8) dt.22.11.06
118 Dehri-On-Sone Nasriganj Hariharganj PR 3.00 35.72 11260(S) 36.81 12.12.07 No 11.03.08 - 22.73 25.03.08 22.73 3.00 3.00 2.50
Jamalpur 25.09.07
(km 0 to 3.0)
119 Dehri-On-Sone G.T Rd to Pahleza stn. PR 2.10 46.06 11555(S) 45.54 10.12.07 No 15.03.08 - 11.47 25.03.08 10.00 2.00 2.00
01.10.07
120 Dehri-On-Sone Salempur Chiksil Munj Rd PR+IRQ 8.00 128.41 11254(S) 123.90 17.12.07 No 16.03.08 - - 25.03.08 4.00
(Km0-5 PR & 6-8 IRQP) P 25.09.07
121 Dehri-On-Sone Nawadih Muriar Chilbila Rd IRQP 6.70 94.81 11253(S) 94.80 10.12.07 No 15.03.08 - 9.18 25.03.08 9.18 5.00
(Km 0-6.70) 25.09.07
122 Dehri-On-Sone Dumraon Bikramganj Road PR 15.40 139.25 11738(S) 139.25 17.12.07 No 16.03.08 - 8.85 25.03.08 8.00
(Km 28-43.4) 05.10.07
123 Dehri-On-Sone G.T. Rd to Khairaha via IRQP 6.10 131.70 11623(S) 130.96 06.12.07 No 15.03.08 - 39.74 25.03.08 41.28 5.00 1.25 4.00
Patpura Road 03.10.07
(Km 0-6.20)
124 Dehri-On-Sone Itimha Sakala Rd PR 11.00 71.00 9489(S) 71.00 09.01.08 No 25.03.08 - - 25.03.08 5.00
(Km 0 to 11) 10.08.07
125 Dehri-On-Sone Dehri Anikut Rd PR 4.00 135.42 11560(S) 132.34 12.02.08 Yes 25.03.08 - 10.93 25.03.08 10.38 1.00 1.00
(Km 0-4) 01.10.07
126 Dehri-On-Sone Sasaram Tilauthu Road (Km13- IRQP 7.00 126.51 10759(S) 126.51 30.01.08 No 25.03.08 - - 25.03.08
19) 12.09.07
126 Dehri-On-Sone <<>> 205.000 6307.880 0.000 6326.775 0.000 0.000 0.000 0.000 367.611 1224.791 0.000 2875.930 1553.340 0.000 126.80 81.250 68.550 24.550 10.000 5.500 4.400 7
Total 0
127 Bihar Sharif Nagar Nausa to Plan (P) 1.70 87.48 6415(s) 97.48 12.12.06 Yes 31.03.07 11.06.08 14.00 83.04 31.03.08 97.48 97.48 1.70 1.70 1.70 1.70 1.70
Khushropur Rd (Km 0-2p) 21.06.06
Page 5 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
128 Bihar Sharif Asthawa Sak Sohra Rd Plan (P) 18.76 1426.70 6645(s) 1507.62 12.12.06 Yes 30.06.07 11.06.08 190.04 795.97 31.03.08 1507.62 1028.00 14.165 17.00 14.50 14.00 12.50 11.00 9.00 19
(Km 0-18.76) 27.06.06 30.04.07
7.0826
03.07.07
129 Bihar Sharif Hilsa Noorsarai Rd Plan (P) 10.00 359.58 527(s) 426.98 12.12.06 Yes 30.06.07 11.06.08 61.42 403.42 31.03.08 426.98 456.00 4.00 10.00 10.00 8.35 8.35 8.35 0.80
(Km 0-10) 18.01.06 30.04.07
+2.00
03.07.07
130 Bihar Sharif Hilsa Noorsarai Rd Plan (P) 8.81 523.09 6068(s) 611.05 12.12.06 Yes 30.06.07 11.06.08 61.19 450.04 31.03.08 611.05 520.00 6.00 8.98 8.98 8.98 8.98 8.98 8.98 11
(Km 11-18.98) 12.06.06 30.04.07
+3.00
03.07.07
131 Bihar Sharif Bihar Nizain Rd Plan (P) 4.77 260.05 5433(s) 287.38 12.12.06 Yes 31.03.07 11.06.08 35.03 129.35 31.03.08 287.31 157.00 2.00 4.77 4.77 4.77 4.00
(Km 12-15.765) 20.05.06 30.04.07
+1.00
03.07.07
132 Bihar Sharif Soradih Vidhipur Rd 12 FC 3.00 693.12 9850(s) 749.79 11.04.06 Yes 13.05.08 13.05.08 85.24 20.03.08 396.88 311.00 3.60 3.00 3.00 3.00 2.40 2.40 0.60 6
(Km 1-3) 23.08.06 30.04.07
3.60
304.12 04.07.07
133 Bihar Sharif Soradih Vidhipur Rd 12 FC 8.00 14.11.07 Yes 13.05.08 - 20.03.08 3.60 8.00 5.50 5.50 3.70 3.70
(Km 11-18) 12.03.08
134 Bihar Sharif Islampur Kewali Rajgir Giriyak W&S 1.90 67.36 10221(S) 66.59 04.01.08 No 03.07.08 - 27.59 1.50 1.50 1.50
Parwatipur Road (Km 24.08.07
48p,49,50p)
135 Bihar Sharif Bihar Nizain Rd W&S 0.22 14.27 11564(S) 12.12 27.12.07 No 26.03.08 - 12.12 0.50 0.22 0.22 0.22 0.22
(km 1p) 01.10.07
136 Bihar Sharif Bihar Bakhtiyarpur Rd (Km W&S 8.00 520.71 8940(S) - 0.53
121 to 128) 29.07.07
137 Bihar Sharif Gridh Kut Rd W&S 1.30 93.78 8880(S) - 0.19
26.07.07
138 Bihar Sharif Swarn Bhandar Rd W&S 1.00 102.48 8881(S) - 0.11
26.07.07
139 Bihar Sharif Virayatan Rd & Japani Mandir W&S 2.15 136.47 9481(S) - 0.12
Rd 10.08.07
140 Bihar Sharif Makdum Kund Rd W&S 0.27 25.36 9905(S) - -
21.08.07
141 Bihar Sharif Ajatshatru Rd W&S 0.25 19.67 8673(S) 1753.34 14.01.08 No 13.07.09 - -
20.07.07
142 Bihar Sharif Rajgir Bazar Rd (Km 1 & 2P) W&S 1.24 132.75 9623(S) - 0.11
16.08.07
143 Bihar Sharif Rajgir Panditpur Rd (Km 1 to W&S 2.25 230.18 9869(S) - 0.23
3P) 21.08.07
144 Bihar Sharif Rajgir Block Rd (305m) W&S 0.31 28.47 8674(S) - -
20.07.07
145 Bihar Sharif Chandi Sohsarai Road (Km 0 W&S 19.98 961.56 9476(S) - 1.09
to 20P) 10.08.07
146 Bihar Sharif Rajgir College Path (Km 1.57) W&S 1.57 127.01 9493(S) - 0.12
10.08.07
147 Bihar Sharif Pawapuri Jalmandir Rd (Km 0 W&S 4.00 450.51 8942(S) 256.36 17.01.08 No 16.07.08 - 16.32 0.50 0.50 0.50
to 4) 27.07.07
148 Bihar Sharif Salepur Soradih Road (Km 4 W&S 7.00 619.76
8943(S)
to 10)
27.07.07 472.52 17.01.08 No 16.10.08 - 61.28 7
149 Bihar Sharif Ghosi Sukhiawan Rd W&S 2.24 153.89
11252(S)
(Km 17.48-19.72)
25.09.07 143.49 29.01.08 No 28.07.08 - 0.26
150 Bihar Sharif Chandi Sohsarai Road Plan 19.47
66.25 1.09
151 Bihar Sharif Bihar Nizain Road Plan 10.00 368.51
870(S)
22.01.07 333.66 25.07.06 Yes 31.05.07 214.12 159.62 368.51 373.00
151 Bihar Sharif <<>> 138.18 7402.76 0.00 6718.38 0.00 0.00 0.00 0.00 727.29 2446.72 0.00 3695.83 2942.98 0.00 62.17 50.67 48.52 25.48 36.13 34.13 1.62 36
Total
152 New Capital Stuwart Rd Plan (P) 4.70 898.16 6669(s) 1192.54 15.12.06 Yes 30.10.07 14.08.08 189.62 02.04.08 322.79 189.62 1.30 1.30 0.80 0.08
(Boring Road) 27.06.06
153 New Capital Harding Rd Plan (P) 3.78 521.54 11648(S) 660.41 15.12.06 Yes 15.08.07 14.08.08 1.78 330.21 02.04.08 629.18 330.21 1.86 1.86 1.03 1.00 0.31 0.90
(Km 0-3.78) 07.10.06
154 New Capital Sahdeo Mahto Path Plan (P) 0.75 111.06 4797(s) 163.65 15.12.06 Yes 01.12.07 14.08.08 2.65 02.04.08 155.29 2.65 0.05 0.02
(Km 0-.75) 20.05.06
155 New Capital Flower Bed & Soil work in Plan (P) 18.94 11131(S) 14.08.08 - -
Sahdeo Mahto Road dt.20.09.06
(Km 0-.75)
156 New Capital Bari Rd Plan (P) 2.62 328.83 6514(s) 413.10 15.12.06 Yes 30.02.08 14.08.08 - 0.08 02.04.08 128.61 0.23 0.05
(Km 0-2.622) 23.06.06
157 New Capital Jagdev Path Plan (P) 3.25 111.24 7993(s) 143.48 15.12.06 Yes 30.06.07 14.08.08 5.36 02.04.08 151.45 5.36 0.47 0.47
(Km 0-3.245) 07.07.06
Page 6 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
158 New Capital Kankarbagh Main Rd (Old Plan (P) 5.64 1007.50 10009(s) 1228.22 15.12.06 Yes 30.04.07 14.08.08 589.50 02.04.08 1216.15 589.50 3.33 2.81 2.20 3.00 0.24
Bypass) 26.08.06
(Km 0-5.64)
159 New Capital East Boring Canal Rd Plan (P) 2.00 540.40 9853(s) 678.35 15.12.06 Yes 15.01.08 14.08.08 5.82 02.04.08 633.84 159.64 1.73 1.73 1.73 1.70 1.40 0.25
(Km 0-2) 23.08.06 159.64
160 New Capital West Boring Canal Rd Plan (P) 2.00 14.08.08 14.08.08 -
(Km 0-2)
161 New Capital Kankarbagh Colony Rd No.-1 Plan (P) 1.15 209.29 4798(s) 268.89 15.12.06 Yes 30.03.07 14.08.08 - 0.06 02.04.08 64.35 0.00
(Km 0-2p) 10.05.06
162 New Capital Rajendra Path Plan (P) 1.83 313.92 4954(s) 394.37 15.12.06 Yes 16.07.07 14.08.08 62.78 02.04.08 103.11 62.78 0.58 0.58 0.58 0.40
(Km 0-1.83) 13.05.06
163 New Capital Mithapur Anisabad Khagaul Rd Plan (P) 3.00 299.12 7950(s) 215.19 15.12.06 Yes 14.08.08 14.08.08 - 242.48 02.04.08 206.81 242.48 1.88 1.88 1.88 1.88 1.88
(Km 0-5p) 6.07.06
164 New Capital Braj Kishor Path Plan (P) 0.82 140.39 4958(s) 172.86 15.12.06 Yes 06.06.07 14.08.08 - 109.54 02.04.08 172.85 109.54 0.70 0.70 0.70 0.65 0.40
(Exhibition Rd) 10.05.06
(Km 0-0.818)
165 New Capital Nala Road Plan (P) 1.23 216.16 6390(s) 266.53 15.12.06 Yes 15.03.08 14.08.08 39.72 02.04.08 46.44 39.72 0.31 0.31 0.31 0.30
(R.K.Avenue Road) 21.06.06
(Km 0-1.23) 140.85
166 New Capital Patna Gaya Road Plan (P) 2.42 283.32 2898(s) 319.53 15.12.06 Yes 31.03.07 14.08.08 - 189.61 02.04.08 300.81 189.60 27.04.07 0.64 0.60 0.60 0.23 0.23
(Buddh Marg) 17.03.06 13.66
(Km 0-2.42) 08.06.07
167 New Capital S.P. Verma Rd Plan (P) 0.34 52.80 4956(s) 66.46 15.12.06 Yes 26.06.07 14.08.08 66.76 02.04.08 66.67 66.76 0.33 0.33 0.33 0.33 0.33
(Km 0-.34) 13.05.06
168 New Capital Jamal Rd Plan (P) 0.47 36.82 4955(s) 43.85 15.12.06 Yes 20.07.07 14.08.08 - 39.00 02.04.08 43.84 39.00 0.43 0.43 0.43 0.43 0.43
(Km 0-.47) 13.05.06
169 New Capital Kankarbagh Colony Plan (P) 1.54 288.70 4796(s) 586.17 15.12.06 Yes 15.04.07 14.08.08 - 0.11 02.04.08 126.50 0.00
Road No.-2 10.05.06
(Km 0-2p)
170 New Capital Kankarbagh Colony Road No.- Plan (P) 0.44 196.59 11522(S) 14.08.08 14.08.08 - -
2 Part -II 03.10.06
(Km )
171 New Capital Bankipur Danapur Plan (P) 5.10 740.48 6580(s) 1401.37 15.12.06 Yes 20.01.08 14.08.08 0.51 201.41 02.04.08 995.34 201.40 1.10 1.10 1.10 1.51 1.10
(Km 0-5) 24.06.06
172 New Capital Kidwaipuri Sri Krishna Nagar Plan (P) 2.24 139.10 7988(s) 158.02 15.12.06 Yes 21.01.08 14.08.08 7.39 - 02.04.08 18.84 0.00
Buddha Colony Bankipur 07.07.06
Danapur Link Rd
(Km 0-2.24)
173 New Capital Ashiana more to Digha Ghat Plan (P) 4.70 376.89 479(s) 536.97 15.12.06 Yes 15.11.07 14.08.08 11.05 258.59 02.04.08 258.59 2.85 2.85 2.85 2.30
Road (Km 0-4.7) 17.01.06
174 New Capital Ashiana more to Patliputra Plan (P) 2.90 201.44 6392(s) 303.72 15.12.06 Yes 15.06.08 14.08.08 2.81 60.51 02.04.08 60.51 0.54 0.53 0.37
Road 21.06.06
(Km 0-2.9)
175 New Capital Sinha Library Path Plan (P) 0.56 124.25 4957(s) 136.46 15.12.06 Yes 30.03.07 14.08.08 - 113.00 02.04.08 136.46 113.00 0.58 0.58 0.58 0.56 0.56
(Km 0-0.63) 10.05.06
176 New Capital Birchand Patel Path Plan (P) 1.22 365.09 9939(s) 422.37 15.12.06 Yes 28.02.07 14.08.08 25.95 351.66 02.04.08 416.84 351.66 0.92 0.92 0.80 0.90 1.00
(Km 0-1.22) 24.08.06
177 New Capital Amarnath Path Plan (P) 0.54 75.01 6668(s) 92.14 15.12.06 Yes 28.02.07 14.08.08 - 76.22 02.04.08 90.26 76.22 0.52 0.52 0.52 0.52 0.52 0.25
(Km 0-.537) 27.06.06
178 New Capital Civil Court Link Rd Plan (P) 1.71 159.50 6667(s) 221.79 15.12.06 Yes 30.08.07 14.08.08 - 56.29 02.04.08 33.07 56.29 0.68 0.68 0.68 0.15
(Km 0-1.708) 27.06.06
179 New Capital Arya Kumar Rd Plan (P) 1.32 211.93 6666(s) 269.63 15.12.06 Yes 25.04.08 14.08.08 - 0.05 02.04.08 70.37 0.00
(Km 0-1.2) 27.06.06
180 New Capital Mithapur Anisabad Khagaul Rd Plan 1.21 274.90 11218(S) 254.66 31.01.07 Yes 30.10.07 30.10.07 - 254.66 106.98 1.00 1.00 0.55 0.40
(Km 0-1.21) 22.09.06
181 New Capital ISB Stand, Mithapur to Plan 1.85 757.71 1592(s) 709.00 02.05.07 Yes 01.05.08 01.05.08 - - 665.23 246.33 1.30 1.20 1.10 0.20
Karbighahia more Road (Incl. 08.02.07
of NH-30 T Junction)
(Km 0-1.852)
182 New Capital Saidpur Road (Premchand Plan 0.50 46.98 7319(S) 50.53 12.10.07 Yes 22.02.08 - - 50.53 2.29 0.20 0.20 0.20
Golumber to Bari Road Jn) 18.06.07
(Km)
183 New Capital T.N Banerjee Path (0.76 km) PR 0.76 33.75 11858(S) 30.86 24.10.07 Yes 23.02.08 - 13.98
09.10.07
184 New Capital Mithapur Anisabad Khagaul Rd- PR 0.86 14.38 11099(S) 13.69 05.11.07 Yes 23.02.08 - 8.34 1.00 1.00 0.55 0.50
Bhikhari Thakur Railway 20.09.07
Overbridge.
185 New Capital Kankarbagh L Sector Rd. B PR 1.13 10.90 11625(S) 10.24 01.11.07 Yes 23.02.08 - 5.02 1.20
to G 03.10.07
186 New Capital Rajendra Nagar ROB west PR 0.69 7.48 11100(S) 7.45 29.10.07 Yes 28.01.08 - 6.94 0.69
Service Rd 20.09.07
(0.69340 km)
187 New Capital Golakpur Link Rd PR 0.60 6.23 11631(S) 6.20 26.10.07 Yes 25.01.08 - 6.89 0.60
03.10.07
Page 7 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
188 New Capital South Harding Rd to Taylor Rd IRQP 2.10 30.21 10220(SD) 30.11 24.10.07 23.02.08 - 21.23
(2.10 km) 24.08.07
189 New Capital Bhattacharya Road IRQP 0.23 20.12 8483(S) 19.81 24.10.07 Yes 23.02.08 - 9.21
18.07.07
190 New Capital I.G Road W&S 0.65 70.33 11568(S) 71.81 21.01.08 No 20.03.08 - 19.83 71.81 0.50 0.50 0.20 0.10
01.10.07
191 New Capital IG & PG Link Ro W&S 0.31 43.42 11557(S) 41.77 19.11.07 Yes 19.01.08 - 11.30 41.77 11.298 0.16 0.16 0.16
01.10.07
192 New Capital Ashok Rajpath (PMCH main W&S 0.35 58.74 8478(S) 62.37 30.08.07 Yes 15.02.08 - 28.12 62.37 20.303 0.30 0.30 0.30 0.30 0.30
gate to Khudabaks Library) 18.07.07
(353m)
193 New Capital Station Road (Nehru Golamber W&S 0.22 31.03 11558(S) 15.50 24.11.07 No 23.01.08 - 3.05 15.50
to Jamal Road) 01.10.07
194 New Capital Dakbanglow Rd (Kotwali to W&S 0.38 51.50 9904(S) 46.22 04.10.07 Yes 03.01.08 - 20.81 46.22 11.29 0.38 0.38 0.38 0.38 0.38
Dakbanglow Chowk-Footpath, 21.08.07
Channel Curve, Urinal etc.
(0.375 km)
195 New Capital Riding Rd (Bailey rd to W&S 0.72 148.54 7905(S) 147.02 29.11.07 Yes 28.01.08 - 33.50 147.02 33.409
Mechanical Work Shop) 04.07.07
196 New Capital Wheelar Rd (Patel Chowk to W&S 1.26 187.48 8476(S) 181.75 29.11.07 Yes 28.02.08 - 33.00 181.75 20.706
Mechanical Workshop) 18.07.07
[1.26km]
197 New Capital Hartali More Junction in Bailey W&S 159.63 8480(S) 169.30 19.11.07 No 28.05.08 - 11.00 165.00 4.04
Road (Km ) 18.07.07
198 New Capital Kankarbagh Rd No.4 (Harding W&S 4.70 679.46 8484(S) 722.10 21.01.08 No 20.10.08 - 6.87 19.75 0.50
Shouldering, Footpath, Drain 18.07.07
and W/S 4696 km)
199 New Capital Improvement of Road Jn near IRQP 64.63 11559(S) 63.95 01.02.08 No 31.05.08 - -
Planetarium 01.01.07
200 New Capital Phulwarisharif Janipur Rajghat W&S 7.00 420.36 12070(S) 330.18 08.03.08 07.09.08 07.09.08 - -
RD(Km3.75-10.75) [NH-98 Jn 15.10.07
to Janipur]
201 New Capital Baily Road(0-4Km) from PR 4.00 155.77 4047(S) 163.50 28.03.08 No 04.04.08 18.37 3.00
Kotwali to Police Wireless 19.03.08
office
201 New Capital <<>> 87.770 11242.011 0.000 13504.058 0.000 0.000 0.000 0.000 55.310 3402.312 0.000 7851.456 3601.404 0.000 26.190 24.470 20.930 0.000 17.140 13.830 3.290 0
Total
202 Patna City Ashok Raj Path Plan (P) 3.10 231.75 5432(s) 249.71 15.12.06 Yes 14.08.08 14.08.08 71.60 115.25 03.04.08 275.00 222.15 10.36 1.40 0.80 3.10 3.10 3
(Km 11p-14p) 25.05.06 06.06.07
1.48
29.06.07
203 Patna City Agam Kuan Maruf Ganj Rd Plan (P) 3.89 346.29 5846(s) 371.93 15.12.06 Yes 14.08.08 14.08.08 56.93 137.26 03.04.08 400.00 162.89 15.40 3.60 3.60 3.60 0.80 3
(Km 0-3.89) 07.06.06 06.06.07
+2.20
29.06.07
204 Patna City Shershah Rd Plan 2.51 198.32 6994(s) 212.03 12.12.06 Yes 14.12.07 14.12.07 38.00 115.53 03.04.08 212.03 151.50 6.36 0.65 0.65 0.65 0.65 0.65 7
(Km 0-2.51) 07.07.06 06.06.07
205 Patna City Barh Mokama Barahiya Rd Plan 10.80 370.17 6993(s) 361.26 12.12.06 Yes 11.06.08 11.06.08 112.54 62.02 03.04.08 300.00 200.00 12.00 2.40 2.00
(Km 90-99) (P1) 5.07.06 06.06.07
2.00
18.02.08
206 Patna City Barh Sahari Sarmera Road Plan 10.00 555.76 5254(s) 539.37 12.12.06 Yes 11.06.08 11.06.08 101.32 214.04 03.04.08 350.00 324.00 13.50 10.00 10.00 9.60 7
(Km 0-10) (P1) 20.05.06 30.04.07
2.70
207 Patna City Khushrupur Nagarnausa Road Plan 12.00 1266.82 8454(s) 945.03 12.12.06 Yes 11.06.08 11.06.08 168.99 437.72 03.04.08 700.00 590.28 4.90 12.00 4.00 3.00 12
(Km 0-12) (P1) 23.08.06 02.03.07
+4.90
12 03 07
208 Patna City Bakhtiarpur Bazar Rd Plan 1.69 211.68 6665(s) 219.55 12.12.06 Yes 11.06.08 11.06.08 125.01 120.25 03.04.08 244.00 222.00 1.22 1.10 0.70 0.66 0.65 1.00 1.00 2
(Km 0-1.69) (P1) 27.06.06 02.03.07
1.22
12.03.07
209 Patna City Pali Ular Masaurhi Rd Plan 6.50 425.02 6881(s) 403.57 12.12.06 Yes 11.06.08 11.06.08 73.29 299.72 03.04.08 400.00 340.00 4.04 6.50 6.50 6.50
(Km 11.5-17.8) (P1) 03.07.06 12.03.07
2.02
210 Patna City Nabab - Bahadur Road Plan 0.50 80.94 3847(S) 83.23 04.07.07 05.02.08 - 61.77 03.04.08 83.23 65.88 0.50 0.50 0.40 0.40 0.40
(Km 11.5-17.8) 19.03.07
211 Patna City Ashok Rajpath to Plan 0.50 89.23 3847(S) 95.08 02.07.07 Yes 03.02.08 - 99.61 03.04.08 95.08 98.20 0.50 0.50 0.50 0.50
Khajekallah Ghat Road 19.03.07
(Km 11.5-17.8)
Page 8 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
212 Patna City Guru Govind Singh Path (Km IRQP 0.70 37.73 11101(S) 37.62 11.10.07 10.04.08 - 11.13 03.04.08 37.63 11.13 0.40 0.20
1p,2p=0.70 km) ) 20.09.07
213 Patna City Barh Sahari Sarmera Road (km PR 4.25 21.24 9485(S) 21.24 14.12.07 13.06.08 - 4.60 03.04.08 20.00 4.59 0.50 0.50
13P to 17) 10.08.07
214 Patna City Bharat Wagon Link Road (km IRQP 1.90 28.77 10125(S) 28.62 21.09.07 20.03.08 - 19.22 28.62 19.22 1.90 0.60
1 & 2p) 23.08.07
215 Patna City Agam Kaun Pahari Rd IRQP 1.35 48.18 10127(S) 48.18 14.12.07 13.01.08 - - 25.00
(km 1 & 2p) 23.08.07
216 Patna City Service cum Haulage Rd PR 2.58 105.30 11250(S) 105.30 14.12.07 28.02.08 - -
(Km 1 to 3p) 25.09.07
217 Patna City Masaurhi Bazar Rd IRQP 0.85 197.47 11741(S) 197.47 10.12.07 09.06.08 - 115.90 03.04.08 80.00 116.00 0.60
(Km 21.65 to 22.50) 05.10.07
218 Patna City Kumhrar Sandalpur Sanichra IRQP 1.20 59.12 12267(S) 57.17 10.12.07 21.08.08 - 1.51 03.04.08 40.00 1.50 0.20
Rd (Km ) 01.11.07
219 Patna City Ashok Rajpath (Old NH-30) to W&S 0.42 101.44 10129(S) 102.00 14.12.07 13.06.08 - 61.44 03.04.08 50.00 60.93 0.40 0.40
Didarganj (New NH 30) Road 23.08.07
220 Patna City Ashok Rajpath IRQP 7.50 298.32 12068(S) 362.34 20.02.08 Yes 21.11.08 - 35.69 03.04.08 35.00
(Km 3.2-10.70) 15.10.07
221 Patna City Barh Sahari Sarmera Road (KM W&S 2.54 156.59 9576(S) 157.00 12.02.08 Yes 11.11.08 - 22.77 03.04.08 40.00 22.77 1.00 2
11, 12 & 13P) 14.08.07
222 Patna City Guru Govind Singh Bypass W&S 1.20 408.17 13656(S) 408.17 20.02.08 19.05.09 - -
Road (1.20km) 27.11.07
223 Patna City AgamKuan-Shershah Rd (Link W&S 0.80 110.55 11563(S) 110.55 15.03.08 14.09.08 - -
Road via NMCH Jall Mina 01.10.07
Bazar(Km 0.7-1.5)
223 Patna City <<>> 76.78 5348.85 0.00 5116.42 0.00 0.00 0.00 0.00 747.68 1935.43 0.00 3415.59 2613.04 0.00 35.85 26.35 28.65 5.01 5.95 5.85 2.10 38
Total
224 Patna West Bailey Rd Gate (Jagdeo path Plan (P) 4.00 1169.35 6645(s) 1541.25 15.12.06 Yes 14.08.08 14.08.08 200.78 411.84 31.03.08 1527.92 487.22 15.42 1.85 1.94 1.78 0.76
to Saguna more) 27.06.06 12.03.07
(Km 0-4) +7.71
02.05.07
225 Patna West Bankipur Danapur Road Plan (P) 9.40 1071.83 9092(s) 1941.92 15.12.06 Yes 14.08.08 14.08.08 142.18 151.47 31.03.08 860.42 158.87 19.42 0.80 0.40 0.88
(Km 0-9.4) 03.08.06 12.03.07
+9.71
02.05.07
226 Patna West Khagaul Danapur Road Plan (P) 6.00 869.13 8257(S) 1197.12 15.12.06 Yes 14.08.08 14.08.08 121.74 220.64 31.03.08 832.16 241.87 11.96 1.60 1.91 0.60
(Km 0-6) 14.7.06 12.03.07
+5.98
02.05.07
227 Patna West Raghopur Pattot Road Plan 13.30 482.39 6513(s) 587.52 12.12.06 Yes 11.06.08 11.06.08 113.24 250.73 31.03.08 360.00 362.30 - 13.00 13.00 13.00 5.35 12
(Km 0-13.3) 23.06.06
228 Patna West Siwala to Bihta Chaurasta Rd Plan 12.86 1267.47 8938(s) 1237.62 16.10.06 Yes 31.12.07 15.04.08 50.22 352.44 31.03.08 1237.61 390.46 6.18 11.00 6.70 1.89 32
(Km 2-13.86) 31.10.06 22.03.07
+6.18
14.05.07
229 Patna West Siwala to Bihta Chaurasta Rd Plan 1.00 101.43 13083(S) 94.97 29.03.07 Yes 18.11.07 28.12.07 - 34.41 31.03.08 94.97 37.53 - 0.97 0.97 0.97
(Km 0-1) dt.22.11.06
230 Patna West Dulhin Bazar Rani Talab Pali Plan 9.14 438.09 9854(s) 382.92 15.11.06 Yes 28.03.08 14.05.08 20.67 122.77 31.03.08 382.92 143.05 1.91 7.90 7.55 2.80 10
Kinjar Road 23.08.06 22.03.07
(Km 0-9.3) +1.91
12.06.07
231 Patna West Anisabad Khagaul Road Plan 1.35 226.67 6391(s) 251.04 12.12.06 Yes 14.06.07 11.06.08 3.50 100.75 31.03.08 251.04 113.07 1.25 0.52 0.53 0.53 0.48 0.26
(Km 0-1.35) 21.06.06 22.03.07
+1.25
19.04.07
232 Patna West Naubatpur Pitmas Plan 10.00 424.58 4652(S) 449.81 21.09.06 Yes 31.01.08 20.03.08 190.73 230.59 31.03.08 374.00 373.26 - 8.80 0.90 4.20 8.80 8.80 8.80 0.19 1
(Km 10.5-20.5) 30.03.08
233 Patna West Khagaul Naubatpur 12 FC 6.80 160.27 6151(s) 159.31 25.09.06 Yes 24.09.07 24.09.07 131.06 12.96 31.03.08 161.80 143.72 - 0.35 6.44 6.44 6.44 0.35
(Km 10-14, 16p-18p) 23.06.06
234 Patna West Bailey Road to Vijay Nagar IRQP 1.54 84.53 8990(S) 75.29 06.03.08 No 05.09.08 - 2.78 31.03.08 2.78
Shivpuram colony 31.07.07
(Km 1-1.54)
235 Patna West Khagaul Siwala Rd Plan 4.00 1464(S) 2.98 0.54
(Km 0-4) 30.12.06
235 Patna West <<>> 79.39 6295.74 0.00 7918.77 0.00 0.00 0.00 0.00 977.09 1891.92 0.00 6082.85 2454.14 0.00 45.64 34.30 26.52 21.07 17.14 15.24 0.54 55
Total
236 Aurangabad Old G.T. Rd Plan 5.90 1268.21 6645(s) 613.17 15.03.07 Yes 14.03.08 - 82.66 31.03.08 126.91 82.66 0.8700 4.70 4.70
(Km 0-5.9) 27.06.06 04.05.07
2.19
18.05.07
237 Aurangabad Piroo Raghunathpur Deokund Plan 15.00 613.59 7955(s) 668.69 08.02.07 Yes 07.02.08 43.88 83.24 31.03.08 236.62 95.64 0.498 10.25 11.00 10
Bantara Uphara Senari 06.07.06 04.05.07
Manikpur Rd (Km 0-15) 2.526
18.05.07
238 Aurangabad Barun Daudnagar Rd Plan 35.30 977.83 9097(s) 917.21 15.03.07 Yes 14.03.08 50.244 619.84 31.03.08 411.62 619.84 0.55254 21.50 12.00 1.00 22.00 14.50 2
(Km 0-30.5) 3.08.06 (Mob adv - 04.05.07
41.00) 3.948
18.05.07
Page 9 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
239 Aurangabad Amba Nabinagar Rd Plan 24.00 524.17 8945(s) 507.24 20.03.07 Yes 19.03.08 53.816 322.71 31.03.08 289.29 322.70 0.11765 16.00 16.00 30
(Km 0-24) 31.07.06 (Mob adv 04.05.07
50.00) 2.243
18.05.07
240 Aurangabad Nabinagar Barun Rd Plan 34.00 733.22 6750(s) 674.41 23.03.07 Yes 22.03.08 - 228.57 31.03.08 242.25 232.50 0.415 24.00 24.00 19.00 48
(Km 11-34) 29.06.06 04.05.07
2.905
18.05.07
241 Aurangabad Barun Nabinagar Link Rd (Km W&S 1.25 37.08 10126(S) 35.10 23.10.07 No 22.04.08 - 11.63 31.03.08 11.62 1.20 1.20
1& 2p) 23.08.07
242 Aurangabad Nabinagar Barun Rd Plan 10.00 264.84 481(S) 264.84 Yes 191.61 - 10.00 10.00 10.00 10.00 10.00
17.01.06
243 Aurangabad Aurangabad Hariharganj Rd Plan 1.30 142.01 6414(S) 159.15 16.03.07 Yes 16.03.08 - 31.69 31.03.08 120.00 31.69 0.79 1.17 1.17
21.06.06 18.05.07
243 Aurangabad <<>> 126.75 4560.95 0.00 3839.81 0.00 0.00 0.00 0.00 235.49 1380.34 0.00 1426.69 1396.65 0.00 71.62 64.07 31.20 10.00 38.00 40.50 0.00 90
Total
244 Gaya - 1 Tekari Konch Khaira Road Plan 8.20 509.06 6519(s) 541.09 09.03.07 Yes 28.02.08 08.03.08 18.72 105.00 31.01.08 541.08 120.00 2.71 8.20 7.00 0.50 19
(Km 0-8.2) 23.06.06 07.06.07
245 Gaya - 1 Tekari Mauu IRQP 3.00 AA not done 121.13 20.02.08 No -
Kurth(1,2P,7P,8P,9P)
246 Gaya - 1 Gewal Bigha Road Under Gaya IRQP 1.28 15.84 12145(S) 15.76 19.11.07 Yes 18.02.08 - -
Town 16.10.07
247 Gaya - 1 Gaya-Bodh Gaya Rd IRQP 3.33 73.11 10474(S) 79.68 20.02.08 No 19.08.08 - 3.35 31.03.08 6.00 6.00 2.00
(2p,3,4p,5p,11,12p) 06.09.07
248 Gaya - 1 Dadarji to Rafiganj Rd (Km 12- IRQP 6.20 267.97 9578(S) 235.30 20.02.08 No 19.02.09 - 9.14 31.03.08 10.00 10.00 6.00
17.20) 14.08.07
249 Gaya - 1 Chichora More to Usas Deora IRQP 3.00 154.23 10753(S) 147.30 27.02.08 No 26.08.08 - 7.19 31.03.08 8.00 8.00 3.00
(Km 9-12) 12.09.07
249 Gaya - 1 Total <<>> 25.01 1020.20 0.00 1140.26 0.00 0.00 0.00 0.00 18.72 124.68 0.00 565.08 144.00 0.00 19.20 7.00 0.00 0.00 0.00 0.00 0.50 19
250 Gaya - 2 Fatehpur Vazirganj Road Plan 19.50 354.25 8947(s) 374.93 23.03.07 Yes 30.06.07 22.03.08 32.38 212.23 31.03.08 374.93 220.00 - 19.50 0.00 10.00 10.00 0.80 14
(Km 0-19.5) 31.07.06
251 Gaya - 2 Khijarsarai Byepass Plan 2.06 69.50 5430(s) 78.34 26.02.07 Yes 30.04.07 30.06.07 20.63 13.00 31.03.08 78.34 30.00 0.39 2.06 2.06 2.06 1.75 1
(Km 0-2) 25.05.06 04.05.07
0.39171
04.07.07
252 Gaya - 2 Tapovan Banganga Plan 9.50 93.92 8412(s) 117.54 20.03.07 Yes 03.06.07 19.03.08 16.68 55.20 31.03.08 117.54 75.00 0.588 9.50 6.00 6
(Km 5.5-15) 19.07.06 04.05.07
0.58786
04.07.07
253 Gaya - 2 Vindas Chamandih Plan 21.35 1092.96 9094(S) 1242.98 02.03.07 Yes 07.06.08 01.03.09 132.68 355.82 31.03.08 600.00 500.00 - 21.35 21.35 2.50 4
(Km 0-21.35) 03.08.06
254 Gaya - 2 Wazirganj Fatehpur Road IRQP 0.64 14.04 11569(S) 14.04 13.11.07 Yes 12.02.08 - 13.16 31.03.08 14.04 14.00 0.60 0.60
(Bazar portion) (km 0.64) 01.10.07
255 Gaya - 2 Falgu Bridge Approach Rd PR 0.83 25.95 9906(S) 25.95 01.10.07 Yes 31.03.08 - 20.95 31.03.08 25.95 25.50 1.00
(0.825 Km) 21.08.07
256 Gaya -2 Atri Jethian Rd IRQP 13.20 497.56 10757(S) 504.82 13.03.08 No 12.03.09 - 75.78 31.03.08 50.00 55.00 8.00
(Km 1-9, 11, 12, 17-18.20) 12.09.07
256 Gaya - 2 Total <<>> 67.08 2148.19 0.00 2358.60 0.00 0.00 0.00 0.00 202.37 746.14 0.00 1260.80 919.50 0.00 60.41 23.41 4.56 2.75 10.60 16.60 0.80 25
257 Jehanabad-1 Bandhuganj-Bhartu Sukiawan Plan 9.00 277.41 6753(s) 288.19 16.06.07 No 19.02.08 - 113.80 28.03.08 156.20 162.50 Nil 7.50 6.00 8.50 1
Road (Km 1-3,7-12) 29.06.06
258 Jehanabad-1 Bandhuganj-Okari Masaurhi Plan 3.50 217.34 6674(s) 207.67 09.05.07 Yes 31.01.08 06.03.08 - 116.87 28.03.08 172.00 175.80 - 3.50 3.25 3.25 3.25 5
Road (Km 6,7,15,16p) 27.06.06
259 Jehanabad-1 Imamganj Karpi Sahartelpa Plan 29.00 1601.18 8955(s) 1461.53 12.03.08 Yes 11.09.08 11.09.08 109.72 477.00 28.03.08 514.00 560.00 Nil 26.00 25.00 14.00 7.20 7
Road (Km 0-29) 31.07.06
260 Jehanabad-1 Makhdumpur Sonwa Plan 13.00 553.97 6991(s) 621.76 12.03.07 Yes 31.12.07 11.03.08 62.49 169.89 28.03.08 371.00 373.00 Nil 13.00 13.00 13.00 0.10 4
Hulasganj Rd (Km 7-20) 5.07.06
261 Jehanabad-1 Makhdumpur Barabar Rd Plan 3.00 145.30 6675(s) 177.41 19.03.07 Yes 27.12.07 - 89.52 28.03.08 145.00 148.00 Nil 3.00 3.00 3.00 3.00 5
(Km 7-9) 27.06.06
262 Jehanabad-1 Ghosi Sukhiawan Hulasganj 12 FC 16.00 567.12 6522(s) 706.40 05.01.07 Yes 31.01.08 31.12.07 52.76 256.69 28.03.08 426.20 432.50 Nil 16.40 16.40 16.40 0.50 11
Khudaganj Rd 23.06.06
(Km 0-18)
263 Jehanabad-1 Bajitpur Terra Road IRQP 4.00 68.90 9908(S) 64.18 12.12.07 No 30.06.08 - 15.45 28.03.08 12.00 16.00 4.00 3.50
(km 7 to 10) 21.08.07
264 Jehanabad-1 Bibipur Barawan Mugal Bigha IRQP 0.59 20.18 9625(S) 20.88 12.12.07 No 18.01.08 - 18.15 28.03.08 8.20 13.00 0.45 0.35
Rd (km 5p,6p,7p) 16.08.07
265 Jehanabad-1 Makdumpur Sonwa Hulasganj W&S 6.00 356.11 11256(S) 375.77 12.03.08 11.01.08 - 20.00 28.03.08 3.00 4
RD (Km 1-6) 25.09.07
266 Jehanabad-1 Makdumpur Barabar Rd (Km 0- W&S 6.00 289.98 11556(S) 319.75 24.02.08 23.10.08 - 30.92 28.03.08 6.00 2.00
6) 01.10.07
267 Jehanabad-1 Hatti More to Korra IRQP 0.46 22.55 3251(S) 22.01 20.03.08 No 19.04.08 8.54 28.03.08 0.23 0.23
Mohrimarsarai Road(5P) 10.03.08
Page 10 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
267 Jehanabad-1 <<>> 90.55 4120.04 0.00 4265.55 0.00 0.00 0.00 0.00 224.97 1316.83 0.00 1804.60 1889.80 0.00 75.40 66.65 62.33 14.05 0.00 0.00 0.58 37
Total
268 Nawada Warsaliganj Barbigha Rd Plan 5.00 100.64 1479(s) 109.61 12.07.06 Yes 11.07.07 11.07.07 57.30 34.54 31.03.08 109.61 96.74 3.84 5.00 5.00 5.00 4.90 2.90
(Km 1-3,9-10) 13.02.06 29.06.07
269 Nawada Warsaliganj Barbigha Rd Plan 19.00 631.41 6579(s) 645.43 13.08.07 Yes 12.08.08 - 54.64 31.03.08 291.50 75.57 3.22 8.50 8.25
(Km 4-8,11-24) 24.06.06 31.03.08
270 Nawada Pakaribarama Kawakol Rd Plan 7.00 167.25 1428(s) 144.22 31.10.06 Yes 30.07.07 30.07.07 28.74 89.93 31.03.08 144.22 118.00 4.05 7.00 7.00 7.00 5.25 4.00
(Km 1-3,7-10) 11.02.06 06.04.07
1.71
13.04.07
271 Nawada Pakaribarama Kawakol Rd Plan 12.20 459.78 6795(s) 482.99 30.03.07 Yes 29.09.08 29.09.08 - 62.38 31.03.08 275.50 64.50 9.66 6.50 6.00 2.50
(Km 4-6,11-19.2) 30.06.06 29.06.07
272 Nawada Warsaliganj Katarpur Rd Plan 11.60 396.22 6518(s) 447.09 30.03.07 Yes 29.03.08 29.03.08 - 23.16 31.03.08 447.06 20.75 8.94 3.25 3.25
(Km 0-11.6) 23.06.06 29.06.07
273 Nawada Hisuwa Khanwa Rd Plan 8.20 172.47 1480(s) 166.91 06.07.06 Yes 05.07.07 05.07.07 81.24 38.77 31.03.08 166.95 117.67 3.33 8.05 8.05 8.05 3.86 1.25
(Km 4-11.2) 13.02.06 29.06.07
274 Nawada Hisuwa Khanwa Rd Plan 3.00 95.82 8462(s) 108.29 15.03.07 Yes 14.03.08 14.03.08 - 20.94 31.03.08 122.19 21.00 1.62 2.25 2.25 1.62
(Km 0-3) 21.07.06 29.06.07
275 Nawada Kadirganj Roh Kowakol Rd Plan 15.00 544.70 11054(s) 561.99 14.03.07 Yes 13.09.08 13.09.08 64.83 190.43 31.03.08 514.50 194.64 2.809 9.00 3.00 7.75 7.75
(Km 17-31) 18.09.06 04.05.07
276 Nawada Atari Jethian Tapowan Plan 5.60 195.77 11647(S) 179.72 23.03.07 Yes 22.03.08 22.03.08 - 85.44 31.03.08 179.15 85.96 Nil 4.00 4.50 4.50 3.00
Wanganga Rd 07.10.06
(Km 27.7-33.3)
277 Nawada Nepura Nowama Rd 12 FC 6.40 85.43 6480(s) 74.65 17.01.07 Yes 16.01.08 16.01.08 - 2.73 31.03.08 74.53 3.19 6.62 0.95
(Km 0-6.4) 22.06.06 29.06.07
278 Nawada Kadirganj Roh Kowakol Rd IRQP 16.00 295.66 10755(S) 298.82 08.02.08 No 31.03.08 - 26.85 31.03.08 8.00 8.00
(Km 1 to 16) 12.09.07
279 Nawada Pakribarama Warsaliganj Rd W&S 12.50 554.32 11257(S) 450.33 30.01.08 No 29.07.09 - 22.50
(Km 1-12.5) 25.09.07
280 Nawada Warsaliganj Kharat Road W&S 11.10 592.19 11255(S) 473.58 25.03.08 No 24.09.09 -
(Km 1-11.10) 25.09.07
280 Nawada Total <<>> 132.60 4291.66 0.00 4143.61 0.00 0.00 0.00 0.00 232.11 652.31 0.00 2325.21 798.02 0.00 53.55 42.80 28.67 14.96 20.25 26.90 0.00 0
281 Begusarai Manjhaul Garhpura Road Plan 5.00 310.30 5645(S) 313.95 01.03.07 Yes 31.08.08 31.08.08 5.20 169.64 31.03.08 236.71 174.98 1.56 5.00 5.00 5.00 3.50 1.20 1.20
(Km 0 - 5) Part-A dt. 31.05.06 09.04.07
+1.56
07.05.07
282 Begusarai Malipur Daulatpur Road Plan 11.83 554.30 6040(S) 490.62 01.04.07 Yes 25.03.08 06.03.09 8.11 526.29 31.03.08 530.39 537.90 4.90 11.83 11.83 11.83 2.00 11.83 10.00
(Km 0 - 11.83) dt. 12.06.06 09.04.07 R.E Pending
+2.45 C.D.O S/11
07.05.07
283 Begusarai Garhpura Bakhri Road Plan 12.00 959.59 4804(S) 821.55 02.05.07 No 25.06.08 06.05.09 0.00 148.87 31.03.08 334.68 148.86 4.10 10.50 10.50 1.00
(Km 0 - 12) dt. 10.05.06 05.06.07
284 Begusarai Dalsingasarai Kaidrabad Malti Plan 30.00 981.88 10551(S) 1066.61 07.03.07 Yes 15.06.08 06.09.08 1.50 476.52 31.03.08 552.77 478.02 5.33 4.50 4.00 4.00 20.50 19.00 19.00
Road (Km 7 - 36) dt. 06.09.06 09.04.07
Widening -11Km +10.66
Strengthening-19 Km 07.05.07
285 Begusarai Mungerghat Rasidpur Road Plan 14.50 1450.08 4596 (S) 777.77 17.05.07 Yes 16.05.08 01.11.08 2.00 232.88 31.03.08 481.27 232.88 3.88 11.00 11.00 4.50 2.70 0.65 BRPNN
Balia Portion dt.31.03.07 13.03.08
(Part-A) [1 to 19p Km] Except
(3,5p,8,9,10)
286 Begusarai Mungerghat Rasidpur Road Plan 19.00 675.00 4596(S) 856.89 18.05.07 No 15.06.08 0.00 173.77 31.03.08 580.95 175.76 15.20 15.20 14.00 0.75
Balia Portion (Part-B) dt31.03.07
(Km 1, 2, 4, 5p, 6, 7, 11-19p,
35-51)
287 Begusarai Begusarai Samho Road Plan 6.70 324.11 5646(S) 355.29 02.03.07 Yes 01.09.08 01.09.08 0.51 124.07 31.03.08 291.83 124.58 3.55 5.95 5.95 5.30 1.90 1.40 0.60
(Km 0 - 6.7) dt. 31.05.06 07.05.07
288 Begusarai Coal Board Road Plan 4.75 183.59 5253(S) 237.76 08.03.07 Yes 31.12.07 07.09.08 40.38 154.43 31.03.08 220.93 194.81 1.18 3.00 4.75 4.75 4.75 4.75
Revised Estimate
(Km 0 - 4.75) dt. 07.05.07 Submitted .
20.05.06
289 Begusarai Begusarai Birpur Sangat Road Plan 27.00 1466.72 11523(S) 1505.12 07.03.07 Yes 15.06.08 06.03.08 127.00 237.19 31.03.08 674.99 239.38 15.05 17.60 17.60 9.50
(Km 0-27) dt.03.10.06 17.04.07
+7.52
07.05.07
290 Begusarai Teghra Mubarakpur Road PR 1.20 7.13 7927(S) 5.80 25.10.07 No 24.11.07 31.03.08 5.80 5.59 1.02
(Km 4 & 5p ) dt.04.07.07 Work Completed
291 Begusarai Rajendra Path Barauni IRQP 0.52 15.68 7899(S) No 0.52 0.52
(Km 1p ) dt.03.07.07 Work Completed
32.91 25.10.07 24.11.07 32.44 31.03.08 32.91 32.43
292 Begusarai Ajit Patrakar Road IRQP 1.34 21.59 7926(S) No 1.33 1.33
(Km 1 & 2p ) dt.04.07.07 Work Completed
Page 11 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
293 Begusarai Khagaria Parihara Bakhari IRQP 8.40 124.99 7925 (S) 130.34 01.02.08 No 31.03.08 113.09 31.03.08 120.43 113.09 7.26 7.26 7.26
Road (Km 21 to 25,26p & dt- Work Completed
27 to 29p) 04.07.07
294 Begusarai Begusarai Railway Over W&S 1.80 164.23 8530(S) 162.79 22.11.07 No 21.02.08 161.31 31.03.08 162.79 161.31 1.80 1.80 1.80 1.80 1.80
Bridge Road dt.18.07.07 Work Completed
(Km 1 to 2p)
295 Begusarai Teghra Railway Station W&S 1.82 60.14 8551(S) 54.34 21.11.07 No 20.02.08 33.59 31.03.08 56.08 33.59 1.82 1.82 1.82 1.00 0.65
Contractor died work
Approach Road dt.18.07.07 closed to Retender
(Km 1 to 2p )
296 Begusarai Manjhaul Garhpura Road W&S 8.80 351.11 9620 (S) 388.57 01.02.08 No 31.01.09 12.55 31.03.08 67.21 12.40 1.94285 2.00 1.50 0.50
(Km 6 to 14p) Part - B dt-16.08.07 13.03.08
297 Begusarai Hasanpur Garhpura Road (Km W&S 11.00 444.65 8671 (S) 488.45 01.02.08 No 31.01.09 75.70 31.03.08 108.02 75.70 5.60 5.60 5.10
0 to 11p) dt 20.07.07
298 Begusarai Sahebpur Kamal Pachveer W&S 2.80 100.97 8540 (S) 111.47 01.02.08 No 30.04.08 46.41 31.03.08 35.58 46.41 2.80 2.80 2.80
Road (Km 1 to 2.8) dt-18.07.07
299 Begusarai Mungerghat Rasidpur Road W&S 4.50 159.45 10239 (S) 172.74 09.02.08 No 08.05.08 13.61 31.03.08 45.86 13.61 0.86372 1.50 1.50 1.50
(Balia Portion ) (Km 3,5p,8 to dt.27.08.07 13.03.08
10) Part - C
299 Begusarai Total <<>> 172.960 8355.508 0.000 7972.972 0.000 0.000 0.000 0.000 184.700 2732.356 0.000 4539.206 2801.303 0.000 107.360 96.100 73.400 32.650 53.540 48.130 0.650 0
300 Darbhanga Shivnagar Ghat to Plan 17.00 2343.98 6645 (S) 1071.19 19.07.07 Yes 08.02.09 1.00
4.5
Ghanshyampur-Rasiari Rd 2343.48 dt.27.06.06 25.10.07
dt.16.02.08 BRPNN
(Km 0 - 19) 5055(S) +4.8
dt.16.04.07 dt.10.03.08
301 Darbhanga Bishanpur Attarbel Road Plan 14.80 1133.80 8952(S) 1212.04 01.03.07 Yes 09.03.08 29.02.08 69.37 228.19 31.03.08 1212.00 300.48 1.52 14.00 14.00 5.00 2.50 0.10 4
(Km 0 - 14.8) dt. 31.07.06 15.06.08 25.05.07
+2.20
22.06.07
302 Darbhanga Bahera Baheri Road Plan 19.20 1736.64 6645(S) 1793.05 13.03.07 Yes 13.07.08 28.02.08 77.80 1075.62 31.03.08 1343.00 1150.50 18.00 18.00 15.00 16.00 6.00 2.00 8
(Km 0 - 19.2) dt. 27.06.06 15.05.08
303 Darbhanga Singhia Hirni Road Plan 3.20 341.94 11521(S) 266.27 28.02.07 Yes 11.09.07 27.08.07 9.66 31.03.08 183.00 45.00 3.00 1.60 0.50
(Km 10 - 13.2) 3.10.06
304 Darbhanga Jathmalpur - Hayaghat - Plan 8.00 2179.33 6645(S) 187.60 28.02.07 Yes 09.03.08 06.03.08 9.15 75.94 31.03.08 187.00 84.37 7.00 7.00 7.00 3.10
Hathauri Road dt. 27.06.06
(Km 0 - 8)
305 Darbhanga Kamtaul - Bharwara Road Plan 12.50 1232.85 12462(S) 1174.71 10.03.07 Yes 27.02.08 27.02.08 3.68 144.75 31.03.08 1174.71 148.43 9.47 12.00 10.20 4.00 0.50
(Km 11p - 23p) dt.08.11.06 09.03.08 22.06.07
+4.68
02.07.07
306 Darbhanga Jhanjharpur Bahera Road Nabard 22.00 1435.21 8878(S) 1188.97 29.07.06 Yes 28.07.08 14.01.09 126.86 57.23 31.03.08 768.00 698.68 8.42 20.00 19.00 18.00 16.00 0.00 6.00 9
(Km 0 - 22) dt. 01.12.05 15.01.07 14.01.09 22.06.07
(Suppl.) +0.78
02.07.07
307 Darbhanga Jalley Atarbel Road Nabard 26.50 2357.55 8878(S) 2221.19 29.04.06 Yes 28.04.08 11.05.08 313.46 321.39 31.03.08 2033.00 634.85 13.85 17.00 18.00 16.00 10.00 5.00 1.00 41
(Km 0 - 26.5) dt. 01.12.05 22.06.07
+4.24
02.07.07
308 Darbhanga Darbhanga Baheri Singhia Nabard 35.00 3044.96 8878(S) 3044.96 13.03.06 Yes 12.03.08 11.05.08 1306.51 1170.35 31.03.08 2761.00 2476.86 35.00 35.00 35.00 35.00 35.00 35.00 30
Roshra Road dt. 12.05.06 Work Completed
(Km 0 -35) 01.12.05
309 Darbhanga Ausi Raiyam Road 12 FC 5.00 183.40 6067(S) 144.43 21.12.06 Yes 20.12.07 29.54 100.00 31.03.08 140.00 129.00 4.80 4.80 4.80 4.80 4.80 4.80
(Km 0 - 5) dt. Work Completed
12.06.06
310 Darbhanga Ashapur Alinagar Road IRQP 4.50 79.74 8549(S) 72.64 20.12.07 No 19.05.08 31.03.08 69.64 5.00 5.00 4.00 1.00
(Km 8,9p & 10 to 12 ) dt.18.07.07
311 Darbhanga Keoti Raiyam Road IRQP 7.50 118.70 8535(S) 112.17 10.12.07 No 10.05.08 82.06 31.03.08 98.76 82.06 7.50 7.50 7.50 7.50 7.50 3.00
(Km 1 to 8p ) dt.18.07.07 Work Completed
312 Darbhanga Sakri Mill Pathan Kabai Road IRQP 4.00 69.16 8534(S) 69.52 31.02.08 No 30.07.08 31.03.08 54.03 3.00 1.00 1.00 2.10
(Km 0 to 4 ) dt.18.07.07
313 Darbhanga Sakri Bahera Road W&S 15.73 1376.58 14097 (S) 1376.58 16.02.08 No 30.01.09 143.44 31.03.08 130.00 143.44 4.00 1.00 1.50 1
(Km 0 to 15.73) dt.07.12.07
313 Darbhanga Total <<>> 194.930 15289.860 0.000 13935.315 0.000 0.000 0.000 0.000 1946.021 3398.970 0.000 10154.140 5898.670 0.000 150.300 131.100 113.800 105.400 62.400 51.800 1.600 93
314 Madhubani Madhubani Pandaul Sakri Plan 6.20 307.84 5435(S) 233.25 25.02.07 Yes 25.10.07 25.10.07 265.97 31.03.08 240.00 200.97 2.33 5.50 6.20 5.50 5.50 5.50 0.64 2
Road (Km 2, 5, 7-9, 11) dt. 13.04.07
Work Completed
25.05.06 + 2.33
19.04.07
315 Madhubani Madhepur Tamuriya Plan 35.00 1325.68 6645(S) 1098.47 07.03.07 Yes 07.03.08 07.03.08 66.00 921.64 31.03.08 1098.47 431.27 21.57 33.00 30.00 32.00 25.50 17.00 11
Andhrathari (Km 0 - 35) dt. 27.06.06 05.07.07
+5.50
01.02.08
316 Madhubani Benipatti-Uchhath-Baswaria Plan 12.80 913.00 6570(S) 919.19 07.03.07 Yes 31.03.08 07.03.08 - 50.00 31.03.08 540.00 - 36.46 4.50 4.50 4.00 1
Road dt. 24.06.06 05.07.07 Agreement Closed
(Km 0 - 12.8) +6.00 & Retender on 17.04.08
18.01.08
Page 12 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
317 Madhubani Ghoghardiha Phulpras Plan 8.20 258.19 6066(S) 241.14 27.02.07 Yes 27.02.08 27.10.07 - 167.88 31.03.08 242.00 50.00 12.05 8.30 8.30 8.30 8.30 8.30 1
Road (Km 0 - 8.2) dt. 13.04.07
Work Completed
12.06.06 +1.205
18.05.07
318 Madhubani Madhubani Saurath Plan 5.70 331.25 4805(S) 331.05 25.02.07 Yes 27.02.08 27.10.07 90.00 233.96 31.03.08 331.00 40.00 9.93 5.70 5.70 5.70 5.20 5.20 5.20
Pokharaini Road dt. 13.04.07
Work Completed
(Km 0 - 10p) 10.05.06 +4.97
29.11.07
319 Madhubani Aunsi Wisfi Road Plan 9.60 385.25 6045(S) 315.42 07.03.07 Yes 31.03.08 07.11.07 - 86.85 31.03.08 315.42 40.00 7.88 8.50 8.25 8.25 4.50
(Km 0 - 9.60) dt. 12.06.06 18.05.07
+31.54
08.02.07
320 Madhubani Raiyam Madhubani Road Plan 9.60 474.44 6043(S) 508.00 07.03.07 Yes 07.11.07 07.11.07 - 242.91 31.03.08 50.80 140.00 12.307 8.50 8.50 8.50 6.50 6.50 6.00 2
(Km 0 - 9.60) dt. 12.06.06 09.05.07
+2.54
05.07.07
321 Madhubani Madhubani Rajnagar Babu Nabard 41.10 3990.60 8875(S) 2535.86 06.06.06 Yes 05.12.08 03.01.09 634.22 951.79 31.03.08 1405.00 1174.85 63.21 35.00 29.50 29.50 24.00 23.50 10.25 4.70 7 Supply Aggm. 313.895
Barhi Road dt. 01.12.05 13.07.07 Lac
(Km 0 - 41.1) +12.85 dt.12.12.06
01.02.08 Date of comp.03.01.09
322 Madhubani Khajauli Basopati Harlakhi Nabard 16.80 1434.90 8875(S) 949.59 19.06.06 Yes 19.12.08 12.01.09 222.22 656.93 31.03.08 700.00 630.00 19.96 14.50 14.50 14.50 12.00 9.50 9.50 0.35
Road (Km 0 - 16.8) dt. 01.12.05 13.04.07
Revised TS
+4.74
05.07.07
323 Madhubani Jhanjharpur Madhepur Road Nabard 13.70 1409.80 8875(S) 957.00 26.10.06 Yes 25.04.09 20.04.09 80.04 341.28 31.03.08 890.00 220.00 4.78 12.50 12.50 12.50 9.50 9.50 7.00 1.00 9
(Km 28p - 42) dt. 01.12.05 13.04.07
+4.78
18.05.07
324 Madhubani Khutauna Tenuahi Road 12 FC 15.50 559.08 6572(S) 335.45 12.12.06 Yes 3/2007 12.12.07 29.19 294.80 31.03.08 335.50 140.00 33.50 15.50 15.50 15.50 15.50
(Km 0 - 16p) dt. 13.04.07 Work Completed
325 Madhubani Padma Chapki Road 12 FC 9.40 155.96 24 06 06
6012(S) 128.98 12.12.06 Yes 3/2007 12.12.07 100.50 31.03.08 128.94 45.00 12.89 9.00 9.00 9.00 6
(Km 0 - 10p) dt. 13.04.07 Work Completed
12.06.06
326 Madhubani Padma Sidabkala Road IRQP 2.00 42.66 9477(S) 42.07 12/07 No 03/08 40.05 31.03.08 42.00 2.00 2.00 2.00 2.00 2.00
(Km 1 & 2 ) 10.08.07
Work Completed
327 Madhubani Jainagar to Inarwa Road IRQP 0.74 40.26 12335 (S) 34.14 01/08 No 03/08 5.04 31.03.08 33.75 0.73 0.73 0.05
(Km 1p) dt.24.10.07
328 Madhubani Rampatti Batlohiya Road IRQP 4.00 59.27 13163 (S) 62.01 02/08 No 03/08 61.77 31.03.08 61.59 4.00 4.00 4.00 4.00
(Km 1-4) dt.14.11.07 Work Completed
328 Madhubani Total <<>> 190.340 11688.170 0.000 8691.617 0.000 0.000 0.000 0.000 1121.670 4421.370 0.000 6414.470 3112.090 0.000 167.230 127.950 129.980 123.000 85.700 99.250 6.740 39
329 Samastipur Singhia Hirani Road Plan 10.00 952.29 10761(S) 550.71 02.03.07 Yes 01.03.08 18.03.08 50.40 133.06 31.03.08 550.71 200.00 5.50 5.00 4.25 4.00 3.00 1.20 7
(Km 0 - 10) dt. 12.09.06 29.05.07
+2.75
22.06.07
330 Samastipur Dalsingsarai Kaidrabad Malti Plan 6.00 314.05 5849(S) 269.00 27.02.07 Yes 26.08.08 26.08.08 15.67 161.01 31.03.08 268.90 180.00 1.345 5.50 5.50 5.00 4.00 4.00 1
Road dt. 07.06.06 04.05.07
(Km 0 - 6) +1.345
22.06.07
331 Samastipur Hasanpur Sakhwaghat Road Plan 9.00 803.38 9724(S) 450.81 25.04.07 Yes 13.06.08 0.20 31.03.08 216.82 80.00 2.25 4.00 3.50 3.00 0.80
(Km 0 - 9) dt.19.08.06 14.06.07 12.01.08 BRPNN
2415(S)
dt.26.02.07
332 Samastipur Hasanpur Bithan Road Plan 12.00 1145.73 8953(S) 660.79 02.03.07 Yes 01.03.08 31.12.08 66.96 66.77 31.03.08 660.79 150.00 9.90 8.00 6.50 1.25
(Km 0 - 12) dt. 31.07.06 27.06.07
S/C & Rescind
+3.30
03.03.08
333 Samastipur Samastipur Dhurlakh Plan 8.50 246.450 9943(S) 276.73 27.02.07 Yes 26.08.08 26.08.08 67.20 197.88 31.03.08 276.00 276.72 8.50 8.50 8.50 8.50 8.50
Gangapur Road dt. Work Completed
(Km 0 - 8.5) 24.08.06
334 Samastipur Hasanpur Sahpur Road Plan 8.00 527.07 9851(S) 445.83 25.04.07 Yes 20.06.08 0.72 31.03.08 427.40 14.00 7.50 3.50 BRPNN
(Km 0 - 8p) dt.23.08.06 21.06.07 6.314 Work Resciend on dt-
2414(S) 03.03.08 25.03.08 by Pul Nirman
dt.26.02.07 Nigam.
335 Samastipur Mahnar Mohiuddingar Nabard 38.00 836.73 1458(S) 817.05 11.03.06 Yes 10.03.08 10.03.08 121.73 517.41 31.03.08 817.05 640.00 12.55 1.00 22.00 25.00 36.00 7.00
Bachchwara Road dt. 31.03.05 07.05.07
(Km 6 - 43) +4.085
29.05.07
336 Samastipur Bazidpur Dalsingsarai Rosera Nabard 40.00 1104.68 1458(S) 1278.49 16.10.06 Yes 15.10.07 15.10.07 310.60 637.45 31.03.08 1278.92 920.00 4.28 5.00 22.00 36.00 37.00 0.50
Road dt. 31.03.05 26.02.07
(Km 1 - 40)
337 Samastipur Darbhanga Bahera Nabard 13.80 1212.65 1458(S) 555.34 28.12.05 Yes 27.12.07 27.12.07 508.46 391.87 31.03.08 555.34 440.00 3.38 12.00 11.00 12.50 11.00 11.00 4.00
SinghiaRosera Road dt. 31.03.05 26.02.07
Seprate
(Part-A) +2.77
(Km 36 - 46p & 60-63p) 12.06.07
Page 13 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
338 Samastipur Darbhanga Bahera Singhia Nabard 13.50 555.34 02.01.06 Yes 01.01.08 01.01.08 31.03.08 555.34 470.00 3.75 11.00 12.50 12.50 11.50 10.00 3.00
Rosera Road (Part-B) (Km 46- 22.02.07
59) 2.77
12.06.07
339 Samastipur Dholi Kalyanpur Road Nabard 17.30 1116.53 1458(S) 607.84 03.01.06 Yes 02.01.08 02.01.08 79.17 65.64 31.03.08 607.83 180.00 14.13 13.50 11.50 11.00 7.00 1.75
(Km 4p - 22p) dt. 31.03.05 04.07.07
+3.03
29.11.07
340 Samastipur Muzaffarpur Samastipur Road Nabard 23.80 789.45 1458(S) 785.08 15.02.06 Yes 03.01.08 14.02.08 197.61 307.46 31.03.08 785.00 510.00 7.88 23.00 22.00 22.00 16.50 15.00 10.50
(Km 27p - 50p) dt. 31.03.05 07.05.07
+3.92
12.06.07
341 Samastipur Tajpur Pusa Gadia Road Nabard 11.00 196.64 1458(S) 239.27 04.12.06 Yes 03.12.07 03.06.07 17.41 109.20 31.03.08 239.27 160.00 3.56 5.00 6.00 9.00 4.00
(Km 1 - 11) dt. 31.03.05 12.04.07
1.19
04.07.07
342 Samastipur Mohiuddin Nagar-Bazar to Nabard 3.90 120.38 1458(S) 141.78 24.01.07 Yes 03/2007 23.07.07 - 91.71 31.03.08 137.87 98.00 2.826 4.00 3.60 3.60
Kursaha-Bakarpur- dt. 08.05.07
Anandgolwa-Shivmandir Rd 31.03.05 +0.70 Work Completed
(Km 1- 4p) 13.06.07
343 Samastipur Rosera Hathauri Kothi Road Nabard 22.70 654.20 1458(S) 754.06 04.12.06 Yes 03.12.07 03.12.07 244.06 296.52 31.03.08 754.00 550.00 3.77 15.00 22.30 19.70 4.00 6
(Km 1 - 23p) dt. 31.03.05 08.05.07
+3.77
27.06.07
344 Samastipur Samastipur Sarairanjan Nabard 12.18 475.49 1458(S) 471.68 24.12.05 Yes 12.12.07 23.12.07 333.78 136.78 31.03.08 471.67 471.67 2.35 12.25 12.25 12.25 12.25 12.25 12.25
Patori Road dt. 27.06.07 Work Completed
(Km 24p - 36) 31.03.05
345 Samastipur Samastipur Hansa Manwara Nabard 10.50 366.97 1458(S) 366.97 30.12.05 Yes 29.12.007 29.12.07 225.38 54.67 31.03.08 366.96 285.00 Nil 10.00 10.00 10.00 10.00 7.00 7.00
Road dt. 31.03.05
(Km 1 - 11p)
346 Samastipur Jalalpur-Bothnala-Shahpur - Nabard 7.00 112.09 1458(S) 99.01 04.01.06 Yes Compl. 03.10.06 83.71 24.45 31.03.08 99.01 94.00 Nil 7.00 7.00 7.00
Barant to Beri No.-2 to dt. 03.12.06
Telgaman-Langra Chawk- 31.03.05 Work Completed
Dasahara Road
(Km 0 - 7)
347 Samastipur Bindgama-Chakshoha- Nabard 7.60 127.01 1458(S) 117.69 29.03.06 Yes 03/2007 28.03.07 72.77 44.76 31.03.08 117.86 117.86 Nil 7.60 7.60 7.60
Pattori Road dt. Work Completed
(Km 1 p- 8p) 31.03.05
348 Samastipur Sarairanjan Kakarghati Road IRQP 1.60 25.81 8487(S) 29.81 14.02.08 No 31.03.08 17.41 31.03.08 29.84 20.00 1.50
(Km 0 to 1.59) dt. 18.07.07
349 Samastipur Vidyapati Kakarghati Road IRQP 3.00 52.69 7923(S) 61.56 14.02.08 No 31.03.08 11.97 31.03.08 61.56 15.00 1.00
(Km 0 to 3) dt. 04.07.07
350 Samastipur Bindgama Chaksaho Road IRQP 0.41 15.49 13655 (S) 16.56 14.02.08 No 31.03.08 31.03.08 16.56 0.00
(Km 3p) dt.27.11.07
351 Samastipur Mohiuddin Nagar Harelberi IRQP 12.25 788.05 12337 (S) 788.05 No
Jaunpur Jalalpur Bindgama dt.24.10.07 Work alloted
Road (Km 1 to 12p,13p) Agreement not done
352 Samastipur Madudabad Patori Road (Km W&S 11.50 423.58 8550 (S) 481.03 14.02.08 No 31.03.08 31.03.08 481.02 2.50
0 to 12p) dt 18.07.07
353 Samastipur Nilmani Road PR 2.75 38.27 7924 (S) 40.35 14.02.08 No 31.03.08 15.03.08 0.00
( Km 0 to 3p ) dt.04.07.07
353 Samastipur Total <<>> 306.293 12445.670 0.000 10860.825 0.000 0.000 0.000 0.000 2395.816 3266.020 0.000 9775.722 5872.250 0.000 135.250 122.000 145.100 194.950 185.500 78.950 0.000 14
354 Chapra Manpur-Garkha Road Plan 9.00 365.270 6049(S) 436.54 30.12.06 Yes 20.05.07 29.12.07 45.96 46.47 26.03.08 436.00 268.41 10.91 9.00 9.00 9.00 7.00 7.00 7.00
(Km 8, 9, 12-18) dt. 12.06.06 08.05.07
+2.18
15.06.07
355 Chapra Chapra Marhawrah Road Plan 20.32 645.170 13142(s) 658.17 22.01.06 Yes 28.04.07 30.06.07 42.97 55.40 18.03.08 658.00 227.89 13.26 1.40 9.00 6.00 0.55
(Km 2p,3p,4-23) dt.24.11.06 08.05.07
+3.29
15.06.07
356 Chapra Chainwa - Chainpur Road Plan 6.40 104.560 599(S) 98.11 29.05.06 Yes 02/2007 01.03.07 93.24 0.00 13.03.07 98.11 93.23 6.10 6.10 6.10 1
(Km 0 - 7p) dt. SDBC completed
20.01.06
357 Chapra Siwan-Paigambarpur Plan 15.24 438.000 475(S) 470.70 26.06.06 Yes 06/2007 25.06.07 408.18 0.00 11.09.07 470.00 429.31 14.00 15.24 15.24 15.24 8
(Siktiya Paigambarpur) Rd dt.17.01.06 SDBC completed.
(Km 0 to 15.24)
358 Chapra Hariharnath Pahlezaghat Plan 6.70 191.640 5431(S) 217.38 30.12.06 Yes 30.12.07 29.12.07 20.81 0.00 18.01.08 217.00 198.01 5.41 5.50 6.70 4.00 5.46 5.46 5.46 35
Rd (Km 2p - 9p) dt.25.05.06 08.05.07 SDBC Completed
+1.09
15.06.07
359 Chapra Khaira Sattarghat Road Plan 28.00 1649.000 4443(S) 2083.72 14.09.07 Yes 31.12.08 0.00 96.52 15.03.08 762.1 21.00 21.00 2.00
(Km 2p - 9p) dt. 29.03.07
360 Chapra Mahraura Amnaur Sonho Road CRF 8.40 337.580 477(S) 382.32 08.12.06 Yes 28.04.07 15.07.07 84.34 0.00 16.01.08 382.00 145.88 5.73 8.40 8.40 8.40 4.00
(Km 8-15.4) dt.17.01.06 08.05.07
+1.91
15.06.07
Page 14 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
361 Chapra Shitalpur Parsa Maker Rd Ec-Im 19.60 747.780 3735(S) 825.64 08.11.06 Yes 07.11.07 07.11.07 151.93 30.58 15.03.08 825.00 419.38 12.39 12.50 13.00 11.50 7.75 5.00
(Shitalpur-Parsa -14.6KM in dt.04.04.06 08.05.07
SH) (Km 0-19.6) +4.13
15.06.07
362 Chapra Chapra-Sonepur Road PR 1.18 21.54 7782(S) 19.10 11.10.07 Yes 31.12.07 0.00 19.10 10.127 0.50 1.00
(Km 1 & 2p) dt.28.06.07 SDBC Completed
363 Chapra Banwar Chak-Pahlezaghat PR 3.00 33.146 8559(S) 33.48 01.10.07 Yes 31.12.07 0.00
Road (Km 1 to 3 ) dt.18.07.07
364 Chapra Garkha-Chirand Road PR 4.10 65.900 8985(S) 56.71 30.11.07 No 31.03.08
(Km 5,6,7p,8p,10p & 11p) dt.30.07.07
365 Chapra Inai Bara Telpa Road IRQP 3.00 63.906 9579(S) 63.88 18.01.08 No 17.05.08 9.31 27.03.08 9.31 0.20
(Km 0 to 3) 14.08.07
366 Chapra Inai Bada Telpa Road IRQP 2.20 143.03 11248 (S) 133.98 18.01.08 No 17.07.08 30.19 25.03.08 30.19 1.00 0.75
(Km 6 to 8p) dt.25.09.07
367 Chapra Chapra Rewaghat Road IRQP 3.60 259.704 9487(S) 257.04 14.12.07 No 13.09.08 0.00
(Km 1,2p,3 & 4p ) dt.10.08.07
368 Chapra Chapra Siwan Road IRQP 0.90 36.680 8558(S) 34.45 01.10.07 Yes 31.12.07 0.00 07.03.08 34.45 12.23 0.90 0.90 0.40 0.40
(Km 1p ) dt.18.07.07
369 Chapra Hariharnath Pahlezaghat Rd IRQP 2.30 43.260 7819(S) 41.74 01.10.07 Yes 31.12.07 29.03.08 41.74 37.59 1.50 2.30 2.30
(Km 1,2p, & 9p ) dt.03.06.07
370 Chapra Chapra - Chapra Ghat Road IRQP 2.20 107.680 7900(S) 97.09 26.11.07 Yes 31.03.08 23.16 31.01.08 97.09 23.15 0.485 1.25 1.00 1.00
(Km 1 to 3p ) dt.03.07.07 25.03.08
371 Chapra Sonepur - Darihara - IRQP 6.00 118.940 8536(S) 111.06 26.10.07 Yes 31.03.08 110.61 28.03.08 110.61 6.00 6.00 6.00
Rewaghat Road dt.18.07.07 SDBC Completed
(Km 0 to 6)
372 Chapra Ashok Nagar - Sakardiha Road IRQP 2.00 31.476 7901(S) 28.81 14.11.07 No 13.02.08 11.65 15.03.08 28.81 11.65 0.30
(Km 1 to 2p ) dt.03.07.07
373 Chapra Puchhari Hadakpura Road (Km IRQP 3.00 95.000 8545 (S) 92.08 25.01.08 No 0.50 0.50 0.20
0 to 3) dt-18.07.07
374 Chapra Manpur-Garkha Road W&S 9.00 511.847 9459(S) 505.51 08.03.08 Yes 07.03.09 75.83 12.03.08 505.51 75.82 3.00 2.00 1.50
(Km 1 to 7,10,11 ) 10.08.07
375 Chapra Chapra Manjhi Darauli Guthani W&S 17.60 1544.730 614 (S) 1544.73 0.00 0.35
Technical bid Sub. To
Road dt.14.01.08 S.E on 29.02.08
(Km 13.7 to 31.40)
375 Chapra Total <<>> 173.740 7555.839 0.000 8192.235 0.000 0.000 0.000 0.000 847.419 489.720 0.000 3812.810 2865.237 0.000 90.150 62.600 54.040 55.450 32.160 43.500 2.000 44
376 Gopalganj Mairwa Kuchaikot Road Plan 12.00 237.070 3353(S) 225.38 20.06.06 Yes 19.06.07 19.06.07 99.03 123.11 31.03.08 225.00 222.14 3.24 12.00 12.00 12.00 12.00 12.00
(Km 0-12) dt.28.03.06 22.03.07
Work Completed
1.08
26.04.07
377 Gopalganj Mairwa Kuchaikot Road Plan 9.00 167.320 6393(S) 190.89 16.03.07 Yes 15.03.08 15.03.08 19.32 96.85 31.03.08 182.00 116.18 0.98 9.00 8.50 3.00 1.50
Hard shoulder-9 Km
(Km 25 - 33) dt. 21.06.06 19.05.02
378 Gopalganj Mirganj-Bhorey-Katiya Road Plan 29.00 691.749 9027(S) 790.07 29.12.06 Yes 28.09.07 28.09.07 208.37 162.10 31.03.08 790.00 370.62 7.90 4.00 6.50 4.00 14.00 10.00 3.00
(Km 0 to 29) dt. 08.12.05 26.04.07
379 Gopalganj Mirganj-Bhorey-Katiya Road Plan 13.00 546.140 9727(S) 586.40 01.03.07 Yes 29.02.08 29.02.08 80.00 85.97 31.03.08 586.40 165.97 3.01 5.00 4.50 4.50 2.75 1
(Km 30 - 42) dt. 19.08.06 19.05.07
380 Gopalganj Tamkuhi-Chhitauni Ghat Road Plan 8.00 667.940 6395(S) 774.83 28.02.07 Yes 27.02.08 27.02.08 2.07 127.41 31.03.08 774.80 129.69 2.15 5.00 4.50 2.10 2.10 6
(Km 0 - 8) dt. 21.06.06 10.05.07
6 No CD works started
+3.77
13.03.08
381 Gopalganj Kateya - Semra Road Plan 6.30 160.852 9163(S) 167.40 168.89 0.00 27.08.07 6.30 6.30 6.30 6.30
(Km 17p to 24p) dt. Work Completed
12.12.05
382 Gopalganj Sasamusa-Baghauch Road Plan 8.00 315.790 5596(S) 337.29 31.03.07 Yes 30.03.08 30.03.08 1.02 142.78 12.03.08 337.29 142.78 1.73 7.50 7.50 2.50 1.00
(Km 0 - 8) dt. 31.05.06 08.06.07
383 Gopalganj Sidhwalia-Jhajhwa Road Plan 6.80 111.843 9029(S) 120.11 117.97 0.00 27.08.07 6.80 6.80 6.30 6.80
(Km 0 to 6.8) dt. Work Completed
08.12.05
384 Gopalganj Bhorey-Pagra Road Plan 12.74 780.620 6394(S) 812.10 13.03.07 Yes 12.09.08 12.09.08 107.64 497.60 31.03.08 518.00 597.59 4.06 12.73 12.73 9.70 9.70 4.00 8
(Km 9 - 21p) dt. 21.06.06 19.05.07
385 Gopalganj Bhorey-Pagra Road ISC 8.00 454.690 1787(S) 465.31 29.12.06 Yes 28.12.07 18.12.07 20.00 207.00 31.03.08 465.30 227.00 4.64 8.00 6.00 3.30 2.75
(Km 0 to 8) dt. 21.02.06 26.04.07
2.33
11.03.08
386 Gopalganj Mirganj-Bhagipatti 12 FC 27.00 781.610 6585(S) 757.61 19.12.06 Yes 18.06.07 18.06.07 493.67 276.64 29.01.08 757.00 776.00 - 27.00 1.00 1.00 2.00 27.00 27.00
Samaur Road dt.24.06.06 Work Completed
(Km 0-27)
387 Gopalganj Mohammadpur-Lakhanpur 12 FC 13.70 197.130 5991(S) 209.49 08.12.06 Yes 30.06.07 30.06.07 39.30 135.85 31.03.08 209.00 173.37 3.14 5.00 11.50 11.50
Road (Km 4p,5p,7-13,15p,16- dt.10.06.06 22.03.07
S/C Rescind
20,21p) +1.04
19.05.07
388 Gopalganj Harakhwa-Khwajepur 12 FC 4.90 64.110 6465(S) 61.78 12.02.07 Yes 11.08.07 11.08.07 61.93 29.01.08 51.00 61.90 0.40 4.90 4.80 4.90
Road (Km 4p - 9p) dt. 22.03.07 Work Completed
22.06.06
389 Gopalganj Mohammadpur-Lakhanpur PR 3.50 39.850 8538(S) 29.87 23.11.07 22.02.08 29.45 29.45 3.50 3.50
Road (Km 0 to 3.5) dt.18.07.07 Work Completed
Page 15 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
390 Gopalganj Majhagarh Allapur Road PR 1.50 11.450 12336 (S) 11.71 18.01.08 No 17.02.08 11.09 11.09 1.50 1.50
(Km 0 to 2p) dt.24.10.07 Work Completed
391 Gopalganj Barauli Kalyanpur Road (Km PR 5.00 63.180 8892 (S) 53.29 20.12.07 No 19.06.08 21.51 31.03.08 21.51 0.50 1.00
1p,4p & 5 to 8) dt.26.07.07
392 Gopalganj Road Around Hathwa Sugar IRQP 3.40 52.250 11246 (S) 52.05 20.12.07 No 19.06.08 22.26 22.26 1.60 1.40
Factory dt.25.09.07
(Km 2 2p,3-6p)
393 Gopalganj Mairwa Kuchaikot Road IRQP 8.37 247.730 8537 (S) 231.51 25.01.08 No 24.10.08 35.61 35.61 4
(Km 34 to 42)) dt.18.07.07
394 Gopalganj Phuldeo Babu Path W&S 1.80 145.520 11249 (S) 140.22 25.01.08 No 24.05.08 33.39 33.39 1.10 1.10 2
(Km 1 & 2p) d.t25.09.07
395 Gopalganj Harakhwa-Khwajepur Road W&S 2.40 183.190 11262 (S) 152.82 25.01.08 No 24.04.08 11.44 11.44 1.00 1.00
(Arar More to Ambedkar dt.25.09.07
Chowk
(Km 2.4)
396 Gopalganj Link Road from Kotnarhwa to W&S 2.60 171.430 13166 (S) 161.47 07.02.08 No 06.06.08 11.48 11.48 1.10
N.H.28 dt.14.11.07
397 Gopalganj Mirganj Bhagipatti samaur W&S 10.70 816.167 9619 (S) 816.67 No Work order given
Road (28-38p) dt.16.08.07 Aggrement not done
397 Gopalganj Total <<>> 197.708 6907.631 0.000 7148.270 0.000 0.000 0.000 0.000 1357.280 2093.470 0.000 4895.790 3159.470 0.000 114.330 50.330 62.300 71.950 45.600 93.150 3.000 21
398 Hajipur Goraul Sandho Mathanmal Rd Plan (P) 12.66 297.530 6410(S) 347.99 30.12.06 Yes 30.12.07 30.12.07 0.00 213.93 31.03.08 347.19 190.00 6.38 12.00 1.90 12.60 10.50
(Km 0 - 12.66) dt. 21.06.06 Brick Soling 12 Km
399 Hajipur Gunj Karhara Rd Plan (P) 19.60 1286.740 6645(S) 1166.23 30.12.06 Yes 30.12.07 30.12.07 130.00 210.43 31.03.08 1166.23 238.60 21.44 12.00 12.00 12.00 2.50
(Km 0 - 19.60) dt. 27.06.06 16.04.07
400 Hajipur Langri-Pakar-Daudnagar- Plan (P) 14.50 392.58 13147(s) 367.04 14.03.07 Yes 13.03.08 13.03.08 276.19 275.92 31.03.08 367.04 320.16 - 5.00 14.00 14.00 14.00 14.00 14.00 2
Mansoorpur to Ambra Chawk dt. 24.11.06
Road (Km 0-15p)
401 Hajipur Ramashish Chowk to Konhara Plan 1.50 237.04 1593 (S) 227.10 04.04.07 Yes 30.09.07 03.10.07 107.29 31.03.08 227.10 123.71 1.13 1.50 1.50 0.59
ghat Road dt.08.02.07 03.10.07 05.06.07
(Km 0 to 1.5 ) +1.13
05.07.07
402 Hajipur Hajipur Bhairopur Mahnar Rd Nabard 30.50 2420.171 8877(S) WE 2175.67 13.06.07 No 12.12.08 31.03.08 1082.82 600.30 10.87 22.00 22.00 23.00 1.00 1.05 6 BRPNN
(Km (1.5 to 32)) dt. 01.12.05
403 Hajipur Hajipur Lalganj Vaishali Rd Nabard 19.00 1661.677 8877(S) WE 893.45 26.10.06 Yes 25.04.08 25.04.08 171.11 298.51 31.03.08 869.00 280.10 4.46 17.00 8.00 8.00 2
(Part-A) (0 - 19 Km) dt. 01.12.05 28.03.07
(Km 0-38p)
404 Hajipur Hajipur Lalganj Vaishali Rd Nabard 18.61 820.78 15.10.06 Yes 15.12.07 15.10.07 31.03.08 820.78 247.40 4.103 18.00 6.20 6.20 1.70 3
(Part-B) (Km19-37.6) (Rd) 18.05.07
15.12.07
405 Hajipur Muzaffarpur Mahua Rd Nabard 14.70 1136.086 1951(S) 1041.61 21.06.07 Yes 20.06.08 24.86 31.03.08 772.06 120.2 10.40 8.00 7.00 7.00 Work executed by
(Km 15-29p) dt.14.02.07 BRPNN
406 Hajipur Mahnar Mahnar Bazar Nabard 5.50 326.659 8877(S) WE 328.98 28.04.06 Yes 27.10.07 27.10.07 125.39 86.03 31.03.08 328.98 238.08 5.50 5.50 5.50 5.00 1.00 3
(Railway station) Road dt. 01.12.05
(Km 0-6(500)
407 Hajipur Old Gandak Rd Nabard 0.90 29.139 8877(S) 14.34 26.04.06 13.98 2.75 0.90 0.90
(Km 1(900)) WE
Work Completed
dt.
01.12.05
408 Hajipur Mahnar Mohaddinagar 12 FC 3.51 130.660 5996(S) 99.54 01.11.06 Yes 06/2007 57.99 40.43 05.09.07 99.64 99.64 3.50 3.50 3.50 3.50 3.50
Road Part-A(Km1p,3,4,5) dt.
(Km 1p , 3 - 6) 10.06.06 Work Completed
409 Hajipur Mahnar Mohaddinagar 12 FC 1.04 41.27 11.06.07 05.09.07 32.24 31.03.08 41.27 41.27 1.04 1.04 1.04 1.04 1.04
Road Part-B (6thKm) Work Completed
(Km )
410 Hajipur Hajipur Bhairopur Mahnar PR 1.50 17.210 7906(S) 14.18 24.09.07 Yes 31.03.08 13.88 31.03.08 14.18 13.97 1.50 1.50
B.S - 1.40 Km
Rd dt.04.07.07
Completed
(Km 1 & 2p )
411 Hajipur Fakuli Lalganj Road PR 4.30 55.800 8555(S) 44.26 26.10.07 Yes 31.03.08 33.40 31.03.08 44.26 39.80 4.30
(Km 10p,12p,13 to dt.18.07.07
16p )
412 Hajipur Ufraul to Abhishek Pushkarni PR 0.55 4.522 7907(S) 3.60 12.11.07 Yes 31.03.08 2.82 31.03.08 3.60 3.20 0.54
Road (Km 4p) dt.04.07.07
413 Hajipur Bonsho Kund Rd PR 1.60 19.182 8556(S) 14.99 12.11.07 Yes 31.03.08 7.80 31.03.08 14.99 14.30 1.46 Pot Patch Work in
(Km 1 & 2p ) dt.18.07.07 Progress
414 Hajipur Old Gandak Approach IRQP 0.90 14.970 8552(S) 12.17 26.10.07 Yes 25.04.08 10.69 31.03.08 12.17 12.00 0.25 0.90
Road (Km 1p to 2p) dt.18.07.07
Work Completed
415 Hajipur Bahuara Patepur Suki Road IRQP 11.60 352.660 8546 (S) 352.66
Retender
(Km0 to 12p) dt.18.07.07
416 Hajipur Hajipur Jandaha Road W&S 1.96 128.560 8486(S) 119.62 12.11.07 Yes 11.05.08 54.65 31.03.08 89.50 70.28 1.96 1.96 1.90
(Km 1 & 2p) dt.18.07.07
Page 16 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
416 Hajipur Total <<>> 164.430 8511.186 0.000 8085.481 0.000 0.000 0.000 0.000 799.524 1390.770 0.000 6300.806 2653.010 27.650 106.460 65.000 71.340 39.640 45.390 42.340 3.340 16
417 Siwan Daraundha to Maharajganj Plan 4.45 230.460 3414(S) 217.93 28.09.06 Yes 31.03.08 27.09.08 19.53 43.77 31.03.08 217.93 65.56 3.25 4.50 2.80 2.00 7
Road (Km 0.13 - 4.58) dt.28.03.06 30.04.07
+1.11
14.06.07
418 Siwan New Siwan Hasua Road Plan 7.24 175.753 484(S) 185.44 02.11.06 Yes 31.12.07 01.08.08 70.07 119.00 13.03.08 185.44 172.20 1.85 7.00 3.50 3.50 7.20 7.20
(Km 0.762-8.0) dt. 22.03.07
Work Completed
17.01.06 HS-3.4
419 Siwan Chapra Manjhi Darauli Guthani Plan (P) 54.60 2791.870 6645(S) 4433.90 12.03.07 Yes 11.03.08 11.03.08 259.78 31.03.08 3094.36 509.52 0.42 54.00 19.30 19.30 3
Road dt. 27.06.06
(Km 31.4 - 86)
420 Siwan Siwan-Paigamberpur Road Plan (P) 26.33 976.740 5845(S) 12.03.07 Yes 11.03.08 11.03.08 273.72 31.03.08 1129.49 285.71 - 25.00 3.80 21.00 21
(Km 0 - 27p) dt. 07.06.06
421 Siwan Chainwa Chainpur Road Plan (P) 3.50 179.560 5644(S) 12.03.07 Yes 11.03.08 11.03.08 208.03 13.03.08 210.04 210.00 - 3.50 3.50 3.50 3.50 3.50 3.50 1
(Km 7p - 10p) dt. Work Completed
31.05.06
422 Siwan Siwan-Ander Road 12 FC 16.25 527.210 6489(S) 584.30 07.11.06 Yes 06/2007 15.07.07 417.59 153.48 03.01.08 584.30 610.00 - 16.25 16.25 16.25 16.25
(Km 0 - 17p) dt. Work Completed
22.06.06 HS-16.25
423 Siwan Pacharukhi Hariharpur Lalgarh 12 FC 23.00 667.450 6574(S) 705.34 20.01.07 Yes 19.01.08 19.01.08 42.75 491.15 31.03.08 705.34 534.92 14.05 20.00 13.00 19.00 18.00 16.00 6
Hard shoulder 18 Km
Road (Km 0 - 23) dt. 24.06.06 14.06.07
Fine ½%
+8.74
31.03.08
424 Siwan Ziradei Narendrapur Rd 12 FC 5.00 148.950 6158(S) 138.49 28.11.06 Yes 03/2007 30.06.07 48.22 99.62 03.01.08 138.49 138.00 1 5.00 4.00 5.00 5.00 1 Work Completed
(Km 0 - 5) dt. HS-5.00
425 Siwan Ziradei Road Bhanta 12 FC 3.70 87.320 14 06 06
6046(S) 90.74 27.11.06 Yes 03/2007 31.03.07 64.08 24.98 03.01.08 90.74 89.67 0.907 3.00 3.45 3.45 3.45 Work Completed
Pokhar (Km 0 - 4p) dt. 23.03.07
HS-3.45
12 06 06
426 Siwan Ander-Raghunathpur PR 2.80 27.044 8890(S) 24.02 20.11.07 No 20.02.08 23.31 13.03.08 23.66 23.43 2.80 2.80
H.S-1.50 Km
Road (Km 8.6 to 11.40) dt.26.07.07 Complete
427 Siwan Badarjimi Kailgrah Road PR 4.71 90.509 8557(S) 74.96 28.11.07 No 27.03.08 70.75 13.03.08 74.96 70.75 5.00 0.37 4.70 0.37
(Km 2 to 7p) dt.18.07.07 Drain-5.70Km
Complete
428 Siwan New Siwan Hasua Road PR 3.00 28.994 8543(S) 23.85 25.10.07 No 24.01.08 22.48 13.03.08 23.85 23.84 0.18 3.00 3.00
HS-1.50 Km
(Km 9 to 11) dt.18.07.07
Complete
429 Siwan Siwan-Siswan Road PR 14.40 374.75 7781(S) 374.75 27.06.07 No 26.12.07 356.91 13.03.08 374.75 357.80 4.00 5.90 5.90 14.40 14.40
(Km1p,2p,3,4,6,7,10,12, dt.28.06.07 H.S - 0.075
16 to 21p,31,32)
429 Siwan Total <<>> 168.978 6306.610 0.000 6853.720 0.000 0.000 0.000 0.000 662.240 2146.980 0.000 6853.350 3091.400 1.770 153.050 38.800 68.570 67.800 46.200 76.300 0.370 39
430 Bettiah Bettiah Sewaghat Plan 13.30 631.458 1879(S) 552.88 25.07.06 Yes 05/2007 24.07.07 389.80 177.38 31.03.08 572.00 572.00 13.30 13.30 13.00 13.30 13.30
Mainatard Rd
Work Completed
(Km 0-39.3 dt.23.02.06
in stretches)
431 Bettiah Majhawlia Jagdishpur Rd Plan 12.50 540.390 6756(S) 551.96 21.03.07 Yes 14.02.08 20.03.08 83.38 58.74 31.03.08 551.96 550.00 12.20 12.20 12.20 12.20 12.20 0.30
(Km 0 - 14.45) dt. Work Completed
29.06.06
432 Bettiah Sariswa Bazar Lalgarh Rd Plan 12.20 627.370 6989(S) 592.41 23.03.07 Yes 14.02.08 22.03.08 78.71 538.64 31.03.08 521.00 520.00 12.20 12.20 12.20 12.00 12.20 12.20
(Km 0 - 12.20) dt. Work Completed
05.07.06
433 Bettiah Bagaha Semara Rd 12 FC 9.00 122.850 6069(S) 77.10 140.32 31.03.08 7.86 7.86 7.86 7.86 7.86 7.86
(Km 1p, 5 - 9, 11 - 14p) dt. Work Completed
12.06.06
434 Bettiah Majhaulia Jagdishpur W&S 2.00 110.332 8885(S) 112.24 28.12.07 Yes 28.03.08 113.50 31.03.08 112.24 112.24 1.95 1.95 1.95 1.95 1.95
Road dt.26.07.07 Work Completed
(Km 12.5 to 14.45)
435 Bettiah Bagaha Sidhwa Harnatard IRQP 7.93 191.175 8886(S) 182.16 28.02.08 04.03.08 31.03.08 182.16
Road (Km 7p,8,9,10,12, dt.26.07.07 Work in Progress
13,16p,20 & 21p)
436 Bettiah Bagaha Semara Road IRQP 2.86 72.850 13165 (S) 72.85 04.03.08 30.06.08
(Km 1p,3,4,14p) dt.14.11.07 Work in Progress
436 Bettiah Total <<>> 59.790 2296.425 0.000 2141.600 0.000 0.000 0.000 0.000 692.210 888.260 0.000 1939.360 1754.240 0.000 47.510 47.510 47.210 33.160 34.210 47.510 0.300 0
437 Ramnagar Lauria Shikarpur Thori Road Plan 10.30 546.800 6400(S) 370.78 18.05.07 24.10.08 16.11.07 115.00 BRPNN
(Km In stretches dt. 21.06.06 18.07.07 02.11.07 200.00
(13p to 25)) 4595(S)
dt-31.03.07
438 Ramnagar Lauria Ramnagar Rd Plan 19.60 893.660 13143(s) 1021.11 23.03.07 Yes 28.02.08 22.03.08 153.11 1193.08 31.03.08 1164.00 1189.08 5.10 19.60 19.60 19.60 20.00 20.00
Revisad A/A needed
(Km 0-20p) dt.24.11.06 27.04.07 Work Completed
439 Ramnagar Bettiah Chanpotia Plan 22.00 892.070 8944(S) 1127.03 23.03.07 Yes 22.12.07 22.12.07 147.73 1127.49 31.03.08 1127.02 1127.49 - 22.20 22.00 22.00 22.00 22.00
Narkatiaganj Rd dt. Work Completed
(Km In stretches) 31.07.06
Page 17 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
440 Ramnagar Narkatiaganj Ramnagar Plan 14.50 481.530 6843(S) 592.41 23.03.07 Yes 22.12.07 22.12.07 79.07 589.82 31.03.08 592.41 589.82 2.63 14.50 9.50 9.50 14.50 14.50
Rd (Km 0-14.5) dt. 27.04.07 Work Completed
01.07.06
441 Ramnagar Dhum Nagar Maldahia Plan 12.80 601.060 6399(S) 714.26 23.03.07 Yes 22.12.07 22.12.07 93.59 685.29 31.03.08 714.26 720.00 3.11 12.80 12.80 12.80 12.80 12.80
Anjuwa Rd dt. 27.04.07 Work Completed
(Km 0 - 12.8) 21.06.06
442 Ramnagar Ramnagar Meghwal Rd 12 FC 3.70 88.650 5989(S) 91.46 12.07.07 No 25.03.08 88.65 31.03.08 93.28 93.28 4.00 3.70 3.70 3.70 0.30
Work Completed
(Km 0 - 4p) dt.
443 Ramnagar Ramnagar Meghwal Rd IRQP 8.50 235.970 8877(S) WE 232.88 20.12.07 No 19.12.08 51.75 31.03.08 38.00 52.00 3.00 7.00
(Km 5-13p) dt. 26.07.07
444 Ramnagar Laheria Lauria Chanpatia Road IRQP 9.56 214.080 8883(S) 210.38 22.11.07 Yes 31.05.08 142.10 31.03.08 106.00 138.00 4.00 9.56 9.30
(Km 6p to14,15p,16p) dt.26.07.07
445 Ramnagar Lauria Nandangardha IRQP 2.00 58.640 8884(S) 56.32 05.11.07 Yes 30.05.08 53.12 31.03.08 54.00 54.22 2.00 2.00 2.00 2.00
Road (Km 1 & 2 ) dt.26.07.07 Work Completed
446 Ramnagar Tikulia Jayantia Gidha Road IRQP 3.20 54.260 8875(S) 51.65 06.11.07 No 31.05.08 9.74 31.03.08 52.00 9.00 1.00 3.00 1.00
(Km 2,3,4 & 8p) dt.26.07.07
447 Ramnagar Ramnagar Someshwar Road IRQP 9.00 232.100 8876 (S) 238.12 08.02.08 12.02.09 84.19 31.03.08 20.00 87.00 3.00 9.00
(Km 4 to 6 & dt.26.07.07
10 to 15)
448 Ramnagar Sathi Mathiaria Road IRQP 5.00 81.160 8887 (S) 84.78 14.12.07 Yes 30.06.08 63.31 31.03.08 11.50 70.00 3.00 5.00 5.00 5.00
B/S Work in Progress
(Km 1 to 4 & 6) dt.26.07.07
449 Ramnagar Bettiah Chanpotia W&S 12.60 766.274 9887 (S) 717.76 07.03.08 No 15.06.08 250.11 31.03.08 25.00 85.00 8.00 6.50
Narkatiaganj Rd (Km dt-21.08.07
1,2p,3p,4,11p,17p,19,20p,23
to 26, 31, 32p, 33 & 35p)
449 Ramnagar Total <<>> 132.760 5146.254 0.000 5508.937 0.000 0.000 0.000 0.000 473.500 4338.650 0.000 3997.470 4214.890 0.000 97.100 70.400 103.160 3.700 86.600 80.000 0.300 0
450 Dhaka Pakaridayal Sirha Madhuba Plan (P) 25.80 1483.860 6645(S) 1372.48 28.03.07 Yes 30.08.08 27.09.08 1774.38 31.03.08 208.00000 150.00 6.86 4.00 6.00 4.00 1.00
Minapur Rd dt. 27.06.06 dt.29.02.08 BRPNN
(Km 1 - 7p, 18p-37p, 38p, 2160
39p) dt.21.02.07
451 Dhaka Motihari Barnaghat Plan (P) 29.00 1224.120 6645(S) 1759.00 28.03.07 Yes 30.08.08 27.09.08 1150.58 31.03.08 495.00000 400.00 8.00 11.00 9.50
Chhraudane Rd dt. 27.06.06 BRPNN
(Km 0 - 29) 2160
dt.21.02.07
452 Dhaka Chakia Madhuban Rd Plan (P) 8.50 360.780 6842(S) 422.22 28.03.07 Yes 30.08.07 27.09.08 360.2 31.03.08 69.66 20.00 2.11 1.80 1.80
(Km 1, 2p, 5p- 11) dt. 01.07.06 11.01.08 BRPNN
2410 (S)
dt.26.02.07
453 Dhaka Motihari Madhubanighat Rd Plan (P) 16.00 1025.430 2413 (S) 858.70 28.03.07 Yes 30.08.08 27.09.08 1025.73 31.03.08 243.00000 200.00 10.00 8.00 6.00 2.20 2 BRPNN
(Km 0 - 16) dt.26.02.07
454 Dhaka Pachpakri Gurhanwa Rd Plan (P) 10.00 382.940 9725(S) 383.07 28.03.06 Yes 30.08.08 383.44 31.03.08 202.00 150.00 9.00 4.50 3.00
(Km 1-6, 7p, 8-11, 12p) dt. 19.08.06 28.03.07
BRPNN
2411 (S)
dt.26.02.07
455 Dhaka Motihari Madhubanighat Plan 0.69 92.630 3354(S) 92.63 91.94 0.69
Rd dt.28.03.06 Work Completed
(Km 1(687))
456 Dhaka Dhaka Ghorasahan Rd BADP 18.50 1222.460 9096(S) 1137.82 04.12.06 Yes 03.06.08 03.06.08 127.870 300.260 31.03.08 971.81110 300.26 6.03 5.00 8.00 6.00 0
(Km 1 - 19p) dt. 03.08.06 13.03.07
+6.01
14.06.07
457 Dhaka Purmahiya Jharokher Rd BADP 8.50 449.790 8949(S) 436.07 22.12.06 Yes 21.12.07 03.06.08 3.305 156.820 31.03.08 436.07 156.82 4.36 8.20 8.00 3.00
(Km 1 - 9p) dt. 31.07.06 07.06.07
+2.18
6.07.07
458 Dhaka Siruna Patahi Rd 12 FC 8.40 218.810 6488(S) 252.43 22.12.06 Yes 21.06.08 21.12.07 6.515 30.440 31.03.08 128.42 57.00 2.51 6.00 4.50 4.50 2.40 0
(Km 0 - 9p) dt. 22.06.06 21.05.07
+1.26
25.05.07
459 Dhaka Bhandar Bhakurahiya Rd 12 FC 6.05 261.590 6198(S) 250.78 22.12.06 Yes 21.12.07 21.12.07 1.420 66.760 31.03.08 250.78000 60.00 1.25 6.00 2.00 3.50 3.50 1.25 0
(Km 1 - 7p) dt. 14.06.06 13.03.07
+1.25
14.06.07
Dhaka Total <<>> 131.437 6722.410 0.000 6965.200 0.000 0.000 0.000 0.000 4181.738 554.280 0.000 3004.741 1494.080 0.000 56.200 49.300 41.300 11.200 3.650 0.000 0.690 2
459
460 Motihari Chhapwa Harsidhi Sewraha Rd Plan (P) 19.15 1119.340 6645(S) 1324.00 28.03.07 Yes 29.09.08 27.09.08 0.00 25.09.07 573.23 21.65 6.63 4.00 1.50 1.50 1.50
(Km 0 - 19.15) dt. 27.06.06 29.02.08 BRPNN
2160
dt-21.02.07
461 Motihari Chakia Kesaria Sattarghat Rd Plan (P) 27.00 1731.750 6645(S) 1813.29 28.03.07 Yes 31.12.08 27.09.08 31.12.07 726.44 126.49818 9.06 1.50 9.50 5.00 BRPNN
(Km 0 - 27.0) dt. 27.06.06 15.11.07
462 Motihari Chintaha Bariarpur Kotwa Rd Plan (P) 15.00 894.780 6586(S) 968.11 28.03.07 Yes 30.06.08 27.09.08 211.90 07.03.08 491.59 101.55 3.00 8.00 5.50
(Km 0 - 15) dt. 24.06.06
Page 18 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
463 Motihari Madhopur Bahurupia Rd 12 FC 5.10 153.810 10552(S) 100.28 12.02.07 Yes 30.04.07 30.06.07 15.66 83.19 21.06.07 100.28 92.11677 5.10 5.10 5.10 5.10
(Km 1 - 7p) dt. Work Completed.
06.09.06
464 Motihari Narirgir Champapur PR 8.50 54.370 10215 (S) 62.39 03.12.07 No 25.03.08 53.47 9.00 9.00 9.00
Adapur Road (Km dt- Work Completed.
,2,3p,4p,5,6p,8 to 10) 24.08.07
465 Motihari Chakia Link Road PR 0.50 3.699 8891 (S) 3.61 11.12.07 No 15.03.08 3.60 3.60 0.50
(Km 4p) dt- Work Completed
26.07.07
466 Motihari Chakia Madurapur Road PR 4.40 26.323 8893 (S) 25.74 11.12.07 No 15.03.08 25.71 10.03.08 10.95825 4.50
(Km 2,5,7,10,12p) IRQP dt-
26.07.07
467 Motihari Arya Samaj Mandir Road PR 2.00 25.400 8989 (S) 24.71 11.12.07 No 15.03.08 22.90 12.03.08 5.91013 0.30 0.50 0.50 2.00
(Km 1 & 3) IRQP dt-
30.07.07
468 Motihari Motihari Rulahi Road PR 3.00 20.470 9885 (S) 20.41 11.12.07 No 15.03.08 20.29 12.03.08 20.28 3.00
(Km 2,3,7) dt-
21.08.07
469 Motihari Ramgardhwa Bye Pass PR 1.40 9.070 9886 (S) 8.91 30.12.07 25.03.08 8.92 25.02.08 8.91 1.50 1.50 1.50
Road (Km 1p,2p) dt.21.08.07 Work Completed
470 Motihari Sugauli Piparpati Road IRQP 4.00 207.900 8888 (S) 186.52 03.12.07 No 31.12.08 64.68 16.02.08 28.80 64.67 4.00 7
(Km 4,5,6 & 7) dt-26.07.07 30.06.08
471 Motihari Bariarpur link Road IRQP 1.53 46.908 8894 (S) 47.60 11.12.07 No 39.88 19.02.08 39.88 1.50 0.60 1.50 1.50
(Km 2p & 3) dt-26.07.07
472 Motihari NarirgirChampapurAdapur IRQP 3.00 304.810 9475 (S) 157.03 03.12.07 30.06.08 22.02.08 8.73 24.34682 0.785
Road (Km 13 to 15) dt.10.08.07 24.03.08
473 Motihari Main Service Road W&S 5.52 208.077 9478 (S) 191.85 24.12.07 No 31.12.08 26.77 13.03.08 18.32 26.71 1.00
(Km 2,3,4p,5p,8p,10p) dt-10.08.07
474 Motihari Approach Road (Km1,2p) W&S 1.24 102.682 11554 (S) 102.68 24.03.08
dt.01.10.07
475 Motihari Lake Road W&S 1.50 111.100 12334 (S) 124.77 13.03.08 30.06.08 25.24 18.03.08 25.23 1.00 0.13
(Km 1,2p) dt.24.10.07
475 Motihari Total <<>> 102.835 5020.489 0.000 5161.906 0.000 0.000 0.000 0.000 227.560 374.650 0.000 1947.397 572.310 0.000 19.100 21.900 24.130 17.600 7.100 25.600 0.000 7
476 Muzaffarpur-1 Muzaffarpur Old Motihari Rd Plan 8.00 728.790 5986(S) 532.41 25.04.07 Yes 04/08 24.04.08 0.72 66.49 30.03.08 532.00 67.21 3.32 4.00 2.50 0.50 18
(Km 0 - 8) dt. 10.06.06 07.06.07
2.66
20.01.08
477 Muzaffarpur-1 Muzaffarpur Mahua Rd Plan 14.40 730.920 11132(S) 901.53 20.03.07 Yes 19.03.08 19.03.08 0.76 312.58 30.03.08 901.00 312.34 4.5 10.00 9.00 6.00 6.00 2.00
(Km 0 - 15p) dt. 20.09.06 03.05.07
4.50
07.06.07
478 Muzaffarpur-1 Majhauli Katra Road Plan 12.80 1926.920 10011(S) 1170.31 07.03.07 Yes 07.08.08 06.08.08 70.48 246.64 30.03.08 896.00 317.12 9.00 1.00
(Km 0 - 13p) Part- A dt. 26.08.06
479 Muzaffarpur-1 Const.of Culvert Majhauli Plan 505.13 12.12.07 11.12.08 70.32 30.03.08 70.32
4/22 Culvert
Katra Rd. (Km) Part-B
480 Muzaffarpur-1 Garha Hathauri Rd Plan 10.97 1902.280 6645(S) 1026.29 07.03.07 Yes 21.08.08 06.08.08 70.06 234.47 30.03.08 737.00 303.92 6.00 1.50
(Km 0 - 10.972) Part-A dt. 27.06.06
481 Muzaffarpur-1 Const. Of Culvert Garha Plan 474.65 12.12.07 11.12.08 4.51 30.03.08 474.65 4.51
2/17 Culvert
Hathauri Rd.(Km) Part-B
482 Muzaffarpur-1 Muzaffarpur Deoria Rd Plan 39.00 1195.71 13637(s) 1143.25 14.03.07 Yes 13.09.08 13.09.08 161.34 705.51 30.03.08 1202.00 871.85 34.00 1.50 33.00 33.00 23.00 23
(Km 0-39) dt.05.12.06
483 Muzaffarpur-1 Muzaffarpur Sitamarhi Road Plan 2.58 140.29 14006(s) 132.62 02.04.07 Yes 26.06.07 25.06.07 0.08 42.52 30.03.08 132.62 42.60 0.66 1.50 1.50
S/C & Rescind
(Km 1p,2p,3p) dt.12.12.06 03.05.07
484 Muzaffarpur-1 Muzaffarpur Rewaghat Road Plan 3.90 236.20 638(s) 259.89 30.03.07 Yes 25.06.07 25.06.07 0.14 151.25 30.03.08 259.89 150.95 1.30 0.00 0.00 0.00 250m Side Drain PCC-
(Km 0-4p) dt.17.01.07 03.05.07 1000mWork in
1.30 Progress.
07.06.07
485 Muzaffarpur-1 Construction of protection Plan 30.49 5592(S) 29.83 18.01.07 25.05.07 26.54 29.06.07 17.56 29.63 Nil
wall of Godawn in Deoria dt.30.05.06
sub - Division Work Completed
(Km )
486 Muzaffarpur-1 Construction of inspection Plan 14.07 5591(S) 13.32 18.01.07 25.05.07 5.88 01.10.07 5.60 13.04
building in Deoria sub - dt.30.05.06
Work Completed
Division
(Km )
487 Muzaffarpur-1 Muzaffarpur Pusa Rd Nabard 15.00 2764.210 8876(S) 978.02 20.03.07 Yes 19.03.08 19.03.08 0.00 113.28 30.03.08 978.00 113.28 4.89 12.00 2.25 2.00
Part-A 0 - 15 (Km ) dt. 01.12.05 04.06.07
4.00
16.01.08
488 Muzaffarpur-1 Muzaffarpur Pusa Rd Nabard 15.08 1072.42 20.03.07 Yes 19.03.08 147.89 30.03.08 1072.00 147.35 5.36 15.80 2.00 2.00
Part-B 16-30.08 (Km ) 16.01.08
489 Muzaffarpur-1 Muzaffarpur Pusa Rd Nabard 1072.42 20.03.07 19.03.08 9.58 177.02 03.12.07 280.00 93.47
culvart Part-C (Km )
490 Muzaffarpur-1 Motipur Sahebganj Rd Nabard 23.20 2968.900 8876(S) anu 2320.97 29.07.06 Yes 28.07.08 28.07.08 171.34 1091.83 30.03.08 1272.00 1262.65 20.00 17.00 17.00 17.00 8.00 1.00 35
(Km 0-23.2) dt. 01.12.05
Page 19 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
491 Muzaffarpur-1 Deoria Jaffarpur Ambara 12 FC 8.60 300.420 6487(S) 286.17 31.08.07 No 28.02.08 187.24 30.03.08 286.00 187.24 2.50 8.71 8.71 8
Rd (Km 11p,12p,13- dt.22.06.06 8/8 Complete
15p,16-18p, 20-22)
492 Muzaffarpur-1 Bochaha Keotsa Road IRQP 6.25 151.617 8991 (S) 126.75 26.02.08 No 20.03.08
(Km31(900),32(850), dt.31.07.07
Work in Progress
33(800),34(500),35(600),36(9
50), 37(800),38(850)
492 Muzaffarpur-1 Total <<>> 159.782 13090.817 0.000 12045.980 0.000 0.000 0.000 0.000 516.920 3551.550 0.000 9046.320 3987.480 0.000 96.800 37.750 34.000 60.500 57.210 34.710 0.000 84
493 Muzaffarpur-2 Sheohar Minapur Road Plan 13.00 1580.840 9090(S) 1135.88 20.03.07 Yes 19.12.08 19.12.08 0.708 553.390 30.03.08 481.68 522.67 5.56 12.00 12.25 9.00 5.00 0.12 12
(Km 21 to 33) dt. 03.08.06 11.05.07
+5.56
16.06.07
494 Muzaffarpur-2 Runnisaidpur Katra Kewtsa Rd Plan 22.00 957.450 3355(S) 518.21 22.12.06 Yes 21.12.07 21.12.07 266.91 317.07 17.03.08 518.21 182.83 2.59 21.00 1.00 4.50 10.75 3.00 1.50
(Road Part) dt. 28.03.06 08.03.07
(Km 2-6p & 7p-24)
495 Muzaffarpur-2 Runnisaidpur Katra Kewtsa Rd Plan 3355(S) 578.31 23.09.06 Yes 23.03.08 23.03.08 25.03.08 578.31 416.61 19
(Culvert Part) dt. 28.03.06
(Km 2-6p & 7p-24)
496 Muzaffarpur-2 Runnisaidpur Katra Kewtsa Rd Plan 16.00 1528.320 6645(S) 1146.29 13.03.07 Yes 12.12.08 12.12.08 328.72 16.03.08 632.31 328.23 - 12.50 2.68 3.75 5.00 0.80 8
(Km 25 - 40) dt. 27.06.06
497 Muzaffarpur-2 Jhapha Minapur Road Nabard 13.00 1355.300 8876(S) 1021.50 10.07.06 Yes 09.07.08 09.07.08 135.42 445.76 30.03.08 744.19 578.70 9.77 12.00 11.50 8.00 6.50 1.80 0.36 1500%
(Km 0-13) dt. 01.12.05 07.03.07
+4.88
08.03.07
498 Muzaffarpur-2 Runisaidpur Belsand Parsauni 12 FC 13.00 589.860 6582(S) 504.67 20.03.07 Yes 11.01.08 11.01.08 24.45 295.33 07.02.08 504.77 319.82 4.70 11.00 2.60 1.90 10.94 8.70 8.70 0.30
Rd (Km 0-13) dt.24.06.06 08.03.07
+2.36
08.05.07
498 Muzaffarpur-2 Total <<>> 77.000 6011.770 0.000 4904.861 0.000 0.000 0.000 0.000 427.488 1940.270 0.000 3459.470 2348.860 0.000 68.500 30.030 27.150 38.190 13.500 10.200 1.580 54
499 Sheohar Sheohar Minapur Road Plan 20.00 1770.500 9091(S) 1273.66 04.04.07 Yes 03.01.09 03.01.08 33.84 129.92 31.03.08 466.25 230.00 6.37 10.50 7.30
(Km 0-20) dt. 03.08.06 04.05.07
+6.36
31.05.07
500 Sheohar Belsand Chhitauni Road Plan 11.00 1274.540 1109(S) 525.00 31.10.07 Yes 03.09.08 136.23 31.03.08 128.77 76.61 10.46
B/S 6.00 Km
( Km 7 to 17) dt.31.01.07
500 Sheohar Total <<>> 31.000 3045.040 0.000 1798.660 0.000 0.000 0.000 0.000 33.840 266.150 0.000 595.020 306.610 0.000 20.960 7.300 0.000 0.000 0.000 0.000 0.000 0
501 Sitamarhi Sitamarhi-Riga-Dheng Rd Plan 23.00 1214.390 9093(S) 1262.50 23.02.07 Yes 22.11.08 22.11.08 124.08 179.42 29.02.08 780.03 303.49 0.675 17.00 14.00 10.26 3.43 1.35
(Km 0 - 23) dt. 03.08.06 06.05.07
0.27
01.06.07
502 Sitamarhi Riga-Majorganj Rd Plan 17.00 1245.870 10010(S) 1227.16 24.02.07 Yes 24.05.08 23.08.08 61.51 581.26 29.03.08 763.16 642.760 0.688 16.00 16.70 9.15 2.00 2.90
(Km 0 - 17) dt. 26.08.06 06.05.07
0.21374
01.06.07
503 Sitamarhi Narha-Dumari Rd Plan 8.00 500.590 6752(S) 543.07 23.02.07 Yes 25.05.08 22.05.08 34.30 137.68 19.03.08 383.93 171.98 0.24961 8.00 8.00 3.50
(Km 1p, 2p, 3-8) dt. 29.06.06 06.05.07
504 Sitamarhi Runnisaidpur Nanpur Pupri Plan 10.00 757.770 6584(S) 862.85 31.01.07 Yes 30.07.08 30.07.08 36.22 166.31 29.03.08 469.87 202.52 0.392 8.50 6.81 1
Road (Km 0 - 10) dt. 24.06.06
505 Sitamarhi Runnisaidpur Nanpur Pupri Plan 12.00 538.620 2945(S) 587.00 16.12.06 Yes 15.04.08 15.04.08 50.58 113.77 08.03.08 350.870 164.35 8.00 7.80 3.43
Road (Km 11-22) dt.18.03.06
506 Sitamarhi RCC High Lavel Bridge at Km Plan 74.200 5998 (S) 111.65 15.11.07 14.05.09 57.76 04.03.08 58.122
10 th of Kumma Bela Road dt.10.06.06 Pilling Work in Progress
Year-06-072x16.5x3.15m
507 Sitamarhi Majorganj-Dheng Rd Plan 11.00 784.870 11055(S) 682.23 07.12.07 06.12.08 0.28 259.85 28.03.08 260.13 10.90 9.66 4.70 0.37
(Km 0 - 11) dt. 18.09.06
508 Sitamarhi Parwaha Lalbandi Rd CRF 11.80 363.040 7920(S) 395.031 23.03.05 Yes 15.06.07 15.06.07 120.47 116.67 25.03.08 395.03 237.12 0.078 4.80 1.30 1.30 2.70 2.70 2.70 0.54 3
(Km 8.0-18.8) dt.18.09.03 06.05.07
509 Sitamarhi Sisaula Kataiya Adauri Link Rd 12 FC 7.44 426.980 6471(S) 444.12 14.12.07 Yes 13.09.08 180.69 27.03.08 172.70 180.69 6.64 1.00 9.00 0.48 3
(Km 0 - 8p) dt.22.06.06
510 Sitamarhi Sisaula Akhta Road 12 FC 4.56 147.500 6470(S) 184.90 03.02.07 Yes 02.02.08 43.37 43.37 114.86 09.02.08 184.90 114.86 0.03382 4.54 4.52 4.52 4.52 4.52 2
(Km 0 - 5p) dt.22.06.06 06.05.07
0.18
01.06.07
511 Sitamarhi Belsand Chhitauni Road IRQP 1.00 28.180 11723 (S) 25.84 27.02.08 25.03.08 13.58 10.03.08 25.81 13.58 1.00 1.00
(Km 4) dt.04.10.07
512 Sitamarhi Parsauni Riga Road PR 3.50 32.330 9480 (S) 32.33 29.01.08 25.03.08 3.50
(Km 1,2,11 & 15p) dt.10.08.07
513 Sitamarhi Sita-Setu Bye Pass Road PR 0.85 89.460 9479 (S) 90.76 23.01.08 25.03.08 40.36 27.03.08 90.76 40.36 0.85 0.85 0.75
(Km 1p) dt.10.08.07
513 Sitamarhi Total <<>> 110.154 6203.800 0.000 6449.440 0.000 0.000 0.000 43.370 470.811 1962.210 0.000 3617.061 2389.962 0.392 86.230 65.270 47.710 13.130 7.220 10.720 5.910 9
514 Araria Saifganj Mathawa Road Plan 14.00 1460.470 8943(S) 807.57 09.03.07 Yes 08.05.08 08.05.08 130.39 584.68 31.03.08 782.41 466.56 14.00 13.50 11.25 6.25 1.10 16
(Km 3 - 16) dt. 31.07.06
Page 20 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
515 Araria Jokihat Dalmalpur Road Plan 5.00 125.250 9940(S) 140.63 23.02.07 Yes 22.10.07 22.10.07 55.09 92.09 13.03.08 140.63 140.63 5.00 1.00 5.00 5.00 5.00
(Km 6 - 10) dt. Work Completed
24.08.06
516 Araria Araria Kursakata Kuari Sikti Plan 45.00 2463.000 6645(S) 2680.57 13.03.07 Yes 12.12.08 12.12.08 617.57 1287.5 31.03.08 1717.24 1287.50 42.00 39.00 29.00 29.00 0.90
Road (Km 0 - 45) dt. 27.06.06
517 Araria Udahat Tekni Road Plan 15.00 1014.600 8942(S) 739.21 09.03.07 Yes 08.06.08 08.06.08 182.64 231.89 31.03.08 666.64 231.89 13.00 12.50 7.00 5.00
(Km 0 - 15) dt. 31.07.06
518 Araria Railway Station Link Road Plan 5.50 52.660 6409(S) 66.60 24.02.07 Yes 23.08.07 23.08.07 15.21 53.69 19.11.07 66.60 68.39 5.50 5.50 5.50 5.50
(Km 0 - 6p) dt. Work Completed
21.06.06
519 Araria Fatehpur Teragachhi Road BADP 7.20 582.820 8814(S) 0.00 15.02.08 78.90 7.00 1.00
(Km 36-43p) dt. 30.11.05 BRPNN
520 Araria Matihari - Kokan Road 12 FC 7.00 542.390 6576(S) 379.52 16.01.07 No 7/08 15.07.08 121.55 31.03.08 362.21 121.54 3.78 7.00 4.50 1.00
(Km 0 - 7) dt. 24.06.06 16.02.08
+1.91
31.03.08
521 Araria Block Link Road IRQP 1.60 23.270 9888(S) 21.88 30.12.07 No 28.02.08 21.31 31.03.08 21.85 21.3 1.60 1.60 1.60 1.60 1.60
(Km 0-1.6) dt.21.08.08
522 Araria Approach Road to Jogbani to IRQP 2.00 176.110 11245 (S) 167.91 08.02.08 No 07.08.08 32.58 31.03.08 34.15 32.57 2.00 2.00 2.00
Aeroduome Road dt.25.09.07
(Km 2,3)
523 Araria Mata Asthan High School IRQP 1.56 39.200 10752(S) 38.46 30.11.07 28.02.08 38.41 31.03.08 38.45 38.41 1.55 1.55 1.55 1.55
Link Road (Km 1.558 ) dt.12.09.07
524 Araria Araria Court Chanderdei IRQP 3.30 108.180 10217 (S) 107.00 04.02.08 03.11.08 36.55 31.03.08 14.50 36.55 3.30 3.30 3.30
Rajokhar Road dt.24.08.07
(Km 2-4,8p)
525 Araria JBC Bhargama Road IRQP 2.30 72.790 9890 (S) 67.85 19.12.07 18.06.08 19.85 31.03.08 32.02 19.85 2.30 2.30 2.30
(Km 11-14) st.21.08.07
526 Araria Bathnaha Birpur Road IRQP 6.00 98.860 10128 (S) 96.61 19.01.08 19.07.08 31.03.08 28.41 10 2.50
(Km 1p,2p,5,6,7,9, dt.23.08.07
10 & 14p)
527 Araria Chanderdei Kamaldaha IRQP 6.00 346.900 13464 (S) 346.90
Paratha Road (Km 1p,5p, 6- dt.23.11.07 Agreement not done
10)
528 Araria Sisauna Link Road IRQP 1.00 41.990 11724(S) 41.57 30.12.07 No 28.02.08 38.10 31.03.08 41.57 38.09 1.00 1.00 1.00 1.00 1.00
(Km 1.00) dt.04.10.07
529 Araria Raniganj Bhargama Road W&S 4.00 279.010 12142 (S) 279.01 18.01.08 17.09.08 12.88 4.00
( Km 11 to 14 ) dt.16.10.07
529 Araria Total <<>> 126.458 7427.500 0.000 5981.289 0.000 0.000 0.000 0.000 1000.900 2571.079 0.000 3946.680 2592.175 0.000 109.250 81.700 70.500 24.250 33.150 14.650 2.000 16
530 Katihar Raghunathpur Balarampur Plan (P) 5.00 215.610 3380(S) 213.53 15.11.06 Yes 14.08.07 14.08.07 221.61 250.66 9.00 10.00 10.00 10.00 9.50 0.50
Drain 500m
Rd (Km 0-5) dt.28.03.06 HS-4.5 Km
1.06
25.03.08 500.75 250.66
531 Katihar Raghunathpur Balarampur Plan (P) 5.00 257.760 5434(S) 287.23 15.11.06 Yes 14.08.07 14.08.07 02.07.07
Rd (Km 6,10-12 & 16) dt.
532 Katihar Korha Falka Rd Plan (P) 12.86 550.580 8948(S) 597.51 12.01.07 Yes 11.06.08 11.07.08 33.25 529.52 28.03.08 579.51 529.52 11.50 12.85 12.85 12.85 9.00
(Km 20 -32p) dt.
31.07.06
533 Katihar Katihar Manihari Rd Plan (P) 26.20 1559.490 8951(S) 1836.24 12.01.07 Yes 11.03.08 11.07.08 470.72 1310.31 25.03.08 1836.23 1310.31 26.20 26.20 26.20 26.20 26.00
(Km 0 - 27p) dt. Work Completed
31.07.06
534 Katihar Kadma block HQ to Plan (P) 13.00 492.980 5985(S) 497.82 12.01.07 Yes 11.06.08 11.07.08 16.95 194.03 18.03.08 448.04 194.03 2.45 10.50 10.50 7.00
Kurumahat via Bharri-Asiyani dt. 10.06.06 23.03.07
Chawki Road +2.45
(Km 0-13) 21.05.07
535 Katihar Purnea Kadawa Sonaili Plan 0.88 83.260 10760(S) 91.64 22.01.07 Yes 21.04.07 21.04.07 33.41 55.43 24.12.07 91.64 55.43 Nil 0.83 0.83 0.83
Azam Nagar Abadapur Rd dt. Work Completed
Phase-I (Km 33p) 12.09.06 Drain -0.835
536 Katihar Chandpur PWD Road to Plan 8.50 501.940 6575(S) 393.13 12.01.07 Yes 11.03.08 11.07.08 24.96 202.10 25.03.08 343.98 202.09 1.96 8.25 7.75 7.50 3.00
Belgachhi - Baisi NH Border dt. 24.06.06 20.03.07
(Km 0 - 10)
537 Katihar Sisiahat to Semapur via Plan 9.75 248.86 12463(S) 292.21 27.03.07 Yes 26.12.07 30.06.07 168.96 27.03.08 292.20 168.95 1.46 6.00 7.00 7.00
Kalikapur Road Part A dt.08.11.06 21.05.07
(Km 0-10p)
538 Katihar Kurum to Gamghatta via 12 FC 16.50 639.780 6573(S) 583.04 09.01.07 Yes 08.03.08 08.07.08 50.68 183.19 29.03.08 506.20 132.68 - 13.50 10.50 8.00 1.25
Balmanki-Balia-Belaun Rd dt. 24.06.06 09.06.08
(Km 24p-38)
539 Katihar Gowaltoli Kushida Rd IRQP 2.00 55.182 9474(S) 59.00 23.11.07 No 22.05.08 21.92 18.01.08 21.92 2.00 2.00
(Km 4 & 5) dt.10.08.07
540 Katihar Link Road to Purnea Katiher IRQP 2.00 52.940 9486(S) 52.94 No
Road and KPRA. dt.10.08.07
(Km 1 & 2)
Page 21 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
541 Katihar Kurum to Gamghatta via IRQP 9.00 272.31 9460 (S) 272.31
Agreement not done
Balmanki-Balia-Belaun Rd dt.10.08.07
Work order given
(Km 1,2,6 to 12)
542 Katihar Azam Nagar Link Road IRQP 1.00 38.800 12333 (S) 40.55 21.01.08 No 20.04.08 10.40 25.02.08 10.4 1.00 1.00
(Km 3) dt.24.10.07
543 Katihar Damdama Azamnagar Road IRQP 2.00 9484 (S) 52.39 12.11.07 No 11.05.08 43.45 26.03.08 43.44 2.00 2.00 2.00 1.00
58.390
(Km 3,4 ) dt.10.08.07
544 Katihar K.P.R.A Road in Km 24 (P) IRQP 0.79 11244 (S) 52.59 16.02.08 No 15.08.08 13.21 24.03.08 13.2 0.79 0.50
53.120
Work for the year 2007-08 dt.25.09.07
545 Katihar Sapani PWD to Hasanganj IRQP 8.70 11565 (S) 148.93
Bhashwa and Bhashwa to dt.01.10.07 Agreement not done
148.927
Chandrama chowk (Km 8 to Work order given
16p)
546 Katihar Karagola Phulabaria Road (Km IRQP 9.70 8666 (S) 201.83
Agreement not done
8 to 11 & 13 to 18p,21p) 201.830 dt.20.07.07
Work order given
547 Katihar Korha Semapur Road (Km 1 to IRQP 4.00 8541 (S) 96.95 Agreement not done
96.950
4) dt.18.07.07 Work order given
547 Katihar Total <<>> 136.882 5528.713 0.000 5769.817 0.000 0.000 0.000 0.000 851.583 2983.182 0.000 4598.544 2932.634 0.000 58.750 91.420 84.880 53.300 28.200 45.500 1.330 0
548 Kishanganj K.T.T.G. Road Plan 25.50 1102.400 9095(S) 1245.45 03.03.07 Yes 08.08.08 02.08.08 159.40 943.15 31.03.08 945.00 1022.54 - 25.00 25.00 25.00 22.00 12.00 0.77 2
(Km 6, 9, 11, 15, 16, 23, 26, dt. 03.08.06 Drain 1500 M
29-32, 34-48p)
549 Kishanganj Day Market Powakhali Plan 31.00 1199.480 6645(S) 918.88 03.03.07 Yes 02.08.08 02.08.08 352.09 208.32 31.03.08 674.00 423.05 18.36 8.00 21.00 21.00 11.00 4
Jiyapokhar Road dt. 27.06.06 15.02.08 Prime Coat 16 Km
(Km 0 - 31) Work Started
550 Kishanganj Kishanganj Bahadurganj Rd Plan 27.20 483.040 799(S) 557.01 14.08.06 Yes 12 15.08.07 410.63 102.66 31.03.08 498.00 541.00 - 19.00 19.00 20.00 5.00
(Km 0-27.2) dt. 24.01.06 months Work Completed
551 Kishanganj Amour Bahadurganj Road Plan 27.19 1007.620 6645(S) 1146.90 03.03.07 Yes 02.08.08 02.08.08 112.25 705.62 31.03.08 815.12 817.87 - 20.00 20.60 20.50 13.00 12.00 1.10 2
Drain 2000m
(Km 14p - 41p) dt. 27.06.06 Prime Coat-13Km
552 Kishanganj College Chudipatti Road Plan 3.10 156.800 9112(S) 178.93 31.01.07 Yes 8 months 30.09.07 43.48 127.52 31.03.08 178.93 178.00 - 2.00 2.20 2.20 2.20 2.20 0.50
Work Completed
(Km 0 - 4p) dt. 03.03.07
553 Kishanganj K.T.T.G. Link Road Plan 3.40 235.860 6013(S) 210.03 31.01.07 Yes 8 months 30.09.07 86.54 128.72 31.03.08 210.00 214.00 - 2.00 2.20 2.20 0.70 0.70 1.60
(Km 0 - 4p) dt. 03.03.07 Work Completed
12.06.06
554 Kishanganj Kishanganj- Dinajpur Plan 3.30 66.720 956(S) 68.138 20.03.06 41.07 24.05 31.03.08 61.84 61.84 3.00 3.00 3.00 3.10
Road (Km 0-3.3) dt. Work Completed
28.01.06
555 Kishanganj Bagalbari Rahmat Para IRQP 3.80 113.930 12910(S) 113.94 07.11.07 Yes 06.05.08 92.69 31.03.08 101.00 102.00 3.80 3.80 3.80 3.80
Alta Barbatta Road dt-
(Km 17p, 18-19) 06.11.07
556 Kishanganj Pothia Link Road PR 3.00 30.410 13164 (S) 30.06 25.01.08 25.03.08 30.06 31.03.08 30.03 30.03 2.00 2.00 2.00 2.00
(Km 3,5,7) dt.04.11.07
557 Kishanganj K.T.T.G Road (Km 1 to W&S 22.00 1121.670 10548 (S) 1085.28 05.02.08 Yes 04.02.09 115.69 31.03.08 103.37 115.69 11.00 10.00
5,7,8,10,12 to 14,17 to dt.06.09.07
22,24,25,27,28 & 33)
557 Kishanganj Total <<>> 149.490 5517.930 0.000 5554.618 0.000 0.000 0.000 0.000 1205.460 2478.480 0.000 3617.290 3506.020 0.000 62.800 109.800 108.700 47.900 24.000 40.800 3.970 8
558 Purnea N.H.- 31 Town portion Plan (P) 6.05 478.670 6015(S) 387.63 16.01.07 Yes 31.03.07 53.86 128.07 31.03.08 181.93 181.93 6.10 6.10 6.10
(Km 404p, 405, 407 to dt. Work Completed
410, 411p) 12.06.06
559 Purnea Amour Bahadurganj Road Plan (P) 9.50 344.470 2890(S) 363.48 16.01.07 Yes 31.12.07 15.06.08 112.25 236.41 31.03.08 535.18 348.66 1.63 9.00 8.50 8.50 8.50 8.50
(Km 1-7, 11p-13) dt. 31.12.08 08.03.07 Work Completed
17.03.06
560 Purnea Baisi Amour Road Plan 5.50 154.710 2888(S) 179.42 20.09.06 Yes 09.06.07 19.06.07 159.02 9.21 31.03.08 179.42 166.234 7.16 5.50 5.50 5.50 5.50 5.50
(Km 3-7p, 13p,14p) dt. 24.04.07
Work Completed
17.03.06 +1.79
20.05.07
561 Purnea Baisi Amour Road Plan 8.50 341.430 5429(S) 319.58 05.01.07 Yes 30.06.07 30.06.07 316.84 31.03.08 319.58 316.84 3.41 8.50 8.50 8.50 8.50 8.50
(Km 0 - 2, 7p, 8 - 12, 13p, dt. 16.03.07
Work Completed.
14p) 25.05.06 +1.59
05.07.07
562 Purnea Chandpur PWD Road to Plan 10.00 493.240 4970(S) 493.99 23.12.06 Yes 15.06.07 15.05.07 145.70 230.69 31.03.08 493.99 376.38 3.58 10.20 10.20 9.00 9.00 7.00
Belgachhi Baisi border NH-31 dt.15.05.06 27.02.07
via Rounia Kanharia Bazar 1.36
Road (Km 0-10) 04.05.07
563 Purnea Krityanand Nagar 12 FC 10.65 163.060 6202(S) 161.33 05.02.07 Yes 30.06.07 30.06.07 44.71 1.12 07.03.08 161.33 110.823 1.06 10.60 10.60 10.60 10.60 10.60
Champanagar Road dt. 29.06.07
Work Completed
(Km 1 - 3, 12, 13p, 14-19) 14.06.06
564 Purnea Purnea Srinagar Road PR 1.00 12.20 8947(S) 11.385 27/11 No 31.12.07 11.38 31.03.08 11.39 11.385 1.00
(Km 1) dt. Work Completed
27.07.07
Page 22 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
565 Purnea Ekahua Mahmadia Dubouli PR 5.00 51.60 9482(S) 52.83 27/11 No 31.01.08 46.52 31.03.08 50.32 46.62 5.00 5.00 5.00
Road dt.10.08.07 Completed
(Km 1 to 5 )
566 Purnea Purnea Kadwa Sonali PR 6.00 48.62 8672(S) 48.62 27/11 No 31.01.08 54.86 31.03.08 55.21 54.86 8.00 6.00
Azamnagar Abadpur Road dt.20.07.07
Work Completed
(Km 0 to 6 )
567 Purnea Gulabbagh Birpur Road PR 2.00 13.30 9573(S) 13.923 11.12.07 No 11.03.08 1.50 31.03.08 15.21 1.50 1.50
(Km 1 & 2 ) dt.14.08.07
568 Purnea Gulabbag Purnea City PR 0.35 2.50 9575(S) 2.622 27/11 No 31.01.08 2.62 31.03.08 2.62 2.62 0.25
Road dt. Work Completed
(Km 1p ) 14.08.07
569 Purnea Purnea Kadwa Sonali IRQP 7.10 186.14 8485 (S) 197.134 12.08.08 31.03.08 25.00
Azamnagar Abadpur Road dt.18.07.07 Retenter
(Km 9,10,14 to 19) )
570 Purnea Dhamdaha Quari Road IRQP 3.00 37.78 9884 (S) 38.6175 25.12.07 25.03.08 38.62 31.03.08 38.62 38.61 3.00 3.00 3.00
(Km 1-3) dt.21.08.07 Completed
571 Purnea Ekahua Mahmadia Dubouli IRQP 10.00 126.13 8532 (S) 135.00 13.03.08 12.12.08 13.71 12.00 13.71 1.00 1.00
Work in Progress
Road (Km9 to 18) dt.18.07.07
572 Purnea Krityanand Nagar IRQP 8.00 100.42 9574 (S) 121.00 13.03.08 12.12.08 0.00
Champanagar Road dt.14.08.07 Work in Progress
(Km 4 to 11)
573 Purnea Amour Bahadurhanj Road (Km W&S 3.50 144.52 8533 (S) 165.00 14.03.08 14.12.08 9.83 2.00 1.00
8 to 11p) dt.18.07.07 Work in Progress
574 Purnea Jokihat Dalmalpur Road (Km 6 W&S 5.00 755.21 13461 (S) 732.00 14.03.08 14.09.09 136.38 3.00 1.00
Work in Progress
to 10 ) dt.23.11.07
574 Purnea Total <<>> 101.150 3453.995 0.000 3187.805 0.000 0.000 0.000 0.000 515.529 1237.760 0.000 2081.796 1670.172 0.000 67.300 46.300 48.200 39.500 16.700 61.450 0.000 0
575 Khagaria Khagaria Alloli Road Plan 18.70 303.820 1014(S) 290.27 29.06.06 Yes 31.05.07 30.03.07 232.30 37.39 31.03.08 290.27 288.58 2.00 17.00 17.75 4.00 10.70 8.00
Material Collection
(Km 6-7,9-10 & 0-19p) dt. 31.01.06 26.03.07
Govt. Plant engaged at
+1.50 other site
04.05.07
576 Khagaria Maheshkhunt Gogari Parbatta Plan 7.00 268.660 3378(S) 292.08 29.06.06 Yes 31.05.07 26.08.07 166.05 92.88 31.03.08 292.08 260.00 3.46 7.00 7.00 7.00 7.00 7.00 4.50 Material Collection
Sultanganjghat Road (Km 11- dt.28.03.06 07.03.08 Govt. Plant engaged at
15, 21-22) other site
577 Khagaria Maheshkhunt Gogari Parbatta Plan 22.00 788.410 6583(S) 861.37 07.07.07 Yes 06.09.08 07.09.08 22.78 107.50 31.03.08 144.00 115.00 6.30 12.00 14.50 5.00 9.00 2.00 1.00
Sultanganjghat Road (Km 0- dt. 24.06.06 01.08.07
8, 10, 16-20, 23-30)
578 Khagaria Khagaria Parihara Bakhari Plan 19.00 903.230 6044(S) 991.37 07.03.07 Yes 06.03.09 07.03.09 26.61 119.13 31.03.08 126.00 118.92 7.42 13.00 17.00 9.00
Road (Km 0 - 19) dt. 12.06.06 01.08.07
579 Khagaria Naugachhia Tintanga Road Plan 16.00 595.410 9942(S) 702.84 11.04.07 Yes 11.10.08 11.10.08 0.19 125.78 31.03.08 83.20 125.87 5.27 13.00 15.00 9.00 1.50
(Km 0 - 16) dt. 24.08.06 01.08.07
580 Khagaria Bihpur Gopalpur Road Plan 19.00 747.210 6041(S) 797.49 09.03.07 Yes 08.09.08 09.09.08 0.32 31.39 31.03.08 101.00 71.00 5.98 16.00 18.00 3.00
(Km 0 - 19) dt. 12.06.06 01.08.07
581 Khagaria Naugachhia Mahadevpur 12 FC 10.00 191.480 6200(S) 227.65 23.11.08 Yes 31.03.07 31.03.07 181.53 46.03 31.03.08 227.65 227.55 10.00 6.00 10.00 10.00 10.00
Ghat Rd (Km 1, 2, 4 - 10, dt. Work Completed
12) 14.06.06
582 Khagaria ROB (South End) to Thana IRQP 0.19 12.830 7932(S) 16.18 18.01.07 31.03.08 7.72 31.03.08 7.71 0.04 0.19 0.19 0.19
Road City Ghat dt.04.07.07 Work Completed
(Km )
583 Khagaria Khagaria Monghyr Ghat Rd IRQP 3.00 40.150 7928(S) 44.57 10.01.08 31.05.08 0.00 31.03.08
(Km 3 to 5 ) dt.04.07.07
584 Khagaria Khagaria Monghyr Ghat IRQP 1.00 40.440 7929 (S) 48.51 18.01.08 31.05.08 48.48 31.03.08 48.47 1.00 1.00 1.00 1.00
Link Road(Km 1 ) dt.04.07.07 Completed
585 Khagaria Gogari Link Road IRQP 2.10 40.100 8488 (S) 44.53 30.12.07 30.06.08 0.00 31.03.08 1.00
(Km 0 to 3p) dt.18.07.07
586 Khagaria Pansalwa Beldaur missing link IRQP 1.31 53.990 12143 (S) 64.64 18.01.08 31.03.08 15.28 31.03.08 15.24 1.00 1.00 0.00
Road (Km 1.2p) dt.16.10.07
587 Khagaria Khagaria Parihara Barbari IRQP 0.13 4.230 12141 (S) 5.34 10.01.08 31.03.08 5.08 31.03.08 5.07 0.13 0.13 0.13
Link Road (Km 1p) dt.16.10.07
588 Khagaria Kataria Tintanga Raod IRQP 0.82 11.150 7930 (S) 12.47 10.01.08 31.03.08 12.47 31.03.08 0.82 0.82
(Km 9p & 10p) dt.04.07.07 Work Completed
589 Khagaria Khararia Sone Mankhi Ghat W&S 2.80 93.070 7933 (S) 100.30 16.03.08 6.91 31.03.08 50.00 6.9 1.00 1.00 1.00
Link Road (Km 0 to 3p) dt.04.07.07
589 Khagaria Total <<>> 123.054 4094.180 0.000 4499.607 0.000 0.000 0.000 0.000 629.766 656.040 0.000 1314.200 1290.310 0.000 91.130 97.415 39.190 39.200 21.010 25.640 0.000 0
590 Madhepura Murliganj Babhangama Plan 6.50 154.380 9098(S) 165.89 18.03.07 Yes 17.12.07 6.00 89.84 31.10.07 165.89 95.38 6.00 6.00 4.00 0.50
Bihariganj Rd dt. 03.08.06
(Km 1p, 16-21)
Page 23 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
591 Madhepura Murliganj Babhangama Plan (P) 14.00 480.870 2895(S) 1070.66 18.11.06 Yes 17.05.08 340.00 655.64 12.02.08 923.22 994.62 Nil 13.55 13.55 13.55 13.55 13.32
Bihariganj Rd dt. Work Completed
(Km 2-15) 17.03.06
592 Madhepura Mirganj Jadia Rd Plan (P) 13.20 440.260 3377(S) Yes 17.05.08
(Km 1-7,9-10,11p-14,19 & dt.28.03.06
20)
593 Madhepura Gwalpara Atalakha Plan 6.00 224.290 10852(S) 162.62 06.03.07 Yes 05.12.07 2.40 112.03 12.03.08 162.62 114.09 0.813 4.00 6.00 6.00 3.50 1.00
Sonbarsha Road dt. 18.05.07
(Km 0 - 6) 13.09.06
594 Madhepura Alamnagar Budhma Mali Plan 16.00 353.550 3376(S) 403.35 18.11.06 Yes 17.11.07 22.64 72.07 03.01.08 403.35 94.71 2.07 5.00 8.00 5.50
Chowk Road dt.28.03.06 04.06.07
(Km 0-16) +2.01
28.03.08
595 Madhepura Udakishanganj Bihariganj Plan 8.40 189.990 9941(S) 209.20 06.03.07 Yes 05.12.07 10.13 93.67 30.11.07 209.02 103.81 5.00 6.40 6.40
Road (Km 0 - 9p) dt. 24.08.06
596 Madhepura Supaul Singheshwar CRF 9.80 144.969 7428(S) 144.97 28.59 9.80 9.80 9.80 9.80
Rd (Km ) dt.20.10.01 Work Completed
597 Madhepura Kishanganj Bihariganj Rd IRQP 2.00 159.590 9865 (S) 150.25 18.12.07 17.06.08 95.28 02.02.08 56.00 95.38
Nala 1800m
(1,2 Km ) dt.21.08.07
598 Madhepura Purnea Saharsa Road IRQP 2.18 96.034 8984(S) 101.87 05.01.08 24.05.08 106.54 100.52 2.10 2.10
(75p,76,77p Km ) dt.30.07.07 Completed
599 Madhepura Mirganj Jadia Rd W&S 6.00 277.614 8665(S) 310.32 29.01.08 28.10.08 76.35 70.57 3.00
(8,11(350), 15-18,19(650) Km dt.20.07.07
)
600 Madhepura Murliganj Babhangama W&S 0.50 58.280 8664(S) 59.61 30.11.07 No 29.03.08 38.42 29.02.08 30.00 38.42 0.50 0.50
Bihariganj Rd dt.20.07.07 Nala 300m
(Km 1p )
601 Madhepura Special Repair on Karma PR 122.35 08.03.07 07.06.08 112.68 119.67 4.80 5.00 5.00
Alamnagar Road (Km 5.6)
601 Madhepura Total <<>> 84.580 2579.827 0.000 2901.089 0.000 0.000 0.000 0.000 409.760 1452.520 0.000 1950.100 1827.170 0.000 43.350 43.450 40.750 32.350 11.900 31.220 0.000 0
602 Saharsa Simri Bakhtiarpur to Salkhua Plan 8.50 585.410 10854(S) 524.25 25.04.07 12.03.08 28.92 61.49 31.03.08 524.25 107.25 4.00 4.60 1
Road dt. 13.09.06
BRPNN
(Km 0 - 9)
603 Saharsa Sonbarsa Gawalpara Road Plan 17.00 1205.330 8937(S) 816.08 25.04.07 Yes 17.06.08 100.86 161.97 31.03.08 584.50 190.10 7.90 12.50 3.00 6
(Km 3 - 20) dt. 31.07.06 BRPNN
1950(S)
dt.14.02.07
604 Saharsa Karanpur - Rajanpur Road Plan 30.00 1321.000 6645(S) 560.14 25.04.07 Yes 04.06.08 259.94 31.03.08 487.83 120.58 12.50 6.50 5.65 1.50
(a) 15 to 29 (Km 15-44) dt. 27.06.06 BRPNN
5055(S)
dt.16.04.07
605 Saharsa Karanpur - Rajanpur Road Plan 672.57 25.04.07 30.04.08 31.03.08 620.42 154.50 6.25 6.03 0.70 2
(b) 30 to 44 (Km )
606 Saharsa Balthi - Musaharnia Road Plan 6.00 227.95 9852(S) 121.20 25.04.07 Yes 31.10.07 16.57 16.64 31.03.08 121.20 16.64 3.00 1
(Km 0 - 6) 222.97 dt. 23.08.06 BRPNN
1950(S)
dt.14.02.07
607 Saharsa Chaughara - Saharsa Road Plan 14.00 497.870 10853(S) 622.00 08.03.07 Yes 07.03.08 07.03.08 78.65 437.18 31.03.08 622.00 518.06 3.11 14.00 13.70 13.70 13.63 12.00 8
(Km 7, 12-24) dt. 13.09.06 30.04.07
HS-6Km
3.11
28.01.08
608 Saharsa Banganw Manshishi Rd IRQP 1.96 26.060 8668(S) 26.77 23.12.07 No 10.03.08 11.66 31.03.08 26.77 16.00 1.00 2.00
(Km ) dt.20.07.07
609 Saharsa Saharsa Salkhua Rd IRQP 2.01 43.990 8544(S) 41.97 21.11.07 No 20.01.08 35.46 31.03.08 41.97 35.13 1.67 1.67 1.67
(Km 1p,3p, & 4p) dt.18.07.07 Work Completed
610 Saharsa Panchagachhia Nauhatta Road IRQP 6.50 107.230 8667 (S) 103.93 28.12.07 31.05.08 15.91 31.03.08 42.92 22.5 1.50
Retaining wall 152.4m
(Km 8 to 14p) dt.20.07.07
611 Saharsa Saharsa Agr.Sc.Centre Sisal to IRQP 10.77 204.330 8547 (S) 194.50 28.12.07 30.06.08 11.68 31.03.08 91.80 13.5 0.60 0.22 1
Agwanpur Bangaon dt.18.07.07
Panchoachhia Road (Km 1 to
12p)
611 Saharsa Total <<>> 90.740 3991.220 0.000 3683.410 0.000 0.000 0.000 0.000 225.000 1011.930 0.000 3163.660 1194.260 12.500 44.320 42.480 19.500 0.000 18.800 13.670 0.220 19
612 Supaul Bathnaha Bhimnagar Rd Plan 23.00 1314.680 6645(S) 1267.99 05.05.07 04.11.08 53.23 31.03.08 902.79 525.00 20.00 23.25 22.50 6.26
(Km 17 - 40) dt. 27.06.06 BRPNN
5055(S)
dt.16.04.07
613 Supaul Pratapganj to Chatapur Road Plan 8.75 470.250 6791(S) 150.93 05.05.07 Yes 04.02.08 66.23 31.03.08 155.62 30.00 3.00 2 BRPNN
Part-A (Km 4 - 13p) dt. 30.06.06 Rescinded
1950(S)
dt.14.02.07
614 Supaul Pratapganj to Chatapur Road Plan 164.55 05.05.07 Yes 04.02.08 31.03.08 169.63 125.00 4.25 4.00 2.25 5 BRPNN
Part-B(Km 9 - 13)
Page 24 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
615 Supaul Tribeniganj Jedia Balua Rd Plan 23.75 1387.320 13312(s) 1338.87 05.05.07 04.11.08 88.64 31.03.08 877.07 280.00 24.00 16.50 11.00 2
(Km 27-51p) dt.27.11.06 BRPNN
1950(S)
14.02.07
616 Supaul Mirganj Jadia Rd Plan 3.00 199.030 9119(S) 185.34 05.05.07 Yes 04.02.08 55.99 31.03.08 179.32 90.00 3.60 3.60 3.60 2.00 0.90
(Km 20p - 23p) dt. 03.08.06 BRPNN
1950(S) B/S-3.60
dt.14.02.07
617 Supaul Balua to Baisi Road Plan 13.50 1009.970 6645(S) 371.64 05.06.07 Yes 04.06.08 31.45 31.03.08 356.83 90.00 1.858 10.00 3.50 3.50 3
(Km 0 - 14p) dt. 27.06.06 BRPNN
5055(S)
dt.16.04.07
618 Supaul Supaul Nebua Rd Plan 9.00 366.500 6524(S) 295.02 05.05.07 Yes 04.02.08 4.83 31.03.08 292.94 50.00 1.48 6.00 2.00 1.25 1 BRPNN
(Km 0 - 9) dt. 23.06.06
619 Supaul Murli Narayanpur Road Plan 8.50 257.640 2896(S) 279.61 12.06.06 Yes 11.12.07 11.12.07 142.78 135.71 31.03.08 279.62 279.62 5.60 8.50 8.50 8.50 8.50 15
(Km 0 - 8.5) dt.17.03.06 28.05.07 Work Completed
+1.40
25.06.07
620 Supaul Mehasimar to Ganpatganj Plan 12.00 695.720 6413(S) 766.36 08.03.07 Yes 07.06.08 07.06.08 8.50 532.31 31.03.08 670.17 525.00 17.00 11.00 8.50 8.50 6.00 6.00 20
Road (Km 0 - 12) dt. 21.06.06 28.05.07
+3.40
31.03.08
621 Supaul Parsarma Chikni Road Plan (P) 14.88 403.730 9726(S) 773.75 08.03.07 Yes 07.05.08 07.06.08 35.38 580.87 31.03.08 773.75 570.00 22.05 11.00 14.27 12.00 1.50 0.30 14
(Km 0 - 15p) dt. 19.08.06 25.06.07
+3.75
31.03.08
622 Supaul Choughara Saharsa Road Plan (P) 6.00 259.370 10855(S) Yes 07.06.08 07.06.08 1.71 6.00 6.00 6.00 6.00 5.00 10
(Km 0 - 6) dt. 13.09.06 11.01.07 B/S 6 Km
623 Supaul Saraigarh Lalganj Ganpathganj Plan 6.20 323.89 12941(s) 350.07 14.03.07 Yes 13.03.08 13.03.08 5.35 125.22 31.03.08 350.06 146.00 8.75 5.50 6.00 6.00 2.00 7
Road dt.18.11.06 11.01.08 Gr-II-6Km
(Km 4-6,7p,8-10p) +1.75 Gr-III-6Km
31.03.08
624 Supaul Karanpur - Rajanpur Road CRF 11.00 376.20 7920(S) 376.20 No 75.00 61.78 376.00 300.00 11.00 11.00 11.00 11.00 11.00 6
(Km 11) dt.
Work Completed
625 Supaul Tharbita to Bishanpur 12 FC 7.00 158.580 6065(S) 158.58 Yes 156.44 7.00 7.00 7.00
NH -106 Road dt. Work Completed
(Km 0 - 7) 12.06.06
626 Supaul Persarma Bakour Rd 12 FC 8.00 181.720 6199(S) 181.72 Yes 185.72 200.00 152.38 Nil 6.84 6.84 6.84 5
Work Completed
(Km 0 - 8) dt.
627 Supaul Simrahi Bazar to eastern PR 6.00 43.427 8539(S) 43.44 31.10.07 No 25.03.08 31.03.08 43.37 43.29 6.00
Koshi embankment Rd dt.18.07.07
Work Completed
(Km 0 to 6)
628 Supaul Raghopur Makhtab Chowk to IRQP 6.80 320.164 9494(S) 337.62 11.12.07 Yes 10.12.08 9.90 31.03.08 161.63 9.78 1.688
Sukha Nagar Chowk dt.10.08.07 22.02.08
(Km 9p to 15p)
629 Supaul Supaul Bina Rd IRQP 5.10 109.220 7922(S) 109.54 11.12.07 Yes 10.12.08 14.25 31.03.08 17.10 20.00 3
(Km 0 to 6p ) dt.04.07.07
630 Supaul BSS College to Parsarma Road IRQP 7.00 203.910 7910(S) 211.20 11.12.07 Yes 10.12.08 65.56 31.03.08 72.97 90.00 4.00 1.00 3.25
(Km 0 to 7) dt.04.07.07
631 Supaul Supaul Railway Station to IRQP 0.27 9.435 8553(S) 8.40 21.11.07 No 25.03.08 8.82 31.03.08 8.40 8.40 0.27
Bairiya Manch Road dt.18.07.07 Work Completed
(0.73 to 1.00) (Km )
632 Supaul Birpur Basmatia Road (Km IRQP 6.20 141.270 7898 (S) 151.79 09.02.08 08.02.09 26.71 31.03.08 22.06 45.00 1.50
1p,4p, to 7p) dt.04.07.07 1.00
633 Supaul BSS College Parsarma Road to IRQP 0.68 28.190 14290 (S) 27.12 10.03.08 09.06.08 5.92 31.03.08 4.00 1
Bina Ekma Railway Station dt.11.12.07
(Km 1p)
[ EXTRA]
634 Supaul Dafarakha Merhia Suryapur IRQP 8.00 209.180 7909 (S) 209.18 17.03.08
Road (0 to 8 Km) dt.04.07.07
635 Supaul Duania Chowk NH-57 to IRQP 7.80 516.099 10218 (S) 514.76 20.03.08 19.06.09 31.03.08
Govindpur Balua Baisi Road dt.24.08.07
(2p to 10p Km)
636 Supaul Ganpatganj Gaddi Diwanhanj W&S 7.50 392.500 8889 (S) 427.32 15.02.08 14.02.09 71.99 31.03.08 154.55 72.00 9
Pratapganj Road (Km 9 to dt. 26.07.07 2 Culvert in Progress
16p)
637 Supaul Tribeniganj Jedia Balua Rd W&S 13.90 826.276 9491 (S) 769.68 29.02.08 28.05.09 31.03.08 20.00 2.00 1.00
(Km 12 to 26) dt.10.03.07
13654 (S)
27.11.07
638 Supaul Dafarakha Merhia Suryapur W&S 9.80 860.200 8475 (S) 860.20 17.03.08 0.16
Raod dt.18.07.07
(11p to 22p Km)
Page 25 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
South and North Wing ROAD CONSTRUCTION DEPARTMENT, BIHAR 10.04.2008
PROGRESS REPORT OF ONGOING ROAD SCHEMES FOR 2007-08
Sr. Division Name of Road Sanction Administrative Agreement Date of Weekly Date of Date of Financial Status on 31.03.08 Physical Progress upto 31.03.08 Remarks
Head
No. ed Approval Amount work Program Completi Completi
Length (Rs. in Lacs) order me on as per on as per
Length Amount Reference received work Agreeme Expenditur Expenditur Dt. of Work Actual Fine E/W GSB WBM/ BUSG BM/ SDBC PCC CD
(Km) (Rs. in or not program nt e upto e upto measure- value as work imposed / (in Km) (in WMM (in Km) DBM / BC / (in Work
Lac) me 31.03.07 31.03.08 ment per target done date Km) (in Km) (in PMC Km) (no.)
(Rs. in (Rs. In (in Lacs) (in Lacs) (in Lacs) Km) (in Km)
Lacs) Lacs)
1 2 3 4 5 6 7 8 9 10 11 11a 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Grand Total <<>> 5473.71 261331.36 256881.33 29390.92 75824.12 0.00 166902.76 98127.27 45.65 3407.97 2583.63 2235.67 1443.84 1300.69 1351.87 68.22 1069.00
Page 26 of 26 C:\Status_MDRs_31.03.08.xls - RoadListAll
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1.Revised by
129.8to 140.2 GSB-10.4 H.C order
Saran WMM- 10.4 5.2 5.45 2.2
1 Gulzarbagh 19 IRQP 019-BR-2005-681 NHO 10.40 499.520 451.62 25.01.08 15.06.08 30.34 41.37 27.10 SDBC-10.4
2. To complete
Construction 5.2 5.70 2.2
(Manjhi- Elai Bazar) CD-2 work by
15.06.08
E/W- 3.1
GSB- 3.1
140.2 to143.3 Saran 3 3 2 1.0 Revied by High
2 Gulzarbagh 19 W&S State 3.10 130.00 127.12 18.01.08 17.02.08 55.02 96.54 12.71 WMM- 3.1
(Elai Bazar-Chapra) Construction BM- 3.1 3 3 2 1.75 Court order.
SDC- 3.1
143.3 to 146.15 Saran Raising work in
3 Gulzarbagh 19 FDR FDR 2.85
(Chapra Bazar) Construction chaora Bazar.
Ms Kumar E/W-8.5
SR work in Km.
Construction, 15.04.07 WMM- 3.85 3.75 3.75 3.0
4 Gulzarbagh 19 IRQP 146.15-150 State 3.85 130 126.55369 15.01.07 73.24 111.94 9.16
Doriganj, 31.12.07 BM- 3.85 3.85 3.85 3.85
Chapra byepass
Chapra SDC- 3.85
150 to 166
No progress
019-BR-2006-1292 204.372 31.03.07 BM-3.05 3.05 10.50
5 Gulzarbagh 19 PR PR 16.00 264.13 Ramakant Singh 15.01.07 54.03 175.27 12.67 SDC- 16
after rainy
(Chapra-Dumri 258.372 31.03.08 3.05 10.50
season..
adda)
165-8 to 183.8 E/W-18
GSB- 18
019-BR-2006-704 15.07.07 17.00 18.00 18.00 3.00 0.5 Complete BM
6 Gulzarbagh 19 W&S NHO 18.00 492.49 400.80 Ramakant Singh 15.01.07 24.32 202.32 11.79 WBM-18
(Dumri adda- 31.12.07 BM-4.5 17.00 18.00 18.00 3.00 0.5 by 21.03.08
Shitalpur) SDC-18
Improvement with 50
mm BM after reparing
Rassing-0.2
Improv with WMM in Km Indarmani 0.2 0.2 3.0
7 Gulzarbagh 19 State 4.50 97.43 108.63 15.02.08 14.04.08 83.63 WMM-0.2
ement 166, 167, 170 to 172, Construction BM-4.5 0.2 0.2 3.9
175 to 179 & 182 of
NH-19
Km 185-195(P) Ramakant
8 Gulzarbagh 19 IRQP State 5.00 67 67
(Shitalpur-Sonpur) Singh
Tender received
Km 184(P) to 196(P) on 18.03.08. T/B
9 Gulzarbagh 19 IRQP In balance chainages State 5 105.00 SDBC-5 received in CE
(Shitalpur-Sonpur) office on
08.04.08
A1-Comp
Mahi Bridge 02.07.00 P1-Comp
10 Gulzarbagh 19 Bridge NHO 338.85 270.37 Ramakant Singh 02.06.99 155.18 156.65 9.75 P2-Part
019-BR-1998-512 31.03.08
A2-Comp
P/R in Km 195.10 to
Trishul
11 Gulzarbagh 19 PR Km 201.0 of NH 19 State 5.90 89.81 105.06 03.03.08 02.05.08 SDC-59
Construction
for the year 2007-08
PR in Km 201.00 to
Trishul 1.5 Work in
12 Gulzarbagh 19 PR 203.25 & 204.20 to State 5.9 89.81 102.26 07.03.08 02.05.08 23.07 SDC-59
Construction 1.5 Progress.
207.85 of NH-19.
WMM- 0.313
Beautifi Km 209 Ashok 15.02.07 BM- 0.68
13 Gulzarbagh 19 State 0.8 60.00 49.74 15.01.07 39.50 46.43 4.67 SDC- 0.68
cation Ramashish Chowk Const
1
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
GSB-0.342
Km 209 M/s Dhaneshar Foot path in
14 Gulzarbagh 19 PR State 0.3 133.39 133.39 26.03.08 25.08.08 0.00 4.61 WMM-0.342
Ramashish Chowk Nath const. SDC-0.342 Progress.
209 to 214(P) of NH-
19. (Hajipur- MG setu To include in PR
15 Gulzarbagh 19 PR State
North Approach list.
Section)
Work awarded
PR work in KM 213 not taken due to
16 Gulzarbagh 19 PR at Toll Plaza of NH- State 0.365 51.62 over lapping
19 with Automatic
toll Plaza.
Pier P-21, P-22, P- Fressinet
12.05.07 External Prestresing of
17 Gulzarbagh 19 Bridge 30 & P-31 PBFF 492.95 416.00 Prestressed conc. 12.09.06 295.62 653.80 4 span.
30.04.07
019-BR-2005-693 Co. ltd
Central Hinge Fressinet
4 no of CHB
18 Gulzarbagh 19 Bridge Bearing is M.G Setu PR 70.9 70.90 Prestressed conc. 01.11.07 28.02.08 0.00 11.77 CHB-13 nos
supplied at site.
019-BR-2006-1265 Co. ltd
Repair of 92 Central
Hingh
Bearings(CHB) by Fressinet
69 no shim Plate
19 Gulzarbagh 19 Bridge inserting shim plates PBFF 19 158.00 122.40 Prestressed conc. 16.02.08 05.05.05 0.00 78.00 Shim 92 No.
replaced.
between plunger and Co. ltd
plate.
(019-BR-07-736)
Additional
Strengthening work
of Pier P4 and P44
Agreement not
and Stitching of gap
executed work
20 Gulzarbagh 19 Bridge between joint 10-11, NHO 132.00 15.04.08 15.04.08
order need to
and 11-12 of Patna
issued
side arm of P44 of
U/s lane(Job No.019-
BR-07-737)
External Prestressing Fressinet Expenditure on
21 Gulzarbagh 19 Bridge of MG Setu(9 Span) NHO 1339.17 1164.60 Prestressed conc. 29.03.08 28.03.09 0.00 126.94 Mobilisation
(019-BR-08-763) Co. ltd Advance.
Replacement of
22 Gulzarbagh 19 Bridge CHB NHO 175.420
19-BR-2008-771
Painting of railing &
central Verge of Ms Rai 80% work
23 Gulzarbagh 19 Bridge State 19.38 18.7 10.01.08 23.02.08 15.56
M.G Setu & its Construction completed.
approach
Rehabilitation of
wearing coat with
Mastic Ashphalt. & M/s Dayanand Work to be
24 Gulzarbagh 19 Bridge State 5.75 399.21 418.54 29.03.08 28.12.08
repair of Expansion Pd Sinha & Co. started.
Joints U/s & D/s of
MG Setu.
PR in Km. 220 to 222
of NH-19.
25 Gulzarbagh 19 PR
(MG setu south
Approach)
2
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-13
KM. 521 to 533 28.02.07 BM-13
26 Muzaffarpur 28 IRQP NHO 13.00 423.45 385.39 Shyam Bihari 29.08.06
30.05.07
295.64 423.00 5.76
SDC-13
028-BR- 2006-713
Marking-13
27 Muzaffarpur 28 IRQP Km.534-543 IRQP
28 Muzaffarpur 28 PR PR in Km. 544 PR
29 Muzaffarpur 28 IRQP Km.545 & 546 IRQP
30 Muzaffarpur 28 IRQP km.547-564 State 18.00
31 Muzaffarpur 28 IRQP IRQP in Km.565
32 Muzaffarpur 28 PR PR in Km. 566-568 PR
33 Muzaffarpur 28 IRQP IRQP in Km.569 IRQP
34 Muzaffarpur 28 PR PR in Km. 570-572 PR
IRQP in Km.573 to
35 Muzaffarpur 28 IRQP IRQP
581
Km 582 to 608
36 Muzaffarpur 28 IRQP (except 584) IRQP
Muzaffarpur-Baruni
37 Muzaffarpur 28 PR Km. 584 PR
Shiwani
4.3 Work alloted on
38 Muzaffarpur 28 PR PR in Km. 609-618 State 10.00 800 384.84 Infratach Pvt 19.03.08 18.06.08 95
4.3 10.03.08
Ltd.
Proposed A/P
39 Muzaffarpur 28 PR PR in Km 619-627
2008-09
Between Km 0-67 E/W-46 Revised estimate
WBM-11 30 11.0 11.0 40.0
40 Motihari 28A IRQP (1-16,23-46,62-67) NHAI 46.00 1157.78 879.57 SriNet & Sandalaya 12.05.06 30.06.07 412.00 776.00 2.69
BM-11 30 11.0 11.0 40.0
sanction
Piprakothi- Raxzul SDC-46 awaited.
41 Motihari 28A Km. 17-22 NHAI
42 Motihari 28A Km.47-49 NHAI
43 Motihari 28A Km.53-59 NHAI
3
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
EW-5
Imp. & Km 50-52, 60 & 61 Ram pravesh Roy WBM-3 2.0 2.5 3 0
44 Motihari 28A NHAI 5.00 230.47539 estate Pvt.Ltd
11.10.07 10.02.08 220.00 BM-3 3.0 3.0 5 5
Str. Piprakothi- Raxzul
SDC-5
M/s North Bihar E/W-30
km. 0 to 30 10.60 WBM-1.41 15.0 1.0 1.0 0.600 17.00
45 Motihari 28B IRQP State 30.00 360.00 423.58 Const 24.01.07 30.06.07 2.17 230.00 BM-1.41
Chapwa-Betia 10.05.07 15.0 1.0 1.0 0.600 17.00
Corporation SDC-30
Ram pravesh E/W-34
Km 31-64 16.10.07 4.57 34.0 0.56 34.0 34.0
46 Motihari 28B IRQP State 34 800.00 914.69 Roy estate 17.01.07 497.83 914.09 WBM-34
Bethia-Chautarwa 18.06.07 PMC-34 34.0 0.56 34.0 34.0
Pvt.Ltd
E/W-19
S.R GSB-19
Km 65-83 21.05.08 0.0 Work in
47 Motihari 28B IRQP State 19 500.00 506.1773 Construction 22.08.07 0.00 436.00 9.00 WBM-19 16.0 16.0 16.0 11.0
Betia-Bagha 31.03.08 PMC-19 0.0 Progress.
(P) Ltd M.P 17.0 17.0 17.0 12.0
GSB-14
Tender
Km 84-112
Committee.
48 Motihari 28B Bridge (28B-BR-07-756) NHO 29 1191.60
Award in
process
Construction of
3x21m (eff span)
High level RCC
Ujjain
49 Motihari 28B Bridge Bridge in KM 83 of NHO 498.21 470.99 26.02.08 25.02.10 Work Started.
Construction
NH-28B
(MALPURWA)
028B-BR-2007-739
Construction of
2x12.00m (eff span)
High Level RCC
Strengt Star
50 Motihari 28B Bridge with footpath NHO 252.65 212.04 20.03.08 19.03.10 Work Started.
hening Construction
at chainage 43.880
of NH-28B
028B-BR-2007-742
Kochas
51 30 IRQP Km. 1-2 NHO 2
at Mohania
Km 3-10
Kochas
52 30 IRQP Mohania-Katra NHO 8
at Mohania
(030-BR-06-724)
Kochas
53 30 IRQP Km 11-48 NHO 38
at Mohania
Kochas 49 to 67
54 30 IRQP NHO 19.00
at Mohania 030-BR-2006-710
Km 68 to 77
Kochas
55 30 IRQP Maliabagh-Arrah NHO 13
at Mohania
(030-BR-06-726)
Kochas Km 78 to 100
56 30 PR PR 23 305.00
at Mohania 030-BR-2006-1290
Kochas Km 101 -102
57 30 IRQP State 2
at Mohania Jagdishpur-Arrah
Kochas Km 103-106
58 30 PR State 4
at Mohania Jagdishpur-Arrah
4
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Kochas Km 107-116
59 30 IRQP State 10
at Mohania Jagdishpur-Arrah
118-120, 134P,
136P, 137P, 151, Calmity
60 Patna West 30 IRQP 152, relief 9.75 148.12 148.12 Umesh Kumar 148.11 148.11
(9.75 Km) fund
Arrah-Maner
121(500), 122(400),
123(100), 124(100),
125(250),
126(150),127(700),
128(200), 129(250),
130(100), 133(100), 1.36 3.0 14.08 1.0
61 Patna West 30 PR State 14.1 271.4 271.40 Umesh Kumar 05.02.07 04.04.07 188.5 271.43 30.03.07
134(50), 137(500), 3.0 14.08 1.0
138(300),154(95),
155(305), 156(410),
157(352), 158(263),
159(365), 160
Arrah-Danapur
IRQP work in Km
121 to 128(500)
Work awarded
,Centre line Ranjit Kumar
by tender
62 Patna West 30 IRQP marking /signage State 7.5 560.80 Construction 4 Month
committee on
in km 118 to 128 Pvt Ltd
04.04.08.
and drain in
km.119 of NH-30
884.8
IRQP work in Km
128(500),129 to
133and 154 to Work awarded
157(400) and Umesh Kumar by tender
63 Patna West 30 IRQP State 8.9 566.43 4 Month
Centre line and Co. committee on
marking /signage 04.04.08.
in km 129 to 166
of NH-30
Km 146 to 149 &
161-166 Ms Krishna 0.52 7.82
64 Patna West 30 PR PR 7.82 145.44 103.31 14.12.06 13.03.07 48.69 103.31
Bihta-Danapur Prasad & Co 06.02.07 7.82
(030-BR-2006-
Restoration
Km 146 to 149
Ms Krishna 4.0
65 Patna West 30 (Only BM) State 4 63.4 63.40 08.02.07 22.02.07 31.72 63.4
Prasad & Co 4.0
Bitha-Danapur
Km.
161,162,163,164, Ms Shrishti 0.67 0.56 0.81 1.20 2.18 2.0
66 Patna West 30 Raising State 2.18 137.27 133.115 04.12.06 03.02.07 101.8 133.12 30.03.07
165, 166 in parts in Developers 0.56 0.81 1.20 2.18 2.0
Builtup area
Koilwar Bridge
67 Patna West 30 Bridge
030-BR-05-672
NHO
Km. 178.6 to 189.4 Suraj Nirman BM-9.8 6.0 Work in
68 Patna East 30 IRQP NHO 10.80 404.56 351.64 26.02.08 25.06.08 0 193.61
SDC-10.8
(Patna Bye Pass) Pvt. Ltd. 6.0 Progress.
5
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
IRQP & Paved
Shoulder from km
Paved Suraj Nirman Work awarded
69 Patna East 30 Shoulder
178.6 to 189.4 State 10.4 559.21 1
Pvt. Ltd. & started.
(Patna Bye pass) of
NH-30
Km 191 to 206, 221
Shrishti
& 222 18.0
70 Patna East 30 PR PR 18 252.89 215.35 Developers Pvt 14.10.06 31.01.07 252.04 252.04
9Job No-030-BR- 18.0
Ltd.
2006-1291)
Km.190,191(400),20
Suraj Nirman BM-20.4
71 Patna East 30 IRQP 7-230 State 20.4 565.29 639.27 24.03.08 23.12.08 SDC-20.40
Pvt. Ltd.
(Except221,222)
Km 207, 208(500),
209(500), 218(100).
220(100), 223(200),
Ms Shristi 3.3
72 Patna East 30 IRQP 225(100), 226(150), State 3.3 40.66 02.01.07 17.02.07 42.56
Developers 3.3
227(150), 229(400),
230(100)
Fatuha-Bakhtiyarpur
7.60
Km 1-11 M/s Suraj 11.0
73 Biharsharif 30A IRQP State 11 300.00 188.87 Nirman Pvt Ltd.
12.01.07 28.02.07 0.00 187.62 04.06.07
11.0
Fatuha-Daniyama
12 to 18
M/s Suraj 30.08.06
74 Biharsharif 30A IRQP 030A-BR-2005-673 NHO 7.00
Nirman Pvt Ltd.
31.07.05
31.03.07
Daniyama-Jaitipur
E/W- 7.15
GSB- 7.15
Km 19 to 26(150) WMM- 7.15
BM- 7.15
Danaiyawan-Jaitipur Ms Dayanand 05.09.07 7.5 7.5 7.5 7.5 7.5 14
75 Biharsharif 30A W&S NHO 7.15 818.53 698.89 06.12.06 224.22 719.50 SDC- 7.15
(Job No -030A-BR- Prasad Sinha 31.12.07 PCC- 0.50 7.5 7.5 7.5 7.5 7.5 Nos
06-716) CD nos.- 14
Marking- 7.15
Signage- 7.15
GSB- 8
WMM- 8
Km. 27-41 Surendra 18.08.07 BM- 15
76 Biharsharif 30A IRQP State 15 400.00 19.05.07 383.91 SDC- 15
Chandi-Harnut Prasad 30.12.07
Flank- E/W-14
Signage- 14
Km 42-70 Sri Surendra 04.05.07 26.50 26.50 26.50
77 Biharsharif 30A IRQP State 29 488.22674 05.01.07 273.58 475.21
Harnaut-Barh Prasad 15.11.07 26.50 26.50 26.50
Const. Of Bridge
030A-BR-2005-692 07.12.07
78 Biharsharif 30A Bridge PBFF 269.94 230.00 Jai Maa Bhawani 07.02.06 165.54 210.10 1 Nos
(Fathua- 31.03.07
Daniyama )
WMM-2.5
Raising Km 58, 59 PCC-550M PCC in Barh
0.20 0.55
79 Biharsharif 30A Raising & PCC in 68/69 & State 1.6 146.44 Surendra Prasad 05.02.08 04.06.08 64.85 BM-2 Km Bazar completed.
SDC-2 Km 0.50 50% work in Progress.
Box culvert in 52-53
Culvert-1
at Ch
2.961(11X13.5 mtr) Foundation (80Pile)
M/s Vikash Substructure 90% foundation
80 Biharsharif 30A Bridge 030A-BR-2007-733 NHO 523.20 458.08 01.11.07 31.10.08 188.53 Super structure
Construction completed.
(Fathua- approach.
Daniyama )
6
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Construction of
2x18.00m (eff span)
Level RCC Bridge Foundation
Substructure 2/16 90% foundation
81 Biharsharif 30A Bridge with footpath at NHO 193.00 192.07 Jai Maa Bhawani 18.03.08 19.09.08 192.07 Super structure pile completed.
chainage 22.315 of approach.
NH-30A.
030A-BR-2007-741
Construction of
2x18.00m (eff span)
High Level RCC Foundation
Substructure
82 Biharsharif 30A Bridge Bridge with footpath NHO 191.21 189.02 Umesh Prasad 01.04.08 30.09.08 189.02 Super structure
at chainage 4.818 of approach.
NH-30A
030A-BR-2007-743
Construction of
2x18m (eff span)
High Level RCC Shristi Foundation
Substructure
83 Biharsharif 30A Bridge Bridge with NHO 224.980 207.36 Developers Pvt 01.04.08 30.02.08 207.06 Super structure
footparth at chainage Ltd. approach.
8.149 of NH-30A
030A-BR-2007-750
Construction of
18.00m (eff span)
High Level RCC Foundation
Substructure
84 Biharsharif 30A Bridge Bridge footpath at NHO 133.230 114.84 Umesh Prasad 01.04.08 30.09.08 114.02 Super structure
Chainage 7.066 of approach.
Nh-30A
030A-BR-2007-752
Construction of
16.00m (eff span)
High Level RCC Foundation
Narayan Substructure
85 Biharsharif 30A Bridge Bridge footpath at NHO 144.900 124.30 01.04.08 30.09.08 124.30 Super structure
Brothers
Chainage 21.957 of approach.
NH-30A
030A-BR-2007-753
Km 48(300), 49, 56 Ms Krishna 18.03.07
86 Biharsharif 31 IRQP State 2.30 79.23779 19.12.06 179.11 179.11
Rajuli-Nawada Prasad & co 26.01.07
7
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
(1) Earlier award
1 tender cancelled.
E/M forfited.
(2) Tender for 50-
Km.50-55, 57, 584,
1 55, 57, 68 on
87 Biharsharif 31 IRQP 128-130(Job No. NHO 387.39
1 10.04.08
031-BR-07-748) (3) F/B for 128-
130 received in
CE office on
08.04.08.
88 Biharsharif 31 IRQP Km.56
Km. 59-62, Saryoo Prasad 10.0 10.0
89 Biharsharif 31 IRQP State 10.00 277.81 277.81 12.03.07 15.05.07 91.05 273.88
99,100,103 to 106 Sinha 10.0 10.0
63 to 72 Ms Krishna 22.12.06 E/W-10
90 Biharsharif 31 PR PR 10.00 130 23.10.06 138.45
SDC-10
031-BR-2006-1294 Prasad & co 20.01.07
Km.73
Saryoo Prasad 27.01.08
91 Biharsharif 31 IRQP 031-BR-2006-712 NHO 706.37 28.07.06 87.70
Sinha 31.01.07
Nawada-Biharsharif
Tender cancelled
due to high
premium
92 Biharsharif 31 IRQP Km.74, 76-78 State 4.00 143.37 retender on
10.04.08.F/B
sent 5E
22.04.08
75 Saryoo Prasad 27.01.08
93 Biharsharif 31 IRQP NHO 706.37 28.07.06 87.70
Nawada-Biharsharif Sinha 31.01.07
79 to 96
Saryoo Prasad 27.01.08
94 Biharsharif 31 IRQP 031-BR-2006-712 NHO 706.37 28.07.06 87.70
Sinha 31.01.07
Nawada-Biharsharif
Km.97-98, 101, 102 & Dayanand Pd
95 Biharsharif 31 IRQP State 6.00 403.11 367.48 01.04.08 30.06.08 0/2.0
107, 110 Sinha
BM- 17
SDC- 17
Km 111-127 Ms Dayanand Flank- 17 17.0 17.0
96 Biharsharif 31 IRQP State 17 570.00 594.51 12.01.07 11.10.07 319.42 583.89 Marking- 17
Nawada-Biharsharif Prasad Sinha 17.0 17.0
Signage- 17
Km 131 to 141 Ms Promod
97 Biharsharif 31 PR PR 11.00 150.88 140.60 172.91
031-BR-2006-1295 Narayan Sinha
Km 142 to 155
Biharsharif-
Sri Surendra 23.10.06
98 Biharsharif 31 IRQP Bakhtiarpur NHO 17 403.36141 13.15 428.04 441.19
Prasad 22.12.06
(Job No031-BR-
2006-. 722)
8
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Km 154.6 to 158
Bakhtiyarpur-
Ms Shristi 12.12.07 0.23
99 Patna East 31 IRQP Athanlgola NHO 3.55 91.27773 13.12.06 98.43 98.43 23.02.07
Developers 15.02.07
(Job No031-BR-
2006-. 719)
Km 161 to 168
Ms Suraj Nirman 31.01.07 0.98 8.0
100 Patna East 31 PR Athamgola-Barh PR 8 106.49 97.92744 15.12.06 96.02 96.02 23.02.07
pvt. Ltd 23.02.07 8.0
(Job No. 1296)
Km 169 to 196
101 Patna East 31 PR Athamgola-Barh
169-185
Km 169(150),
170(200),
171(100).174(150),
177(150), 178(50),
Ms Suraj Nirman Dec' 06
102 Patna East 31 IRQP 179(150), 183(300), State 2.05 25.03494 23.9100 26.88
pvt. Ltd April' 06
191(200), 194(300),
195(300)
Bakhtiyarpur-
Mokama
197 to 207 BM-11
Suraj Nirman Pvt. SDC-11 11.0 11.0
103 Patna East 31 IRQP 031-BR-2006-711 NHO 11.00 320.35 292.74 Ltd.
15.01.07 14.02.07 183.38 310.44 7.31
Marking-11 11.0 11.0
(Mokamah Bypass) Signage-11
Km 208 to 217
Mokama-Barauni Devendra & 14.03.07 8.7
104 Patna East 31 PR PR 8.7 94.99 15.11.06 98.14000 98.14
(Job No. 031- Devendra 31.01.07 8.7
BR-2006-1293)
Devendra
Devendra
Km.217, 218P 28.02.07 1.6
Patna East
&
105 31 IRQP State 1.60 43.24 15.01.07 43.24 52.57
Barauni 31.01.07 1.6
Km 218 to 226
E/W-9
Barauni-Begusarai 30.12.06
106 Khagaria 31 PR PR 9 105.94795 Exel Venture 83.44 103.35 SDC-9
(031-BR-2006- 30.05.07
1287)
E/W-3
Km 227-229 M/s Exel 12.01.07 3.00 3.00
107 Khagaria 31 IRQP State 3 160.98 118.00 164.21 0.42 BM-3
Begusarai Venture 31.03.07 SDC-3 3.00 3.00
Km.230-249
108 Khagaria 31 PR PR 20.00 295.07
031-BR-2007-1310
109 Khagaria 31 PR Km.250-256 State 7.00 96.25
9
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
BM- 17
Km 257 to 273 M/s Exel SDC- 17 17.00 17.00
110 Khagaria 31 IRQP State 17.00 510.00 518.16 08.01.07 31.03.07 517.89 11.23 Flank E/W- 17
Begusarai-Khagaria- Venture 17.00 17.00
Marking- 17
274 to 278
111 Khagaria 31 PR (Khagaria- State 5.00 94.33 17.19
Mansi )
WBM- 7
BUSG- 14
Km 279-301 BM- 11 Work
M/s CK 31.03.07 6.58 23.00 5.00 14.00 11.00 11.00
112 Khagaria 31 IRQP Maheshkhunt- State 13 496.00 487.19 08.01.07 157.75 435.94 SDC- 14.5 Completed.
Construction 15.01.08 04.05.07 Flank- 23 23.00 5.00 14.60 14.50 11.00
Pasaraha Except Marking
Marking- 23
KMP-23
302 to 318
M/s C.K 30.06.06
113 Khagaria 31 IRQP (Pasraha Zone) NHO 17 349 02.06.06 311 351
Construction 31.12.06
031-BR-2006-699
319 to 321
Tender on
114 Khagaria 31 PR (Narayanpur- State 3.00 94.33
24.04.08
Bihapur )
WBM- 10
BUSG- 10
Km 322 to 331 M/s CK 31.03.07 BM- 10 10.0 10.0 10.0 10.0
115 Khagaria 31 IRQP State 10.00 300.00 335.76 12.01.07 57.24 333.43 6.96 SDC- 10
Khagaria-Naugachia Construction 30.11.07 10.0 10.0 10.0 10.0
Flank E/W- 10
Marking- 10
Km 332 to 357 E/W-25
Ms Higway & 30.05.07 16.77 BM-25 2.0 25.00 8.0
116 Purnea 31 IRQP Kharik-Kurshala NHO 26 930.16 851.99 15.01.07 26.56 642.83 SDC-25
Hydel 06.07.07 4.0 25.00 10.0
(031-BR2006-720) Marking-25
E/W-15
30.05.07 BUSG-6
358-372 Ms M. K. Gupta
117 Purnea 31 IRQP State 15 777.63 15.01.07 28.02.07 61.45 702.76 11.64 BM-15
Kurshaila-Korha & Co. SDC-15
15.06.07
Marking-15
GSB-4
373 to 377, 381 to E/W-13.50
384 & 394 to WBM-4
Bihar Rajaya Pul
118 Purnea 31 IRQP 398(500) State 13.50 547.27 260.00 BM-13.50
Nirman Nigam. SDC-13.50
Kursel-Purnea
Marking-13.50
Section)
Signage-13.50
E/W-12
IRQP work in Km. 05.07.07 GSB-12
WMM-12
119 Purnea 31 IRQP 378-380 & 385-393 State 12 508.00 483.21 M/s Singh Const. 06.01.07 30.04.07 53.36 437.69 BM-12
Kursela-Purnea 30.05.07 SDC-12
Marking-12
IRQP work in Km. M/s Singh
120 Purnea 31 IRQP State 2 95.02519 15.01.07 76.36 90.94 90.94
399-400 Purnea Construction
Km 401 to 410
Baba 02.12.06
121 Purnea 31 IRQP Purnea bypass NHO 10 415.52062 2.57 408.1
Construction 01.06.07
(031-BR-2006-718)
Km.1-25 except Km
1(617), 2, 8, 22
M/s Suraj 24.02.06
122 Muz-II 77 IRQP 077-BR-05-682 NHO 21.4 475.0 Nirman Pvt Ltd. 23.10.06
Hajipur-Sarai-
Bhagawanpur
10
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Km 1(617), 2, 8, 22, Shivani E/W-13
15.06.07
123 Muz-II 77 IRQP 26-35 State 13.6 350 319.44 Construction 11.12.07 68.95 235.74 4.80 BM-13.6
15.12.07 SDC-13.6
(Hajipur-Turki) Pvt. Ltd.
E/W-13.2
Km. 37-48.2 16.05.07 6 13.2 7
124 Muz-II 77 IRQP State 13.2 350.00 300.37 Shyam Bihari 17.01.07 59.98 246.00 5.90 BM-13.2
Hajipur-Muzaffarpur 30.12.07 SDC- 13.2 6 13.2 7
Work Rescind
Km. 1-8 M/s R.S Pandey 0 0 03 0 and transferred
125 Muz-II 77 IRQP State 8 300.00 222.28 22.01.07 31.01.08 40.08 67.77 2.20
Muz-Sitamarhi & Co. 2 .30 13.20 6.90 to Bihar Raj Pul
Nirman Nigam.
Km 9 to 24
Work Rescind
(Job No 077-BR-06- E/W-16
M/s R.S Pandey 09.05.07 0 0 6 0 and transferred
126 Muz-II 77 IRQP 698) NHO 16 441.66 399.49 10.11.06 85.01 119.54 6.00 WMM-14
& Co. 30.03.08 PMC-16 2 0.3 07 3.40 to Bihar Raj Pul
(Muzaffarpur-
Nirman Nigam.
Sitamarhi)
(Km 9-24 old) Work Rescind
Muzaffarpur- M/s R.S Pandey 15.06.07 and transferred
127 Muz-II 77 IRQP State 16 239.00 239.00 20.04.07 0.00 115.00 BM- 16
Kataunjha & Co. 31.01.08 to Bihar Raj Pul
(Additional Work) Nirman Nigam.
128 Muz-II 77 IRQP Km. 25-27 State
Muzaffarpur-
Calmity
Restoratio Sitamarhi Section Ram Binod
129 Muz-II 77 n
relief 4 42.00 52.96
Km. 28 Singh
fund
Katunjha-Runni
29 & 30
Ram Binod 02.06.06
130 Muz-II 77 IRQP 077-BR-2006-709 NHO 2.00 52.58
Singh 01.12.06
.
Muz.-Sitamarchi
31 to 50
05.01.06
131 Muz-II 77 IRQP 077-BR-2005-686 NHO 441.80466 M/s Prachi Cont.
04.07.06
70.00
Muzaffarpur Sitamarhi
Km 51 to 67 Ashok Kr Singh
19.12.06
132 Muz-II 77 IRQP (Muzaffarpur- State 17 297.15509 & Madhup Kr 206.07 293.64
18.05.07
Sitamarhi) Singh
Km 68 to 78
(77--BR-08-760)
133 Sitamarhi 77 IRQP NHO 11 529.43 Work Awarded.
(Sitamarhi-
Sonbarsa)
Km 79 to 90
(77--BR-08-761)
134 Sitamarhi 77 IRQP NHO 11.45 528.65 Work Awarded.
(Sitamarhi-
Sonbarsa)
SR of
In Km 16 Ram Binod
135 Muz-II 77 S.P State 50.00 48.68 20.04.07 20.07.07 48.68
Maksudpur Bridge Singh
Bridge g
Bhanaspati Bridge 30.04.08- Comp- Piling work
in Km. 28 Foundation 30.05.08- Comp- Substructure.
Substructure
136 Muz-II 77 Bridge 077-BR-07-729 NHO 499.84 437.65 Ram Binod Singh. 03.04.07 30.05.08 88.00 30.05.08- Comp- Decking
Deck slab
Muzaffarpur- Approach
Progress
Sitamarhi Plle foundation of one, Abutment and Jhama Pier completed.
Km 38 Target
Job No. 077-BR-05- 04.10.06 Complete GSB & open to traffic by Approach slab Road in
137 Muz-II 77 Bridge NHO 184.03 163.87 Shyam Bihari 05.01.06 57.65 105.67 0.82 3 Span Bridge
677 15.02.08 Progress.
(Chandarhatti)
11
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Takaur in Km. 39
077-BR-05-676 23.02.07
138 Muz-II 77 Bridge NHO 287.96 250.98 M/s Prachi Cont. 24.02.06
31.03.08
179.12 248.11
Muzaffarpur-
Sitamarhi
Km 83 New
139 Muz-II 77 IRQP (Km 28 old) State 1 16.38 Raj Construction
Bhanaspati
Calmity
Raising work Enatulla Khan &
140 Muz-II 77 Raising relief 0.375 50.00
Sitamarhi Town Ansur Rahman
fund
Km 19 Khanwaghat Foundation
77-BR-05-684/ 05.01.06 Substructure
141 Muz-II 77 Bridge NHO 135.43211 Sri Prakash
04.10.06
371.00 Deck slab
08.07.05
Muzaffarpur-Sitamarhi Approach
Km 22
Job No. 077-BR-05-
679 M/s Narayani 05.01.06
142 Muz-II 77 Bridge NHO 166.96733 220.00
(Pitaujhia Construciton July' 07
Muzaffarpur-
Sitamarhi Section)
HL Bridge Bagmati
River at Basatpur Agreement to be
143 Muz-II 77 Bridge NHO 731.02 645.00 5.02.08 04.08.08
on Km 30 of NH-77 executed.
( 077-BR-2007-731)
Km 28 Runni
144 Muz-II 77 Bridge 77-BR-05-683 NHO 399.39173 Ram Binod Singh 45.00
Muzaffarpur-Sitamarhi
3.98 BM -4.50
Km 1-11 M/s Devendra & SDC- 10.6 10.0 4.5 10.6
145 Lakhisarai 80 IRQP State 10.6 350 198.96 23.11.06 22.05.07 138.55 198.54 +0.98 Flank- 10.6
(Mokama-Barahia) Devendra 10.6 4.5 10.6
08.05.07 Marking- 10.6
BM- 2.51
02.05.07 3.26 SDC- 5.37
Km 12-17 PCC- 0.6 3.0 2.51 5.37 0.64
146 Lakhisarai 80 IRQP State 4.77 160.00 163.08 Exel Venture 08.01.07 26.01.07 87.70 139.20 +0.81 Flank- 6
Barhiya-Pratappur 5.0 2.51 5.37 0.64
30.05.07 08.05.07 Marking-6
In Km 18-28 3.02 E/W- 11
Ms Munger 22.05.07 5.0 11.0
147 Lakhisarai 80 IRQP Pratapur- State 11 175.00 150.81 23.11.06 40.49 130.64 0.75 SDC 11
Construction 15.11.07 5.0 11.0
Surajgaraha 08.06.07
In Km 29-40
Ms Munger 23.11.06 2.40+0.81 SDC-12 10.0 12.0
148 Lakhisarai 80 IRQP Pratapur- State 12 162.44 112.11 147.38 10.04.07 E/W-12
Construction 22.05.07 10.0 12.0
Surajgaraha
WBM/GSB/BSG 0.47
29.04.07 BM 4
4.89+0.69 0.47 0.47 0.47 4.0 3.0
149 Lakhisarai 80 IRQP Km 41-44 State 4 170.00 138.60 Niranjan Sharma 30.12.06 25.12.07 32.92 84.61 SDC 4 2.00
08.06.07 Flank 4 0.475 0.475 0.53 4.0 4.0
15.03.08 2.00
Marking 4
Km 45-54 2.97 SDC-10
Ms Munger 9.0
150 Lakhisarai 80 IRQP Suryagarha- State 10 180.00 162.81 30.12.06 29.04.07 13.15 156.00 +0.81 Flank-10
Construction Marking-10 9.0
Safiasarai 10.04.07
12
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-2.4
55 to 73 WBM-2.4
080-BR-2006-707 Ms Highway & 12.10.07 10.61+2.65 BM-19 2.0 2.4 2.4 18.0 5.5
151 Lakhisarai 80 IRQP NHO 18.57 579.98 530.66 13.10.06 161.47 323.53
Medni Chowk Safia Hydel 31.01.08 08.06.07 SDC-19 2.0 2.4 2.4 19.0 5.5
Flank-19
Sarai
Marking-19
Km 74-93 SDC-20
5.97+1.49 Flank-20 20.0 20.0
152 Lakhisarai 80 IRQP Suryagarha- State 20 310.00 298.58 Niranjan Sharma 30.12.06 29.04.07 142.55 274.44 Marking-20
10.04.07 20.0 20.0
Safiasarai Signage-20
WBM- 1.75
BUSG- 4.80
BM- 18.25
SDC- 18.25
94-113 26.03 1.75 3.25 2.5
153 Bhagalpur 80 IRQP State 20 700.00 743.77 Ramakant Singh 08.03.08 30.06.08 110.00 149.58 Drain- 2.10 3 Nos
Ghorghat-Bhagalpur 05.07.07 CD work- 7 no 1.75 3.25 2.5
Flank- 20
Marking- 20
BM- 13.6
114-128 (Except SDD- 13.60
14.12.07 13.34 2.0 10.0 2.5
154 Bhagalpur 80 IRQP Km.123,124) State 13.6 500.00 444.80 Niranjan Sharma 15.01.07 93.76 230.87 Drain- 2.0
31.12.07 05.07.07 Flank- 15 2.0 10.0 2.0
Ghorghat-Bhagalpur
Marking- 15
124 Sri Siv Prakash GSB- 1 0.0
155 Bhagalpur 80 PCC State 1 135.00 133.94 15.01.07 87.73 130.00 PCC- 1
Nath Nagar Sharma 1.0
WBM- 0.30
BUSG-0.30
129-150 4.29 BM- 2.70 0.3 0.3 0.5 3.5
156 Bhagalpur 80 PR State 22 440.00 254.69 Ramakant Singh 08.03.08 30.06.08 37.65 SDC- 22
Bhagalpur-Kahalgan 05.07.07 0.5 0.3 0.5 3.5
Flank- 22
Marking- 22
E/W-2
IRQP work in Km. GSB-1
WBM-1
151, 152 1.53 01
157 Bhagalpur 80 IRQP State 2.00 80.00 76.27 Ramakant Singh 08.03.08 30.06.08 10.00 BM-2
Bhagalpur- 05.07.07 SDC-2 01
Mirzachouki Flank-2
Marking-2
153-166
W&S
158 Bhagalpur 80 (Bhagalpur-Pirpaiti NHO 14.00 832.47 Tender invited.
Section)
167-100
(Bhagalpur-Pirpaiti
W&S
159 Bhagalpur 80 Section) NHO 14.00 1272.92 Tender invited.
(Job No. 080-BR-08-
768)
E/W-5
181-185 GSB-5
080-BR-2005-689 Calcutta WMM-5
W&S
13.43 5.0 5.0 5.0 5.0
160 Bhagalpur 80 (Pirpaiti- PBFF 5.00 417.61 380.39 Industrial Suplly 23.01.06 22.12.06 217.00 403.47 SDC=5 7 Nos
05.07.07 CD work- 7 no 5.0 5.0 5.0 5.0
Mirzachowki Corporation
Marking- 5
Section)
KMP-5
13
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Fly Ash- 3
E/W- 5
Fly
Calcutta GSB- 5 Ash
W&S
186 to 190 04.12.07 13.94 5.0 5.0 5.0 Work in
161 Bhagalpur 80 NHO 5.00 462.57 413.30 Industrial Suplly 05.01.07 324.10 WMM- 5 3
080-BR-2006-702 16.05.07 SDC- 5 5.0 5.0 5.0 Progress.
Corporation 3
CD work- 6
Marking- 5
151- Culvert
Bridge in Km 151, 15.07.07
162 Bhagalpur 80 Bridge NHO 86.76 Arun Kr Verma 15.01.07 77.00 152- App. Road
153, 154 15.12.07 153- App. Road
Work in
31.03.04 Foundation-100%
Gerua in Km. 127 Progress.
163 Bhagalpur 80 Bridge NHO 382.00 308.28 NPCC 28.02.03 28.02.08 237.55 270.29 5.78 Super Str
080-BR-2002-611 31.03.08 Approach RE sanctioned
421.26 lacs.
Construction of
Retaining wall in the
164 Bhagalpur 80 approach road of State 100.67 103.25 27.02.08 26.05.08 49.63
Gerua Bridge in Km
155 to NH-80
Estimate
165 Bhagalpur 80 Bridge In km 94 (Ghorghat) submitted to
Ministry.
Construction of
4x30m (eff span)
High Level RCC Tender received
166 Bhagalpur 80 Bridge Bridge PSC Girder NHO 1101.06 on 04.03.08 T/B
across river Vena in awaited.
Km 155 to NH-80
080-BR-2007-749
Construction of
4x300m (eff span)
High Level RCC Tender received
167 Bhagalpur 81 Bridge Bridge PSC Gorder NHO 1118.59 on 04.03.08 T/B
across Champa Nala awaited.
in Km 123 of NH-80
080-BR-2007-754
E/W-10
Abhuday GSB-10
Km 1 to 10 Housing & 30.06.07 WBM-10
168 Purnea 81 IRQP State 10 582.73 602.28 15.01.07 150.71 552.87 9.03 BM-10
Korha-Katihar Consruction Pvt. 30.11.07
SDC-10
Ltd
Marking-10
E/W-10
BM-10
Km. 10(P)-20(P) 15.07.07
169 Purnea 81 IRQP State 10 300.00 407.16 M.K Gupta 15.01.07 274.27 5.45 SDC-10
Korha-Katihar 30.12.07 Marking-10
Signage
20P to 29 P 6.0
170 Purnea 81 IRQP 9 km Road Division.
of Katihar Town) 6.0
km 29P-39 BUSG - 6
(Katihar-Pranpur) BM -3.5 3.00 6.00 2.00 3.00
171 Purnea 81 IRQP State 10 350.00 208.67 BRPNN 45.00 SDC 3.50
Korha-Katihar- 3.00 6.00 2.00 3.00
PCC -3.50
Pranpur
14
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
HL Bdg. In km 33rd
(3X124 mtr) One tender
172 Purnea 81 Bridge (Katihar-Pranpur) NHO 272.14 received on
Korha-Katihar- 28.03.08.
Pranpur
HL Bdg. In km 36th
(2X24 mtr) One tender
173 Purnea 81 Bridge (Katihar-Pranpur) NHO 212.53 5.52 received on
Korha-Katihar- 28.03.08.
Pranpur
one tender
received on
01.03.08 but
174 Biharsharif II 82 PR Km.1-17 PR 17 491.00 failed on T/B
insicted to call
tender with
relazation.
Tender on
175 Biharsharif II 82 PR Km.18-28 PR 17 317.17
11.03.08
Work awarded
M/s Om
176 Biharsharif II 82 PR Km.36-51 PR 17 216.00 234.43 10.03.08 10.06.08 on
Construction
22.02.08(Agree
Work awarded
M/s Om on
177 Biharsharif II 82 PR Km 52-68 PR 17 216.57 236.51 10.03.08 10.06.08
Construction 22.02.08(Agree
ment to execute)
SDC- 26.5
Km 69-94 M/s Promod Flank E/W- 26.5 26.50 26.5
178 Biharsharif II 82 IRQP State 26.5 375.00 359.01 16.01.07 15.07.07 148.18 213.40 Marking- 26.5
Rajgir-Biharsharif Narayan Sinha 26.50 26.5
Signage- 26.5
Km.95
179 Biharsharif II 82 IRQP Road Division.
Biharsharif Town
E/W - 3
Biharsharif Bazar G.S.B -1.25
0 0.6 0.6 0.6 0.6 0.6 1.75 1.0 Work almost
180 Biharsharif II 82 IRQP portion 96-98 State 3.00 280.00 247.88 13.02.08 12.08 8.00 81.56 229.98 WBM-3
SDC-1.25 3 1.25 1.25 1.25 0.6 0.6 1.75 1.0 completed.
Biharsharif-town
CD work-1 no.
(99-108)
Ms Promod 09.04.07 0.6 0.6 0.6 0.6 1.75
181 Biharsharif II 82 IRQP Biharsharif- State 10.00 128.0 120.76 09.01.07 97.93 97.93 1 Nos
Narayan Sinha 15.03.07 0.6 0.6 0.6 0.6 1.75
Barbhigha
BM- 13
Km 109-121 15.07.07 1.63 SDC- 13 7.0 12.5 10.0 Work in
182 Biharsharif II 82 IRQP State 13 400.00 325.14 Arjun Engicons 16.01.07 76.36 232.68 Flank E/W- 13
Biharsharif-Barbigha 15.02.08 06.07.07 7.0 12.5 12.0 progress
Signage- 13
Km 122-133 Not included in
183 Biharsharif II 82 W&S 12
Barbigha- Mokama A/P 08-09
(133 to 143)
Suraj Nirman
184 Biharsharif II 82 IRQP 082-BR-2002- 643 NHO 11.00 428 Pvt Ltd.
24.05.07 31.01.06 204.777
(Sarmera-Mokama )
Estimate not
Km 144-147
185 Biharsharif II 82 W&S sanction by
Barbigha- Mokama
Ministry.
15
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Replacement of Old
& Damage culverts.
30.03.07
186 Biharsharif II 82 C/D In Km 25 & 29 State 55.00 42.00 Jai Maa Bhawani 30.12.06 2.57 32.05 2.56 1x5x5 Box Culvert 1 Nos
15.06.07
Gaya-Hissua
Section.
Const of Box culvert
in Km 107, 109(2),
187 Biharsharif II 82 CRF CRF 8 161.00 156.28 Arbind Kunar 19.02.08 18.05.08
113, 116(4) of NH-
82
Raigir Junction
Improvement in Km Dayanand Pd 06.02.08 12.02.08/
188 Biharsharif II 82 CRF CRF 1 60.00 60.00
73, 74 of NH- Sinha 16.02.08 22.02.08
82(CRF)
No tender
Km. 0-8.4
189 Gaya 83 IRQP NHO 8.4 222.34 received on
(083-BR-07-738)
27.03.08
190 Gaya 83 W&S Km.8.4-12.5 NHO 4.1 110.62
BUSG-2 0 0
191 Gaya 83 FDR Km.12.8 to 14.8 FDR 3.015 76.90 42 M/s Glaxy FDR PC-2 2 1
Not included in
192 Gaya 83 IRQP Km 14.8 to 21.6 FDR 6.8
A/P 08-09
Morhar in Km. 19 Bihar Rajaya Pul
193 Gaya 83 Bridge PBFF 258.43 30.04.07 189 189.00
083-BR-2002-628 Nirman Nigam.
WBM- 6.4
Km 21.6 to 29 BUSG- 6.4
M/s Roy 13.05.07 4.257 0.0 6.34 6.34 6.34
194 Gaya 83 IRQP except 28 State 6.40 300.00 212.83 14.01.07 36.40 169.92 PC- 6.4
Construction 15.12.07 09.05.07 Flank E/w-6.4 0.0 6.34 6.34 6.34
Punpun-Masaurhi
Flank E/W-
Not sanctioned
Km 28,30
195 Gaya 83 IRQP by Ministry in
Punpun-Masaurhi
07-08.
31-35, 44-48
Mosauri Bazar, BM-10
Ms Krishna 27.04.07 3.45 SDC- 10 0.0 9.5 9.5
196 Gaya 83 IRQP Jehanabad Bazar, NHO 10 383.90 344.58 28.12.06 50.21 309.56 Flank E/W-10
Prasad & Co 31.11.07 21.03.07 0.0 9.5 9.5
Gaya Town Marking-10
(083-BR-2006-723)
GSB-
WMM
197 Gaya 83 IRQP Km. 36-43 NHO 8 325.53 265.77 A.K Builders 27.03.08 26.09.08 Primer Work started.
BM-
SDC-8
E/W-3.3
WBM-3.0
1.08 3.0 3.0 3.0 3.0 3.0
198 Gaya 83 CRF Km 49-51 3 107.70 107.72 23.12.06 31.01.07 107.77 BUSG-3.0
22.03.07 BM-3 3.0 3.0 3.0 3.0 3.0
SDBC-3
16
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
In Km 52(300),
53(300), 54, 55,
56(600), 59(800),
62(900), 63, BM- 20
64(400), 65(300), SDC-20 S/C issued. Final
Kumar AS 22.05.07 9.867 3.0 7.0 7.0
199 Gaya 83 IRQP 66(400), 67- State 20 550.00 493.33 31.03.08 168.64 164.21 Flank E/W-20 measurment on
Construction 31.12.07 09.05.07 Marking- 20 3.0 7.0 7.0
70(300),72(300), 09.04.08
74(300), 76(300),
77(400), 78(400)&
91&94-99
Jehanabad-Gaya
Between 51 to 92 in Work order
different balance issued.
200 Gaya 83 IRQP State 27 500.00 612.52 A.K Builders 27.03.08 26.09.08
parts. Agreement to be
Jehanabad-Gaya executed.
Work order
issued .
201 Gaya 83 IRQP Km.92-93 NHO 2 137.82 130.82 A.K Builders 05.04.08
Agreement to be
executed
BM-7
Km. 100-106 Kumar AS 13.03.07 2.0 7.0 7.0
202 Gaya 83 IRQP State 7 200.00 180.31 14.01.07 14.52 176.60 1.80 SDC-7
Gaya town Construction 15.11.07 Flank-7 2.0 7.0 7.0
SC-19
Flank E/W-19
Km 107 to 125 Shristi 15.05.07 19.0 19.0 19.0
203 Gaya 83 PR State 19 170.00 138.18 16.03.07 131.40 Marking-19
Gaya-Dobhi Developers 15.12.07 Signage-19 19.0 19.0 19.0
BUSG-19
2-10 BM-9.0 S/C rescind and
27.03.07 4.09 9.0 6.33
204 Patna West 84 IRQP Arrah-Bibiganj NHO 9 222.05 204.32 Achaldeo Singh 28.11.06 44.58 158.77 SDC-9.0 blacklist Work
16.04.07 Flank-9.0 9.0 6.33
(084-BR-2006-725) Comppleted.
BM-6 Work to be
205 Patna West 84 IRQP Km.11-16 State 6 131.29 138.33 Mahindra Singh 10.04.08 SDC-6 stareted.
Km 17 - 21, 31, 32
1.14 SDC-6.70 7.0
206 Patna West 84 PR Arrah-Bihia-Bhojpur- State 7 80.00 77.33 Surendra Singh 25.01.07 24.03.07 52.96 77.33 CD work-1 no.
16.04.07 7.0
Buxar
Km 22-36
Ms Shristi 16.12.06 1.56 3.0 11.5
207 Patna West 84 IRQP (15 Km) State 11.50 155.394 155.4 16.12.06 13.82 155.07 20.02.07
SDC-11.5
Developers 15.04.07 3.0 11.5
Arrah-Buxar
37 to 50 GSB- 11.0
WMM- 11.0
084-BR-05-691 18.09.07 10.0 4.0 1.5 1.0
208 Patna West 84 IRQP State 14.00 686.17 589.17 Surendra Singh 19.03.07 211.23 2.95 BM- 14.0
Barhampur- 20.03.08 SDC- 14.0 10.0 4.0 1.5 1.0
Dumraon Flank- 14.0
51 to 60 056 10.0
209 Patna West 84 IRQP PR 10 123.69 111.58 Krishna Febicons 09.12.06 08.12.06 94.78 111.58 SDC-9
084-BR-2006-1289 30.03.07 10.0
Km 61-71
0.65 BM-2.0 2.0 11.0
210 Patna West 84 IRQP Arrah-Bihia-Bhojpur- State 11 140.00 129.56 Krishna Febicons 15.01.07 14.03.07 3.96 129.50 SDC-11.0
30.03.07 2.0 11.0
Buxar
Km 72-73
211 Patna West 84 Condition Fair
Buxar
Km 74
212 Patna West 84 Bridge Condition Fair
Buxar Bridge
17
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Km. 51, 54, 56, 57 &
Culverts
60 M/s Dayanand Pd. 05.03.05
213 Patna West 84
084-BR-2004-664
NHO 134.38 Sinha & Co. 04.09.06
176.08
(Dumraon-Buxar )
Km 1 to 10 E/W-10
M/s Saran 23.05.07 2.90 BM-10 0.0 0.92 9.5 8.0 4.0
214 Gopalganj 85 IRQP 085-BR-2006-721 NHO 10 323.45 291.54 69.32 263.49 SDC-10
Construction 31.12.07 21.05.07 0.0 0.92 9.5 8.0 4.0
Chapra-Kopa CD work-5
11, 12, 13(500),
15(300), 17(300),
Calmity
20(500), 21(350), M/s Saran 29.11.06
215 Gopalganj 85 IRQP relief 5.05 66.545
23(300), 24(500), 26 Construction 28.02.07
fund
(300)
Kopa-Ekma
Tender on
16.01.08 failed.
12.5 to 35
216 Gopalganj 85 IRQP State 23 550.39 In T/B retender
to be done
06/05/08.
Km.36-60
F/B ub tender
217 Gopalganj 85 PR (Rasalpur-Siwan State 25 476.55
Committee.
Section)
Km. 61 to 92 except
Km.(65, 68, 70, 72)
218 Gopalganj 85 IRQP PR 28.0 244.15986 M/s Prasad Cons. 28.11.05 63.91
085-BR-05-1259
(Siwan-Gopalganj )
M/s North Bihar
In Km 65, 68, 70, 0.52 4.0 4.0
219 Gopalganj 85 PR State 4 55.00 53.61 Const 12.01.07 53.61 53.61 12.03.07
72 Siwan-Mirganj 4.0 4.0
Corporation
Km.75(500),76(500)
220 Gopalganj 85 SR 1.472 45.56 25.04.08 24.07.08 S.E level tender.
,.77(442) Mirganj
Foundation
20.07.06 Substructure
Km 78 of NH 85
221 Gopalganj 85 Bridge NHO 52.68 48.14 Ms Prasad Cons. 21.03.07 31.03.07 19.85 44.20 Deck slab-1
085-BR-2006-695 Approach
15.06.07
Completed 07-08
Widening to 4 lace
Km 0 to 3.25 M/s Dayanand GSB-
222 Patna West 98 4 laning NHO 3 666.36 540.55 19.03.08 18.12.08 WMM
Work started.
Anisabad-Bhusaula Pd & Co.
SDC-
Work awarded
Km 3.25 to 7 Ms Umesh
223 Patna West 98 W&S NHO 4 by tender
Anisabad-Bhusaula Kumar & Co.
committee.
Restoration
Km 8-17 Tender
224 Patna West 98 (Bhusaula- State 10.2 973.00 committee under
Naubatpur) negotiation.
27.06.07
Km 18-35 Mother India 1.18 BM-13.33 14.0 14.0 13.33 13.33
225 Patna West 98 IRQP State 13.33 240.00 236.35 28.02.07 15.12.07 2.71 208.84 SDC-13.33
Naubatpur-Kanpa Construction Ltd 30.03.07 0.0 0.0 13.33 13.33
15.03.08
E/W -0.27
GSB- 0.27
Junction
Km 35 Mother India 08.06.07 WMM- 0.27 0.27 0.27 0.27 0 0.24 11
226 Patna West 98 State 1 150.00 172.77 09.02.07 36.33 159.44 BUSG BM- 0.27
Kanpa Construction Ltd 15.12.08 0.27 0.27 0.27 0.27 0.24 11
SDC- 0.27
PCC- 2x0.12
18
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Calmity
Km 36 to 52 Mother India 17.0 17.0
227 Patna West 98 IRQP relief 17 150.37456 150.37
Kanpa-Mahabalipur Construction Ltd 17.0 17.0
fund
GSB - 7.5
53 to 64 WMM-12
PC-12
098-BR-05-669 Ms Dayanand 22.02.07
228 Aurangabad 98 IRQP NHO 12.00 580.81 464.14 23.02.06 371.00 475.00 CD work- 14
(Mahabalipur-Arwal- Pd. Sinha & Co 10.06.07 FlankE/W-12
Bidrabad ) Marking-07
Signage-12
Km 65-89 BUSG- 0.85
Ms Ram Briksh 17.07.07 BM- 18
229 Aurangabad 98 IRQP Daudnagar- State 25 460.00 475.38 15.01.07 219.19 475.00 SDC- 25
Singh 30.11.07
Aurangabad Flank-25
90 to 127.520
BM-6
098-BR-05-671 Mr 02.06.07 22.0 3.0 27.0
230 Aurangabad 98 IRQP NHO 38.52 490.72 499.00 02.12.06 45.00 286.00 Nil SDC- 38.52
(Arwal Aurangabad R.B Singh Flank- 38.5 22.00 3.0 27.0
Section)
E/W-24
Km 130 to 154 GSB-24
M/s AK Builders WMM-24 24.0 24.0 23.0 19.0 3.50 7
231 Aurangabad 98 IRQP Aurangabad - State 24 600.00 1061.23 15.01.07 15.04.05 287.81 1015.00 SDC-24
& Transport 24.0 24.0 24.0 21.0 3.50 7
Hariharganj Drain-3.50
CD work- 4 nos
Km 11 RE being
098-BR-2006-700 Bihar Rajaya Pul prepared by
232 Aurangabad 98 Bridge NHO 353.47
Nirman Nigam.
Aurangabad- Bihar Raj Pul
Hariharganj Nirman Nigam.
Km 0-14.5
233 Chapra 101 W&S
GSB-15.5
Km 14.5-30 M/s Kumar 15.07.07 3.28 E/W-15.5 15.0 0.0 5.0 5.0
234 Chapra 101 IRQP State 15.5 200.00 171.21 16.01.07 45.25 100.00 BUSG-4.5
Jalalpur-Shahajitpur Const. 31.01.08 4/7 15.0 0.0 5.0 5.0
SDC-15.5
31 to 45 E/W-15
GSB-15
0101-BR-2005-685 Kamla 27.06.07
235 Chapra 101 IRQP NHO 15.00 1256.91 959.08 28.03.06 479.60 995.00 WMM-15
Chhapra-Baniapur- Construction 30.04.07 PMC-15
Muhammadpur CD work-28
E/W-10
GSB-10
46 to 55 06.08.07
236 Chapra 101 IRQP NHO 10.00 866.70 708.90 Vaibhav Const. 07.11.06
30.05.07
112.11 755.10 3.54 WMM-10
0101-BR-2006-705 PMC-10
CD work-20
E/W-10
GSB-10
Km56 to 65 Vaibhav 25.12.07
237 Chapra 101 IRQP NHO 10.00 874.54 808.45 26.12.06 300.45 602.00 WMM-10
0101-BR-2006-714 Const. 25.12.07 PMC-10
CD work-11
Km '1-5 09.04.07
238 Chapra 102 IRQP State 5 142.63357 Rai Const 10.01.07 305.00 305.00
Chapra-Rewaghat 28.02.07
09.04.07 E/W-7
Km '6-12 GSB-0.4
239 Chapra 102 IRQP State 7 100.00 104.19 Rai Const 10.01.07 25.00 104.00 0.52 BUSG-6.6
Chapra-Rewaghat
SDC-6.6
19
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-15
Km 13 to 27 GSB-15
(Job No 0102-BR-06- Nav Nirman 30.07.08 16.12 WMM-15 13.0 15.0 2.5 8
240 Chapra 102 IRQP NHO 15 1328.40 1216.84 31.01.07 0.00 396.00 PMC-15
717) Builders 14.05.07 14.0 15.0 2.5 8
CD work-11
Chapra-Rewaghat
Signage-15
E/W-9.2
GSB-9.2
R.P Estate Pvt 0
241 Chapra 102 W&S Km. 28 to 36.2 NHO 9 790.65 680.40 19.03.08 18.03.09 102.00 WMM-9.2 Work awarded.
Ltd. PC-9.2 0
CD work-15
242 Chapra 102 IRQP Km.36.2 to 38
E/W-4
Km 38-41 BUSG-2 2.0 1.5 4.0
243 Chapra 102 PR State 4 100.00 86.58 R.B.C Buliders 15.01.07 31.12.07 74.47 1.29 BM-2
Rewaghat-Bakhara 2.0 1.5 4.0
SDC-4
244 Chapra 102 PR Km.42-44
E/W-16
WBM-4
Km 45-60 BUSG-4
Nav Nirman 15.01.08 5.54 4.0 4.0 4.0 16.0 16.0
245 Chapra 102 IRQP Rewaghat- State 16 800.00 715.05 16.01.07 153.40 681.72 BM-16
Builders 30.12.07 13.04.07 SDC-16 4.0 4.0 4.0 16.0 16.0
Muzaffarpur
Marking-16
Signage-16
246 Chapra 102 PR Km.61-69
E/W-4.70
70(P) to 75(P) R.B.C Builders 22.03.07
247 Chapra 102 PR PR 4.70 77.59 60.66 23.12.06 22.00 60.65 1.14 BUSG-1
0102-BR-2006-1297 Pvt Ltd. 28.02.07 SDC-4.70
Included in A/P
248 Gulzarbagh 103 IRQP Km.1- 1.9
2008-09
E/W-12.1
Ms Dayanand Pd GSB-12.1 2.0
249 Gulzarbagh 103 W&S Km.1.9 to 14 NHO 12.1 772.27 26.03.08 25.01.09 Work started.
Sinha & Co. WBM-12.1 2.5
69.11 SDC-12.1
250 Gulzarbagh 103 IRQP Km.15-32
W& S including
251 Gulzarbagh 103 IRQP Km.33-36
in AP-08-09
Km.37-44 Ms Dayanand Pd 1
252 Gulzarbagh 103 IRQP NHO 8 479.87 Work Started.
(0103-BR-07-740W Sinha & Co. 1
435.61 27.03.08 26.01.09
45 to 49 E/W-5
GSB-5
103-BR-2005-688 Ramakant 4.67 4.67 4.67 1.00
253 Gulzarbagh 103 IRQP PBFF 5.00 318.41 289.89 10.01.06 09.10.07 227.49 227.49 11.76 WMM-5
Rasalpur- Singh SDC-5 4.67 4.67 4.67 1.00
Musarigharari Signage-5
20
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-9.51
GSB-9.51
50 to 58.510 31.12.07 WMM-9.51 9.5 92 9.0
254 Gulzarbagh 103 IRQP NHO 9.51 707.95 554.46 Ramakant Singh 25.01.07 0.00 144.48 8.31
SDC-9.51
0103-BR-2006-703 30.04.08 9.5 92 9.20
Marking-9.51
Signage-9.51
H.L R.C.C Bridge in Km
45
255 Gulzarbagh 103 Bridge Baruna River NHO 723.24 572.00 Ramakant Singh 30.11.07 29.05.09 0.00 0.00
(Job No-0103-BR-2007-
728)
1 to 22.35
104-BR-28A-0625 Shivani Construction
256 Motihari 104 IRQP NHO 22.35 273.71 Pvt. Ltd.
(Chakia-
Madhuwan )
Km 22.35-27 Shivani
1.25 4.65 0.85 0.80
257 Motihari 104 IRQP Madhuban-Banjaria NHO 4.65 143.41 125.09 Construction 25.01.07 26.06.07 31.00 SDC22.39
10.5.07 4.65 1.50 1.50
(104-Br-2006-727) Pvt. Ltd.
Br At Km 21/1
258 Motihari 104 Bridge NHO 415.840
104-BR-2008-769
Br At Km 23/1
259 Motihari 104 Bridge NHO 387.970
104-BR-2008-770
260 Motihari 104 Km.28-40
FDR
Improvement in 41 to
45(800) and 46(650) to
Sri Madhup
261 Sitamarhi 104 IRQP 63 NHO 22.45 211.44871 30.01.07
0104-BR-05-687
Kumar
Sheohar-Sitamarhi
E/W-
GSB
WMM
Calmity WIDE
64, 65, 66 M/s Madhup Kr 12.01.07
262 Sitamarhi 104 IRQP relief 3 59.9964 BUSG
Sitamarhi Town Singh 12.03.07 BM
fund
SDC
PCC
CD work
Dismantling
completed. E/W
Bridge in Km 38 Foundation excavation for
Substructure
263 Sitamarhi 104 Bridge Fatehpur NHO 131.02 116.55 Sri Prakash 30.11.07 30.06.07 Deck slab
one aboutment
0104-BR-07-732 Approach one pier doen.
Work in
progress.
Km 74 Foundation
M/s Amrendra 27.08.07 Substructure
264 Sitamarhi 104 Bridge 0104-BR-2006-696 NHO 198.92 171.29 28.08.06 24.71 144.53 1.71 Deck slab-3
Pd Singh 30.06.07
Sitamarhi-Bhitamore Approach
265 Sitamarhi 104 W&S Km.69-96
21
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
97-111
Durga Tower Work awarded
266 Jainagar 104 IRQP Bhithamore- State 7.60 500.00 277.93 Nine month
(P) Ltd on 20.03.08
Saharghat
Sri Shyam Work Awarded
267 Jainagar 104 IRQP Km 104-111 State 8.00 363.47 Six month
Kishore yadav on 24.03.08
E/W-4.84
Km 112P-117P WBM-4.84 4.8 4.70
268 Jainagar 104 IRQP State 6 90.00 94.50 M.s Jaya Const. 12.01.07 15.11.07 38.14 86.27 7.59 BUSG-4.84
Basuki-Saharghat 4.8 4.70
SDC- 4.84
E/W-15.39
GSB-15.39(pat)
Km 117-132 M/s Jaya 7.58 8.00 7.00 8.0 0.80 6.50
269 Jainagar 104 IRQP State 15 360.00 379.33 24.01.07 31.05.07 209.61 WBM-12.39(part)
Saharghat- Umagaon Construction 09.05.07 BUSG-3 9.0 8.0 8.0 0.80 8.00
SDC-15.39
To be included
270 Jainagar 104 PR 133-142
in plan/PR.
E/W-13.8
Calmity GSB-6
143 to 156(P) M/s Jaya 4.0 5.0 10.70 4.0 11.00
271 Jainagar 104 PR relief 11.5 155.00 159.96 12.01.07 31.03.07 115.00 115.00 4.80 WBM-13.8
Chattauni-Bela Construction BM-4 4.0 5.0 10.70 4.0 11.00
fund
SDC- 13.8
E/W-13.2
GSB-10
Km 156(P)-169 Durga Tower WBM-11 13.2 10.0 11.0 5.0 4.0 13.2
272 Jainagar 104 IRQP State 13.2 205.00 213.37 12.01.07 31.05.07 121.95 207.47 7.47 BUSG-5
Jainagar-Tenuahi Pvt Ltd. 13.2 10.0 11.0 5.0 4.0 13.2
BM-4
SDC-13.2
E/W-7
GSB-4
Km 170-176 Durga Tower WBM-7 5.0 4.0 7.0 5.0 7.0 7.0
273 Jainagar 104 IRQP State 7.0 150.00 147.07 24.01.07 31.05.07 145.98 3.82 BUSG-5
Temahi-Ladania Pvt Ltd. 5.0 4.0 7.0 5.0 7.0 7.0
BM-7
SDC-7
Estimate sent to
Km 177-181 Ministry for AP-
274 Jainagar 104 W&S
Ladania 07-08 but not
sanctioned.
H.P culvert in Km
81-97 M/s Ashok Kr 04.04.07
275 Jainagar 104 Bridge 75.00 69.03 05.12.06 47.30 68.36 2.76 9 Nos
Sitamarhi- Singh 04.04.07
Bhittamore
Infrastructure
DPR for Bhutahi Engineers &
Balan Consultants JV
21.09.07 Work in
276 Jainagar 104 Bridge Km 161 to 214 NHO 34.56 32.63 Planing & 20.04.07
31.01.08 progress
(Job No 0104-BR-06- Infrastructure
431) Development
Consultants
22
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Construction of
2x6.00m (eff span)
High Level RCC
277 Jainagar 104 Bridge Bridge in Km 95 of NHO 75.04 17.04.08
NH-104(Sitamashi
section of NH-104
0104-BR-2007-751
Km 1 to 2 Calmity
2.0 2.0 2.0 2.0
278 Jainagar 105 PR Darbhanga to relief 20.36 Brajendra Kumar
2.0 2.0 2.0 2.0
Aendkum fund
Km 3 to 11
M/s Brajendra 25.03.07 9.00 9.00 9.00 9.00
279 Jainagar 105 PR Aerodkuma to State 9.00 101.36325 12.12.06 101.36 101.36
Kumar 15.02.07 9.00 9.00 9.00 9.00
Kewati
Calmity
12 to 18 Ashok Kr & 25.03.07 7.00 7.00 7.00 7.00 7.00
280 Jainagar 105 PR relief 7 77.45412 23.12.06
Kewati to Aunsi Brothers 30.04.07 7.00 7.00 7.00 7.00 7.00
fund
E/W-15.5
GSB-15.5
Km 19-34P M/s Brajendra 6.22 5.0 11.8 11.8 11.07 9.80
281 Jainagar 105 IRQP State 15.5 285.00 291.35 15.01.07 15.06.07 59.64 163.50 BM-15.5
Aunsi-Muraith Kumar 09.05.07 WBM-15.5 5.0 11.8 11.8 11.07 9.80
SDC-15.5
E/W-13.5
GSB-2.1
Km 34(P) to 47 M/s Ashok Kr & 19.09.07 1.55 WBM-2.1 13.0 1.8 1.8 13.0 13.25 13.00
282 Jainagar 105 IRQP State 13.5 310.00 311.51 20.12.06 204.78 301.63 BUSG-13
(Muraith-Jainagar) Brothers 19.09.07 09.05.07 13.0 1.8 1.8 13.0 13.25 13.00
BM-13.5
SDC-13.5
E/W-6.5
GSB-4.5
WBM-4
Km 48 to 54(P) Durga Tower (P) 23.09.07 6.0 4.5 4.5 6.5 6.5 6.5
283 Jainagar 105 IRQP State 7.00 259.00 280.24 23.12.06 27.38 271.04 10.00 BUSG-6.5
Muraith-Jainagar Ltd 30.11.07 BM-6.5 6.0 4.5 4.5 6.5 6.5 6.5
SDC-6.5
Marking
Km 1
25.08.07
284 Jainagar 105 Bridge 0105-BR-2006-697 NHO 116.25 99.18 Ms. Yogendra Roy 24.08.06
30.06.07
44.04 106.46 0.49591
Darbhanga-Jainagar
Mohini in Km 9 08.05.07
285 Jainagar 105 Bridge NHO 181.56 166.08 Ms. Yogendra Roy 09.05.06
08.05.07
122.93 180.45 4.91
0105-BR-2005-694
Km 4
17.08.07
286 Jainagar 105 Bridge 0105-BR-2006-701 NHO 70.98 57.49 Ms. Yogendra Roy 18.08.06
31.03.07
43.62 59.90
Darbhanga-Jainagar
11
0105-BR-2006-708 M/s Ashok Kr & 25.08.07
287 Jainagar 105 Bridge NHO 116.54 101.39 Brothers
26.08.06
30.05.07
47.72 63.03 0.50965
Darbhanga-
Jainagar )
Construction of
2x6.00m (eff span)
High Level RCC
288 Jainagar 105 Bridge NHO 85.473
Bridge in Km 43 of
NH-105 (Darbhanga
Jainagar Section)
23
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Construction of
3x6.00m (eff span)
High Level RCC
289 Jainagar 105 Bridge NHO 107.450
Bridge in Km 7 of
NH-105 (Darbhanga
Jainagar Section)
Construction of
3x6.00m (eff span)
High Level RCC
290 Jainagar 105 Bridge NHO 108.780
Bridge in Km 8 of
NH-105 (Darbhanga
Jainagar Section)
Construction of
2x6.00m (eff span)
High Level RCC
291 Jainagar 105 Bridge NHO 92.150
Bridge in Km 5 of
NH-105 (Darbhanga
Jainagar Section)
E/W-19
Km 1-19 WBM-19
4.5 10.0 10.0 3.5 3.5
292 Madhepura 106 IRQP Birpur-Karzain State 20 200.00 439.55 BRPNN 03.10.07 02.04.08 114.00 BUSG-19
BM-19 4.5 10.0 10.0 3.5 3.5
Bazar
SDC-19
Km.20-35 E/W-16
(A/A-21to 57-1150 GSB-16
8.0 8.50 7.0 0.00 Work in
293 Madhepura 106 IRQP lacs) State 16 1150.00 1488.99 BRPNN 03.10.07 02.10.08 800.00 347.24 WMM-16
BM-16 8.5 8.50 7.0 5.50 progress
-Karzain Bazar-
SDC-16
Dandari
Km 36 to 50 E/W-15
GSB-15
(AA for 40-49) M/s Dayanand 16.01.08 5.90 15.00 15.00 15.00 15.00 3.0 Completed by
294 Madhepura 106 IRQP State 15.0 700.00 1176.44 17.01.07 132.40 1070.20 WMM-15
Manikpur-Rasana- Pd & Co. 16.01.08 17.04.07 BM-15 15.00 15.00 15.00 15.00 3.0 31.03.08
Bhalwahi SDC-15
E/W-7
GSB-7
Km 51-57 M/s Dayanand 16.01.07 7.0 7.0 7.0 7.0 7.0
295 Madhepura 106 IRQP State 7 630.00 533.71 17.01.07 166.84 513.19 WMM-3
Fakirna-Dandari Pd. Sinha & Co. 31.12.07 BM-7 7.0 7.0 7.0 7.0 7.0
SDC-7
Estimate not
Km 58-66
296 Madhepura 106 W&S sanctioned by
Fakirna-Dandari
Ministry.
Km 68-76 E/W-10
Vishal Biltuck 16.01.08 2.10 0.0 8.0 10.0 5.0
297 Madhepura 106 IRQP Sinheshwar- State 10 300.00 413.06 17.01.07 350.05 397.95 BM-10
(India) Pvt Ltd. 31.12.07 20.04.07 SDC-10 0.0 8.00 10.0 5.0
Madhepura
E/W-12
16.07.07 GSB-12
Km.77-88 Dinesh Kr 2.50 0.0 12.0 4.0
298 Madhepura 106 IRQP State 12 360.00 500.73 17.01.07 31.12.07 22.01 170.22 WMM-12
Madhepura-Fulaut Yadav 20.04.07 BM-12 0.0 12.0 4.0
10.02.08
SDC-12
E/W-10
Vishal Biltuck 27.01.07 1.50 0.0 10.0 10.0
299 Madhepura 106 IRQP Km 89 - 98 State 10.0 300.00 296.43 27.01.07 216.90 276.78 BM-10
(India) Pvt Ltd. 31.12.07 20.04.07 SDC-10 0.0 10.0 10.0
24
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-
GSB
99 to 124 WMM
WIDE
0106-BR-03-648 Vishal Bilteck 23.03.05
300 Madhepura 106 IRQP 26.00 NHO 381.31 24.03.04 BUSG
(Kishanganj- (India) Pvt Ltd. 31.01.07 BM
Fulaut). SDC
PCC
CD work
E/W-15
Km 1-15 WBM-08 Work completed
M/s Ramsagar BM-15 10.0 8.0 15.0 14.0
301 Khagaria 107 IRQP Maaheshkhunt-Mali State 15 400.00 390.93 08.01.07 07.10.07 176.08 379.69 SDC-15
except Marking
Construction 10.0 8.0 15.0 15.0
chowk Marking-15 & signage.
Signage- 15
E/W-11.3
Km 16-30.3 WBM-5
Sri Rajendra 1.85 BM- 13.3 4.0 5.0 9.0
302 Khagaria 107 IRQP Maaheshkhunt-Mali State 15.3 360.00 370.85 08.01.07 07.10.07 140.93 243.27 SDC- 14.3
Sharma 09.05.07 4.0 5.0 9.0
chowk Marking- 15.3
KMP-15.3
Construciton of
RCC H.L Birdge in
Bihar Rajaya Pul
303 Khagaria 107 Bridge Km 3 of State 461.81 BRPNN
Nirman Nigam.
Maheshkhunt-
Malichowk Section
Construction of
RCC H.L Birdge in
Bihar Rajaya Pul Throught pul
304 Khagaria 107 Bridge Km 5 of State 523.10
Nirman Nigam. Nirman
Maheshkhunt-
Malichowk Section
Construction of
RCC H.L Birdge in
Throught pul
305 Khagaria 107 Bridge Km 7 of State 238.04
Nirman
Maheshkhunt-
Malichowk Section
Construction of
RCC H.L Birdge in
Bihar Raj Pul Throught pul
306 Khagaria 107 Bridge Km 8 of State 355.56
Nirman Nigam Nirman
Maheshkhunt-
Malichowk Section
Construction of
RCC H.L Birdge in
Bihar Raj Pul Throught pul
307 Khagaria 107 Bridge Km 21 at Pansalva State 309.54
Nirman Nigam Nirman
of Maheshkhunt-
Malichowk Section
E/W-5.7
GSB-0.8
In Km 30.3-36 Sri Arvind Kr 16.07.07 1.85 1.25 1.2 4.80 4.80
308 Madhepura 107 IRQP State 5.7 200.00 185.60 17.01.07 63.91 164.35 WMM-0.5
Malichowk-Manouri Singh 31.12.07 20.04.07 BM-5.7 1.73 1.33 5.53 5.53
SDC5.7
Vishal Bilteck E/W-5
Km 37-40 GSB-5
India P Ltd. 31.03.08 3.5
309 Madhepura 107 IRQP Manauri-Simri- State 5 200.00 619.18 01.10.07 298.66 WMM-5 9 Nos.
Tender 31.03.08 BM-5 3.5
Bakhtiyarpur
Committee SDC5.5
Km 41-45
New Sanction
Manauri-Simri-
310 Madhepura 107 W&S NHO 5 927.03 Tender to be
Bakhtiyarpur
done
(107-BR-08-766)
Km 46-50 Estimate sent to
311 Madhepura 107 W&S Manauri-Simri- Ministry but not
Bakhtiyarpur sanctioned.
25
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-15.8
51 to 66 20.01.06 GSB-15.8
M/s Vishal 2.15 WMM-15.8 6.0 14.0 9.5 9.0 0.0 7 Nos.
312 Madhepura 107 IRQP 0107-BR-2004-656 NHO 16.00 486.42 429.75 Builtech
10.08.07 31.12.07 58.29 239.05 BUSG-15.8 6.0 14.0 10.50 9.5 5.0 5 Nos.
20.04.07
Pipra-Singhashwar 31.03.08 SDC-15.8
CD work-12
E/W-29
16.01.08 GSB-8
In Km 66(P) -95(P) Vishal Biltuck 10.0 8.0 8.0 28.0 8.0
313 Madhepura 107 IRQP State 29 1250.00 1081.37 17.01.07 15.01.08 663.83 972.20 WBM-8
Bariyahi-Madhepura (India) Pvt Ltd. BM-29 10 8.0 8.0 28.0 8.0
31.03.08
SDC-29
In Km96.620- Estimate not
314 Madhepura 107 IRQP 99.130 sanctioned by
Bariyahi-Madhepura Ministry.
Km 101-110 15.01.07 E/W-10
Krishna Febicon WBM-3
315 Purnea 107 IRQP Madhepura- State 10.00 150.00 136.30 15.01.07 31.03.07 84.00 123.25 2.04 BM-3
P Ltd.
Murliganj 10.06.07 SDC-10
E/W-10
GSB-8
Km 111-120 WBM-8
Baba 15.07.07
316 Purnea 107 IRQP Madhepura- State 10 300.00 400.08 15.01.07 10.56 368.68 10.00 BM-9
Construction 31.12.07 SDC-9
Jankinagar
PCC-1
Marking-10
Bansal E/W-10
Km 121-130 Construction Ltd. GSB-10(2)
13.19 WBM-6 2.0 8.50
317 Purnea 107 IRQP Muraliganj- State 10 600.00 659.31 Agreement 16.03.07 15.08.07 178.81 BM-10
6.00 2.0
25.03.08 2.0 8.50
Jankinagar Bazar exeucted on SDC-10 6.00 2.0
08.05.2007 Marking-
E/W-10
Km. 131-140 GSB-8
13.19 WBM-10 2.00 8.50 4.60 2.0 3.50
318 Purnea 107 IRQP Vinobagram- State 10 550.00 682.61 Baba Const 15.01.07 15.07.08 68.26 450.62 BM-10
28.03.08 2.00 8.50 6.00 3.0 3.50
Banmankhi-Islampur SDC-10
Marking-10
E/W-10
WBM-3
Km 141-150 15.07.07
319 Purnea 107 IRQP State 10 540.00 430.82 Baba Const 15.01.07 112.25 413.50 4.30 BM-10
Dharahara-Sarsi 30.05.07 SDC-10
Marking-10
E/W-10
Km. 151-160 15.07.07 WBM-10
320 Purnea 107 IRQP Vinobagram- State 10 350.00 359.44 Baba Const 15.01.07 31.03.07 228.45 359.27 BM-10
Banmankhi-Islampur 30.05.07 SDC-10
Marking-10
E/W-10
Km 161-170 15.07.07 WBM-3
321 Purnea 107 IRQP Krityanagar-Purnea State 10 390.00 420.53 Baba Const 15.01.07 31.03.07 163.16 418.35 BM-10
(Maranga chowk) 30.05.08 SDC-10
Marking-10
Km 171-180 E/W-3
BM-10
322 Purnea 107 IRQP Krityanagar-Purnea State 10 340.00 355.98 Ashutosh Kr 15.01.07 15.07.07 31.24 349.35 4.50 SDC-10
(Maranga chowk) Sing Marking-10
E/W-16
Km 0 to 16 GSB-16
Biharsharif- WMM-16
Ms Dayanand 15.09.07 16.0 16.0 16.0 16.0 17
323 Biharsharif II 110 W&S Ekangarsarai NHO 16 756.96 676.86 16.12.06 275.28 411.99 4.45 PC-16
Prasad Sinha CD work-14 16.0 16.0 16.0 16.0 Nos
(Job No-0110-BR-
Marking-16
2006-715)
Signage-16
26
National Highways Wing
Physical & Financial Progress of ongoing works on NHs in Bihar including status of remaining stretches (as on 25.04.08)
Financial Status as on Physical Progress as on31.03.08\25.04.08
Payment Head
Remarks
Sanc. Agreement Date of Date of
Length Name of
S.N Division NH Work Stretch/Section Amt Amount Work Completion as Upto date Total Fine SDBC/
(In Km) Contractor Work to be done as WBM/ BM/ CD
(In lakh) (In Lacs) order per agreement Exp by Exp by 31 imposed + E/W GSB BUSG BC/ PCC
per agreement WMM DBM works
Mar 07 March Fine with (Km) (Km) (Km) PMC (Km)
(In Km) (Km) (Km) (Nos)
2008 date (Km)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
E/W-19
GSB-19
Km 17-35 WMM-19
Ms Dayanand 31.05.07 19.0 19.0 19.0 19.0 12.0 32
324 Biharsharif II 110 IRQP Biharsharif- State 19 750.00 848.84 01.01.07 339.50 724.20 8.48 SDC-19
Prasad Sinha CD work- 32 19.0 19.0 19.0 19.0 12 Nos
Ekangarsarai
Marking-19
Signage-19
Km. 36-54 Calmity
Bihar Rajaya Pul 19 18 15.5 14.5 0.4
325 Gaya 110 IRQP Ekangarsarai- relief 18.2 259.00 259.00 30.11.07 232.00
Nirman Nigam. 19 18 15.5 14.5 0.4
Jehanabad fund
Rehabiliation of 17
spans Screw pile
Rehabil Ram Nandan
326 Gaya 110 Bridge in Km 53 of State 0.03 37.28
iation NH-110 for the year 07 Prasad
08
Km 55-69 Bihar Rajaya Pul 5 5.5 4 1.9 0.48
327 Gaya 110 IRQP State 15 290.00 290.00 125.00
Arwal-Jehanabad Nirman Nigam. 5 5.5 4 1.9 0.48
Km 70-89 Bihar Rajaya Pul 13 16 11 10.5
328 Gaya 110 IRQP State 20 305.00 350.00 158.00
Arwal-Jehanabad Nirman Nigam. 13 16 11 10.5
Byepass Planning & Work in
329 Bhagalpur II 80 Bypass NHO 15.4
080-BR-04-430 Infrastructure progress
SR in Km
Simanchal
330 Purnea 57A IRQP 1,2,3,6,7P,12,13P NHAI 5.50 198 155.90 82.90 82.90
Construction
Farbesganj-Jogwani
W& S from km 19
331 Aurangabad 2C W&S to 32 of NH-2C NHO 14.00 864.700
2C-BR-2008-772
Total 72290.00 18305.53 43703.09 959.79
27
Related docs
Get documents about "