CS-04a Cameron – Creole
Maintenance
(Operations Request)
September 20, 2011
Plan View of CS-04a Cameron-
Creole Maintenance
Peconi Bayou Structure
Mangrove Bayou Structure
Grand Bayou Structure
Lambert Bayou Structure
No Name Structure
Historical Information
The Cameron-Creole Maintenance (CS-
04a) project area is located about 6 miles
northeast of Cameron, Louisiana, in
Cameron Parish. It is bordered on the
west by the eastern shore of Calcasieu
Lake, on the north by the Gulf Intracoastal
Waterway, and to the east and south by
Louisiana Highway 27. It encompasses
approximately 54,076 acres of fresh-to-
saline marsh and open water.
Historical Information – Cont.
The Cameron-Creole Watershed Management
Project, a NRCS project completed in 1974,
consists of five large control structures and a 19
mile levee along the eastern rim of Calcasieu
Lake. The project has reduced salinities and
increased marsh productivity; however, funding
for maintenance was not included in the original
construction costs.
In 1993 funds for maintenance of the project
were included on the CWPPRA PPL 3 list.
2004 Maintenance Event Details
Replaced eight operating stems that were
vandalized and changed three operating
nuts at Lambert Bayou Structure.
Construction was completed in 2004.
Total Project Cost: $59,860
2005 Maintenance Event Details
Pedestals and actuators on all five structures
were sandblasted and painted. The pedestals
were also grouted along with snap tie holes.
Monitoring equipment also installed.
Three DC generators installed and solar panels
removed on Grand, Lambert and Peconi Bayou
structures.
Changed 21 actuator motors with stainless steel
housings on three of the structures.
Construction was completed in 2006.
Total Project Cost: $356,948
2007 Maintenance Event
Details
Repair four breaches along the levee
system as a result of damages sustained
from Hurricane Rita.
Construction was completed in 2008.
Total Project Cost: $4,044,920*
* FEMA Funding
2009 Maintenance Event
Details
Rebuild 1.6 miles of levee system
damaged as a result of Hurricane Rita and
Ike. (From T-Boy McCall to No Name Str.).
Construction was completed in 2010.
Total Project Cost: $1,120,079*
* FEMA Funding
2010 Maintenance Event
Details
Rebuild 16 miles of levee system
damaged as a result of Hurricane Rita and
Ike. (From No Name Str. to McCord’s).
Currently under construction. ( Expected
completion date Oct. 2011).
Total Project Cost: $14,155,386*
* State Only Funding/FEMA Reimbursement
Proposed Operations and
Maintenance Details for FY 2012
USFWS will cease operations of the Cameron-Creole Watershed
Project effective January 1, 2012. The task of operating the five
structures will now be incumbent upon CWPPRA using a contractor
via the public bid process. Generator equipment and wiring will be
removed from three structures in 2012.
TOTAL ESTIMATED O&M COST for FY 2012: $202,487
Recommended CS-04a
Operations and Maintenance
Request
FY 12 Projected Budget: $ 202,487
FY 13 Projected Budget: $ 110,219
FY 14 Projected Budget: $ 2,168,014
3 YEAR BUDGET ESTIMATE: $ 2,480,720
REMAINING O&M FUNDS: $ 1,954,913
3 YR. FUNDING REQUEST: $ 525,807
ADDN’L O&M FOR PROJECT LIFE: $ 233,607