					                        The International Linear Collider R&D
                                                      program




SPAFOA BNL April 2011                                      1
Mike Harrison
                        Technical Design Phase and Beyond



   RDR Baseline                  Baseline updated                     TDP Baseline
                                                                                       TDR
                                                                    Technical Design

                          Beijing Workshop



                                             CERN Workshop
                                                             RDR ACD concepts


                                                             R&D Demonstrations


    AD&I studies
    2009                2010                                 2011           2012         2013

SPAFOA BNL April 2011                                                                    2
Mike Harrison
                       Five Themes to Develop
                                            N Walker

 Industrialisati
             on
        in-kind
   contribution
        models




         Site
 requirements


       Project
     Schedule

Remaining
Technical
              Project                                      >2012
activities
           Implementatio
              n Plan
                                                       3
                        Design changes since 2007
                  RDR           SB2009


                                           • Single Tunnel for main linac


                                           •Move positron source to end o
                                           linac


                                           • Reduce number of bunches
                                           factor of two (lower power)


                                           • Reduce size of damping rings
                                           (3.2km)


                                           • Integrate central region


                                           •Single stage bunch compresso
                                           ????




SPAFOA BNL April 2011                                             4
Mike Harrison
                                               Cryomodules

•   Cryomodules are complex
     – Cavities made from pure Nb
     – Smooth & ultra clean surfaces
     – Cavity handling is crucial
     – Operate in 2K superfluid He
     – 1200 parts!

•   Cryomodules are expensive
•   Single most expensive component of the ILC
•   Must industrialize cavities, components, and
    maybe assembly
•   Developing the extensive infrastructure to
    build and test CM’s
•   FNAL leads an international team working to
    improve the TESLA CM design for ILC
    (DESY, INFN, KEK, CERN, SLAC, India, etc )
•   Global plug compatibility
•   Plan to have an improved ILC design ready
    for bids - deferred




                                                             5
  US ILC Program – Resources (FY11 $30M)


SRF Technology Development (~ 45%)
             Cavity gradient & yield
       Cryomodule design and fabrication
     Industrial tech transfer (US & Canada)
                Value engineering


         RF systems ( ~ 20%)
  Klystron cluster RF power distribution system
       Solid State modulator development
                      LLRF


            Particle Sources
Prototype high voltage electron gun/photocathode
               Positron simulations
      Positron target hardware development
                Cavity Gradient Milestone Achieved


                                                TDR
                                                Goal


                                                2010
                                              Milestone




SPAFOA BNL April 2011                              7
Mike Harrison
            GDE – SRF Industry partnership

    in lieu of (or together with) contracted in-depth
                studies: five-point request
                  Cost estimates, with breakdown, for 6 cases
                        (one absolute (with breakdown); other 6 relative)
                       Factory siting recommendation
                  Project / industry shared responsibilities
                                Deliverables
              Consortium (multi-industry / lab) recommendation
     to be discussed and received in time for PAC
                review (Taipei, 19-20.05)
     Satellite meeting – SRF 2011 Chicago (24.07)
ALCPG Eugene, 19 March 2011   Marc Ross, Fermilab                           8
                                         A. Yamamoto




ALCPG Eugene, 23.03.2011   Nick Walker                 9
ALCPG Eugene, 23.03.2011   Nick Walker   10
                         PAC Report (11.2010)

       ILCSC Project Advisory Committee (L.
        Evans, Chair) - from the PAC report
    “chemistry is under control” “if material and
        welds are good … cavities are good”
                     “big strides”
         Automate the process to get 100%
     “policy for industrialization will govern the
                         RD”
         “not so positive for cryomodule…”
                         field emission remains a problem
ALCPG Eugene, 19 March 2011   Marc Ross, Fermilab           13
                              High-Level RF Solutions
                         2×35 10MW MB klystrons
                                                  Klystron Cluster Scheme, KCS (SLAC)




                                                  Distributed RF Sources, DRFS (KEK)




              ~4000×800kW klystrons



SPAFOA BNL April 2011                                                                   14
Mike Harrison
GDE – Conventional construction
   Ready to build…?




                                  15
The International Linear Collider
  A technical progress report.




                                    16
                            ILC possible timeline
 CY    2010         2011           2012        2013         2014             2015            2016    2017   2018
      Baseline established Technical Design Report complete
                                                          Decision to proceed

                                            TDR reviews
ILC   Technical design & R&D program                            Site EOI’s   Site/host established


                     Cost Estimating              SRF system tests


        Project Implementation Plan complete                                  XFEL operation



                   Physics Run 1          Interconnect repair                Physics Run 2


LHC                 Existence of low-                                         Higgs energy
                    lying SUSY known                                          scale known




                                                          timegap




                                                                                                            17
 GDE - Technically-driven post 2012 program




 SCRF Systems tests; Mass production issues; Value
                  Engineering, etc.

Design evolution: 1 TeV; Positrons; R&D toward major
                   technical advances

 Must preserve GDE-like global decision making and
      coordination in new pre-project organization

                                                     18
                        The Americas Program– Post 2012


The NML SRF string test plan & goals need to be established but the operation will
    not start until ~FY13. System tests are the obvious next step to the TDP R&D
           program. Cryostat component development would be part of this.

We would plan to keep the US SRF industrial base active at a minimally useful level
                        (~12 cavities per year, 1 cryomodule).

   Value engineering on the cryomodules will remain a highly leveraged activity.

                              Next Generation SRF :
                              Low loss re-entrant shapes, superstructures
                Barrel polishing (tumbling) to improve yield and reduce costs - now
    Automated processing – 2011 initial results (integrated cavity processing concept @ JLAB)
                            Thin films to reduce costs – 2011 initial results
     Multi-layer films to increase gradient significantly (and reduce costs) – 2011 initial results
                   Hydroforming to improve yield and reduce costs – no results yet

				