					Haka Block House Construction Costs                                                        Date: 2009-08-31

     Typical 5m Diam Rondavel                              Floor area              19.64 Sq M

     Item       Description                              Dimensions (metres) Total
                                                           Qty                           Rate      Amount        Notes
                                                         L      w      h      Vol / Qty R/???      Rands
            1   Foundation 3:2:1 Concrete              1 15.714    0.4   0.25       1.57    280.00        440.00 Add Labour
            2   Dampcourse Row (blocks)                1 15.714           0.4      39.29      5.50        216.07
            3   Floor slab    3:2:1 Concrete           1   6.25   0.05 3.1429       0.98    280.00        275.00 Add Labour
            4   walls to 2.4 m (Haka Blocks)           8 15.714      1      1     125.71      5.50        691.43
            5   Plaster Mix 3 bags Cement              3             1              1.50    125.00        187.50
            6   Doorframe                              1             1              1.00    450.00        450.00
            7   Window frames                          2             1              2.00    650.00      1,300.00
            8   Windows incl glass                     2             1              2.00    750.00      1,500.00
            9   Roof frame Galv Steel                  1            12    3.2      38.40     15.00        576.00
           10   Roof netting                           1   6.25   1.25 3.1429      24.55     10.00        245.54
           11   Roof Plaster (Bags Cement)             2             1              2.00    125.00        250.00
           13   Roof Sealer/ paint                    20             1             20.00    120.00      2,400.00
           14   Galv Guttering                         1             5 3.1429      15.71     28.00        440.00
           15   Paint Walls litres                    20             1             20.00     65.00      1,300.00
           16   Labour        For building             8             2             16.00     80.00      1,280.00
           17   Cement for Founds                10.214              1             10.21     65.00
           18   Sand for Building                     15             1             15.00    120.00
           19   Stone for founds                 5.1071              1              5.11    160.00
           20   Other         Contingency       Tools                                                     500.00
           21   Other         Miscellaneous     Fittings                                                  500.00
           22   Total         Nett excl supervision and taxes/ vat                                  R 12,551.54
                              Cost nett / sq m floor area                                R 638.99

     A Typical homestead of three Rondavels 5m Diameter total about 60 sq m effective floor area would cost                  R 37,654.61

     Cost can be reduced if "Foundations" are replced with simple 100mm concrete slab.                Reduction   R 320.00
Haka Block House Construction Costs                                                            Date: 2009-08-31

Typical 5m Diam Double Rondavel & Centre room                                                                           Floor area         64.29 Sq M

Item       Description                                     Dimensions (metres) Total
                                                               Qty                        Rate       Amount                                          Notes
                                                           L      w      h      Vol / Qty R/???      Rands
       1   Foundation      3:2:1 Concrete                1 25.714    0.4   0.25      2.57     280.00        720.00                                   Add Labour (16)
       2   Dampcourse Row (blocks)                       1 25.714           0.4     64.29       5.50        353.57
       3   Floor slab      3:2:1 Concrete                1   6.25   0.05 3.1429      2.23     280.00        625.00                                   Add Labour (16)
       4   Extl walls to 2.4 m (Haka Blocks)             8 25.714      1      1    205.71       5.50      1,131.43                                   Add Labour (16)
       5   Plaster Mix 3 bags Cement                     6             1             3.00     125.00        375.00                                   Add Labour (16)
       6   Doorframe                                     2             1             2.00     450.00        900.00
       7   Window frames                                 5             1             5.00     650.00      3,250.00
       8   Windows incl glass                            5             1             5.00     750.00      3,750.00
       9   Roof frame      Galv Steel                    1            12    3.2     69.65      15.00      1,044.75
      10   Roof netting                                  1   6.25   1.25 3.1429     49.11      10.00        491.07
      11   Roof Plaster (Bags Cement)                    4             1             4.00     125.00        500.00                                   Add   Labour   (16)
      13   Roof Sealer/ paint                           40             1            40.00      90.00      3,600.00                                   Add   Labour   (16)
      14   Galv Guttering                                1             5 3.1429     31.43      28.00        880.00                                   Add   Labour   (16)
      15   Paint Walls     litres                       60             1            60.00      65.00      3,900.00                                   Add   Labour   (16)
      16   Labour          For building                 12             2            24.00      80.00      1,920.00
      17   Cement for Founds                        19.21              1            19.21      65.00
      18   Sand for Building                        15.00              1            15.00     120.00
      19   Stone for founds                           9.61             1             9.61     160.00
      20   Other           Contingency           Tools                                                      500.00
      21   Other           Miscellaneous         Fittings                                                   800.00
      22   Total           Nett excl supervision and taxes/ vat                                       R 24,740.82
                           Cost nett / sq m floor area                                     R 384.86

By Comparison: A Typical homestead of three Rondavels 5m Diameter total about 60 sq m effective floor area would cost                  R 37,654.61

Cost can be reduced if "Foundations" are replced with simple 100mm concrete slab.                         Reduction         R 320.00

				