					                                                                                                                                                                                 Planned start & finish
No.   Type                Name of the Project/Tender                                          Brief Scope of Work                                    Location of the Project
                                                                                                                                                                                        Dates
                                                                   Gas injection project has been commissioned in Dec-2001 using GG-II gas,
                                                                   which contains sour gas. The existing facilities will be contaminated with H2S
                                                                   due to Gas lift and Gas break-through.Since presently the existing facilities                               Planned Award : Q3 2009
                P-8151 : Gas Lift Operability Upgrade and Gas
 1    Project                                                      are not designed for the sour gas, these facilities are required to be modified        Upper Zakum                   Finish         :
                Detection System - (Work Package III )             in order to avoid personnel exposure to H2S. Package III involves the EPC                                   Q3 2011
                                                                   works for Toxic Gas detection system.



                                                                   ZADCO have carried out a QRA in order to assess and evaluate the
                                                                   effects of loss of containment on its Oil & Gas facilities on Zirku
                                                                   Island. From the findings of this study there was a recommendation to                                       Planned Award : Q2 2011
 2    Project   P-8363 : Fire & Gas detection system at Zirku      provide adequate F&G detection and alarm system to replace the                             Zirku                      Finish        :
                                                                   existing aging system.As a result, ZADCO has initiated this project                                         Q4 2012
                                                                   with the aim of providing Zirku with a new F&G system to increase the
                                                                   level of safety on the facility. FEED and EPC works to be carried out.

                                                                                                                                                                               FEED
                                                                                                                                                                                   Planned Award : Q2
                                                                   Installation of two RO type desalination plants, each with capacity of                                      2009               Finish
 3    Project   Potable Water & Sewage Treatment Plant at Zirku    1200m3/day to meet acute shortage of potable water and sewage                              Zirku                  : Q2 2010  EPC
                                                                   treatment plant at Zirku. EPC works to be carried for this project.
                                                                                                                                                                               Planned Award : Q1 2011
                                                                                                                                                                                         Finish         :
                                                                                                                                                                               FEED
                                                                                                                                                                                   Planned Award : Q2
                                                                   In order to improve overall reliability and availability to meet cooling                                    2009               Finish
                                                                   water demand in future & post GTP expansion phase-1, the sixth                                                    : Q2 2010    EPC
 4    Project   Sixth New Winning Pump & Back up header                                                                                                   Upper Zakum
                                                                   winning pump to be installed. It is proposed to install a new discharge
                                                                   back-up header suitable for future capacity.                                                                Planned Award : Q1 2010
                                                                                                                                                                                         Finish        :
                                                                                                                                                                               Q4 2012

                                                           There are leakage problems at all floors of ACPT-2, this has wet the
                                                           floor covering material (fire retardant insulation). The existing sanitary
                                                           rooms are found to be the leakage sources, these are required to be
                                                           demolished completely and re-built, in order to eliminate the leakage
                                                                                                                                                                               Planned Award : Q3 2009
                ACPT-2 Floor Repair & ACPT 1 & 2 Dormitory sources. Finally, the damaged flooring needs to be replaced.
 5    Project                                                                                                                                             Upper Zakum                    Finish        :
                Conversion - EPC                           Eliminate all substandard living conditions (converted some existing
                                                                                                                                                                               Q4 2011
                                                           facilities at ACPT-1 & 2 to bedrooms/dormitories) and convert the
                                                           dormitories into standard accommodation.
                                                                              ( ACPT : Accommodation Platform at Upper Zakum)
                                                                                                                                                                               Planned start & finish
No.      Type                   Name of the Project/Tender                                        Brief Scope of Work                              Location of the Project
                                                                                                                                                                                      Dates

                                                                           Install new riser protectors on 10 wellhead platforms (WHPT-
                                                                          03/11/13/14/16/19 to 23) in order to provide protection against boat                               Planned Award : Q3 2009
                      P 7317 : RISER PROTECTORS INSTALLATION
 6    Constlucction                                                       impact on the riser. The detailed design engineering to be carriedout         Umm Al Dalkh                   Finish        :
                      IN UAD
                                                                          by ZADCO and material procurement & installation by contractor                                     Q4 2011
                                                                          using Zadco hired M/V Barracuda for offshore works.


                                                                                                                                                                             Planned Award : Q2 2010
                                                                          To construct deck extension for new offices and modification in
 7    Construction    P7283 Cellar & Main Deck Extension                                                                                                Umm Al Dalkh                   Finish        :
                                                                          existing mechanical workshop at Umm Al Dalkh CPC.
                                                                                                                                                                             Q3 2011

                                                                                                                                                                             Planned Award : Q4 2008
                      P - 8712 Implementation of intelligent smart plant Implementation of smart plant enterprises ( SPE) and practices for the
 8      Service                                                                                                                                        ZADCO offices                    Finish
                      application                                        benefit of engineering,operation and maintenance in ZADCO
                                                                                                                                                                             : Q2 2011
                                                                                                                                                                             FEED
                                                                          Installation of additional power generation facilities at Zirku Island                                 Planned Award : Q2
                                                                          since the existing power generation facilities enhancement due to the                              2009               Finish
 9      Project       P 8374 - Power upgrade at ZIRKU                                                                                                       Zirku
                                                                          operational constraints for maintenance of aging turbines, increase in                                   : Q3 2010  EPC
                                                                          demand for the future projects and improve flexibility of operations
                                                                                                                                                                             Planned Award : Q2 2011
                                                                                                                                                                                       Finish        :
                                                                          A conceptual study is planned to be performed during 2009 to
                                                                                                                                                                             Planned Award : Q2 2009
                                                                          upgrade the water injection rate in Upper Zakum field to 1,238,000
10      Project       P 8341 Water Injection Plant (WIP) Upgrade                                                                                        Upper Zakum                   Finish         :
                                                                          BWPD (35% higher than current rate), due to the sought after
                                                                                                                                                                             Q2 2010
                                                                          production rate of 750,000 BOPD. To meet the future demand, it is
                                                                          required to upgrade the existing Water Injection Plant in UZ-CC.
                                                                          Due to the planned upgrade of upper Zakum production, a study is
                                                                                                                                                                             Planned Award : Q2 2009
                                                                          planned to be performed during 2009 to establish adequacy of the
11    Consultancy     P 8341 : Power System Adequacy Study                                                                                              Upper Zakum                   Finish         :
                                                                          existing system and resulting upgrade, followed by conceptual design
                                                                                                                                                                             Q2 2010
                                                                          for the same.
                                                                          Phase I : A common set of corporate 'Rules' was developed including
                                                                          Best Practice and Procedure that are Mandatory to applicble to all BU
                                                                          sites.                                      Phase II : Based on the
12      Service       Operations Standard Manual                          Corporate Operations 'Rules' review, revise, rationalise, standardise,          All Sites          Year 2009
                                                                          formally authorise and improve existing procedures (circa 700) and
                                                                          develop new procedures as required to reflect the currenet method of
                                                                          operating to International Best Practice.

                                                                          To translate, revise and update the existing Maintenance Policy &
                                                                          Startegy Manuals into practical Maintenane Plan, impememted via
13      Service       Maintenance Management System                                                                                                       All sites          End of Year 2008
                                                                          Maximo as per ISO 14224 in ordeer to ensure that installed equipment
                                                                          will perform to meet the next five years production targets.
                                                                                                                                                                             Planned start & finish
No.      Type                  Name of the Project/Tender                                     Brief Scope of Work                                Location of the Project
                                                                                                                                                                                    Dates

                                                                       Supply, Installation, Test And Commissioning Of 36 Inch Bi-                                         Start : Q4 2008
14      Project      Prover Loop System Replacement                    Directional Meter Prover System. To Replace - Prover Pipe Works, 4-            ZIRKU ISLAND
                                                                       Way Valve, Hydraulic System And System Cabling.                                                     Finish : Q2 2010



                                                                       Existing Two - 2 MW / 3.3 KV Diesel Engine Driven Electric Generator                                Start : Q1 2009
                     Replacement Of Two - Emergency Diesel Power                                                                            ZIRKU ISLAND - UTILITIES -
15      Project                                                        Sets To Be Replaced With 2.5 MW Capacity Sets, Complete With
                     Generators                                                                                                             PART A
                                                                       Auxiliaries, Accessories And Controls                                                               Finish : Q4 2010



                     Roof Leak & Structural Integrity Of Workshop      Demolition & Rebuilding Of Roof - To Remove RCC Slab And                ZIRKU ISLAND - MAIN         Start : Q4 2008
16    Construction
                     Buildings                                         Replace With Structural Steel Roof. Area Approx. 660 Sq. Mtrs.          WORKSHOP                    Finish : Q4 2010


                                                                       Replace The Exisitng 6 Inch Cs / Phenolic Lined Piping With 8 Inch
                                                                       Cs / Cement Lined Piping, 400 Mtrs. Also Install 6 Inch (20 Mtr), 3
                                                                                                                                               ZIRKU ISLAND - EXPORT GAS Start : Q2 2009
17    Construction   Replacement Of Cooling Water Piping In Unit 411   Inch (30 Mtr) And 2 Inch (60 Mtr) Cu-Ni Branch Piping. All The Piping
                                                                                                                                               UNIT                      Finish : Q2 2011
                                                                       On Pipe Rack, 5 Mtr Above Ground. Necessary Pipe Supports Shall
                                                                       Be Provided.

                                                                       Concrete Repairs In 10 Concrete Buildings / Rcc Structures; Non -       ZIRKU ISLAND - VARIOUS      Start : Q4 2008
18    Construction   Non-Industrial Area Concrete Repairs
                                                                       Residential Buildings                                                   AREAS.                      Finish : Q4 2010


                                                                       Supply And Installation Of Fibre Optic Cabling System, Together With ZIRKU ISLAND - PLANT AND
                                                                                                                                                                     Start : Q4 2008
20    Construction   Fibre Optic Cabling For Zirku Island              4 - Fibre Optic Batch Panels. Estimated Lenghth Of Fibre Optic Cable ACCOMMODATION AREAS, A
                                                                                                                                                                     Finish : Q2 2010
                                                                       25 Km.                                                               & B.
          Name of the Project/Tender                                            Brief Scope of Work                                        Location of the Project      Planned start & finish Dates
  P-8151 : Gas Lift Operability Upgrade and Gas                                                                                         Zakum                        Planned Award : Mid 2009
     Detection System - (Work Package III )          Gas injection project has been commissioned in Dec-2001 using GG-II gas,                                           Finish            : Mid 2011
                                                     which contains sour gas. The existing facilities will be contaminated with H2S
                                                     due to Gas lift and Gas break-through.Since presently the existing facilities
                                                     are not designed for the sour gas, these facilities are required to be modified
                                                     in order to avoid personnel exposure to H2S. Package III involves the EPC
                                                     works for Toxic Gas detection system.


P-8363 : Fire & Gas detection system at Zirku        ZADCO have carried out a QRA in order to assess and evaluate the effects           Zirku                        Planned Award : 2nd Qtr 2011
                                                     of loss of containment on its Oil & Gas facilities on Zirku Island. From the                                           Finish            : 4th Qtr
                                                     findings of this study there was a recommendation to provide adequate F&G                                       2012
                                                     detection and alarm system to replace the existing aging system.As a result,
                                                     ZADCO has initiated this project with the aim of providing Zirku with a new
                                                     F&G system to increase the level of safety on the facility. FEED and EPC
                                                     works to be carried out.
Potable Water & Sewage Treatment Plant at Zirku                                                                                         Zirku                         FEED
                                                                                                                                                                     Planned Award : 2nd Qtr 2009
                                                     Installation of two RO type desalination plants, each with capacity of                                                 Finish           : 2nd Qtr
                                                     1200m3/day to meet acute shortage of potable water and sewage treatment                                         2010            EPC
                                                     plant at Zirku. EPC works to be carried for this project.                                                                           Planned award :
                                                                                                                                                                     1st Qtr 2011            Finish
                                                                                                                                                                          : 4th Qtr 2012
Sixth New Winning Pump & Back up header                                                                                                 Upper Zakum                  FEED
                                                                                                                                                                     Planned Award : 2nd Qtr 2009
                                                                                                                                                                            Finish           : 2nd Qtr
                                                     In order to improve overall reliability and availability to meet cooling water                                  2010            EPC
                                                     demand in future & post GTP expansion phase-1, the sixth winning pump to
                                                                                                                                                                                         Planned award :
                                                     be installed. It is proposed to install a new discharge back-up header suitable
                                                     for future capacity.
                                                                                                                                                                     1st Qtr 2010            Finish
                                                                                                                                                                          : 4th Qtr 2012


ACPT-2 Floor Repair & ACPT 1 & 2 Dormitory There are leakage problems at all floors of ACPT-2, this has wet the floor                   Upper Zakum                  Planned Award : 3rd Qtr 2009
Conversion - EPC                           covering material (fire retardant insulation). The existing sanitary rooms are                                                  Finish             : 4th Qtr
                                                     found to be the leakage sources, these are required to be demolished                                            2011
                                                     completely and re-built, in order to eliminate the leakage sources. Finally, the
                                                     damaged flooring needs to be replaced.
                                                     Eliminate all substandard living conditions (converted some existing facilities
                                                     at ACPT-1 & 2 to bedrooms/dormitories) and convert the dormitories into
                                                     standard accommodation.                                                   (
                                                     ACPT : Accommodation Platform at Upper Zakum)

P 7317 : RISER PROTECTORS INSTALLATION                Install new riser protectors on 10 wellhead platforms (WHPT-                      Umm Al Dalkh                 Planned Award : 3rd Qtr 2009
IN UAD                                               03/11/13/14/16/19 to 23) in order to provide protection against boat                                                  Finish             : 2nd Qtr
                                                     impact on the riser. The detailed design engineering to be carriedout                                           2011
                                                     by ZADCO and material procurement & installation by contractor
                                                     using Zadco hired M/V Barracuda for offshore works.




P7283 Cellar & Main Deck Extension                   To construct deck extension for new offices and modification in                    Umm Al Dalkh                 Planned Award : 2nd Qtr 2010
                                                     existing mechanical workshop at Umm Al Dalkh CPC.                                                                      Finish            : 3rd Qtr
                                                                                                                                                                     2011

P - 8712 Implementation of intelligent smart plant Implementation of smart plant enterprises ( SPE) and practices for                   ZADCO offices                Planned Award : 4rd Qtr 2008
application                                        the benefit of engineering,operation and maintenance in ZADCO                                                           Finish             : 2nd Qtr
                                                                                                                                                                     2011

P 8374 - Power upgrade at ZIRKU                      Installation of additional power generation facilities at Zirku Island             Zirku                        FEED
                                                     since the existing power generation facilities enhancement due to the                                           Planned Award : 2nd Qtr 2009
                                                     operational constraints for maintenance of aging turbines, increase in                                                 Finish           : 3nd Qtr
                                                     demand for the future projects and improve flexibility of operations                                            2010            EPC
                                                                                                                                                                                         Planned award :
                                                                                                                                                                     2nd Qtr 2011             Finish
P 8341 Water Injection Plant (WIP) Upgrade                                                                                Upper Zakum                                     : 4th Qtr 2013
                                                                                                                                                                      Planned Award : 2nd Qtr 2009
                                                     A conceptual study is planned to be performed during 2009 to                                                             Finish            : 2nd Qtr
                                                     upgrade the water injection rate in Upper Zakum field to 1,238,000                                              2010
                                                     BWPD (35% higher than current rate), due to the sought after
                                                     production rate of 750,000 BOPD. To meet the future demand, it is
                                                     required to upgrade the existing Water Injection Plant in UZ-CC.
P 8341 : Power System Adequacy Study                 Due to the planned upgrade of upper Zakum production, a study is Upper Zakum                                    Planned Award : 2nd Qtr 2009
                                                     planned to be performed during 2009 to establish adequacy of the                                                       Finish            : 2nd Qtr
                                                     existing system and resulting upgrade, followed by conceptual design                                            2010
                                                     for the same.



                                                                                                                                                                                              D:\Docstoc\Working\pdf\2bc462c8-a992-4cd2-a734-f9474e858c92.xls

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:10
posted:9/19/2011
language:English
pages:4
Description: Startegy Recommendation document sample