SECTION 15440 Plumbing Fixtures and Trim

VIEWS: 43 PAGES: 9

  • pg 1
									                             DIVISION 15 - MECHANICAL

                  SECTION 15440 - PLUMBING FIXTURES AND TRIM


PART 1 - GENERAL

1.01   SECTION INCLUDES

       A.   CONTRACTOR shall provide all labor, materials, equipment and incidentals as
            shown, specified, and required to furnish and install plumbing fixtures and trim
            complete with accessories.
1.02   RELATED SECTIONS

       A.    Section 01080 - REFERENCE STANDARDS

       B.    Section 01340 – SUBMITTALS

       C.    Section 01400 – QUALITY CONTROL

       D.    Section 01720 – PROJECT RECORD DOCUMENTS

       E.    Section 01735 – OPERATION AND MAINTENANCE TRAINING

       F.    Section 01785      –    OPERATION        AND      MAINTENANCE       MANUAL
             INFORMATION

       G.    Section 09900 – PAINTING

1.03   REFERENCE SPECIFICATIONS, CODES, AND STANDARDS

       A.    Codes: Comply with applicable requirements of the codes referenced in Section
             01080 REFERENCE STANDARDS.

       B.    Requirements of Regulatory Agencies: Comply with applicable provisions and
             recommendations of the following except as otherwise shown or specified.

             1.     International Plumbing Code.

             2.     Local and State Building Codes and Ordinances.

             3.     Underwriters Laboratories, Incorporated.

             4.     National Fire Protection Association.

             5.     National Electric Code.



9/11/11                                  15440-1                                   Phase 7B
            6.     National Electrical Manufacturers' Association.

            7.     Institute of Electrical and Electronic Engineers.

            8.     American National Standards Institute.

            9.     Permits: CONTRACTOR shall obtain and pay for all required permits, fees
                   and inspections.

       C.   Federal Specification, FS WW-P-541b, Plumbing Fixtures-Land Use.

       D.   ANSI/ASME A112.19.1, Enameled Cast Iron Plumbing Fixtures.

       E.   ANSI/ASME A112.19.2, Vitreous China Plumbing Fixtures.

       F.   ANSI/ASME A117.1, Requirements for the Physically Challenged.

       G.   ANSI/ASME Requirements          for    Low   Consumption,    Water    Conservation
            Requirements.

       H.   Source Quality Control: Equipment shall be completely manufactured and pre-
            assembled in accordance with Reference Standards.

1.04   SUBMITTALS

       A.   Shop drawings, specifications, brochures, calculations, and samples shall be
            submitted for all items to be furnished in accordance with the provisions of Section
            01340 SUBMITTALS and shall include but not limited to the following:

            1.     Manufacturer's literature, illustrations, specifications, weight, dimensions,
                   required clearances, materials of construction, and performance data for all
                   equipment.

            2.     Drawings showing fabrication methods, assembly, accessories, installation
                   details and wiring diagrams.

            3.     Setting drawings, templates, and directions for the installation of anchor
                   bolts and other anchorages.

            4.     Deviations from Contract Documents.




9/11/11                                  15440-2                                      Phase 7B
       B.   Shop Drawing Data: All materials to be submitted simultaneously as specified
            elsewhere:

            1.     Detailed installation drawing of each individual component showing:

                   a.     Mounting requirements.

                   b.     Piping and roughing connections, labeled and coded.

                   c.     Instructions.

                   d.     Materials of construction.

                   e.     Data sheets.

            2.     Detailed description of each component.

            3.     Catalog cuts.

            4.     Complete equipment list.

            5.     Spare parts list and recommended quantities.

       C.   Operation and Maintenance Manual Information:          Submit complete manuals
            including:

            1.     Submit appropriate level of O&M Manual Information in accordance with
                   Section 01785 OPERATION AND MAINTENANCE MANUAL
                   INFORMATION.

1.05   QUALITY ASSURANCE

       A.   Manufacturer’s Qualifications:

            1.     Manufacturer’s qualifications shall conform to Section 01400 QUALITY
                   CONTROL.

       B.   Factory Testing:

            1.     Factory test equipment to insure that the entire package has been properly
                   fabricated and assembled, that all the controls function as specified herein
                   and that the package meets the specified performance requirements
                   including manufacturer’s data report.




9/11/11                                   15440-3                                    Phase 7B
       C.   Manufacturer’s Responsibilities:

            1.     CONTRACTOR shall insure that complete equipment systems be the direct
                   product of one manufacturer and supplier who shall assume all
                   responsibility for:

                   a.     Manufacturing.

                   b.     Warranty.

1.06   PRODUCT DELIVERY, STORAGE, AND HANDLING

       A.   Delivery of Materials:

            1.     Deliver materials to the site to ensure uninterrupted progress of the Work.
                   Deliver anchor bolts and anchorage devices, which are to be embedded in
                   cast-in-place concrete, in ample time to prevent delay of the Work.

            2.     All boxes, crates and packages shall be inspected by CONTRACTOR upon
                   delivery to the site. CONTRACTOR shall notify OWNER if any loss or
                   damage exists to equipment or components. Replace lost equipment or
                   components and repair damage to new condition, in accordance with
                   manufacturer’s instructions.

       B.   Storage of Materials:

            1.     Store materials to permit easy access for inspection and identification.
                   Keep all material off the ground, using pallets, platforms, or other supports.
                   Protect steel members and packaged materials from corrosion and
                   deterioration.

            2.     Store all equipment in covered storage off the ground and prevent
                   condensation and in accordance with the manufacturer’s recommendations
                   for long-term storage.

1.07   WARRANTY

       A.   Guarantee and warranty shall be furnished in accordance with the General
            Conditions.




9/11/11                                  15440-4                                       Phase 7B
PART 2 - PRODUCTS

2.01   MATERIALS

       A.   Electric Water Cooler:

            1.     Manufacturer: Provide products of one of the following:

                   a.       Halsey Taylor, Model S300-2D-Q.

                   b.       Haws.

                   c.       Oasis Corporation.

            2.     Type: Free-standing, self contained water cooler.

       B.   Service Sink:

            1.     Manufacturer: Provide products of one of the following:

                   a.       Eljer, Fig. No. 242-0125.

                   b.       Kohler, Fig. No. K-6719.

                   c.       American Standard, Fig. No. 7696.016.

            2.     Type: Enameled cast iron service sink, wall hanger, plain back.

            3.     Accessories:

                   a.       Rim Guard:

                            1)      Manufacturer: Provide products of one of the following:

                                    a)       Eljer, Fig. No. 805-0160.

                                    b)       Kohler, Fig. No. K-8937.

                                    c)       American Standard, Fig. No. 47077-07.

                   b.       Trap Standard:

                            1)      Manufacturer: Provide products of one of the following:

                                    a)       Eljer, Fig. No. 804-1060.




9/11/11                                   15440-5                                     Phase 7B
                            b)        Kohler, Fig. No. K-6673.

                               c)     American Standard, Fig. No. 7798.176.

                     2)        Type: P-trap with 3-inch female threads inlet and outlet,
                               rubber washer, inlet strainer and cleanout plug. Acid
                               resisting enamel interior.

               c.    Faucet:

                     1)        Manufacturer: Provide products of one of the following:

                               a)     Eljer, Fig. No. 749-1200.

                            b)        Kohler, Fig. No. K-8908.

                               c)     American Standard, Fig. No. 8344.111.

                     2)        Description: Exposed service sink faucet with vacuum
                               breaker, integral stops, lever or four arm handles, spout with
                               pail hook and hose end, and top single brace, 1/2-inch I.P.S.
                               female couplings and renewable seats.

               d.     Carrier:

                     1)        Manufacturer: Provide products of one of the following:

                               a)     Jay R. Smith, Fig. No. 0871.

                            b)        Zurn Industries, Fig. No. Z-1229.

                               c)     Josam Series No. 17725.

                     2)        Description: Floor mounted heavy-duty carrier with hanger
                               plate, adjustable supporting and bearing studs, structural
                               uprights and block bases secured to concrete slab with
                               stainless steel expansion type inserts for service sinks.

          4.   Reference: ANSI Standard A112.19.1M.




9/11/11                               15440-6                                      Phase 7B
PART 3 - EXECUTION

3.01   INSTALLATION

       A.   General:

            1.     Install all items as shown, specified, and as recommended by the
                   manufacturer.

            2.     Request instructions from OWNER when there is a conflict between the
                   manufacturer's recommendations and the Contract Documents.

            3.     Present conflicts to OWNER attention for directions.

            4.     Do not modify structures to facilitate installation of fixtures unless
                   specifically approved by OWNER.

            5.     Installation to conform to requirements of all local and state codes.

            6.     Hangers and carriers shall be installed in accordance with manufacturer’s
                   recommendations and in accordance with good practice and workmanship.

            7.     All fixtures shall be provided with shut off valves or stops for the required
                   water supplies.

            8.     All exposed valves and escutcheons provided shall be chrome plated.

            9.     Provide insulation for all plumbing piping under handicapped lavatories.


3.02   FIELD QUALITY CONTROL

       A.   Field Tests:

            1.     Fill all systems and fully test all equipment, valves, .and appurtenances in
                   operation.

            2.     All wall hung fixtures after mounted and supported shall be load tested in
                   accordance with manufacturer’s recommendation.

            3.     Installed systems and components will not be released to OWNER unless
                   all systems have been tested and approved by the OWNER.




9/11/11                                  15440-7                                           Phase 7B
       B.   Inspection:

            1.     Examine areas to receive plumbing fixtures and accessories for:

                   a.     Defects that adversely affect execution and quality of Work.

                   b.     Deviations beyond allowable tolerances for equipment and
                          accessories.

                   c.     Start work only when conditions are satisfactory.

            2.     The OWNER reserves the right to reject and/or authorize replacement of
                   equipment and accessories found to be defective.

3.03   ADJUSTING & CLEANING

       A.   Adjusting:

            1.     Adjust all controls for proper settings.

            2.     While system is operable, balance all equipment, valves, and appurtenances
                   to achieve design conditions.

       B.   Cleaning:

            1.     Thoroughly clean all equipment and accessories prior to installation.

            2.     Upon completion of the Work, all labels shall be removed; fixtures and trim
                   shall be cleaned of all dirt, grease and markings.

            3.     Remove all dirt, rust, and dust from equipment in preparation for required
                   painting.

            4.     Remove and dispose of all debris and waste from the site resulting from
                   installation.

3.04   DISINFECTION

       A.   Prior to placing the potable water supply in service, all equipment, piping and
            accessories shall be disinfected in accordance with AWWA Standard C601 and any
            additional requirements prescribed by the public health authorities having
            jurisdiction.




9/11/11                                   15440-8                                     Phase 7B
3.05   PAINTING
       A.   All equipment and accessories shall be painted as required in accordance with
            Section 09900 PAINTING.

3.06   MANUFACTURER’S TRAINING

       A.    Manufacturer’s training shall be provided for training of OWNER’S personnel for
             the equipment in accordance with Section 01735 OPERATION AND
             MAINTENANCE TRAINING.


                                   END OF SECTION