Implementation Planning of Guangzhou Solid Waste Disposal Center

Document Sample
Implementation Planning of Guangzhou Solid Waste Disposal Center Powered By Docstoc
					            Public Disclosure Authorized   Public Disclosure Authorized                                Public Disclosure Authorized   Public Disclosure Authorized




                                                                      Implementation Planning of
                                                               Guangzhou Solid Waste Disposal Center
                                                                                                                                                       Volume 2
                                                                                                                                                                  RP202




FILE COPY
I
                                                            Table of Contents
 1.      General ....................................................................                                                            1

 1.1           Introduction ....................................................................                                                  1

 1.2           Project summarization ................................................................... 1

       1.2.1           Site selection and nature of the project ...................................................................              1

       1.2.2           Overview of the project area ...........................                      ....................................... 2

 1.3           Analyses of the economic environment of the project resettlement ................................. 5

      1.3.1            Objective of the analysis of the economic environment of the resettlement ............ 5

      1.3.2           Socioeconomic characteristics of the project area .................................................... 5

      1.3.2           Employment environment of the PAPs with low income in project area ................. 6

2.       Status of the PAPs and the resettlement, compensation and rehabilitation plans for them 10

2.1             Status of the PAPs whose land is affected and the resettlement, compensation and

rehabilitation plans for them ...................................................................                                             10

      2.1.1           Type and quantity of affected land ...................................................................                  10

      2.1.2           Status of the labor force whose property is affected ............................................... 10

      2.1.3           Resettlement, compensation and rehabilitation measures ...............                             ....................... 10

2.2           Affected houses and their resettlement, compensation and rehabilitation measures ....... 11

      2.2.1           Quantity of affected houses ...................................................................                         11

     2.2.2            Affected people ...................................................................                                      11

     2.2.3            Resettlement, compensation and rehabilitation measures ....................................... 11

3.      Status of the affected and the resettlement, compensation and rehabilitation plans for them

        12

3.1           Basic situation of the affected .12

3.2           Resettlement, compensation and rehabilitation plans for the affected .12

4.      Explanation on preparation of Resettlement and Compensation Standard for Guangzhou

Urban Environmental Project ....................                                                                                             13
 4.1           Compensation standard for land ............................                                                          13
       4.1.1         Compensation standard for land requisition (please see Annexed Table 13.1.1).... 13

       4.1.2         Compensation for retracted land and free land (See Annexed Table 13.1.2 for

       details)      15

 4.2           Compensation standard for houses with property right .15

 4.3           Other compensation standards .17

 5.        Institutional structure of the resettlement and the ability building .21

 5.1           Arrangement of Resettlement organization.21

 5.2           Responsibilities of Resettlement Organization .21

 5.3           Capability construction of resettlement organizations .21

 5.4          Strengthening of Resettlement Organization .21

      5.4.1         Training plan for resettlement work personnel .22

      5.4.2         Resettlement work mode .22

6.       Information disclosure plan                       ..                                                                      24

6.1           Information disclosure already unfolded                            .       .                 .24

6.2           Information disclosure plan in the next stage                          .        .                .24

7.      Public participation and consultation .25

7.1        Public participation and consultation activities already unfolded                               .           .     .25

7.2        Achievements of public participation and consultation activity                              .           .        .27

7.3        Public participation and consultation plan in the next stage                            .           .           .28

8.       Monitoring and evaluation                         ..                                                                      37

8.1        Internal monitoring                              .                .               .37

8.2        Independent supervision                              .                .             .37

8.3        Schedule of the information publishing, public participation and consultation and

supervision and evaluation ...................                                                                                     38
9.    Cost estimate and fund plan of the project .................................................       39

9.1    Description of project estimate ................................................                  39

9.2    Compilation standard for and explanation of pipeline estimation .................................. 41

9.3    Project budget ................................................                                   43
m   -   I
 Implementation Planningof Guangzhou Solid Waste Disposal Center



 1.         General

 1.1        Introduction

 1.1.1 Project summarization
 1)         Site selection and nature of the project
 Guangzhou Solid Waste Disposal Center is a sub-item of Guangzhou Urban Environment Project.

According to the layout, this project is to be localized in Liangtian Village of Liangtian Town in

the northern of Baiyun District of Guangzhou City, with controlled land area being 500 Mu (with

range extending to Jingzhu Freeway in the east, the old Guangcong Highway in the west,

Zhongluotan Town of Baiyun District in the north and Qianjiawei Brick Field of Liangtian Town

in the south, adjacent to the north foot of Baiyun Mountain).              This project is to provide

comprehensive facility for the final treatment & disposal of hazardous waste of public institutions

of Guangzhou City, so as to, instead of all enterprises and institutions, safely and effectively

dispose the various hazardous and harmful waste material that is difficult to utilize or unable to be

disposed.

2)         Construction content and scale of the project
(1)        Construction content:

           The construction content of Guangzhou Solid Waste Disposal Center mainly includes:

           Waste Allocation       and Switching Central,   Physico-chemical      Treatment Workshop,

           Stabilization/solidification Workshop and Safe Filling Ground, etc.

(2)        Construction scale:

       *     Scale of land use:

             The area of affected land for the initial stage of this project is 200,000square meters

             (300Mu), and the total area of control land within the layout red line is 333,335 square

            meters (500Mu).

       *    Construction scale:

            In accordance with the generation amount and predicted amount of the hazardous waste

            to be land filled in Guangzhou City, the construction scale for the safety landfill of this

            project is 850,000cubic meters (the capacity of land filled waste substance after being

            compacted is generally 1.2T/m 3 -1.6T/ m), of which:
 Implernentation Planningof Guangzhou Solid Waste Disposal Center


            The construction scale for phase I is 150,000 mi ;
                                                           3



            The construction scale for phase II is300, 000 m3 ;

            The construction scale for phase III is 400,000 m3 .

 3) Schedule of project construction

                                       Schedule of project construction

               Work description                                                      Construction
                                                         Scheduled time
                                                                                     period (days)
  1. Formal assessment by the World Bank              Dec. 2003
  2. Engineering design (from the
  determination of the Design Entity to the     Oct. 30, 2003      May 25, 2004          145
  consummation of construction drawing)
  3. The project resettlement work
  (including the land of plant area and pipe    Dec. 10, 2003      March 1, 2004         80
  network resettlement)
  4. Engineering construction (from the
  determination of tender to the completion     Jan. 5, 2004-April 20, 2005              470
  of pipe network construction)
  5. Acceptance of completed project            April 20, 2005     April 30,
  (including planned environment                2005                                     10
 protection items and labor protections)


1.1.2    Overview of the project area

1.1.2.1 A brief description of the project area

Guangzhou Solid Waste Disposal Center is located in Baiyun District of Guangzhou City. And

Baiyun District is located in the northeastern and western of Guangzhou City, connecting to

Zengcheng City in the east and Nanhai City in the west, adjacent to Huadu City and Conghua City

in the north and bordering on Liwan District, Yuexiu District, Tianhe District and Huangpu

District in the south, with total area being 1042.7km 2 of which cultivation land area occupies for

340,00OMu and total population for 858,40. The agricultural resources are rich and natural

landscape is beautiful in this district; there are plenty of touristry attractions, such as Baiyun

Mountain Beauty Spot, East Paradise and Sanyuanli Englishman Fighting Site, etc, with

convenient traffic.

1.1.2.2 Waste substance pollution status in the project area

An investigation of annual enterprise waste and its disposition, which was performed by

Guangzhou Solid Waste Control Center in 2001, revealed that enterprises and institutions annually
Implementation Planning of Guangzhou Solid Waste Disposal Center


produce 263,570.97 tons of hazardous waste. However, because of low level of comprehensive

utilization and treatment technology as well as small scale, the actually comprehensive utilization

amount and treatment capacity are only 121,351.21 tons and 138,221.33 tons respectively; the

comprehensive utilization rate and treatment rate are only 46.04% and 52.44% respectively, which

has not reached environmental protection requirement.
Implementation Planningof Guangzhou Solid Waste Disposal Center


        Table: Enterprises Generating Solid Waste in Guangzhou City

                                                                                                      Administr
  No.                     Enterprises                                  Address                           ative
                                                                                                      division
(1)          Guangdong         South         Alkali    # 488 Huangpu District, Guangzhou             Huangpu
l______      Preparation Co. ltd                       City, Guangdong Province                      District
(2)
l            Sinnopec                  Guangzhou       Shihua Road #176, Huangpu District,           Huangpu
             Petrochemical Complex                     Guangzhou City                                District
(3)          Guangzhou        Huali        Pigment     Nangang West Road #238, Huangpu               Huangpu
            Chemical Co., ltd.                         District, Guangzhou City                      District
(4)          Guangzhou Zhujiang Steel Co.,             Xiji   Road,      economic      Technical     Huangpu
             ltd                                       Development Area, Guangzhou City,             District
                                                       Guangdong Province
(5)         Guangzhou        Shenli     Electronic     Fengwei Village, Jiufu Town, Baiyun           Baiyun
            Scientific & Technology Co., ltd           District, Guangzhou City                      District
(6)         1st    Factory     of     Guangzhou        Lianglong Street, Huashan, Huadu              Huadu
            Flashlight Industrial Corporation          District, Guangzhou City                      District
(7)         Guangzhou Steel Co., ltd                   Fanfcun Avenue #1, Fangcun District,          Fangcun
                                                       Guangzhou City                                District
(8)         Guangzhou Thermal Power Plant              Dongfeng West Road #26, Liwan                Liwan
                                                      IDistrict, Guangzhou City                     District
According to the prediction conducted by Guangzhou Environment Protection Scientific Research

Institute, the total amount of hazardous waste that needs to be centrally treated tends to increase in

Guangzhou City from 2001 to 2003, but its annual increase rate declines year after year, the

details are as follows:

      Table 1. Total amount of hazardous waste that is generated by industrial enterprises in

                             Guangzhou City and needed to centrally treat
                                                                                            Total amount
            Item               2001 (T)        2005 (T)       2010 (T)      2023 (T)           during
                                                                                           construction (T)
 Amount of hazardous           13369.81         16251          18840           21441           410036
  waste needed to be
 centrally incinerated
 Amount of hazardous           32056.68         38965            45171         51049               882063
  waste needed to be
  centrally land filled
        Table2. Annual average increase rate of hazardous waste in Guangzhou City
            Year                    2001      2005             2005       2010             2010-2023
      Annual average                         5%                           3%                            100
        increase rate




                                                         A
 Implementation Planningof Guangzhou Solid Waste Disposal Center



 1.2       Analyses          of   the    economic         enviromment           of    the    project

           resettlement

 1.2.1     Objective of the analysis of the economic environment of the resettlement
 (1)       From analysis in Paragraph 2.4 of the Involuntary Resettlement Planningfor Guangzhou

           Urban Environment Project-- Resettlement Policy, the social environment in Guangzhou

           City is very much compatible to the project affected people and is easy to accept those

           people; the economy in Guangzhou is developing very fast while the space for further

           development remains considerably prospective, which means more jobs will be available

           and the capacity for taking the project affected people is very strong; in addition, the

           social security and job security system in Guangzhou are considerably mature while the

           infrastructure is well developed too, which provides to the project affected people good

          space for living and development.

          Nevertheless, in order to better protect the PAP's interest and keep the integrity of the

          original living area and social relationship of the PAP's as far as possible, this section

          intends to analyze the economic environment of the region in which the project is located,

          thereon to analyze the employment environment of the PAPs and the business

          environment of enterprises thus extending to the analysis of the recovery capability of the

          PAP's living under the specific economic environment of the project, so as to set out the

          points for resettlement work attention in this project. In this way, the resettlement plan

          and measures that are made in Resettlement Implementation Plan are more directional,

          and the resettlement goal can be realized as desired.

(2)       This project will focus on the employment and resettlement of the rural PAPs because the

          project only involves the land requisition of rural area, and project-affected people are

          rural residents.

1.2.2     Socioeconomic characteristics of the project area
The area in which the project is to be constructed is in Baiyun District of Guangzhou city, and the

economic characteristics of this area is follows:

1)        Large scale of agricultural enterprises
         (1)      This district attaches its importance to the development of five rising agricultural
 Implementation Planning of Guangzhou Solid Waste Disposal Center


                  industries such as horticulture. There are over 140 agricultural enterprises whose

                  products account for above 90% of the total agricultural commodities of this

                  district.

         (2)     Its total output of agriculture in 2002 is RMB 24.828 billion Yuan, of which the

                 production output of township and village enterprises is RMB 23.398 billion Yuan,

                 accounting for 94.24% of the total agricultural output.

2)         Rapid progress of light industries
In 2002 this district established eight industry parks that have attracted total 158 enterprises

engaged in product production of dozens of industries such as electronic information and folk food.

Just in the first half of the year of 2003 these eight industry parks achieved an accumulative

industrial output of RMB 4.571 billion Yuan, accounting for 23.1% of the total of the whole

district in the corresponding period. Its rapid progress becomes a major economic growth point of

this district.

3)        Developed leisure tourism
Relying on its geographic advantages such as wide territory and diversified landforms, this district

gives a full play to the development of agricultural and ecological tourism industries. It has

developed about 20 tourist spots including Baiyun Mountain, a famous mountain in Guangdong. It

has abundant tourist products. In 2002 its total income of tourism industry is RMB 1.68 billion

Yuan, accounting for 10.37% of the service sector's GDP of this district.

1.2.3     Employment environment of the PAPs with low income in project area
The characteristics of regional economic development decide the development direction and

potential of trades in this district, and such direction and potential decide the development

direction of various posts of every trade and the number of employment opportunities. Such

economic characteristics of project area result in the distribution of low-income posts of various

trades in following table:
 Implementation Planning of Guanigzhou Solid Waste Disposal Center




                                                 Analysis on the Employment Situation of Low-Income Posts in Baiyun District

  Type of trade                                                                                                        Quantity of   Percentage of the    Ranking
                            Trade subdivision                 Post       Skills required by the       Applicable       employe o     employees in total     number
                                                                                  post                population          2002)        population of      (totally 12
 1. Agriculture,                                                                                                                      Guangzhou City       districts)
                      1. Agriculture                      Salesclerks,   No special               Mainly middle-aged       700            4.80%                5
forestry, animal     2. Livestock husbandry               processing     requirements             and young men and       1812           46.22%                1
husbandry and        3. Agriculture, forestry, animal     worker, etc.                            women                   6929           66.24%                1
fishery              husbandry and fishery service
                     1. Food processing industry         Pipelining      Pipelining worker and    Mainly middle-aged      3028            16.82%              2
                     2. Dress and other fibres           worker,         packer shall master      and young men and      28427            13.17%              3
                     manufacturing industry              packer,         relevant skills. There   women
                     3. Leather, fur, eider down and     Securities      is no special                                   55213           33.31%               1
                     their manufacturing industry        Custody         requirements for
2. Manufactunng      4. Medicine manufacturing           Clerk,          securities custody
industry             industry                                                                                             6658           30.98%               1
                                                         cleaner, etc.   clerk and cleaner
                     5. Metal product industry           Pipelining      Relevant skills are      Mainly middle-aged     18470           21.90%               2
                     6. Transport and                    worker,         required                 and young men with     14903           16.18%               2
                     communication facilities            carter,                                  strong body
                     manufacturing industry              welder, etc.
3. Wholesale         Various wholesale businesses        Salesclerks     No special               Mainly young men       18795            9.910%              5
business                                                                 requirements             and women
4. Retail business   Various retail businesses           Salesclerks                              Mainly middle-aged     9866             8.7 %               6
5. Restaurant &      Various restaurant and              Waiter, dish    Waiter shall accept      and young women
beverage
                                                                                                                         12316           12 .04%              4
                     beverage businesses                 washing         relevant training.
business                                                 worker          There is no special
                     All kinds of hotels                 Waiter,         requirements for         Mainly middle-aged     7458            11.43 %              4
6. Hotel business                                        sanitation      sanitation worker and    and young women
                                                         worker          dish washing worker
                     All kinds of tourism industries     Tour guide,     Tour guide shall have    Mainly middle-aged      395            5.350%               6
7. Tourism                                               workers in      tour license, No         and young men and
industry                                                 the sight       special requirements     women
                                                         spot            for workers in the
                                                                         sight spot




                                                                                     7
Implementation Planningof Guangzhou Solid Waste Disposal Center




Notes:

1. Total employees of each district [unit: person]: the entire city: 3573132; Dongshan District: 374655; Liwan District: 166698; Yuexiu District: 231975; Haizhu

District: 306620; Tianhe District: 470075; Fangcun District: 86806; Baiyun District: 491630; Huangpu District: 232679; Panyu District: 627192; Huadu District:

208530; Zengcheng City: 253618; Conghua City: 122654

2. The data are from Collection of the Second-time Census Data of Fundamental Units of Guangzhou. As census is carried out per five years and the last census was

carried out in 2001, so the data in the table were counted at the end of 2001.

3. Some data in the table may be not correct, but they are the most authoritative data available for the Project at present.




                                                                                     8
Implementation Planningof Guangzhou Solid Waste Disposal Center

From the analysis on the employment situation of low-income posts in Baiyun District in aforesaid table
we can see that:
(1)     In Baiyun District, there are a large number of employees and posts in agriculture, forestry,
        animal husbandry and fishery service industries, which rank first among industries in
        Guangzhou and facilitate the employment resettlement for rural area PAPs.
(2)    Manufacturing industry has a large demand for labor force (mainly for young ones), while most
       posts require relevant skills, so such training may be offered for PAPs to help them
       trans-employed in these trades.
(3)    Service sectors including wholesale business, retail business, restaurant and beverage industry,
       hotel business and tourism industry have not superior demand for labor force to that in other
       districts, while there are many posts for young female labour force and most of them have no
       special requirements.
(4)    There are a small number of posts for middle-aged PAPs to whom more attention shall be paid
       in this district.
 Implementation Planningof Guangzhou Solid Waste Disposal Center



 2.       Status of the PAPs and the resettlement, compensation and
          rehabilitation plans for them
 2.1      Status of the PAPs whose land is affected and the resettlement,
          compensation and rehabilitation plans for them
 2.1.1    Type and quantity of affected land
 The project is to requisition the farmland for 300.4 Mu in Liangtian Village of Baiyun District of
 Guangzhou, of which:
 Infield: 42.89 Mu, accounting for 14.28% of the area of affected land
 Woodland: 113.84 Mu, accounting for 37.90% of the area of affected land
 Garden land: 139.3Mu, accounting for 46.37% of the area of affected land
 Pound: 2.0lMu, accounting for 0.67% of the area of affected land
 Other agricultural land: 2.36Mu, accounting for 0.79% of the area of affected land.

2.1.2    Status of the labor force whose property is affected
In the light of China policy, for the rural area where land adjustment is unable to conduct, the
agricultural population shall be converted into nonagricultural population. In general condition, the
original ratio between agricultural population and infield shall remain unchanged, according to which the
per capita infield is 1.2 Mu, affected land is 300.4 Mu, and the affected agricultural population is 253 in
Liangtian Village.
Since the site of this project has just been determined and the land requisitioning has not been
undertaken, and also, Liangtian Village has not determined which farmers or farmer families will be
converted into nonagricultural population, the affected farmer families can not be investigated.
2.1.3    Resettlement, compensation and rehabilitation measures
1)       The affected rural people shall obtain compensation according to Resettlement Policy, and the
         compensation fund shall be paid in a time manner.
2)       When conducting land requisition, the affected structures shall be restored in a timely manner if
         they are non-independent structures (which are connected to other structures having not been
         removed); care shall be taken to reduce the impact on the integral function of buildings.
3)       The govemmental expenses of taxation related to the affected land of that year shall be deducted
         in the expenses of taxation of the next year.
4)       During the construction of the solid waste disposal center, if temporary labor force is needed,
         the young adults from the rural PAPs shall be given priority.
5)       After the establishment of the solid waste disposal center, appropriate personnel from the rural
         PAPs will be arranged to deal with work that requires less technology or the work that can be
         done after training, such as handling, entrance guard, transportation driver and cleanness keeper,
         etc.
6)       The Project will contact with labor employment training authorities in providing necessary
 Implementation Planningof Guangzhou Solid Waste DisposalCenter

         psychological assistance and skill training for the rural PAPs, so as to allow them to go over the
         rehabilitation period and to obtain new skill.
 7)      The Project shall negotiate with the real property companies of resettlement sites to provide job
         posts, such as security and house keeper.
 8)      The Project will contact with the real property companies of resettlement sites and street
         housekeeping service points to provide job posts, e.g., cleanness keeper and housekeeping
         service, for the young and middle-aged women of rural PAPs.
 9)      The Project will retain experts to give counsel for the use and investment of rural compensation
         fun, for, example, investing in the Liangtian Village Industry Park being built, so as to speed up
        the construction of industry park and supporting facilities, to increase the attraction to foreign
        investment, and to allow the investment of compensation fund to gain better earnings ratio, thus
        promoting the development of local economy. By carrying out such measures, the Project hopes
        to provide employment opportunities for farmers as well as to benefit from the shares. In this
        way, a good circulation of economic development is formed, and the living standard of the rural
        PAPs can be continually improved.
 10)    The Project will negotiate well with the affected farmers, the chances shall be, as practical as
        possible, given to the young adults who have certain skill.

2.2     Affected        houses       and their resettlement,                  compensation           and
        rehabilitation measures
2.2.1   Quantity of affected houses
The affected houses are 1128.4m in total, of which duck shed(shed structure) is 624.3m 2 and simple
                       2~~~~~~
                    2
structure is 504. Im .
2.2.2   Affected people
Two families and 13 persons will be affected. These people are non-native residents who rent the land of
Liangtian Village for dealing with fish breeding and poultry rising.
2.2.3   Resettlement, compensation and rehabilitation measures
1)      Since the layout management for this area is not strict, these houses will be compensated
        according to replacement price.
2)      The affected people will be compensated with house-moving fee.
3)      Relevant structures will be compensated as per replacement price.
4)      The two families of non-native personnel will be assured to rent basically identical land    from
        Liangtian Village (or neighbor villages) for fish breeding and poultry rising.
Implementation Planningof Guangzhou Solid Waste Disposal Center



3.       Status of the affected and the resettlement, compensation and
         rehabilitation plans for them
3.1      Basic situation of the affected
Disadvantageous groups is not a really affected kind by project, it is a group of people needed special
attention among all affected kinds.
According to the scope definition about disadvantageous groups in 4.3.3 of "Resettlement Policy", the
general conditions of the sub-item disadvantageous are groups as follow:
(The investigation not finished and the contents will be added)
3.2     Resettlement,          compensation and rehabilitation plans for the
        affected
The Project will give the following helps to the affecteds besides the resettlement and compensation
specified in the Resettlement Policy:
1)      After the establishment of the solid waste disposal center, they will be, in a priority manner,
        arranged to deal with work that requires less technology or the work that can be done after
        training, such as handling, entrance guard, transportation driver and cleanness keeper, etc.
2)      The Project will negotiate with villagers' committee to provide a certain job posts of the
        constructing industry park to the affected affecteds.
3)      At the PAP's willing, the Project will help them to find proper jobs in the resettlement sites of
        sub-items, and will contact with the social labor authorities to provide appropriate community
        training, allowing them to deal with housekeeping, cleanness keeping and keeper.
4)      The Project will pay attention to the affected(the elder who has no grown-up children to
        accompany, widow, single-parent family, the handicapped, chronic patient and poverty family),
        and will periodically pay a return visit to them and provide help for special difficulties after the
        project has been established.
I
 Implementation Planningof Guangzhou Solid Waste Disposal Center




 4.           Explanation on preparation of Resettlement and Compensation
              Standard for Guangzhou Urban Environmental Project
 4.1          Compensation standard for land
 4.1.1        Compensation standard for land requisition (please see Annexed Table 13.1.1)
 1)           Reference to compilation of compensation standard
Reference to compilation of the standard:
         *     Article 47 in Land Administration Law of the People's Republic of China;

         *     Article   30    in   Enforcement Method of Guangdonig Province for Land
               Administration Law of the People's Republic of China;
         *     Provisional Regulations on Compensation and Resettlement of Peasant
               Collective-owned Land Affected for Construction Land in Guangzhou (Opinion
               Requisition Version).
2)           Determination of compensation base number
According to the above regulations, the compensation base number is the average annual output of the
requisition land in the previous three years. Due to the large range of the wastewater project which
covers several villages in different districts, and presently, the district statistic bureaus can only provide
the statistics data of partial villages, this compensation standard list only shows the compensation base
numbers for the villages for which the statistics data have been provided. For the other villages, the base
number for the adjacent village will be referred to for the base number determination (criteria has been
provided in the list).
3)           Land compensation fund
*            Calculation formula
             Land compensation fund=compensation base number X compensation times
*            Determination of compensation times
For the reason that the wastewater project belongs to municipal project, the compensation fund may be
on the low side. Therefore, for the compensation times in this project, the lower limit in the range of
various land compensation times listed in Clause 30 in "Implementation of 'Land Administration Law
of the People's Republic of China' in Guangzhou Province " will be referred to.
Implementation Planning of Guangzhou Solid Waste Disposal Center




                                                                  Compensation times            Times
                                                                   range stipulated in       adopted in
                                                                  Guangzhou Province        this project
                                             Basic farmland           8- 10 times              8 times
                           Plowland            Nonbasic               6-8 times               6 times
                                                farmland
    Agricultural land                 Fish pond                       8 - 12 times            8 times
                                     Garden plot
                                     Forest land                              .
                                                                               me
                                                                             ti7              5 time
                              Grassland and feed land
          Rural            Agricultural construction land
    construction land     Non-agricultural construction land           6-8 times              5 times
     Other rural land                                                  3-4 times              3 times


4)         Resettlement compensation
*          Calculation formula
           Resettlement compensation=compensation base number X compensation times
*          Determination of compensation times
           Due to the lack of statistic data in the statistics bureau about the land holdings per capita, the
           agricultural population to be resettled cannot be calculated and it is impossible to work out the
           resettlement allowance based on the population. Thus, in this project, the method in
           "Provisional Regulations on Compensation and Resettlement of Peasant Collective-owned Land
           Affected for Construction Land in Guangzhou (Exposure Draft )" has been referred to so as to
           work out the resettlement allowance based on times.
           In this criteria, the compensation times is determined referring to the related regulation in
           "Provisional Regulations on Compensation and Resettlement of Peasant Collective-owned Land
           Affected for Construction Land in Guangzhou (Exposure Draft )" and is adjusted based on the
           following circumstances.
*          Resettlement allowance for plowland.
           Due to the large area, Baiyun District is subdivided. For Songzhoujie near to the urban district,
           12-time will be adopted and 5-time for Taihe Town and Renhe Town far away from the urban
           district.
          5-time is given for Liwan District in the original regulation, and 13-time is adopted in this
          project considering balancing it to that for the other old urban district.
          See the following list for comparison details:




                                                      14A
 Implementation Planning of Guangzhou Solid Waste Disposal Center



                                        Times provided prelinminarily          Times in this
                                             in discussion draft                 project
               Haizhu                                  .
              D istrict                             1___                         ___   __1 _ ___   ___
              Fangcun                              14times                          14times
               District
               Liwan                                 Stimes                         l3times
               District
                              Taihe                                                 Stimes
                              Town
              Baiyun          Renhe                    .
              District        Town
                            Songzhou                                                12times
                               Jie
               Tianhe                               12times                         12times
               District
              Huangpu                               12times                         12times
               District


          Resettlement allowance for other agricultural land except plow land.
5-time is given as the calculation times for other agricultural land except, however, 3-5 times is provided
in the provincial regulation. As this project is a municipal works, the lower limit is adopted here.
4.1.2     Compensation for retracted land and free land (See Annexed Table 13.1.2 for
         details)
4.2       Compensation standard for houses with property right
1)        Compensation for dwelling houses with property right (See Annexed Table
          13.2.1 for details)
        (1)        This price system is based on the second-hand house market investigation and real estate
                   assess and the 8 administration districts of Guangzhou City, and 6 classes are defined for
                   each district considering various factors including district environment, surrounding
                   facilities, traffic, economic level, population, social environment and land application
                   state. The compensation price grades are clearly defined according to these two
                   standards. Due to the obvious difference of house price in different locations in Class 1-3
                   districts, the price fluctuation is obvious while the price fluctuation is tiny in Class 4-6
                   districts.
        (2)        Based on the experience, the compensation standard is given considering the frame
                   structure, mixed structure, half-timbered structure, simple structure and shed structure.
        (3)        Based on the experience and second-hand house price, the compensation standard for the
                   houses depreciation is regulated in terms of different service life such as less than five
                   years, 5-15 years, 15-25 years, 25-35 years and over 35 years.
2)       Compensation for commercial houses with property right (See Annexed Table
         13.2.2 for details)
Implementation Planning of Guangzhou Solid Waste Disposal Center


This price system is based on the second-hand house market investigation and real estate assess and the
8 administration districts of Guangzhou City, and 6 classes are defined for each district considering
various factors including district environment, surrounding facilities, traffic, amenity degree of the
shopping environment, land application state economic prosperity degree, business scale and
congregation degree. The compensation price grades are clearly defined according to these two standards.
Due to the obvious difference of house price in different locations in Class 1-3 districts, the price
fluctuation is obvious while the price fluctuation is tiny in Class 4-6 districts, which is near to the price
for office houses with property right.
As for the commercial houses with property right, the compensation price is fluctuated based on the
district economic prosperity degree. Therefore, the compensation standard is stipulated in terms of
commercial road, common street and alleyway. Commercial road locates in the prosperous central
section, which belongs to Class 1-3.
The price for ground floor, the first floor and the second floor and the floor above second floor decreases
by degree. The compensation for affected above second floor in Class 1-3 district is slightly higher than
that for office houses with property right while compensation for affected above second floor in Class
4-6 districts is near to that for office houses with property right.
The price of ground floor affected varies much depending on the longitudinal depth; therefore, the price
in the compensation standard is decreased by degree in term of the depth of 0-12 m, 12-24m, depth
above 24m. in Class 1-3 district, the price fluctuation of the three grades is obvious and that for Class
4-6 fluctuates slightly.
Based on the experience, the compensation standard are made considering the frame structure, mixed
structure, half-timbered structure, simple structure and shed structure of the houses in each building plot.
Based on the experience and second-hand house price, the compensation standard for the houses
depreciation is regulated in terms of different service life such as less than five years, 5-15 years, 15-25
years, 25-35 years and over 35 years.
3)       Compensation for office houses with property right (See Annexed Table 13.2.3
        for details)
       (1)      This price system is based on the second-hand house market investigation and real estate
                assess and the 8 administration districts of Guangzhou City, and 1-6 classes are defined
                for each district considering various factors including district environment, surrounding
                facilities, traffic, economic prosperity degree and economic development level and etc.
                The compensation price grades are clearly defined according to these two standards. Due
                to the obvious difference of house price in different locations in Class 1-3 districts, the
                price fluctuation is obvious while the price fluctuation is tiny in Class 4-6 districts,
                which is near to the price for office houses with property right.
       (2)      As for the commercial houses with property right, the compensation price is fluctuated
                based on the district economic prosperity degree. Therefore, the compensation standard
                is stipulated in terms of commercial road, common street and alleyway.
Implementation Planning of Guangzhou Solid Waste Disposal Center


                  Based on the experience, the compensation standard are made considering the frame
                  structure, mixed structure, half-timbered structure, simple structure and shed structure of
                  the houses in each building plot.
      (3)         Based on the experience and second-hand house price, the compensation standard for the
                  houses depreciation is regulated in terms of different service life such as less than five
                  years, 5-15 years, 15-25 years, 25-35 years and over 35 years.
4)     Houses with property right used as firms and warehouse (See Annexed Table
       13.2.4 for details)
            (1)     This price system is based on the second-hand house market investigation and real
                    estate assess and the 8 administration districts of Guangzhou City, and 1-6 classes are
                    defined for each district considering various factors including district environment,
                    water and electricity and other infrastructures, aggregation degree of the related
                    industries, environment pollution and pipeline condition, land application state and
                    traffic condition. The compensation price grades are clearly defined according to these
                   two standards. Due to the obvious difference of house price in different locations in
                   Class 1-3 districts, the price fluctuation is obvious while the price fluctuation is tiny in
                   Class 4-6 districts, which is near to the price for office houses with property right.
        (2)        Based on the experience, the compensation standard are made considering the frame
                   structure, mixed structure, half-timbered structure, simple structure and shed structure
                   of the houses in each building plot.
        (3)        Based on the experience and second-hand house price, the compensation standard for
                   the houses depreciation is regulated in terms of different service life such as less than
                   five years, 5-15 years, 15-25 years, 25-35 years and over 35 years.

4.3   Other compensation standards
1)    Compensation for houses built on household plot (See Annexed Table 13.3.1 for
      details)
        (1)        Implementation of "Compensation standard for Temporarily Borrowed Land and
                   Houses Built on Household Plot in Public Utility Construction Project of Guangzhou"
                   (See Annexed Table 9).
       (2)         As the price of houses built on household plot does not vary much for the reason of
                   the location, the compensation standard is stipulated based on the 1-6 grades defined
                   considering the various factors such as district environment, productive forces cost,
                   traffic, economic development level, population and social environment.
       (3)         Based on the experience, the compensation standard is given considering the frame
                   structure, mixed structure, half-timbered structure, simple structure and shed structure.
       (4)        Based on the experience and second-hand house price, the compensation standard for
                  the houses depreciation is regulated in terms of different service life such as less than


                                                      17
 Implementation Planningof Guangzhou Solid Waste DisposalCenter


                               five years, 5-15 years, 15-25 years, 25-35 years and over 35 years. The difference
                               between adjacent grades is 50-10ORMB/M 2.
 2)             Compensation for houses with a record of use history (See Annexed Table
                13.3.2)
The compensation of houses with a record of use history is the construction cost of the houses. The
compensation standard are made referring to "Data Sheet of Urban Privately-built Houses" of "Statistical
Yearbook of Guangzhou".

3)              Compensation for undue temporary construction:
The compensation standard as follows for each square meter of construction area of the central district
houses is according to "Standard and Operation Regulations on Compensation and Resettlement for
Land Requisition and Demolition in Municipal Project":

                                                                                                                                 Unit: Yuan/M 2

                              Structure           P
                                            Frame structure             ~~~~Mixed
                                                                                .            Half-timbered                                   Shed
                                                                                                                     Simple structure
                                                                      construction             structure                                   structure
                              Function      Shops      Others       Shops       Others      Shops        Others      Shops     Others      Others
                                            430         250           350           200      300             150      250       100           50
4)              Moving cost
The compensation standard according to "Standard and Operation Regulations on Compensation and
Resettlement for Land Requisition and Demolition in Municipal Project" are as bellows:

                                                                                                                                 Unit: Yuan/M 2


                                                                                             Moving cost
                                                                Dwelling house             Non-dwelling house with
      Type        CATV           Gaspipeline
                                         Telephone            with property right                  property right
                                                              Above 5 Below 5             Below       50-200      Above          Shops
                                                              people                          2           2              2
                                                                             people       50 m           m          200 m

 Amount           350            3000          400              450           600          100           3000        5000      15 Yuan/
5)            Demolition cost
(1)           The house demolition cost is determined based on the local productive cost, machine cost and
              transportation cost, and the different district and different of floor number as following:

                                                                                                                                 Unit: Yuan/M 2
      Structure                Frame structure                  Mixed construction
                                                                                            Half-timbered           Simple       Shed
                    Floor           Floor      Above       Floor Floor          Above            structure         structure   structure
        Floor
                        1-3         3-6        Floor 6        1-3      3-6      Floor 6
       Class 1
                        65           70           75          55       60           65              45                35          25
       district
       Class 2
                        62           67           71          52       57           62              43                33          24
       district
             Class3 59               63           68          50       54           59              41               32           23
Implementation Planning of Guangzhou Solid Waste Disposal Center

       district
      Class 4
                            55        60              64                47    51     55             38             30         21
       district
      Class 5
                            52        56              60                44   48     52              36             28         20
      district
       Class 6
                            49         53             56                41    45     49             34             26         19
       districtI
The compensation standard according to "Standard and Operation Regulations on Compensation and
Resettlement for Land Requisition and Demolition in Municipal Project" are as bellows:

                                                                                                    Unit: Yuan/M 2

                                            Fence                       Foundation above           Other special demolition
                                                                             30 cm
                                                15                             15                Based on the actual condition
6)          Restoration cost
                                                                                                 Unit: Yuan/M 2
     Frame structure                  Mixed construction                       Half-timbered structure             Simple structure
            100                                      120                                   150                           60
7)          Structures
Compensation standard according to "Standard and Operation Regulations on Compensation and
Resettlement for Land Requisition and Demolition in Municipal Project" as follows:

                                                                                            Unit: Yuan/M 2




                 (1)            °>                                       ~~~~~~~~~
                             Temporary Sdemolition-cost for houses -D property r
                                                             ii
                                                                    with  pD



                                                                    0   ~~~~~~~~~~~                      0~~~~~0

                       8)          demolition
                                 Temporary                 coTomb

                                            CZ~        ~~C




                             The compensation standard is provided according to "Standard and Operation
                             Regulations on Compensation and Resettlement for Land Requisition and Demolition
                             in Municipal Project" and based on the classification of commercial house, office,
                             dwelling house, firm house and warehouse.
            (2)              Cost for temporary demolition of land:
                             Implementation of "Compensation standard for Temporarily BorrowendLiti
                                                                                                  and
                             Houses Built on Household Plot in Public Utility Construction Project of
Implementation Planningof Guangzhou Solid Waste DisposalCenter


                  Guangzhou".
9)      Loss of business suspension (See Compensation standard for Temporarily
        Borrowed Land and Houses Built on Household Plot in Public Utility
        Construction Project of Guangzhou Annexed Table 13.3.8)
The criteria are given according to the provisions regarding commercial house and firm house and
warehouse in "Standard and Operation Regulations on Compensation and Resettlement for Land
Requisition and Demolition in Municipal Project".
10)     Loss due to service in strange district (See Annexed Table 13.3.9 for details)
The demolition and moving will causes certain loss of affected after the relocation point is arranged and
before the business is resumed, therefore, the compensation standard is provided according to Hui Kuo
"Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and
Demolition in Municipal Project".
11)     Cost for pipeline reconstruction
Reconstruction cost for pipeline is determined according to the construction drawing, and the quota
given in "Method on Valuation of Installation Project in Guangdong Province", "Regulation on
Establishement of Items in BOQ for Installation Project in Guangdong Province", "Comprehensive
Norm for Installation Project in Guangdong Province", "Method on Valuation of Municipal Project in
Guangdong Province", "Regulation on Establishment of Items in BOQ for Municipal Project in
Guangdong Province", "Comprehensive Norm for Municipal Project in Guangdong Province", "Budget
Norm for Communication Construction Project" (1995), "Composition of Budgeted Expense and
Computing Standard for Construction of Thermal Power, Power Transmission and Transformation
Engineering" and "Indices for Investment Estimate of Nationwide Municipal Works"(in 1996) of
Construction Ministry, and by the method of engineering budget and final estimate.
 Implementation Planningof Guangzhou Solid Waste DisposalCenter




 5.      Institutional structure of the resettlement and the ability
         building
5.1      Arrangement of Resettlement organization
The concrete arrangement of the resettlement organization of this sub-item is as follows:
 1)      Overall coordination unit of the PAP: Guangzhou Solid Waste Disposal Center
2)       Internal monitor unit: Guangzhou Solid Waste Disposal Center
3)       Independent surveillance unit: (to be determined)
4)       Physical quantity investigation and social economy investigation unit: GZ Road Engineering
         and Expansion Office
5)       Resettlement implementation unit: (to be finally determined)
6)       Other relevant units: Guangzhou Urban Layout Bureau
                               Guangzhou Land & House Administration Bureau
                               Guangzhou Urban House Demolition Management Office
                              Guangzhou People's Court
                               Guangzhou Labor Bureau
                              Town governments and villager's committees with the subitem-related
                              resettlement area

5.2      Responsibilities of Resettlement Organization
For the responsibilities of various resettlement organizations, see chapter 6 of Resettlement Policy.

5.3      Capability construction of resettlement organizations
In order to allow resettlement organizations to be appropriately adjusted and strengthened according to
the characteristics of Guangzhou Solid Waste Disposal Center, it is vital importance to further perfect
and embody the capability construction of resettlement organizations.

5.3.1 Strengthening of Resettlement Organization
1)      Retaining resettlement experts and advisors
Being insufficient experience in resettlement, Guangzhou Solid Waste Disposal Center, which is the
coordination unit of resettlement, will strengthen the resettlement management training as well as retain
resettlement experts and advisors for identifying and solving any issue occurred.
2)      Carrying out unified payment of compensation fund
In order to allow the compensation fund to be timely and safely paid to Liangtian Village, the
resettlement implementation unit is only responsible for the negotiation and subscription of the
Compensation Agreement. And after the Compensation Agreement is signed, Guangzhou Solid Waste
Disposal Center will directly pay the compensation fund to Liangtian Village.
3)      Checking the operation of the compensation fund
Because the compensation fund is directly paid to the Villager's Committee, the independent
 Implementation Planningof Guangzhou Solid Waste Disposal Center

 surveillance unit will check the utilization and effect of the compensation fund so as to ensure that the
 use of compensation fund is in favor of the improvement of the villager living standard or at least
 restoring to the standard prior to the land requisition.
 4)         Special project resettlement office
 Guangzhou Solid Waste Disposal Center will establish the Special Project Resettlement Office under its
 control. In addition to the daily resettlement coordination, this Office will focus on:
        *       Helping the affected of the PAPs to contact relevant social security and aid agencies.
        *       Contacting and introducing part of the villagers for work in the established Industry Park.
        *       Responding to the grievances/appeal accepted by the Appeal Acceptance Group and making
                disposal.
5.3.2       Training plan for resettlement work personnel
In order to allow the resettlement work of Guangzhou Solid Waste Disposal Center to better integrate
with the requirement of the World Bank resettlement work, Guangzhou Solid Waste Disposal Center and
the resettlement implementation units will make concrete training plans for the resettlement management
personnel and implementation personnel by way of combining the characteristics of the sub-item.
1)          Training plan for resettlement management personnel:
            *       Resettlement laws and codes
            *       Management theory and practice of resettlement project
            *       Specific seminar on rural resettlement characteristics and key control points
            *       Rural construction planning
            *       Theory and method for rural resettlement surveillance and assessment (including the
                    basic analysis technique for statistics data)
            *       Planning and organization of the public participation, consultation and investigation
            *       Reviewing succeeded rural resettlement projects
2)          Training plan for resettlement implementation personnel:
            *       Education on rural resettlement laws and codes
            *       Education on World Bank OP/BP4.12 Guideline
            *       Filling and input of standardized resettlement work statistics
            *       Principle and technique for the public participation and consultation
            *       Case analysis and simulation training for rural resettlement
            *       Field training
3)          Notices for the implementation of training plan:
Although the resettlements work of this sub-item and the resettlement work of other three sewage
treatment sub-items are under the management of the owners from different items, both of them belong
to the sub-item of environment project. As the Owner of the project, Guangzhou Solid Waste Disposal
Center will coordinate with Guangzhou Tunnel Development Co., Ltd to adopt the same training
organization and experts as far as possible.
5.3.3       Resettlement work mode
Implementation Planningof Guangzhou Solid Waste DisposalCenter

According to the comparison and analysis of economic contract and responsibility contract that is
conducted in Resettlement Policy, the economic contract would possibly cause the Owner and the
contractor to scrabble for interest, thus causing harm to the PAP's interest. The responsibility contract
would make the both parties to focus their work on solving the problems encountered during
resettlement, thus forming resultant force to promote the development of resettlement work.
Particularly in this sub-item, Liangtian Village is in Baiyun District of Guangzhou city, far away from
the downtown area, and so the quality of farmers is relatively low, and the knowledge of law is less, thus
the farmers are easily satisfied. In this condition, the Owner of the project will adopt the work mode of
responsibility contract so as to enforce the monitoring of the resettlement implementation unit and to
ensure the farmers' interest.
I
Implementation Planningof Guangzhou Solid Waste Disposal Center




6.       Information disclosure plan
6.1      Information disclosure already unfolded
The resettlement range of Guangzhou Solid Waste Disposal Center is relative concentrated compared to
other three sewage sub-items. Therefore, the information disclosure activity is combined with the public
participation. From August to September 2003 when the environment assessment of this project was
conducted, the Owner and the environment assessment group stated the overview and significance of
this project to the Villager's Committee and villagers of Liangtian Village while taking counsel with
Liangtian Village. Meanwhile, the Owner of the project distributed Announcement for Collecting the
Comments on Environmental Impact for the Project-Guangzhou Solid Waste Disposal Center to be
Constructed, and post the relevant information on its website for the PAPs and other non-resettlement
public to access.
In October 2003, GZ Road Engineering and Expansion Office performed a social & economic situation
investigation for the Liangtian Village where the land is to be affected, they brought this village with
rural resettlement policy, laws and possible resettlement period while they were preliminarily understood
the social & economic situation of this village.

6.2     Information disclosure plan in the next stage
With the actual development of the resettlement work, the information disclosure activity will become
more frequent and purposeful so as to match with the progress of the entire resettlement work.
Meanwhile, the information disclosure often inosculates or crosses the public participation and
consultation, therefore, for the next schedule of this work, see table 8-1 "Period Planning table of
Information disclosure, Public Participation ( Consultation) and Monitoring & Assessment".
I   m
 Implementation Planningof Guangzhou Solid Waste Disposal Center




 7.      Public participation and consultation
 During the identification and preparation periods of the sub-item of Guangzhou Solid Waste Disposal
 Center, the design and environment protection departments visited the villagers of Liangtian Village and
 some of the units within the project-affected area, introduced the vision of the sub-item and widely
 collected and heard the comments of the affected people. After having compared the optional sites
 Xingfeng Village, Shantian Village and Liangtian Village, Liangtian Village of Baiyun District was
 finally determined to be the site in which the project is to be constructed on the base of full public
 participation and consultation. After the determination of the site, GZ Road Engineering and Expansion
 Office immediately performed an investigation to Liangtian Village, and heard the comment of the
village cadres and villagers to the land requisition. Meanwhile, GZ Road Engineering and Expansion
Office interviewed some of the large-scaled enterprises along the waste transportation line and heard the
comments of the indirectly affected people, so as to give a consideration when preparing Resettlement
Action Plan.

7.1      Public participation and consultation activities already unfolded
 1)      The public participation in siting: Environmental Protection Bureau in Baiyun District of
         Guangzhou performed a comment survey to Xingfeng site in the form of symposia on January
         10, 2003. The participants of the symposium include: the govemment of Taihe Town,
        Environmental Protection Bureau, Land administration Bureau, Environmental Hygiene Bureau,
        layout Sub-bureau and the resident representatives of Xingfeng Village and Huifeng Village.
        The project environment assessment group of Guangzhou Environment Protection Scientific
        Research Institute held a small symposium in Liangtian Town on September 23, 2003, in which
        the public comment on the site to be selected (Liangtian Site) and the optional site (Shatian Site)
        was surveyed. The participants of the symposia include: the resident representatives of Shatian
        Village and Liangtian Village, and the relevant personnel of Liangtian Town. Through the
        symposium, the investigation comment on the construction project was obtained.
2)      Participation of other public: in order to obtain the recommendation of other citizen to this
        project, the Owner of the project distributed Announcement for Collecting the Comments on
        Environmental Impact for the Project-Guangzhou Solid Waste Disposal Center to be
        Constructed, and post this announcement on its website for the public to access and to express
        opinions, so as to realize the participation of other public.
3)      After Liangtian Village of Baiyun District was determined to be the site of the project, GZ Road
        Engineering and Expansion Office performed an investigation to Liangtian Village in October,
        2003, and got to know the social & economic situation of this village, the impact of the land
        requisition on the production and life of the villagers, and the comment and suggestions of the
        villagers to the resettlement compensation.
4)      Participation of the units along the solid waste transportation line: GZ Road Engineering and
 Implementation Planningof Guangzhou Solid Waste Disposal Center

         Expansion Office interviewed some of the units along the solid waste transportation line in
         October, 2003, and heard the comment of the indirectly affected people to the possibly potential
         impact, so as to realize the full participation of indirectly affected people.
 Units along the transportation line that have been interviewed:
(1)      Sinnopec Guangzhou Petrochemical Complex:
         Shihua Road       -   -     Dasha East Road (Huangpu Young Palace)               --      Guangyuan East
         Road(Olympic Sports Center, Guangzhou Honda Factory Area)                       Taihe Road (Taihe Town,
         Guangzhou Yanggang Psychosis Hospital, Guangzhou No 15 Middle School,                      Penitentiary of
         Guangzhou Public Security Bureau)                   Shatai Road (Youth Cadre Institute, Sanjiu Brain
         Hospital, South Hospital, No. 1 Surgeon University,             Guangzhou Economy & Trade Institute,
         Guangdong Xinan Institute, Guangzhou Traffic Vestibule School and Guangzhou Friendly
         Hospital)         Liangsha Road-Disposal Center
(2)      Guangzhou Huali Pigment Chemical Co., Itd.:
         Nangang West Road               Guangshen Highway (Guangzhou No 87 Middle School, Huangpu
         District Hospital) -- Guangyuan East Road (Olympic Sports Center, Guangzhou Honda

         Factory Area) -- Taihe Road (Taihe Town, Guangzhou Yanggang Psychosis Hospital,

         Guangzhou No 15 Middle School, Penitentiary of Guangzhou Public Security Bureau)
         Shatai Road (Youth Cadre Institute, Sanjiu Brain Hospital, South Hospital, No. 1 Surgeon
         University,   Guangzhou Economy & Trade Institute, Guangdong Xinan Institute, Guangzhou
         Traffic Vestibule School and Guangzhou Friendly Hospital)                   Liangsha Road-Disposal
         Center
(3)      Guangzhou Zhujiang Steel Co., ltd:
         The     company       --Xiji      Industry   Park   -   -   Xiagang    Avenue   (Guangzhou     Economic
         Developing-area) -- Guangyuan East Road (Olympic Sports Center, Guangzhou Honda

         Factory Area) -- Taihe Road (Taihe Town, Guangzhou Yanggang Psychosis Hospital,

         Guangzhou No 15 Middle School, Penitentiary of Guangzhou Public Security Bureau)
         Shatai Road (Youth Cadre Institute, Sanjiu Brain Hospital, South Hospital, No. 1 Surgeon
        University,    Guangzhou Economy & Trade Institute, Guangdong Xinan Institute, Guangzhou
        Traffic Vestibule School and Guangzhou Friendly Hospital) -Liangsha                    Road-Disposal
        Center
(4)     Guangzhou Shenli Electronic Scientific & Technology Co., ltd:
        The company            Guangcong Road          Liangsha Road           Treatment Center
(5)      1st Factory of Guangzhou Flashlight Industrial Corporation:
        The company                106 national highway          North tai Road (Guangzhou Xingzhi Institute,
        North Village of Longgui Town) -- Guangcong Road--Liangsha Road--Disposal
        Center
 Implementation Planningof Guangzhou Solid Waste Disposal Center

 (6)       Guangzhou Steel Co., ltd:
           The company       Fangcun Avenue (Workers Hospital of Guangzhou Steel Co., ltd, Guangzhou
           Hospital) Hedong Road--Huadi Avenue--Zhujiang                  Tunnel--Inner Loop--
           Guangcong Road       Liangsha Road        Disposal Center
(7)        Guangzhou Thermal Power Plant:
           This plant    Dongfeng West Road          Zengcha Road-Inner Loop            Guangcong Road
               Liangsha Road       Disposal Center

7.2        Achievements of public participation and consultation activity
1)         Determination of the site
After the above consultations and symposia, the public comments of various sites are as follows:
Comments about the Xingfeng site:
The optional Xingfeng site is a protective zone of basic farmland, around which there are Tongluo Bay
Forest Ecological Park, Maofeng Shan Mountain Forest Natural Reserve and Helong Reservoir, and so
the environmental and geographical location are very special and sensitive.
Xingfeng site is in Taihe Town. According to Guangzhou North Priority Strategy and Taihe Planning and
Development, the green scientific & technological gallery to be constructed in this area would play
inestimable adjustment role for Guangzhou atmosphere. After the establishment of the solid waste
disposal center, the released waste gas and the to-and-fro waste transportation trucks would cause
all-round negative impact to this area.
There has been constructed a domestic waste landfill yard in Xingfeng. Because of large flow of garbage
trucks, the wastewater flowing out of the garbage trucks and the dropped garbage make the road to
become black and odorous and to emit repulsive odor, for which the local residents have bad opinions.
Therefore, for the solution of construction of solid waste disposal center, the local villagers take issue
with it.
To sum up the above comments, Environment Protection Bureau of Baiyun District recommended that
the solid waste disposal center be localized in another place.
Comments about the Shatian Village site:
Shatian Village has more than 9000 Mu of mountainous area, and its geographical environment is
suitable for constructing landfill yard. The Villager's Committee of Shatian Village held a meeting for
discussion and put this matter to the vote, and the passed by a unanimous vote. This indicated that the
villagers are very pleased for the construction of the disposal center.
Although the siting of Shatian Village obtained the support of local govemment and villagers,
Guangzhou Urban Layout Bureau verified (Huigui[2003]401) that the siting was inconsistent with the
overall urban layout, and this siting shall not be determined and constructed until professional
department have demonstrated and justified and adjusted according to legal procedures.
Comments about the Liangtian Village:
Liangtian Village has plenty of hill area and land, with population being above ten thousands. Since the


                                                     I17
 Implementation Plaining of Guangzhou Solid Waste Disposal Center

 income in this village is low, the villagers believe that the development of this area can promote the
 economic development; therefore, they support the construction of the disposal center in this village.
 With respect to the environment pollution after the establishment of the project, the villagers of
 Liangtian Village think there may be certain pollution, but if the construction and management of this
 project are strictly according to national standard, the environment pollution can be minimized, thus this
 village would be less affected.
 After site comparison and having fully taken counsel with the affected people, Liangtian Village of
 Baiyun District was finally determined to be the site for the project.
 2)       Determining the focus of the resettlement work within this project area
 After the social & economic investigation of the resettlement of Liangtian Village, the focus of the future
resettlement work is determined:
Most of the land to be affected this time is woodland, and only small part of it is infield, and so the land
requisition does not involve the villager's houses, and impacts less on the production and life of the
affected people.
The villagers' income is a little low. According to the information supplied by the Villager's Committee,
the per capita annual income was 6301yuan RMB (525yuan RMB/month) in 2002, slightly higher than
the minimum living security line (422yuan RMB/month) of laid-off employee of Guangzhou city.
Therefore, the villagers hope to build the road through this project and to obtain certain job opportunities
after this project has been constructed.
At present, an industry park is being constructed in Liangtian Village of Baiyun District. Therefore, the
villagers hope to use the land compensation fund of this project to invest in the construction of this
industry park, so as to promote the village's economic development.
The villagers of this village are little educated and have weak legal consciousness. Therefore, the
Villager's Committee hopes to be given more explanation and instructions on resettlement laws and
policy in the next PAP participation activity.
Also, the Villager's Committee hopes that the representatives of villagers can participate in various
decision-making meetings of the project and understand the project schedule and work method so as to
carry out surveillance to this project.
3)       Collecting      the comments of the affected people along the solid waste
         transportation line
        (1)      The transportation trucks and technology used for the project shall meet relevant
                   national regulations and technical standards, risk management system shall be
                 established for responding to any unexpected accident along the line, relevant measures
                 and systems shall be opened to the public and be supervised by the public.
       (2)      For the greatly affected units along the line, after review and verification, the concerning
                 departments shall take resettlement measures.

7.3     Public participation and consultation plan in the next stage
Based on the above-mentioned public participation and consultation results, Guangzhou Solid Waste
Implementation Planningof Guangzhou Solid Waste Disposal Center

Disposal Center, the resettlement implementation units and independent surveillance organizations
carried out purposeful public participation and consultation activities respectively so as to help the
project management to continually improve resettlement plan and resettlement work, allowing the PAP's
living standard to improve or to at least restore to the former standard prior to the construction of this
project, these activities include:
1)       Giving explanation to the villagers of Liangtian Village on Resettlement Policy, laws & codes
         and appeal procedure of this project so as to assure the lawful rights and interests of the villagers
         during resettlement.
2)       As for arranging the villagers to work in the established Guangzhou Solid Waste Disposal
         Center, employment symposium shall be held to make the public know the possible employment
         posts and concrete post requirements, and relevant matter shall be discussed as well.
3)       After the project has been established, the units along the solid waste transportation line shall be
         interviewed to hear the comments, and the consideration if a subsequent resettlement is needed
        shall be taken.
For the next detailed period planning on public participation and consultation activity, see table 8-1
 "Period Planning table of Information Disclosure, Public Participation ( Consultation) and Monitoring
& Assessment".
Implementation Planninigof Guanigzholu Solid Waste Disposal Center




       Rlft     fFi                                                     MSB
                                                                         laf            AtWt~*if



2002. 11-                                                            >f>M]        iH   ,X   t      g   S        tt'l
 2003.11                                                                                                    J




  2003. 1     niFx fffA1oX91                                                                                               ~F




 2003. 81                         f i      it         Jf J                                             il          4   1    &
                                                                                                                            kW        BIt4fJ5
                2003. 9t                        &)WtAiA                                At                                   A   AY3




                                                                             30
Implementation Planning of Guangzliou Solid Waste Disposal Center




    |        W   ;2                     elKgilR lli                                             2>'r 1                          1


 2003. 10


                      gtM R~~~~~~H 1i)<l%
                                      Xl3 * 4A,tt
                                          t,




 2003. 11                                 vii -2-1
                                               llf       A




 2003. 11
                                                                                                     KFifLi                         2)J&
                                                                                                                                     TRA




 2003. 11    HA X MdL ..
               tiSgRLXM8t,
                   1Vu          ,r4'l                I       J




                                                                         _. Cg< Wt-
                                                                                 r,   i I r HOD 9:       L   :   .   W#'SITti




                                                                    31
Implementation Planning of Guangzhou Solid Waste Disposal Center




                                                                               H E afl ±il- W
                                                                                       IYIIfITm±




                                                                        '6-4k@84t
                                                                              R1
                                                                             H1 4J41~h             -IlIi   0.   l '

                                                                          fI    A
                                                                               KA]                 >




 2003. 12   rfiJ
              Z       M(QF M ff ii±-A         :r41 f   T




                                                                   32
Implementation Planningof Guangzhou Solid Waste Disposal Center




                                                                 A         ., 4;Ipp)t b'4-.
                                                                                 41RG
                                                                       -,Z NW E(:WfR.A# 2




                                                                                                                                       4 jI,.flt
                                                                                                                                           mi't    Irri-



                                                     ;z
                                        t13J' Et§iT "ttltJ'@1t                                                  V1'    .2 '
                                                                                                                        !II   HJIAW
                It |.Jill It
                       4        fttL"       -A                                                                  S H'i ml: t;
                                                                                                                tt#4fF9MP
                                                                                                                       1
                  _4sn         4k, Thffifl1fLit- &        4Th                                                   iT      ttIW 5 T
                                                                                                                             #A




                                                                                              ~h~Ifltiii~ThtU   A A 4&            14
                                                                                                                                 4+1                       20044i-5
                                                                     UFM'IR1f AI
                                                                          M-k                                   I. t'it±l                                  )pIfl4fft Y
2003. 12-                                                                                                                                                     P
  2004.3
       3'__                                               _;_                                                                                      _




                 b=B:2At       W09f,2MMWTAIFV, Aff,91                                                           \ZR3




                                                                                   33
Implementation Planning of Guanigzhou Solid Waste Disposal Center




  2004. 67        tfa ffl,I
                        ME              f:-                                              l   0   Ii,'IlUl
  2004. 7                                                                                                   y
                                                                                                            VI '-F''!   frp       ~~2005   #S   1




                                                                                                          tit JgF
                                                                         ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~f It' tEt"
2004.12                       t:129-W@l'aiWlits \                                       tJIItIr-.,-lta            .d                   X2




  2005. 34-




                                               M
           ~2kT W&A
     2005.1>-                 KlAHPLV               k   kltU 'V                                  I "']411
  2005.312

                                    :              , . T11 F " ^
                                                         t                                                                         2       WB
  2005. 12      FxA [fl- ft
                  av-A         3f       !.




 2005. 13-                    titYait9V             A      t7, I                                       t                               tR-
 2005. 12         ±8;,g i
                 []r                                                                                                                       x
                              bW&             JP'tWzldz4fThIVPJ3



                                                                    34
Implementation Planningof Guangzhou Solid Waste DisposalCenter




                            psirStA¾jTh      I'2E, au                                 ','171.lJZ   -',




                                                         't}!Q& tR±K1A                        ,    1
                                                         FMfA'- IRM, IXA]M   4M
                                                                              WAtS          27RA
                                                                                             -4:t@f
                                                                                                Mi




 2005. 12                                                                            vi   I.: I1
                                                                                                             2006 4p 1
                                                                                                         .   11,
                                                                                                             fm1 m




                                                                       35
Implementation Planningof Guangzhou Solid Waste Disposal Center
 Implementation Planning of Guangzhou Solid Waste Disposal Center




 8.       Monitoring and evaluation
 8.1      Internal monitoring
 The resettlement work of "Guangzhou Solid Waste Disposal Center"           project has been received the
 internal monitoring from Guangzhou Solid Waste Disposal Center since the project was determined. In
 fact, Guangzhou Solid Waste Disposal Center has not only monitored all the first-phase preparations of
 resettlement work of the project, but also coordinated the work relation and content of relevant units. In
 addition, Guangzhou Solid Waste Disposal Center has actively participated in various concrete work
 related to the resettlement, including the preparing Resettlement Policy of the overall project and
 Resettlement Action Plan of the sub-item, as well as solving the problems encountered during the
preparation of these reports.
In the next stage, Guangzhou Solid Waste Disposal Center will continually carry out internal monitoring
for the Liangtian Village resettlement work conducted by the resettlement implementation units,
according to the arrangement of    "Period Planning table of Information Disclosure, Public Participation
(Consultation) and Monitoring & Assessment" and the specification, format and requirement specified in
Resettlement Policy; and submit internal monitoring report to the World Bank according to the relevant
specifications in Resettlement Policy.

8.2      Independent supervision
At present, the candidates for the independent organizations initially determined by the general project
are as follows:

       *The resettlement bureau of the yellow river conservancy committee

       -Guangdong provincial social science academy

       *The Chinese race group study center of Zhongshan University
The project employer will choose one of the above organizations as the independent supervision
organization of the general project and the sub-item, after the confirmation and putting on the record of
the World Bank. The independent supervision organization selected will do its work of independent
supervision and evaluation according to the time planning table of " the opening of the information,
public participation and consultation and the supervision and evaluation". Among which the main
attentions are as follows:
1)       Monitoring the use of the land compensation fund, namely, whether a democratic mode is
         adopted to determine the use of the compensation fund and whether there is any evidence of
         appropriation.
2)       Monitoring the investment results of the land compensation fund and identifying whether the
        use of the compensation fund is in favor of the improvement of the villagers living standard.
3)      Monitoring the pollution extent of the project to the surrounding environment after the project
Implementation Planningof Guangzhou Solid Waste Disposal Center

        has been established and whether the health of the PAPs is affected.

8.3     Schedule of the information publishing, public participation and
        consultation and supervision and evaluation
In the whole process of resettlement work, the activities of the opening of information, the public
participation and consultation and the supervision and evaluation are done in interlude each other and the
activities of opening information and public participation and consultation is the major measure of the
supervision and evaluation. Therefore, the both can not be completely separated. The work content
described in "information disclosure" and "public participation and consultation" is also the important
content of "monitoring and assessment". For the overall arrangement of the next step, see table 8-1
 "Period Planning table of Information Disclosure, Public Participation (Consultation) and Monitoring
& Assessment". During the in-service use of table 8-1, the following items shall be paid with attention:
1)      This period planning table will be appropriately adjusted according to the engineering schedule
        of Guangzhou Solid Waste Disposal Center sewage project.
2)      The frequency and content of various work tasks listed in this table may be increased as
        required.
3)      The independent surveillance organizations shall make annually detailed work plan by using this
        table as program.
Implementation Planning of Guangzhou Solid Waste Disposal Center




9.      Cost estimate and fund plan of the project
9.1    Description of project estimate
1)     The explanation of the land requisition and demolition budget

      (1)     The problems of regions.

              The budget is established according to the price in the regions where the sub-item is
              dominantly located so as to avoid the complexity of data. The future compensation will
              also follow the practical standard.

      (2)     The problems of depreciation.

              As the detailed investigation to find out the real intention has not been completed, the
              present cursory inspection showed that the fixed number of years of depreciation of the
              demolition houses is centered in the period of 5-20 years.

      (3)     Houses with a record of use history and the temporary demolish compensation standard.

              The compensation standard of the house with a record of use history would be divided
              according to their floors and structures. The difference of floors leading to large
              difference of price therefore, the 3-5 floors price calculation is adapted. The temporary
              demolition is a kind of could -be built demolition so, the compensation standard is the
              repeat establishment price of construction. That is to say, it is the same as the houses
              with a record of use history compensation standard. The future compensation will also
              follow the practical standard.

      (4)     The expense of knock down.

              The knock down expense criteria is divided according to the floors and structures. The
              difference of floors leading to large difference of price therefore, the 3-5 floors price
              calculation is adapted. The future compensation will also follow the practical standard.

      (5)    The problems of temporary demolition expense.

             For the partially demolished houses, their temporary demolition square meters will be
             determined according the real conditions. If the budget could not be determined, it can
             be estimated according to 1.5 times by experience.

      (6)    The problems of the time of temporary demolition.

             The temporary resettlement period for the partial demolished houses is set in half a year.
             The temporary resettlement period of the temporary requisition houses which will be
             rebuilt is set in one year. The temporary resettlement period of land, including the period
             of construction and rebuilding is set in half a year together.
    Implementation Planning of Guangzhou Solid Waste Disposal Center

          (7)      The expense of house repair.

                   It is calculated according to the difference of structures and the left square meters after
                   the demolition.


                                                                                         Unit:     Yuan/M 2

                      Frame work               Mixed           Brick and wood              Simple

                            100                 120                    150                   60

          (8)      Various miscellaneous expenses:

                   It includes the expenses of: the end case of land requisition, demolition administration
                   and the mapping, requisition and examination, and the notarization of the demolition
                   notice; they are calculated according to houses with property right30Yuan/M 2 .

          (9)      The unpredictable expense: The unpredictable expense of pipeline transfer is calculated
                   by 10%; the unpredictable expenses of demolition by 5%; and no unpredictable expenses
                   for land requisition.

          (10)     The problem of the knock down area:

                   It includes the mature temporary building areas and the peccancy building areas, which
                   will not get the compensation.

          (11)     The problems of land compensation standard.

                   Because the village boundary is not clear, the compensation standard is set according to
                   the average value of the same kind of land in the same district. The compensation will be
                   given according to the practical criteria after the village boundary is clear by the further
                   inspection.

          (12)    The problems of capital apportion.

                   The capital is planned to be shared equally every month. At present, the construction
                   schedule of each pipeline could not be determined for lacking of detailed material
                   descriptions. Therefore, the time limit of demolition is temporarily set at half a year
                   before the construction schedule to the start of construction. The capital in every month
                   is required to be shared according to proportion:

                   The first      The second    The third      The fourth    The fifth   The sixth
      Month
                    month           month         month          month        month        month

    Proportion                       15%          20%            250            25%         100
[     shared

9.1.2     The descriptions of pipeline transfer estimation.

                                                          AA
Implementation Planningof Guangzhou Solid Waste Disposal Center

      (1)       The project amount is estimated by the stat data of the pipeline electronic map of the
                planning bureau and the integrated unit price of the project is estimated by the Budget
               Estimate Indices for Demolition and Relocation Of Pipeline in Municipal Engineering of
                GZ Road Engineering and Expansion Office.

      (2)      Because the data of the pipe line electronic map of the planning bureau is not full, much
               pipe line materials can not be known correctly, such as: the types of pipe channel, the
               number of pipe holes, the models of electric (light) cable, the installations in the
               transformer substation, the thickness of pipe wall, etc., all of them can not be known
               clearly. Then these data can only be estimated by the normal standard and the practical
               work experience in many years.

      (3)      The estimated pipeline distance is mostly the direct distance of the would-be-transferred
               pipeline between the two pipe wells. In general cases, the length of the transferred
               pipeline is 1.2-1.35 times of direct distance. Considering that the pipe line transfer
               caused by the project is a zonal sewage pipe network, the transfer amount of the existing
               pipe line could be reduced by the optimization of design and the technical measure of
               engineering during the implementation of the sub-item. Therefore, the estimation of the
               project does not take the transfer as multiple.

      (4)      Because of the reason above, the estimation of pipeline transfer is not accurate. Then it is
               not called the budget but the estimation.

9.2    Compilation standard for and explanation of pipeline estimation
1)    The Budget Estimate Indices for Demolition and Relocation of Pipeline in Municipal
      Engineering is drawn for the purpose of reasonably and correctly control of the project
      investment of down planning, strengthening the investment administration of our office to the
      town planning construction, the macro control, regulating the management of project budgetary
      estimation, and the control of project cost (hereafter it is called this criteria).
2)    Compilation index for budgetary estimation
      (1)      "The Indices for Budgetary Estimate of Power Transmission and Distributing Line
               Engineering"

      (2) "The Indices for Estimate of Water Supply Engineering"

      (3) "The Indices for Estimate of Gas Engineering"
      (4) "The Indices for Estimate of Communication Engineering"
      (5) "The Budget Estimate Indices for Cable Television Engineering (it is not perfect)"

      Among which, "Budget Estimate Indices for Cable Television Engineering" has not been
      completed yet.

3)    The basis of compiling the budgetary estimate
Implementation Planning of Guangzhou Solid Waste Disposal Center

      (1)     " Method on Valuation of Installation Project in Guangdong Province"
      (2)     "Regulation on Establishment of Items in BOQ for Installation Project in Guangdong
              Province"
       (3)    "Comprehensive Norm for Installation Project in Guangdong Province"
       (4)    "Method on Valuation of Municipal Project in Guangdong Province"
       (5)    "Regulation on Establishment of Items in BOQ for Municipal Project in Guangdong
              Province"
       (6)    "Comprehensive Norm for Municipal Project in Guangdong Province"
       (7)    " Budget Norm for Communication Construction Project (1995)"
       (8)    "Composition of Budgeted Expense and Computing Standard for Construction of
              Thermal Power, Power Transmission and Transformation Engineering"
       (9)    "Indices for Investment Estimate of Nationwide Municipal Works (1996,drawn by the
              state construction department) "
       (10)   "Guiding Price for Engineering Materials in Guangzhou Region (The document of the
              ration station of Guangdong provincial electric power construction issued in the first
              quarter of 2003, Number YDD 2003. 2)"
       (11)   " Budgetary Price for Materials Used in Electric Power Facilities"
       (12)   "The 2002 Collection of Nationwide Prices for Conventional Plant Used in Electric
              Power Engineering (the telecommunication material price by post and telecommunication
              department, 94 edition)"
       (13)   "The city planning park document No. 1997.338"
4)    The composition of budgetary estimate index
       (1)    The unit project cost.
       (2)    Other expenses of project (Referring to the projects of demolition, repair and so on
              related to the main project in the unit project cost).
       (3)    The safety measure expense.
       (4)    The design expense.
       (5)    The road compensation expense.
       (6)    The water consumption expense.
       (7)    The stoppage expense (in telecommunication project).
       (8)    The prepare expense.
       (9)    The administration expense of construction unit.
               Among the index mentioned above, the expenses of road compensation, water
               consumption and stoppage are great and it is more difficult to determine correctly.
5)    The principle of pipeline budgetary estimate.
It is regulated by the state that the principle of "Static control and dynamic management" should be
followed in the implementation of project budgetary estimate. Once it is examined and approved, it
should not be adjusted at random. The principle of "the budgetary estimate should not exceed the


                                                     Al
Implementation Planningof Guangzhou Solid Waste Disposal Center

assessment and the budget should not exceed the budgetary estimate" should be implemented in the
process of construction. When the intending practical investment of the project exceeds the budgetary
estimate, the analysis report must be brought forward and it could be carried out only after the approval.
6)        This index does not include the 10kv built-on-tilts isolated leads and the plastic-steel pipe and
          plastic pipe in the low-pressure line project, water supply and gas project.
7)        This budgetary estimate criterion is only used in compiling the pipeline budgetary estimate. The
          amount of future practical compensation will be calculated according to the pre-balance criteria
          of the project.

          Annex:

          (1)      "Indices   for Budgetary Estimate     of Power Transmission           and Distributing Line
                   Engineering (Annex 18.2.1-1, Annex 18.2. 1-2, and Annex 18.2. 1-3)"

          (2)      "Indices for Estimate of Water Supply Engineering (Annex 18.2. 2)"

          (3)      "Indices for Estimate of Gas Engineering (Annex 18.2. 3)"

          (4)      "Indices for Estimate of Communication Engineering (Annex 18.2.4-1. Annex 18.2.4-2)"

9.3        Project budget
1)         The budgetary estimate for the overall project is 35,341,444.35yuan RMB in total
 1. Permanent requisition
 compensation for houses with
 property right
   1.1 dwelling houses
   1.2 commercials
   1.3.offices
   1.4. Workshops
     1.5 total
     2.houses built on household plot
     2.1 frame structure
     2.2 mixed structure
     2.3 half-timbered structure
     2.4 simple structure
     2.5 shed structure
     2.6 total
  3. Temporary requisition
 compensation for houses with
 property right and houses built on
 household plot
  3.1 frame structure
  3.3 mixed structure
  3.3 half-timbered structure
  3.4 simple structure
  3.5 shed structure
     3.6 total
     4. Compensation for houses with a
Implementation Planning of Guangzhou Solid Waste Disposal Center


 record of use history
  4.1   frame structure
  4.2   mixed structure
  4.4   half-timbered structure
  4.4   simple structure
  4.5   shed structure
  4.6 total
  5. Undue temporary construction
  5.1 commercial purpose
  5.1. Iframe structure
  5.1.2mixed structure
  5.1.3half-timbered structure
  5.1.4simple structure
  5.1.5shed structure
  5.1.6 sub-total
  5.2 other purpose
  5.2. 1frame structure
  5.2.2mixed structure
  5.2.3half-timbered structure
  5.2.4simple structure                  504.10           200.00             100,820.00
  5.2.5shed structure                    624.30           100.00             62,430.00
  5.2.6 sub-total                         1,128.40                           163,250.00

  5.3 total                               1,128.40                           163,250.00
  6. Land compensation
  6.1 infield                              42.89                8.16      3,499,824.00
  6.2woodland                             113.84                5.93      6,750,712.00
  6.3garden land                          139.30                5.93      8,260,490.00
  6.4 pound                                 2.01                7.89          158,589.00
  6.5other agricultural land                2.36                5.93          139,948.00
  6.4 total                                 300.40                         18,809,563.00
  7.temporary demolition expenses
  7.1houses with property right
 temporary demolition expenses
  7.1.1 dwelling houses
  7.1.2 commercials
  7.1.3 offices
  7.1.4 workshops and warehouses
  7.1.5sub-total
  7.2 expenses for temporarily
 borrowed land
  7.2.1 expenses for temporarily
 borrowed infield
  7.2.2 expenses for temporarily
 borrowed construction land
  7.2.3 expenses for infield
 rehabilitation
  7.2.4 compensation for young crops
  7.2.5 sub-total
  7.3 total                                          __    __   _   ___                    __   _




                                               AA
Implementation Planning of Guangzhou Solid Waste Disposal Center



  8. Expenses for rehabilitating
 houses with property right
  8.1frame structure
  8.2mixed structure
  8.3half-timbered structure                                                                   _
  8.4simple structure
  8.5shed structure
  8.6 total
  9. Compensation for requisitioning                                                                17,250.00
 structures
  10. Other compensation expenses                                                                                       =
   10. Ishutout loss
   10.2 strange land business loss
   10.3 moving expenses                        1,128.40        10.00                                 11,284.00
   10.4 telephone transfer charge
   10.5CATV transfer charge
   10.6 tube coal gas transfer charge                                                                                   =
   10.7 total                                  1,128.40                                              11,284.00
   11. House demolition expenses
   12. Tree transfer charge                    1,606.00      533.16                                 856,250.00
   13. pipeline transfer charge
   13. lpower cable conduit
   13.2 telecommunication cable
 conduit
   13.3 coal gas, water supply and other
 industrial pipelines
  13.4 total
  14.expenses for demolition notice,
 survey, land requisition review and                           30.00
 notarization
  15. Expense for ending land                    300.40    40,000.00                   12,016,000.00
 requisition
   16. Administration expenses for
 demolition
  17. Unpredictable expenses
   17.1 Unpredictable expenses for                                                         1,593,679.85
 land requisition and house demolition
   17.2 Unpredictable expenses for
    pipeline transfer
   17.3 total                                                                                   1,593,679.85
   18. Expenses for resettlement work
   18.lexpenses for resettlement                                                               334,672.77
 planning                                                              _   _   _   _   _   _    _   _   _   _   _   _


  18.2 expenses for resettlement                                                               167,336.38
      monitoring & assessment
  18.3 expenses for social & economic                                                          100,401.83
 assessment
  18.4 expenses for resettlement                                                               267,738.21
 surveillance and management
  18.5 expenses for resettlement                                                           1,004,018.31
 implementation                                        _                                       ,_
   18.6 total                              _1,874,167.50
Implementation Planningof Guangzhou Solid Waste DisposalCenter


!   19. Sum total                   !            1          1    35,341,444.35
Implementation Planningof Guangzhou Solid Waste Disposal Center

2)         Detailed composition
                                                      Unit rice for   Unit price for
                       Q'ty                                land        resettlement         Compensation
        Item            MU)            Unit        compensation        grant-in-aid          sum (Yuan)
                                 Mu)             ~~~~(ten thousands   (ten thousands
l__________                                           Yuan/Mu)          Yuan/Mu)
    Infield           42.89             Mu                 4.45           3.71              3,499,824.00
   Woodland           113.84            Mu                  3.71          2.22              6,750,712.00
  Garden land         139.30            Mu                 3.71           2.22              8,260,490.00
     Pound             2.01             Mu                 5.67           2.22               158,589.00
     Other
  agricultural         2.36             Mu                3.71                2.22           139,948.00
      land
    Subtotal           300.40                                                               18,809,563.00
 Remark: the land    requisition data excludes the road outside the site.

        Item        Structure      Area   (i)          Unit price     Compensation
                                                       (yuan/m2 )      sum (Yuan)
     Duck shed         Shed            624.30            100.00             62,430.00
                     structure
     Henhouse         Simple           504.10            200.00         100,820.00
                     structure
   Sub-total                    1,128.40                    163,250.00
 Remark: this area belongs to non-layout control area, the structures are
 compensated as houses with a record of use history.

                     Diameter
       Name           breast       Unit (tree)         Unit price      Budget sum
                   N height        U    (             (tree/Yuan)        (Yuan)
                       (CM)        _             L_l_                                   I
        Lichi           5-15            348               1000           348000
____________       |16-25                96               2000            192000
     Orange tree        5-15             222              400             88800
       r
       Copse       l    5-15             677              200             135400
       Coe          1 16-25             263                350            92050
      Subtotal                          1606                            856,250.00

                     Quantity      Unit price         Sum (Yuan)
      Pound           120m33            125r      _        _15000_l

     enclosure        1                 1                150
        Rail            90              25               2250
                                                         17250