Project Name:
Nb. 1 2 3 4 Item Description Design Development Testing Documentation
ABC Project
Start Date 2/20/2009 2/24/2009 2/27/2009 3/4/2009 End Date 2/25/2009 3/3/2009 3/7/2009 3/19/2009
Project Position by /aa/2009
10
Number of Assigned Items: Number of Unssigned Items: % 100.0 (4 items) of the project has been completed. 2 items have been completed late 2 items have been completed early or on time Total Number of Days Behind Schedule: Total Number of Days Ahead of Schedule: 7 1 3 1
9
8
7 6 5 4 3 2
1
0
Days -
Assigned To
Paul Smith Jennifer Young Jane Doe Not Assigned
Completed? Yes Yes Yes Yes
Completion Date 2/25/2009 3/4/2009 3/6/2009 3/25/2009
If Completed Completion Note
Delay 0 1 -1 6 -
Gannt Chart
5
10
15
20
25
2/20/2009
Day
Delay 0 1 -1 6 -
30
Project Item Tracker
1) 2) 3) Fill the project teams/personnel list on the right. You may leave the unused ones blank. Fill the item list. You may leave the unused ones blank. Type the name of the project: ABC Project Project Item Tracker is ready to use. Project items can be scheduled using the Project Schedule sheet by entering the start and end dates. Items can be assigned to project team members. Gannt chart of the project schedule will be created and an analysis of the situation of the project will be provided. Project Team/Personnel List 1 P