					                                                                 Chris Bassett Eagle Project Schedule                                                 9/3/2011




                                                       #                                        Pre
Step   TASK                                   HOURS PEOPLE TOOLS NEEDED SUPPLIES NEEDED 6/11 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/20 6/21 6/22 6/23
 1     write project plan                       21    me                                          14
 2     review with scoutmaster                   4    me                                            4
 3     schedule conservation commission          1    me                                            1
 4     survey some signs                        30         pencils,                                 2 18 10
                                                           notebooks, digital
                                                           cameras, maps,
                                                           cars
 5     brief conservation commission             3    me                                            3
 6     get signatures                            2    me                                            2
 7     inventory signs                          96         pencils,
                                                           notebooks, digital
                                                           cameras, maps,
                                                           cars
  8 build inventory database                    21                                                  2
  9 select signs for repair                      2
 10 repair signs                                48         tarps, hammers,    sand paper, brush
                                                           saws, hedge        cleaner
                                                           trimmers, router,
                                                           template,
                                                           manpower charts,
                                                           wire brushes,
                                                           scrapers, maps,
                                                           work gloves
 11 complete project report                      6    me
 12 coordinate with conservation commission      2    me
 13 get approvals for project results            3    me




967d5bf9-9a16-409e-8324-d7cbdb83e17e.xls                                                                                                            page 1 of 5
                                                                  Chris Bassett Eagle Project Schedule                                                                   9/3/2011




Step   TASK                                   HOURS 6/24 6/25 6/26 6/27 6/28 6/29 6/30   7/1   7/2   7/3   7/4   7/5   7/6   7/7   7/8   7/9 7/10 7/11 7/12 7/13 7/14 7/15
 1     write project plan                       21                         1    1    1     1                 1     2
 2     review with scoutmaster                   4
 3     schedule conservation commission          1
 4     survey some signs                        30



 5     brief conservation commission             3
 6     get signatures                            2
 7     inventory signs                          96



  8 build inventory database                    21                                                                                                                 2       2
  9 select signs for repair                      2
 10 repair signs                                48




 11 complete project report                     6
 12 coordinate with conservation commission     2
 13 get approvals for project results           3




967d5bf9-9a16-409e-8324-d7cbdb83e17e.xls                                                                                                                               page 2 of 5
                                                                  Chris Bassett Eagle Project Schedule                                                                9/3/2011




Step   TASK                                   HOURS 7/16 7/17 7/18 7/19 7/20 7/21 7/22 7/23 7/24 7/25 7/26 7/27 7/28 7/29 7/30 7/31   8/1   8/2   8/3   8/4   8/5     8/6
 1     write project plan                       21
 2     review with scoutmaster                   4
 3     schedule conservation commission          1
 4     survey some signs                        30



 5     brief conservation commission             3
 6     get signatures                            2
 7     inventory signs                          96                                       24   24                                                                      24



  8 build inventory database                    21           2                                      2    2
  9 select signs for repair                      2
 10 repair signs                                48




 11 complete project report                     6
 12 coordinate with conservation commission     2
 13 get approvals for project results           3




967d5bf9-9a16-409e-8324-d7cbdb83e17e.xls                                                                                                                            page 3 of 5
                                                                   Chris Bassett Eagle Project Schedule                                                            9/3/2011




Step   TASK                                   HOURS   8/7   8/8   8/9 8/10 8/11 8/12 8/13 8/14 8/15 8/16 8/17 8/18 8/19 8/20 8/21 8/22 8/23 8/24 8/25 8/26 8/27 8/28
 1     write project plan                       21
 2     review with scoutmaster                   4
 3     schedule conservation commission          1
 4     survey some signs                        30



 5     brief conservation commission            3
 6     get signatures                           2
 7     inventory signs                         96     24



  8 build inventory database                   21            3     3    3
  9 select signs for repair                     2                            2
 10 repair signs                               48                                                                                                           24     24




 11 complete project report                     6
 12 coordinate with conservation commission     2
 13 get approvals for project results           3




967d5bf9-9a16-409e-8324-d7cbdb83e17e.xls                                                                                                                         page 4 of 5
                                                                 Chris Bassett Eagle Project Schedule                             9/3/2011




Step   TASK                                   HOURS 8/29 8/30 8/31   9/1   9/2   9/3   9/4   9/5   9/6   9/7   9/8   9/9 9/10
 1     write project plan                       21
 2     review with scoutmaster                   4
 3     schedule conservation commission          1
 4     survey some signs                        30



 5     brief conservation commission             3
 6     get signatures                            2
 7     inventory signs                          96



  8 build inventory database                    21
  9 select signs for repair                      2
 10 repair signs                                48




 11 complete project report                     6      2    2   2
 12 coordinate with conservation commission     2                                                   2
 13 get approvals for project results           3                                                                          3




967d5bf9-9a16-409e-8324-d7cbdb83e17e.xls                                                                                        page 5 of 5

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:15
posted:9/3/2011
language:English
pages:5