							                                                     Safe Work Method and Environment Statement
Company                                                                                                                                 Subcontractor:
Project                                                                                                                                 Date:
JobTask                                 Demolition                                                                                      SWMES No.
To be reviewed

Licences/Permits
Required or other
Competencies
Australian
Standards/Codes of
Practice/Legislation
Personal Protective
Clothing Required
Plant & Equipment
Required
Material Safety Data
Sheets - less than 5
years old
Have you considered the site specific   Have you considered weather conditions? Eg.       IN PREPARING A SAFE WORK METHOD STATEMENT YOU MUST:
hazards? Eg.                            - wind                                            1. Consider any site specific potential hazards and include any identified risks in Safe Work Method
- lay of the land                       - rain                                            Statement (SWMS)
- obstacles (buildings, workers,        - heat                                            2. Assess the risk
excavations, plant)                     - cold etc                                        3. Insert controls using the hierarchy of controls for the hazards identified
- changes to site conditions            Have you considered job specific details?         4. Review the residual risk to ensure controls are adequate to safely perform the work
- other contractors’ work in progress   - different material                              5. Document the matters contained in items 1 – 4, above, in this SWMS
                                        - different equipment                             6. Complete the SWMS and Delete these notes to demonstrate that you have considered all relevant
                                                                                          matters
                                        Any other factor that may make affect the risks   7. Ensure that all relevant employees have read, understood and signed off on the SWMS
                                        associated with performing this task?             8. Ensure that work is carried out in a safe manner in accordance with the SWMS
                                                                                          NB: If you are unsure of anything seek professional advice. Master Builders WHS department can assist
                                                                                          members in developing and implementing safety plans, including SWMS.




Company
Authority:                                                                                 Cover Page                                                                                        Page 1
                                             STEP 1
                                 Hazard - Possible Consequences
                  Possible
                                                              Description
    Code        consequences
                                    Death, Toxic release off site with detrimental effect,
                 Catastrophic
      5                              huge financial loss
                                    Extensive injury, loss of production capability, off site
                     Major
      4                             release with no detrimental effects, Major financial loss
                                    Medical Treatment required, on site release contained
                   Moderate
      3                             with outside assistance, high financial loss
                                    First aid treatment required, on site release immediate
                     Minor
      2                             containment, medium financial loss
                 Insignificant      No injury, low financial loss
      1

                                             STEP 2
                               Hazarda - Likelihood of occurrence
                       Likelihood of
    Code                                                       Description
                        Occurance
                                                The event is expected to occur in most
      A               Almost Certain            circumstances
      B                   Likely                The event will probably occur in most circumstances
      C                  Possible               The event could occur at some time
      D                  Unlikely               The event might occur at some time
                                                The event is expected to occur only in exceptional
      E                      Rare               circumstances

                                               STEP 3
                                    Hazard - Risk Analysis Matrix
                 Insignificant       Minor        Moderate        Major            Catastrophic
Likelihood             1               2              3            4                    5
  A (Almost
   Certain)            H                H                E             E                 E
       B
    (Likely)          M                 H              H               E                 E
       C
  (Possible)           L                M              H               E                 E
       D
   (unlikely)          L                 L             M               H                 E
       E
    (Rare)             L                 L             M               H                 H



                                                STEP 4
Legend
     E          Extreme Risk - Immediate Action Required
     H          High Risk - Senior Management Attention required
     M          Moderate Risk - Management responsibility must be specified
     L          Low Risk - Manage by routine procedures
            Job Steps                Potential Hazard           Risk                  Control                        Residual   Person On Site
                                                                                                                       Risk
                                                                Rate                                                            Who Will Ensure
                                                                                                                                 This Happens
  Break the job down into steps     What can cause harm at       E     What is going to be done to make                E
                                          each step              H       the job as safe as possible                   H
                                                                 M                                                     M
                                                                 L                                                     L
Prepare the site                  Manual Handling                      Placement of barricades to prevent entry
                                  Unauthorised persons                 to site
                                  Plant contact worker and/or          Only workers trained in manual handling
                                  member of public                     to erect barricades and signs
                                                                       Safety Signs in place
                                                                       Clear access & egress to site
                                                                 H     Plant to be secured when unattended and          M       [insert responsible person]
                                                                       flashing lights to be utilised at all times
                                                                       where fitted
                                                                       If structure greater than 6 meters
                                                                       notification of certain works to SafeWork
                                                                       SA

                                  Hazardous substances                 Evaluation and identification of all
                                  Exposure asbestos in:                hazardous substances on site before
                                  Vinyl Tiles                          work commences
                                  Asbestos roofing sheets              Identify all substances that require
                                  Lift brake linings                   specialist removal
                                  Gaskets                              MSDS sheets required for PPE and
                                  Insulating materials                 disposal methods
                                                                       Containment procedure as per MSDS
                                                                 E     Ensure any hazardous substances and              H       [insert responsible person]
                                                                       material is removed by licensed business
                                                                       prior to commencement of work.
                                                                       Consult the asbestos register
                                                                       All asbestos related products to be
                                                                       removed by a licensed specialist only,
                                                                       and disposed of in the required methods
                                                                       and place




                                                                  Demolition
Identify Services    Electric Shock                     Identify all services available at the site &
                     Gas                                locate
                     Water                              Isolation to be certified in writing by
                     Sewerage                       H   qualified persons                               M   [insert responsible person]
                                                        Tags to be placed as required
                                                        Checks for residual electricity to be made
                                                        before work commences
Remove PCBs          Exposure to PCBs                   All PCB related products to be removed
                                                        by a licensed specialist only, and
                                                    E   disposed of in the required method              H   [insert responsible person]
                                                        Place in sealed bin


General Demolition   Dust inhalation                    Wear dust masks appropriate to material
                     Foreign body in eye                on site, safety glasses, safety footwear
                     Cuts, lacerations, punctures       and long clothing
                                                    E   Salvage re-usable materials                     H   [insert responsible person]
                                                        Remove waste from site
                                                        Obtain relevant engineering/council sign
                                                        off
                     Structural collapse                Engineering report & demolition plan
                     Inadequate bracing                 required before start
                     Build up of debris                 Demolition to follow plan and separated
                     Plant around site                  components
                                                        Bracing as per plan
                                                        No debris to be allowed around site, only
                                                    E   in the designated area                          H   [insert responsible person]
                                                        Plant to be sectionalised away from semi
                                                        demolished structures
                                                        Area to undergo a daily inspection for
                                                        instability or non compliance with plan by
                                                        appropriate person
                     Fall from heights                  Use of EWP from ground level only
                     Removal of trusses                 No Go zone under areas where working
                                                        above is in progress, set up as per site
                                                    H   plan
                                                                                                        M   [insert responsible person]
                                                        If working over side of EWP, safety
                                                        harness required
Pack up site         Manual Handling                    Only workers trained in manual handling
                     Cuts, lacerations, punctures       to dismantle signs and barricades.
                     Slips, trips, falls                Appropraite PPE to be worn at all times.
                                                    H   Work area to be kept clear of trip hazards      M   [insert responsible person]
                                                        at all times




                                                    Demolition
                                                       Safe Work Method and Environment Statement

We, the undersigned, confirm that we have been consulted regarding the above SWMES and that its content is clearly understood. We also confirm that our
required qualification/s to undertake this activity are current and that we are competent to complete the work safely and without risk to our own health or the health of
others. We clearly understand that the control/s in this SWMES must be applied as documented, otherwise work is to cease immediately, and we will ensure that the
work area is made safe should risks to other works, visitors or the public remain.


              Name                              Job/Title                        Employed By                          Date                        Signed




I, the undersigned Supervisor confirm that I have checked all qualifications tendered and verify they are applicable and current. I have also ensured that
all inductions have taken place and that all tools and equipment are properly maintained and safe to use. I have issued all relevant permits and have
ensured to the best of my ability that the work area is safe and that the work will not damage any property or injure any persons.

Supervisor Name____________________                       Supervisor Signature____________________                                Date____________




                                                                             Sign Off Page

						
Related docs
Other docs by suchenfz
armtrack
Views: 1440  |  Downloads: 0
Miscellaneous Items - GSA Home
Views: 269  |  Downloads: 0
BRAIN_CHIPS
Views: 316  |  Downloads: 0
National Informatics Centre (DOC download)
Views: 125  |  Downloads: 0
preps
Views: 278  |  Downloads: 0
FLKS_Supplies_Invoice2
Views: 0  |  Downloads: 0
D46940-Georgia O'Keefe
Views: 0  |  Downloads: 0
info - Excel Document - Village of Nobleford
Views: 0  |  Downloads: 0
Workpapers
Views: 229  |  Downloads: 0