					                  Status of API-CRE Subcommittee on Inspection Work Program as of 4/24/2010




Document        Title of Current Edition          Rev.       Chair/                  Status                Start
                                                  Due        Expert                                        Work
 API 510   Pressure Vessel Inspection          2011      M Geisenhoff/    ’09 funds approved for         In Process
           Code—9th Edition, 2006                                         contractor to begin 10th
                                                                          edition
 API 570   Piping Inspection Code—3rd          2014                       New publication Nov 2009       Fall 2012
           Edition, 2009
 RP 571    Damage mechanisms                                              Inspection Guidance – start    In Process
                                                                          balloting Summer 2010 but
                                                                          need Master Editor to
                                                                          complete.
 RP 572    Inspection of Pressure Vessels—     2014                       New publication Nov 2009       Spring
           3rd Edition, 2009                                                                             2013
 RP 573    Inspection of Fired Boilers and     2008      Riley/Furillo    Frank Furillo under contract   In Process
           Heaters—2nd Edition, 2002                                      9/08
 RP 574    Inspection Practices for Piping     2014                       New publication Nov 2009       Fall 2011
           System Components—3rd Edition,
           2009
 RP 575    Inspection of Atmospheric and       2010      ?/Furillo        Need to begin preparation      In Process
           Low Pressure Storage Tanks—2nd                                 for 3rd Edition revision
           Edition, 2005
 RP 576    Inspection of Pressure Relieving    2014                       New publication Nov 2009       Fall 2011
           Devices—3rd Edition, 2009
 RP 577    Welding Inspection and              2009      O’Brien/Furill   Frank Furillo under contract   In Process
           Metallurgy—1st t Edition, 2004                o                9/08
 RP 578    Material Verification Program for   2015                       New publication April 2010.    Spring
           New and Existing Alloy Piping                                                                 2014
           Systems—2nd Edition, 2009
   RP      Fitness for Service—2nd Edition,    2012                       Handled elsewhere
 579-1     2007
 RP 580    Risk Based Inspection—2nd           2014                       New publication Nov 2009       Fall 2012
           Edition, 2009
 RP 581    Risk Based Inspection               2013      E Egholm         Funding available in 2009      Ongoing
               Status of API-CRE Subcommittee on Inspection Work Program as of 4/24/2010

         Technology—2nd Edition, 2008
RP 582   Supplementary Welding            2006                    Handled elsewhere
         Guidelines—1st Edition, 2001
RP 583   Corrosion Under Insulation—NEW          O’Brien/Furill   Frank Furillo under contract
                                                 o                9/08
RP 584   Integrity Operating Windows—            Clay             In progress
         NEW                                     White/Reynol
                                                 ds
RP 585   Pressure Equipment Failure—NEW          Konet/SBS        In progress
         QUTE Program                            Krynicki/Davis   2010 $60K for QUTE, PAUT