					ID   % Complete   Task Name                                                              Duration               Start           Finish        Predecessors   Resource Names
                                                                                                                                                                                                   S
1           0%    Software Development Project Plan                                         56 days        Thu 10-06-03       Mon 10-08-23
2
3           0%        Project Kick-Off                                                     0.5 days        Thu 10-06-03       Thu 10-06-03
4           0%            Prepare Kick-Off Meeting agenda                                 0.25 days         Thu 10-06-03      Thu 10-06-03                   Project Manager
5           0%            Conduct Kick-Off Meeting                                        0.25 days         Thu 10-06-03      Thu 10-06-03 4                 Project Manager
6           0%            Review / distribute project documentation                          0 days         Thu 10-06-03      Thu 10-06-03 5SS               Project Manager
7           0%            Provide project site co-ordinates                                  0 days         Thu 10-06-03      Thu 10-06-03 5SS               Project Manager
8
9           0%        Requirements Management                                              9.5 days        Thu 10-06-03       Wed 10-06-16
10          0%            Requirements Planning                                                  1 day     Thu 10-06-03        Fri 10-06-04
11          0%                 Elicitation activities preparation                                1 day      Thu 10-06-03       Fri 10-06-04 3                Business Analyst
12          0%            Requirements Elicitation                                         3.5 days            Fri 10-06-04   Wed 10-06-09
13          0%                 W orkshop                                                     2 days            Fri 10-06-04   Tue 10-06-08 11                Business Analyst,SMEs
14          0%                 Interviews                                                   0.5 days        Tue 10-06-08      Tue 10-06-08 13                Business Analyst,Business Lead
15          0%                 Documentation Review                                              1 day     W ed 10-06-09      W ed 10-06-09 13,14            Business Analyst
16          0%            Requirements Analysis & Documentation                            2.5 days        Thu 10-06-10       Mon 10-06-14
17          0%                 Analysis                                                          1 day      Thu 10-06-10      Thu 10-06-10 12                Business Analyst
18          0%                 Documentation                                                1.5 days           Fri 10-06-11   Mon 10-06-14 17                Business Analyst
19          0%            Requirements Validation                                          2.5 days        Mon 10-06-14       Wed 10-06-16
20          0%                 Business Requirements package review                          2 days        Mon 10-06-14       W ed 10-06-16 16               Business Lead,SMEs
21          0%                 Team Review                                                  0.5 days       W ed 10-06-16      W ed 10-06-16 20               Business Analyst,Business Lead,SMEs
22          0%                 Obtain sign-off from Project Sponsor                          0 days        W ed 10-06-16      W ed 10-06-16 21               Project Manager
23
24          0%        Solution Definition                                                   13 days        Thu 10-06-17       Tue 10-07-06
25          0%            Solution Design                                                    5 days         Thu 10-06-17      W ed 10-06-23 22               Solution Architect
26          0%            Functional Specifications documentation                            3 days         Thu 10-06-24      Mon 10-06-28 25                Business Analyst
27          0%            Functional Specifications review                                       1 day      Tue 10-06-29      Tue 10-06-29 26                Solution Architect,Development Team
28          0%            Project Team Review                                                    1 day      Tue 10-07-06      Tue 10-07-06 27FS+3days        Business Lead,SMEs
29          0%            Obtain sign-off from Project Sponsor                               0 days         Tue 10-07-06      Tue 10-07-06 28                Project Manager
30
31          0%        Solution Development & Delivery                                     26.5 days        Wed 10-07-07        Fri 10-08-13
32          0%            Development                                                       20 days        W ed 10-07-07      W ed 10-08-04 29               Development Team
33          0%            Conduct Unit Testing                                               5 days         Thu 10-08-05      W ed 10-08-11 32               Development Team
34          0%            Create Test environment                                           0.5 days        Thu 10-08-12      Thu 10-08-12 33                Development Team
35          0%            Create UAT environment                                            0.5 days        Thu 10-08-12      Thu 10-08-12 34                Development Team
36          0%            Deployment to Test environment                                    0.5 days           Fri 10-08-13    Fri 10-08-13 35               Development Team
37
38          0%        Data Migration (DM)                                                 5.75 days        Wed 10-07-07       Wed 10-07-14
39          0%            Create Migration Checklist                                      0.25 days        W ed 10-07-07      W ed 10-07-07 29               Business Analyst
40          0%            Data Load preparation                                              3 days        W ed 10-07-07      Mon 10-07-12 39                Business Analyst,Business Lead


                           Task                                       Milestone                     External Tasks

                           Split                                      Summary                       External Milestone

                           Progress                                   Project Summary               Deadline

                                                                                        Page 1
ID   % Complete   Task Name                                                                   Duration               Start          Finish         Predecessors   Resource Names
                                                                                                                                                                                                               S
41          0%           Load Clients                                                            0.5 days       Mon 10-07-12       Mon 10-07-12 40                SMEs
42          0%           Load Orders                                                             0.5 days       Mon 10-07-12       Tue 10-07-13 41                SMEs
43          0%           Load Issues                                                             0.5 days        Tue 10-07-13      Tue 10-07-13 42                SMEs
44          0%           Load Quotes                                                             0.5 days        Tue 10-07-13      W ed 10-07-14 43               SMEs
45          0%           Load Users                                                            0.25 days        W ed 10-07-14      W ed 10-07-14 44               SMEs
46          0%           Load Roles                                                            0.25 days        W ed 10-07-14      W ed 10-07-14 45               SMEs
47
48          0%       Solution Validation                                                       25.5 days        Wed 10-07-07       Thu 10-08-12
49          0%           Develop Test Plan                                                            1 day     W ed 10-07-07      Thu 10-07-08 39                Project Manager,Business Analyst
50          0%           Create Test Cases                                                        5 days        W ed 10-07-07      Tue 10-07-13 31SS              Business Analyst,Business Lead,SMEs
51          0%           Conduct Functional System Testing                                       10 days        W ed 10-07-14      Tue 10-07-27 50                Business Analyst
52          0%           Deployment to UAT environment                                           0.5 days       W ed 10-07-28      W ed 10-07-28 51               Development Team
53          0%           Conduct User Acceptance Testing (UAT) - DM & Functional                 10 days        W ed 10-07-28      Thu 10-08-12 52                Business Lead,SMEs
54          0%           Obtain sign-off from Project Sponsor                                     0 days         Thu 10-08-12      Thu 10-08-12 53                Project Manager
55
56          0%       Training                                                                   7.5 days        Thu 10-08-12       Mon 10-08-23
57          0%           Prepare Training environment                                          0.25 days         Thu 10-08-12      Thu 10-08-12 54                Development Team
58          0%           Co-ordinate Training Sessions                                         0.25 days         Thu 10-08-12      Thu 10-08-12 57SS              Business Analyst
59          0%           Prepare Classroom Training materials (End-User and Administrator)        5 days         Thu 10-08-12      Thu 10-08-19 54                Business Analyst
60          0%           Conduct End-User Classroom Training Session #1                               1 day      Thu 10-08-19       Fri 10-08-20 59               Business Analyst
61          0%           Conduct End-User Classroom Training Session #2                               1 day         Fri 10-08-20   Mon 10-08-23 60                Business Analyst
62          0%           Conduct Administrator Classroom Training Session                        0.5 days       Mon 10-08-23       Mon 10-08-23 61                Business Analyst
63
64          0%       Solution Deployment                                                      26.75 days        Wed 10-07-07        Fri 10-08-13
65          0%           Prepare Deployment Checklist                                          0.25 days        W ed 10-07-07      W ed 10-07-07 29               Project Manager,Business Analyst
66          0%           Create Production environment                                         0.25 days         Thu 10-08-12      Thu 10-08-12 54                Development Team
67          0%           Issue outage notification (pre-deployment)                               0 days         Thu 10-08-12      Thu 10-08-12 66                Project Manager
68          0%           Deployment Checklist completion                                              1 day      Thu 10-08-12       Fri 10-08-13 67               Project Manager,Business Analyst,Developme
69          0%           Issue outage notification (post-deployment)                              0 days            Fri 10-08-13    Fri 10-08-13 68               Project Manager
70          0%           Go-Live                                                                  0 days            Fri 10-08-13    Fri 10-08-13 69
71
72          0%       Post-Implementation Activities                                            1.38 days            Fri 10-08-13   Tue 10-08-17
73          0%           On-site support                                                          0 days            Fri 10-08-13    Fri 10-08-13 70               Business Analyst
74          0%           Prepare for Post-Implementation Review                                0.25 days            Fri 10-08-13    Fri 10-08-13 73               Project Manager,Business Analyst
75          0%           Conduct Post-Implementation Review                                    0.13 days        Mon 10-08-16       Mon 10-08-16 74                Project Manager
76          0%           Document/publish Post-Implementation Review                                  1 day     Mon 10-08-16       Tue 10-08-17 75                Project Manager,Business Analyst




                          Task                                         Milestone                         External Tasks

                          Split                                        Summary                           External Milestone

                          Progress                                     Project Summary                   Deadline