									                                 TRD DCS Planning 31.1.06

1. HV - ISEG                                                      Who       Ready
      a. ISEG PS; new module
              i. In Heidelberg being tested                       MS        15.2
      b. OPC server + Fw component
              i. Not yet working; MS is in contact with SP        MS        8.2
      c. Lab setup (complete chain): PVSS panels, OPC, HVPS       MS        15.2
      d. FSM implemented                                          MS        1.5
      e. PVSS configuration (oracle), archival, alarms            MS+JM     1.5
      f. Interlocks; define cabling, order, install               AA + MS   15.4
      g. Final installation at P2 for 1 super-module              MS        30.6
2. HV - Distribution Box
      a. Distribution Box                                         MV, AP    1.5
      b. CAN controller on DCS board                              AM        1.5
      c. Control program on DCS board                             MV        1.5
      d. DIMsrv on DCS board + DIMclient on HV-PC                 MV        1.5
      e. DIMsrv on HV-PC + DIMclient on PVSS-PC                   MV        1.5
      f. Lab setup (complete chain): PVSS panels to HV Box        MV        1.5
      g. FSM implemented combining ISEG and Box                   MV + MS   1.5
      h. PVSS configuration (oracle), archival (oracle), alarms   MV + MS   15.5
      i. Interlocks: covered by the ISEG interlock                MS        1.6
      j. Final installation at P2 for 1 super-module              MV + MS   30.6
3. FEE hardware – network, switches, cables, DCS board
      a. Definition of uplinks (number, speed, copper/fiber)      TRD       1.4
      b. B-field test of new switch, check ventilator current     MS        15.2
      c. Switch MTBF checks                                       MS        15.2
      d. Cable length, patch panel, grounding tests               TRD       15.2
      e. Purchase of switches                                     ACC       15.2 – 1.4
      f. Installation of switches at P2                           ACC       1.4 – 1.5
4. FEE software
      a. DIMsrv on DCS board + DIMclient on FED-PC                KS        15.2
      b. DIMsrv on FED-PC + DIMclient on DCS-PC                   JM        15.2
      c. Lab setup: PVSS to hardware: DCS lab test                JM+GT     1.5
      d. FSM implemented                                          JM        15.5
      e. PVSS configuration (oracle), archival (oracle), alarms   GT        1.5
      f. FEE configuration (oracle)                               KO+TD     1.4
      g. Test full chain with DCS + ECS + DAQ in lab at CERN      KS        30.5
      h. Final installation at P2 for 1 super-module              KS        30.6
5. LV
      a. Order LVPS                                               MS        1.4
      b. Racks: power, patch panels, cabling, water – prototype   MS        1.4
      c. Lab setup: PVSS to hardware                              MS        1.4
      d. FSM implemented                                          JM, GT    1.5
      e. PVSS configuration (oracle), archival (oracle), alarms   MS+GT     1.5
      f. Interlocks; define cabling, order, install               MS        1.5
      g. Final installation at P2 for 1 super-module              MS        30.6
6. Cooling
                                       TRD DCS Planning 31.1.06

          a.   Reception of cooling PLC system from CERN TS/CV          AM
          b.   Interface PVSS – cooling system                          AM+JM
          c.   Lab setup: PVSS to hardware                              JM,AM
          d.   FSM implemented                                          JM
          e.   PVSS configuration (oracle), archival (oracle), alarms   AM, GT
          f.   Final installation at P2 for 1 super-module              AM,JM    30.6

   7. Gas
         a. Reception of Gas control system from CERN GWG               CG
         b. Integration with ALICE DCS (FSM)                            CG+JM
         c. Integration with TRD DCS (FSM)                              CG+JM
         d. PVSS configuration (oracle), archival (oracle), alarms      CG+GT
         e. Final installation at P2 for 1 super-module                 CG+JM    30.6
   8. TRD DCS
         a. Integration with each sub-system                            KS       30.6
         b. Integration with ALICE DCS                                  KS       30.6
         c. Integration with ECS                                        JM       30.6
         d. Final installation at P2 for 1 super-module                 KS       30.6
         e. Synchronization with other detectors                        KS       30.6

AM: Ana Marin
TD: Tom Dietel
KO: Ken Oyama
MS: Marc Stockmeier
KS: Kai Schweda
JM: Jorge Mercado
GT: Georgios Tsiledakis
RB: Roland Bramm
MV: Maria Vassilliou
AP: Angelos Petridis
AM: Antonis Markouizos
AA: Andre Augustinus
CG: Chilos Garabatos
ACC: Central DCS Team

								