Acrobat PDF

Distributed Power Test and Demonstration Plan for Nevada Test Site

You must be logged in to download this document
Reviews
Shared by: NuclearSafety
Stats
views:
30
downloads:
0
rating:
not rated
reviews:
0
posted:
7/9/2008
language:
English
pages:
0
Distributed Power Test and Demonstration Plan for Nevada Test Site Subcontract No. 30605 - 05 Presented by Susan Horgan Distributed Utility Associates Principal Investigators: Susan Horgan, Bill Erdman, Chuck Whitaker, Joe Iannucci NREL Technical Monitor: Ben Kroposki Presented at U.S. Department of Energy Distributed Power Program Annual Review Meeting January 29-30, 2002 1 Arlington, VA Project Description: Feasibility study for performing extensive DER electrical system integration testing at NTS ? Part of DPP field test project at NTS • Define role and establish basis for site development • Develop and plan specify activities best suited to NTS • Identify equipment and upgrades needed to carry out tests • Design Mobile Skid for easing DG connections at test site 2 Jan’ DOE DPP Annual Review 02 Nevada Test Site Distributed Power Test and Demonstration Plan Area 25 3 Jan’ DOE DPP Annual Review 02 NTS Area 25 ? The site was identified as a potential test facility with existing assets: • Unused, minimally restricted 2.5 MVA substation and overhead distribution line • Local connected building load • Indoor facilities for office, communication and data acquisition • Large inventory of miscellaneous DG hardware including Diesel gensets, load banks, distribution level switchgear Test site could be used to support ambitious distribution system testing Potential comprehensive test facility, flexible configuration, distribution voltage and real world feeder test facility ? ? 4 Jan’ DOE DPP Annual Review 02 Test Facility - Attributes ? ? ? ? ? ? Balances need for isolation and controlled testing environment with real distribution configurations Co-location of distributed resources and loads Real world distribution system pole yard with 30 miles of feeder Distribution field can be easily configured: • variable length feeder 0-30 miles • voltage 2..4 to 21kV • variable load and DR placement • as a network system Makes use of NTS material and personnel Flexible DAS for monitoring DR and loads 5 Jan’ DOE DPP Annual Review 02 Fundamental Considerations that Drive the Facility Design ? Testing at distribution voltages vs. low voltages Clearly some tests can adequately be performed at low voltage – but some cannot (How do low voltage results scale or apply to distribution voltages?) Real World (distributed parameter) feeder vs lumped parameter approximation of short, medium, and long feeder Deep penetration of distribution system NTS design provides flexibility and variability ? ? ? Conclusion: The proposed real world feeder and voltage levels eliminate the nagging questions and add certainty in the test results 6 Jan’ DOE DPP Annual Review 02 Elements of a NTS Test Facility Area 25 Area 25 2.5 MVA 2.5 MVA Substation Substation Elements of a Elements of a NTS Test NTS Test Facility Facility ¼ Mile (1320 ft.) Distributed Resources Load 2.4 – 21 KV Pole Yard Combined Transformer Interconnect and Transformer 10,000 Sq. ft. Area 100,000 Sq. ft Usable 30 Mile Overhead Pole Yard 800 ft. 1.0 M Sq. ft. DAS DAS Building Building Loads Loads Building 4015 Building 4015 Recommended Site for Construction H 8 Jan’ DOE DPP Annual Review 02 Overhead Line Pole and Yard Geometries 9 Jan’ DOE DPP Annual Review 02 Interconnect Area 240 Interconnect Points 30-3 Phase Interconnect Nodes, 8 DR/Loads each Feeder Configurations 1-30 Mile Single 30-1 Mile Parallel Operating Voltage 2.4 kV to 21kV, 4 wire Fault Staging locations 150ft or 1 Mile increments 10 MVA – Total Capacity 10 Jan’ DOE DPP Annual Review 02 NTS Bill of Material Summary Feeder Yard and Interconnect Area Item 1 2 3 4 5 6 Quantity 280 1120 90 miles 15 miles 2592 140 Description 45 ft., class 4 pole 9 ft cross/alley arm 397 MCM AAC conductor Ground conductor Post insulator /clamp Ground Insulator Item 7 8 9 10 11 12 Quantity 64 768 128 64 8 2 miles Description Dead end guy wire Dead end insulator End pole crossarm Turnaround crossarm NEMA 3R termination Underground conductor 11 Jan’ DOE DPP Annual Review 02 NTS Facility Cost Estimates Completed Cost Estimates for the following: ? Overhead Pole Yard Materials and Construction – using Standard Utility Pricing based on two California utility data bases. Interconnect Area Materials - Switchgear quotation from 2 Suppliers, surface preparation and underground cable installation excluded. High Speed Data Acquisition System Infrastructure National Instrument Based System 12 Jan’ DOE DPP Annual Review 02 ? ? Design of Mobile Test Skid ? Develop detailed electrical and mechanical specs for a standard mobile skid including: • DG unit • Electrical quick-connection apparatus • Integrated fuel storage • Industry partners to participate in characterization and field testing of DG 13 Jan’ DOE DPP Annual Review 02 Nevada Test Site Summary ? NTS long-term Test Plan in draft. This work can support DOE DPP testing goals. (1547 and beyond) NTS offers unique opportunity to develop a large-scale distributed power test facility NTS facility could support large number of testing options including functional, long and short term, and even abnormal condition testing. ? ? 14 Jan’ DOE DPP Annual Review 02
Related docs
Other docs by NuclearSafety