					                HARDWARE AND LAN ACQUISITION/INSTALLATION
        Phase/Activity                           Task/Subtasks                            Potential
                                                                                        Deliverables
 The following activities, tasks and deliverables should be reviewed for each project on a case-by-case
 basis. Projects may utilize this model and adapt or tailor to the specific needs of the project. This means
 that not all activities and tasks are necessary for every project, and that additional activities and tasks
 may need to be included.
 Note: This project type is generally performed in support of an application development project. In this
 case participants on the project from NCS or CRM would manage or facilitate the work identified in this
 model. The Acquisition/Installation activities and tasks would be a sub project, managed by NCS or
 CRM, of the overall application development project. This is because purchase of hardware, servers, etc
 must be approved through NCS and prep and installation is their responsibility.
 Exceptions to this rule occur when a platform or set of components is being selected and acquired to
 establish a standard inventory of components and/or to create, enhance, or modify a list of authorized
 vendors. In this case there is no specific application development project. NCS and/or CRM would use
 the model for a project to accomplish these goals.
 Note: The degree of detail required will vary from project to project. It should be decided upon when
 the HW/LAN project is chartered.
 1.0 Initiating –
 Note: The numbering starts at “1” to enable integration into the project management lifecycle “Initiation
 Phase” which is the first of five project phases.
 1.1 Creation of Initiation Documents
 1.1.1 Input to the Business
 Case
 1.1.2 Input to the APD




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                                1
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                          Task/Subtasks                          Potential
                                                                                     Deliverables
 2.0 Planning –
 Note: The numbering starts at “2” to enable integration into the project management lifecycle “Planning
 Phase” which is the second of five project phases.




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                            2
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                          Task/Subtasks                            Potential
                                                                                       Deliverables
 3.0 Executing –
 Note: The numbering starts at “3” to enable integration into the project management lifecycle
 “Executing Phase” which is the third of five project phases.
 3.1 Feasibility Study – Note: Requirements definition is an extension of the process started in the
 Feasibility Study. Please see the Feasibility Lifecycle model.
 3.2 Requirements Identification
 Note: When more than one application project is being performed for the platform to be installed, this
 phase results in a composite statement of the requirements for the platform. The result of these steps
 must be validated and agreed to by NCS, CRM, AMS, DRM and P&P.

 3.2.1 Document storage           Ensure that data storage estimates are         Statement of storage
 volume requirements (RAM,        reasonable and complete.                       requirements
 hard disk, CD-ROM, etc.)
                                  Convert application data model information     List and description of
                                  into specific capacity requirements.           storage devices to be
                                                                                 used (number of each
                                  Determine the type of storage devices that     type, size, speed, etc.)
                                  will be required.

                                  Ensure that expansion requirements are
                                  identified and estimated.


 3.2.2 Document usage             Ensure that application requirements           Statement of usage
 requirements (number of          regarding retention, number of users, type     requirements
 users, transaction volume,       of use, frequency and volume of use,
 response times, etc.)            security, back up, recovery, contingency,      Estimate of processing
                                  performance constraints, printing              power, communication
                                  requirements, and type of processing are       capacity and internal
                                  known.                                         memory requirements
                                  Ensure that expansion requirements are
                                  identified and estimated


 3.2.3 Document site              Ensure that the site has been identified and   Site description(s)
 requirements                     that all satellite sites and mobility
                                  requirements are identified.                   Statement of mobility
                                                                                 requirements
                                  Ensure that off-site back-up requirements
                                  are known.
                                  Ensure that site relocation or change
                                  possibilities are known.


 3.2.4 Document interface         Ensure that all interfaces (needs for          Statement of interface
 requirements                     exchange of data, cooperative processing       requirements
                                  plans, network protocol and cabling
                                  requirements (topology), data transfer
                                  needs, etc.) that will be required between
                                  the installed platform and other platforms,
                                  LANs, WANs, etc., are known.




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                             3
                 HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                           Task/Subtasks                             Potential
                                                                                         Deliverables
 3.3 Configure the System
 Note: In most cases, the configuration should be in generic terms, unless there has been pre-selection of
 specific products or vendors.

 3.3.1 Identify hardware           Identify and describe the CPUs, RAM             Description of the
 components (computers,            (memory, region size), disk drives              hardware configuration
 cabling, and peripherals)         (DASD), printers, cables, modems,               or additions to existing
                                   terminals, communications lines, special        configurations
                                   expansion boards, and other hardware
                                   devices to be acquired to fulfill
                                   requirements.


 3.3.2 Identify system            Identify and describe operating system,          Description of the
 software (including utilities    DBMS, utilities, and user interface shell        system software
 and user interface software)     software (e.g., Windows) required to fulfill     configuration
                                  requirements.


 3.3.3 Identify the                Identify the features and functions of the      Description of network
 communications software           network operating system required.              system features,
 (e.g., LAN)                                                                       functions, and capacity


 3.3.4 Identify furniture,         Identify and describe the desks, tables,        Description of furniture
 supplies, and equipment           chairs, file cabinets, supplies (e.g., paper,   and equipment
 requirements                      toner, diskettes, etc.), and other furniture    requirements
                                   and equipment needed for the installation.


 3.3.5 Determine or reaffirm
 overall approach and scope.      Ensure that the results of application project   Configuration
                                  feasibility and requirements analysis are        acceptance
                                  valid and that the expected approach is
                                  feasible.                                        Statement of approach

                                  Validate that the configuration meets            Cost estimate
                                  current and projected needs of the
                                  application(s).                                  Statement of changes in
                                                                                   the original approach




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                               4
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                           Task/Subtasks                             Potential
                                                                                         Deliverables
 3.4 Acquire Hardware, Software, and/or Services

 Note: This phase may be done once for a class of platforms or components to establish an inventory or
 authorized vendor list, which is then used in many projects. It is therefore possible that this phase may
 be part of a stand-alone project. If it is, a requirements definition and configuration definition process
 would be performed.

 3.4.1 Establish selection        Identify the criteria (specific product,         List of weighted
 criteria                         vendor or service characteristics, such as       selection criteria
                                  price, number and type of features, stability,
                                  etc.) upon which selection will be based.
                                  Weight criteria in terms of importance.


 3.4.2 Prepare Request(s) for     State the requirements and request               Request(s) for Proposal
 Proposal (RFP) or for            proposals from prospective vendors (either       and/or for Information
 Information (RFI)                for information only or for the purpose of
                                  making a vendor selection).

                                  Provide guidelines for vendors that will
                                  enable them to present proposals that are
                                  useful to decision makers.




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                               5
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                           Task/Subtasks                           Potential
                                                                                       Deliverables
 3.5 Plan for Installation

 3.5.1 Estimate support and       Describe the operations and support            Role and responsibility
 operations roles and             functions (LAN manager, back-up and            assignments
 responsibilities                 recovery, technical support, etc.) that will
                                  be required.

                                  Identify staff and organizational
                                  responsibilities.


 3.5.2 Estimate training needs    Define training requirements.                  Training requirements
 for operators, support staff,                                                   definition
 and users                        Create training outlines and course
                                  materials for courses that must be             Training course
                                  developed in-house.                            materials

                                  Acquire/schedule training services and/or      Contracts with training
                                  courses.                                       service providers

                                  Schedule users, operators, and support staff   Training schedule
                                  for training sessions.


 3.5.3 Establish platform         Define the procedures and security             Procedures
 level environmental controls     restrictions for the platform:
 (security, contingency, back-                                                   Security software
 up, etc.)                        Security requirements                          selection
                                  Back-up and recovery
                                  Contingency procedures
                                  Normal operations (start-up, end of day, add
                                  new user, etc.).


 3.5.4 Develop hardware and      Ensure that there is a test plan for all        Test objectives
 system software acceptance      components to be accepted upon delivery
 test strategy and plan          (including the main CPU, work stations,         Levels of testing
                                 network software, peripherals).
                                                                                 Test cycles
                                  Note: This testing is for the platform and
                                  its individual components. Application         Test plan data
                                  testing is addressed in the application
                                  development activity list. The platform        Acceptance criteria
                                  should be tested before it is used in the
                                  testing of the application.                    Role and responsibility
                                                                                 assignments for testing


 3.5.5 Develop (walk-             Ensure that all required implementation        Issues and resolutions
 through) installation plans      activities have been identified and
                                  scheduled.


 3.5.6 Reaffirm or revise the     Ensure that the project plan is accurate       Revised or reaffirmed
 project plan                     given the information determined during        project plan
                                  this phase.
                                                                                 Detailed plan for the
                                                                                 next phase(s)



Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                            6
                HARDWARE AND LAN ACQUISITION/INSTALLATION
        Phase/Activity                           Task/Subtasks                              Potential
                                                                                          Deliverables
 3.6 Acquire Hardware, Software, and/or Services

 Note: This phase may be done once for a class of platforms or components to establish an inventory or
 authorized vendor list, which is then used in many projects. It is therefore possible that this phase may
 be part of a stand-alone project. If it is, a requirements definition and configuration definition process
 would be performed.

 3.6.1 Select vendor(s) and       Meet with vendors.                                Scores for each proposal
 product(s)                                                                         based on the selection
                                  Interview and/or visit current clients of         criteria
                                  prospective vendors.
                                                                                    Acquisition decision
                                  Evaluate each proposal with respect to pre-       (which could be to not
                                  established selection criteria.                   acquire)

                                  Conduct benchmark tests.                          Rationale for selection
                                                                                    decision
                                  Select vendor(s) and product(s).

                                   Note: Often, the selection is made in two
                                   rounds, the first to select finalists (a short
                                   list) and the second to make the final
                                   selection.


 3.6.2 Negotiate contract(s)      Define the terms and conditions of                Contract terms and
                                  acquisition, delivery and support, including      conditions ready for
                                  acceptance criteria and methods.                  signing

                                  Obtain management and sponsor approval.


 3.6.3 Determine or reaffirm      Identify any scope changes that have been         Statement of approach
 overall approach and scope.      made as a result of the selection process and
                                  contract negotiations.                            Cost estimate

                                  Ensure that previous estimates and time           Statement of changes in
                                  schedules are refined to reflect actual costs     the original approach
                                  and delivery arrangements.
                                                                                    Note: These
                                                                                    deliverables revise
                                                                                    earlier results based on
                                                                                    actual prices.


 3.6.4 Review the                 Obtain approval by reviewing the                  Acquisition Approval
 configuration and approve.       configuration and approving the
                                  selection(s), contract terms, costs, and
                                  schedules.


 3.6.5 Execute contract (s) or    To commit legally to the acquisitions.            Signed contract(s)
 purchase agreement(s)                                                              and/or purchase
                                                                                    agreement(s)




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                                7
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                           Task/Subtasks                           Potential
                                                                                       Deliverables
 3.7 Plan for Installation

 3.7.1 Schedule delivery/(ies)    Set delivery schedule(s) with vendor(s).       Coordinated schedules
 and installation(s)                                                             agreed upon by vendors,
                                  Set site preparation schedule(s).              application developers,
                                                                                 and users
                                  Set telecommunications line and service
                                  installation schedules.

                                  Set installation schedule(s).


 3.7.2 Evaluate support and       Describe the operations and support            Role and responsibility
 operations roles and             functions (LAN manager, back-up and            assignments
 responsibilities based on        recovery, technical support, etc.) that will
 solution                         be required.

                                  Identify staff and organizational
                                  responsibilities.


 3.7.3 Evaluate training plan     Define training requirements.                  Training requirements
 for operators, support staff,                                                   definition
 and users based on solution      Create training outlines and course
                                  materials for courses that must be             Training course
                                  developed in-house.                            materials

                                  Acquire/schedule training services and/or      Contracts with training
                                  courses.                                       service providers

                                  Schedule users, operators, and support staff   Training schedule
                                  for training sessions.


 3.7.4 Reaffirm platform          Define the procedures and security             Procedures
 level environmental controls     restrictions for the platform:
 (security, contingency, back-                                                   Security software
 up, etc.)                        Security requirements                          selection
                                  Back-up and recovery
                                  Contingency procedures
                                  Normal operations (start-up, end of day, add
                                  new user, etc.).


 3.7.5 Modify and perform        Ensure that there is a test plan for all        Test objectives
 hardware and system             components to be accepted upon delivery
 software acceptance test        (including the main CPU, work stations,         Levels of testing
 strategy and plan               network software, peripherals).
                                                                                 Test cycles
                                  Note: This testing is for the platform and
                                  its individual components. Application         Test plan data
                                  testing is addressed in the application
                                  development activity list. The platform        Acceptance criteria
                                  should be tested before it is used in the
                                  testing of the application.                    Role and responsibility
                                                                                 assignments for testing




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                            8
                HARDWARE AND LAN ACQUISITION/INSTALLATION
        Phase/Activity                          Task/Subtasks                        Potential
                                                                                   Deliverables

 3.7.6 Review (walk-through)      Ensure that all required implementation    Issues and resolutions
 installation plans               activities have been identified and
                                  scheduled.


 3.7.7 Reaffirm or revise the     Ensure that the project plan is accurate   Revised or reaffirmed
 project plan                     given the information determined during    project plan
                                  this phase.
                                                                             Detailed plan for the
                                                                             next phase(s)




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                       9
                HARDWARE AND LAN ACQUISITION/INSTALLATION


        Phase/Activity                           Task/Subtasks                          Potential
                                                                                      Deliverables
 3.8 Install

 3.8.1 Prepare the site           Make the installation site ready for the      Test site ready for
                                  hardware (including cabling and furniture).   installation


 3.8.2 Receive hardware and        Take delivery of the hardware and            Hardware and software
 software                          software.                                    available for acceptance
                                                                                test


 3.8.3 Install communication      Put cabling, furniture, system hardware and   Installed hardware and
 lines and hardware               supplies in place.                            communication lines.


 3.8.4 Perform hardware           Test the hardware components                  Servers ready for
 acceptance test(s)               independently of one another to validate      installation and/or
                                  that they perform according to acceptance     application test
                                  criteria.
                                                                                Documented issues and
                                  Test the integrated platform.                 defects and their
                                                                                resolutions
                                  Identify deficiencies.

                                  Correct deficiencies.

                                  Accept the components and platform.


 3.8.5 Prepare and submit         Complete request for vendor remote access     External VPN access
 request for vendor access to     to servers defined in the SLA. Submit to      request submitted for
 servers.                         ISO for approval.                             approval


 3.8.6 Install operating system   Upgrade firmware to latest versions.          Operating system
                                                                                installed on all servers
                                  Determine and implement disk
                                  configuration based on hardware, DHS
                                  standards and application requirements.
                                  Load operating system with settings defined
                                  in the pre-configuration document.


 3.8.7 Setup outbound             Determine network configuration based on      Servers connected to the
 network connectivity             type of server and security required for      internet for access to
                                  server.                                       security updates and
                                                                                patches
                                  Configure network properties of server.

                                  Configure firewall services module to allow
                                  necessary outbound network connectivity.

                                  Test the connectivity.




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                            10
                HARDWARE AND LAN ACQUISITION/INSTALLATION
        Phase/Activity                           Task/Subtasks                           Potential
                                                                                       Deliverables

 3.8.8 Install OS security       Apply all operating system security patches     Servers are ready for
 patches and updates             and upgrades allowed and/or required by         access through the DHS
                                 current DHS standards and application           network.
                                 requirements.

                                 Verify all patches and upgrades are applied.


 3.8.9 Create a list of all      Determine each additional software              Detailed list of all
 server software required by     component required on each server based on      software necessary for
 application installation        application architecture requirements.          application functionality.
 documentation.
                                 Identify the installation order and timing of   Detailed task list for
                                 the installation of the software. Each          installation of software.
                                 software component is required to be
                                 installed before, during or after the
                                 application software installation.


 3.8.10 Install database         Install and configure the database              Database servers ready
 management system software      management software (DBMS) on each              for application
 on each server required by      database server.                                installation
 application architecture.
                                 Apply all DBMS security patches and
                                 upgrades allowed and/or required by current
                                 DHS standards and application
                                 requirements.


 3.8.11 Install web service      Install and configure the web service           Web servers ready for
 software on each server         software on each web server.                    application installation
 required by application
 architecture.                   Apply all web service security patches and
                                 upgrades allowed and/or required by current
                                 DHS standards and application
                                 requirements.


 3.8.12 Install additional       Install and configure any additional            All servers ready for
 software required by            software on each server required by             application installation
 application architecture and    application architecture.
 security patches and updates
                                 Apply all additional software security
                                 patches and upgrades allowed and/or
                                 required by current DHS standards and
                                 application requirements.


 3.8.13 Perform inventory of     Verify all software required before             Verification of servers
 software installed to meet      application installation is installed.          ready for application
 application installation                                                        installation
 requirements.


 3.8.14 Install remote           Install remote administration software.         Servers are configured
 administration tools and        Configure access rights for all administrator   for remote
 configure                       users.                                          administration.




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                              11
                 HARDWARE AND LAN ACQUISITION/INSTALLATION
        Phase/Activity                            Task/Subtasks                             Potential
                                                                                          Deliverables

 3.8.15 Apply DHS standard         Configure minimal security settings that         Account policies and
 OS base security                  will not interfere with application software     audit policies are applied
                                   installation.                                    to servers.


 3.8.16 Review all accesses to     Create network requests for all accesses to      Network infrastructure is
 the servers are defined and       the servers.                                     defined. Network
 approved.                                                                          security requests are
                                   Verify ISO approved vendor access to             prepared. External access
                                   servers.                                         to servers is approved.


 3.8.17 Setup all network          Configure firewall rules, VPN accesses and       Servers are accessible by
 connectivity for                  accounts for server administrators, backup       remote administrators,
 administration, backup, DRM       administrator, database administrators and       backup server, database
 and vendor                        vendor administrators if necessary.              administrators and
                                                                                    vendors.


 3.8.18 Install backup             Install backup software and configure server     Servers are configured in
 software and configure            backup schedule.                                 the backup system and
 standard server backup                                                             scheduled for standard
 strategy                                                                           server backups.


 3.8.19 Setup application          Configure firewall rules defined by the          Servers are accessible by
 network connectivity as           vendor’s application network architecture        vendor remotely.
 defined by vendor                 requirements.


 3.8.20 Install application        Install and configure application software       Core application
                                   defined in the vendor’s software installation    software is installed and
                                   documentation.                                   configured.


 3.8.21 Install post application   Install remaining software defined by            All software is installed
 installation software.            application installation instructions required   to support the
                                   after application install.                       application.


 3.8.22 Setup AMS network          Configure firewall rules for AMS                 Development servers are
 connectivity for development      developers to access the development             accessible by AMS using
                                   servers if applicable.                           the required
                                                                                    development tools.


 3.8.23 Apply DHS standard         Apply each security setting to the servers       Servers meet the DHS
 security policies.                individually and test functionality of           standard security
                                   application. Document each setting that          policies. All exceptions
                                   cannot be retained due to application failure.   to the policies are
                                   Provide ISO with document of exceptions to       documented and
                                   the standard security settings.                  provided to the ISO.


 3.8.24 Verify the servers are     Ensure that the platform is initialized to be    Installed and initialized
 ready for application user        ready to support the application(s).             systems software,
 acceptance testing.                                                                utilities, network and
                                                                                    application




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                                 12
                HARDWARE AND LAN ACQUISITION/INSTALLATION
        Phase/Activity                           Task/Subtasks                            Potential
                                                                                        Deliverables

 Implement database backup        Create jobs to backup databases using           Databases being backed
 strategies.                      database administration standards. Create       up and maintained for
                                  jobs for database maintenance defined by        performance and
                                  application architects.                         optimization.




 3.8.25 Train operators and       Ensure that people responsible for              Trained staff
 support staff (make sure this    maintenance and operation of the platform
 training is planned in concert   are trained.
 with application level
 training)


 3.8.26 Implement back-up,        Ensure that procedures are in use.              Procedures in use by
 contingency, and normal                                                          users and/or operators
 operations procedures


 3.8.27 Validate the              Ensure that the platform and its components     Accepted installed
 installation                     are working in accordance with acceptance       platform
                                  criteria.

                                  Ensures that the installation process has not
                                  introduced deficiencies.




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                            13
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                           Task/Subtasks                             Potential
                                                                                         Deliverables
 3.9 Post Implementation Evaluation

 Note: Systems performance reviews may be held more than once during the life of a product. When all
 or part of the change or new system will not be used until long after the project (e.g., a change that will
 impact year-end processing is made months ahead of time), follow-up should be planned.


 3.9.1 Conduct a system            Evaluate the performance of the system in       System performance
 performance review                terms of capacity, speed, usability, and the    review, with
                                   degree to which it met expectations.            recommendations for
                                                                                   change


 3.9.2 Conduct a vendor            Evaluate the adequacy of installation,          Vendor service
 service review                    training, and support services.                 review(s), with
                                                                                   recommendations for
                                                                                   change




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                                14
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                          Task/Subtasks                          Potential
                                                                                     Deliverables
 4.0 Controlling

 Note: The numbering starts at “4” to enable integration into the project management lifecycle
 “Controlling Phase” which is the fourth of five project phases.
 4.1 Training Plan Log
 4.1.1 Input to Training Plan




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                     15
                HARDWARE AND LAN ACQUISITION/INSTALLATION

        Phase/Activity                          Task/Subtasks                          Potential
                                                                                     Deliverables
 5.0 Closing

 Note: The numbering starts at “4” to enable integration into the project management lifecycle “Closing
 Phase” which is the fifth of five project phases.
 5.1 Administrative Closure
 5.1.1 Turn over to OIS-
 NCS-Computer Services
 5.1.2 Turn over to OIS-
 NCS-Network Services




Hardware LAN
D:\Docstoc\Working\pdf\8ef27376-7b9f-48cc-96df-86917fdf185a.doc                                           16

				
DOCUMENT INFO
Description: Standards Lan Hardware Template document sample