PROSAN ENGINEERING COY. LIMITED




2.0 KEY PERSONNEL

Our key staffs are hereby presented with their various, years of experience and their area of
specialization.


S/No Name of Staff                             Qualification                Years of
                                                                            Experience

1.     ENGR. PETER O. SANNI           B.SC CIVIL ENGINEERING                24 YEARS


2.     ENGR. A ADIGUN                 Diploma in Water Engr. (England)
                                      M.sc Mechanical Engr. (Germany)       20 years


3.     MR. JOHN YAKUBU                HND Geology                           10 years


4.     MR. MUIDEEN OLAITAN            HND Accounting / Finance              18 Years
                                      ICAN PE II


5.     MR. ETTAH JAMES               B.SC Geology                           20 years


6.     MR. DAVID OYERINDE             B.sc Building Technology              9 years


7.     MR. PETER I. PETERS            Diploma in marketing
                                      Diploma in Computer Studies           5 years


8.     MR. OJO SANNI                  Trade Test I, II, III, Welding and
                                      Fabrication                           10 years


9.     MR. FRIDAY OGEATOR             Trade Test I, II, III, Drilling       10 years


10.    MR. OBINNA AGU                 Trade Test I, II, III, Plumbing       12 years


11.    MR. BIODUN KADIRI              Driving License Grade E               15 years
Company Facilities & Equipments
PROSAN ENGINEERING COY. LIMITED


          SPECIFICATION OF OUR MAJOR EQUIPMENT
NO OF UNITS   EQUIPMENT                CONDITION                OWNED, LEASED

A.            DRILLING EQUIPMENT S
1.            DRILLING RIGS:
              GORGE E. FAILING RIGS    REFURBISHED              OWNED
              RUSSIAN RIG              FAIRLY USED              OWNED
              PORTA RIG                REFURBISHED              OWNED
              GORGE E. FAILING RIG     REFURBISHED              OWNED
2.            ATLAS COPCO XR 350       NEW IN EXCELLENT STATE   OWNED
              AIR COMPRESSOR           NEW IN EXCELLENT STATE   OWNED

3.            MUD PUMPS                NEW IN EXCELLENT STATE   OWNED

4.            HYAB CRANE MOUNTED ON    REFURBISHED              OWNED
              T 3 TRUCK

5.            NISSAN PATROL            RE-CONDITION ED          OWNED

6.            GEOPHYSICAL SURVEY
              EQUIPMENT                NEW IN EXCELLENT STATE   OWNED

7.            TEST PUMPING EQUIPMENT   NEW IN EXCELLENT STATE   OWNED
8.            LOWBED TRAILER WITH
              T 3 IVECO HEAD

B.            TREATMENT PLANT
              EQUIPMENTS

1.            WELDING GENERATORS       NEW IN EXCELLENT STATE   OWNED

2.            175 KVA GENERATOR SET    GOOD CONDITIONED         OWNED

3.            WELDING MACHINES         NEW IN EXCELLENT STATE   OWNED

4.            SAND BLASTING
              EQUIPMENT                NEW IN EXCELLENT STATE   OWNED

5.            CUTTING MACHINES
              EQUIPMENT                NEW IN EXCELLENT STATE   OWNED

6.            DRILLING MACHINES
              EQUIPMENT                NEW IN EXCELLENT STATE   OWNED

C.            CIVIL ENGINEERING
              EQUIPMENTS

1.            THEODOLITES              NEW IN EXCELLENT STATE   OWNED
2.            PIPELINE PRESSURE
              TESTING MACHINE          NEW IN EXCELLENT STATE   OWNED
3.                DUMPY LEVELS            NEW IN EXCELLENT STATE   OWNED

4.                LASER LEVEL             FAIRLY USED              OWNED

5.                TRUCK WITH LOW BED      FAIRLY USED              OWNED

6.                PICK UP (PEUGEOT 504)   FAILY USED               OWNED

D.                ADMIN. EQUIPMENTS

1.                PHOTOCOPIERS            FAIRLY USED              OWNED

2.                COMPUTERS               NEW IN EXCELLENT STATE   OWNED

3.                PORTACABINS (FOR SITE
                  OFFICE)                 REFURBISHED              OWNED

4.                LAMINATING MACHINE      NEW IN EXCELLENT STATE   OWNED




Company Profile
REFERENCE LIST/MAJOR
  JOBS EXECUTED
                                        REFERENCE LIST / MAJOR JOBS EXECUTED

DATE                  CLIENT              LOCATION           STATUS OF        SCOPE OF WORK
                                                             PROJECT

1993          Bran & Luebbe Water         Silame             100% Completed   Water Supply Scheme
              Engrs. Nig. Ltd. Kaduna     Sokoto State                        consisting of borehole
                                                                              Drilling, Pipe reticulation,
                                                                              Overhead water tank,
                                                                              Generator house together
                                                                              With generator and stand taps.

1993          Waterline Engineering       Wurno              100% Completed   Ditto
              Nig. Ltd. Kaduna            Sokoto State


1996          Federal Ministry of         Ikot Nakanda       100% Completed   Water Supply Scheme consisting
              Water Resources             Bakasisi Main                       of Fabrication, of water treatment
              And Rural Development       land Cross River                    Plant. Construction of pipe
              Abuja.                      State                               Reticulation and stand taps.

1997          Bran & Luebbe               Ilorin             100% Completed   Water Supply scheme to Police
              Water Engr. Nig. Ltd        Kwara State                         Barrack B & D Division Consisting
              Kaduna                                                          of borehole drilling, Construction of
                                                                              Ground and high level tanks,
                                                                              Booster station, generator House with
                                                                              Generator.

1998          Kaduna State                Kaduna North       100% Completed   Design and construction of emergency over
              water Board                 Water Works                         flow facilities for 3 No.s presetting tanks.


PROSAN ENGINEERING COY. LIMITED
DATE                  CLIENT              LOCATION                     STATUS OF               SCOPE OF WORK
                                                                       PROJECT

1998          Homelink Ventures Ltd.      Archibong & Abanna           100% Completed   Fabrication and erection of 3 Nos Package
              Calabar Abana               Towns on Bakassi                              Water Treatment Plant type AC5
                                          Island Cross River State


1998        Cross River Basin and Rural   Akpa Okoyong            100% Completed        Fabrication and erection of 2 Nos Package
            Development Authority         and Oban in Cross River                       Water Treatment Plant type AC 10
            Calabar.                      State.


1998          Waterline Engineering Nig   Markafi and Kujama           100% Completed   Semi Urban Water Scheme consisting
              Ltd. (in association)       Kaduna State                                  of borehole drilling erection of ground
                                                                                        And high level tanks, Pipe reticulation
                                                                                        and stand taps booster station generator
                                                                                        house with generator.

1998          Federal Ministry of Water   Kaura Namoda;              100% Completed     Consultancy on the Expansion of
              Resources                   Zamfara State                                 township water scheme


1998          Bran & Luebbe               Kazaure Jigawa State         100% Completed   Fabrication of flocculation and sedimentation
              Water Engrs. Nig. Ltd.                                                    for package water treatment plant including
                                                                                        Pontoon intake structure.




PROSAN ENGINEERING COY. LIMITED
DATE                 CLIENT                LOCATION              STATUS OF                SCOPE OF WORK
                                                                 PROJECT

1999          Waterline Engineering           Gusau              100%              Consultancy Services and Design Gusau
              Nig. Ltd. Gusau                 Zamfara State                        Water Scheme.

1999          Waterline Engineering           Gusau                                Consultancy of intake structure
              Nig. Ltd. Gusau                 Zamfara State      100%              Generator House and Access Bridge in
                                                                                   Gusau

1999          NASTON Engineering              Zungeru                              Design of Zungeru Water Treatment Plant
              Nig. Ltd. Abuja                 Niger State        100%              and ancillary works.

2000          Zamfara State Ministry          Gusau              In progress       Drilling of 20 Nos hand Pump Well in
              of Water Resources              environs                             Gusau and environs.

2000          Waterline Engineering           Gusau              100% Completed    Construction of 4.5km pipelines of 450mm
              Nig. Ltd. Gusau                 Zamfara State                        dia pipelines in Gusau.

2001          Zamfara State, Ministry of      Gusau              In progress       Drilling of 100 Nos Hand Pump boreholes
              Water Resources Gusau.          Environs


2001          Bran & Luebbe Water             Zamfara and        In Progress       Drilling of 56 Nos hand Pump boreholes in
              Engrs. (Nig.) Ltd.              Sokoto States.                       Zamfara and Sokoto States.

2002          World Mission Agency            Covenant University                  Drilling of 2 Nos Motorized boreholes in
              Sango Otta. Ogun State          Otta                100% completed   Covenant University Otta.

2002          Cross River Basin               Oban Village       100% completed    Rehabilitation of Compact Water Treatment
              Authority Calabar.                                                   Plant and Pipe Network.

PROSAN ENGINEERING COY. LIMITED
DATE                  CLIENT              LOCATION               STATUS OF          SCOPE OF WORK
                                                                 PROJECT

2003          Mak & Mak Nig. Ltd          Isiagu, Ebonyi State   100%        Fabrication and erection of AC 5 Water
              Lagos                                                          Treatment Plant.

2003          Nigeria Deposit Insurance   Abuja
              Company, Abuja                                     100%        Fabrication and erection of AC 5 Water
                                                                             Treatment Plant.

2004          Bran & Luebbe Water                                            Drilling of 5 Nos borehole in Zaria LGA
              Engineers Nig. Ltd.         Kaduna                 100%        Kaduna.


2005          Kogi State Government       Kogi state             100%        Drilling of 4 Nos sedimentary
                                                                             boreholes with 4 Nos overhead tanks

2005          Kogi State Government       Kogi State             100%        Construction of Ajaka booster Station


2005         Kogi State Government        Kogi State             75%         Construction of Koton Karfe Surface water
                                                                             scheme and pipe lay

2006         Kaduna State Water Board     Kaduna State           100%        Rehabilitation of starter panels at Zaria
                                                                             Dam intake
2006         Kaduna State Water Board     Kaduna State           100%        Washing of filter media and rehabilitation
                                                                             of filter beds at Malali Water Works



PROSAN ENGINEERING COY. LIMITED
DATE                  CLIENT             LOCATION            STATUS OF          SCOPE OF WORK
                                                             PROJECT

2006       Cross River Basin and Rural      OBAN              100%       Rehabilitation of Surface Water Scheme
           Development Authority                                         including Prosan Water Treatment Plant.

2006       Cross River Basin and Rural     AKPAP – OKOYONG    100%       Rehabilitation of Surface Water Scheme
           Development Authority                                         including Prosan Water treatment Plant.

2007       Cross River Basin and Rural
           Development Authority.        NSIT, IKOT EKWERE     100%      Fabrication and installation of Prosan Tech.
                                                                         AC50 Package water treatment plant
2007       Cross River Basin and Rural
           Development Authority.        UKPE – OGOJA         100%       Fabrication and installation of Prosan Tech.
                                                                         AC5 Package water treatment plant.