Docstoc

Taxes an the Labour Supply

Document Sample
Taxes an the Labour Supply Powered By Docstoc
					                                                                       UNIT BREAK UP PRICE SCHEDULE - ANNEXURE - 1 - WESCO (Bargarh)
                                                                         INSTALLATION OF HVDS SYSTEM :- (Including Supply of Material)
                                                                                   Supply                                             Installation                                     Total




                                                                                                                                                                             Total Unit
                                                                                                                                                                            charges for
                                                                                                                                                                        execution (Supply
                                                                                                                                                                         of material with
                                                                                 Unit Freight,                      Unit Erection,                   Total Unit charges     Erection &
                                                             Unit Supply price    Insurance       Total Unit price   Handling &                       FOR Erection &     Commissioning
                                                              with all Taxes     charges for      of material FOR Commissioning                       Commissioning           Charges)     Total Cost of the
   Sl.                                                          and Duties        Transit &         destination    charges/ Labour Service tax* on    (with all taxes)    (with all taxes)       Item
   No.         Item-Description          Unit         Qty.        (In Rs.)       storage etc.          (5+6)           charges      Column No. 8            (8+9)              (7+10)           (4*11)
    1                   2                 3            4             5                 6                 7                8               9                   10                 11                12
    A HVDS System with 16 KVA,
       11/0.25       KV     Distribution
       Transformer with following break
       up as per standard condition.

    1   SUPPORT (9 M x 300 Kg PSC Poles)      No.      1                                                0                                                    0                  0                  0

    2   V - Cross arm (G.I) with ISMC 75 x No.         1                                                0                                                    0                  0                  0
        40 mm
    3   Horizontal Cross arm (G.I) with No.            1                                                0                                                    0                  0                  0
        ISMC 75x40x1150 mm.
    4   11 KV 200 Amps Horn Gap Fuse (1 set            1                                                0                                                    0                  0                  0
        set = 2 Nos.)
    5   11 KV Pin insulators with G.I Pin  No.         2                                                0                                                    0                  0                  0

    6   11 KV L.A                             No.      2                                                0                                                    0                  0                  0
    7   Painted M.S Angle 50x50x6 mm -        No.      1                                                0                                                    0                  0                  0
        600 mm for L.A' s fitting.
    8   16 KVA, 11/0.24 KV Transformer        No.      1                 To be issued by WESCO                                                               0                  0                  0

    9 Pole base plate                         No.      1                                                0                                                    0                  0                  0
    10 Earthing of Single Pole mounted         Lot     1
       substation as per specification,       per
       approved drawing & ISS usuing         substa
       materials like 40 mm dia G.I. Earth    tion
       Electrode, 25x4 mm G.I Flat & 8
       SWG G.I. wire.
    a) 40 mm dia, 2.5 Long G.I.Pipe = 3                                                                 0                                                    0                  0                  0
       Nos
    b) 25x4 mm G.I. flat & 8 SWG                                                                        0                                                    0                  0                  0
       G.I.wire = Qty. as required.
    11 G.I Nut, bolt, clamps etc as           Lot      1                                                0                                                    0                  0                  0
       required
    12 G.I Hot line clamps                    Nos      2                                                0                                                    0                  0                  0
    13 LT service distribution box            No.      1                 To be issued by WESCO                                                               0                  0                  0
    14 Pole anti climbing device (as per      Lot      1                                                0                                                    0                  0                  0
       approved drawing & ISS/REC).

    15 Danger Board                           Lot      1                                                0                                                    0                  0                  0




Name of the Bidder                                                                               Page No. ______                                                                    Stamp / Signature Date
                                                                                Supply                                             Installation                                     Total




                                                                                                                                                                          Total Unit
                                                                                                                                                                         charges for
                                                                                                                                                                     execution (Supply
                                                                                                                                                                      of material with
                                                                              Unit Freight,                      Unit Erection,                   Total Unit charges     Erection &
                                                          Unit Supply price    Insurance       Total Unit price   Handling &                       FOR Erection &     Commissioning
                                                           with all Taxes     charges for      of material FOR Commissioning                       Commissioning           Charges)     Total Cost of the
   Sl.                                                       and Duties        Transit &         destination    charges/ Labour Service tax* on    (with all taxes)    (with all taxes)       Item
   No.          Item-Description        Unit       Qty.        (In Rs.)       storage etc.          (5+6)           charges      Column No. 8            (8+9)              (7+10)           (4*11)
    1                   2                3          4             5                 6                 7                8               9                   10                 11                12
   16 Providing service connection to Lot           1                                                 0                                                    0                  0                 0
       existing consumers of locality.
       Total Price for HVDS System with Per         1                                                0                                                    0                  0                  0
       16 KVA, 11/0.25 KV Distribution Subst
       Transformer (as breaked up ation.
       above under SL.No. 1 to 16 of                      Total Value (In Words) :
       section A) per substation.

    B   11 KV Link Line (3 phase) to
        Substation with 55 sq.mm AAA
        Conductor (With following break
        up in approximate as per
        Standard condition) per KM of
        line.
    1   Single Pole structure on 8.0 M, Nos        14                                                0                                                    0                  0                  0
        200 Kg PSC Pole & its erection
        including fitting of all accessories
        (X-arm, insulator, fitting, earthing,
        grouting,       danger        board,
        anticlimbing etc. complete) as per
        standard                   approved
        drawing/schedule & ISS/REC.
    2   Single Pole structure on 9.0 M, Nos         2                                                0                                                    0                  0                  0
        300 kg PSC Pole & its erection
        including fitting of all accessories
        (X-arm, insulator, fitting, earthing,
        grouting,       danger        board,
        anticlimbing etc. complete) as per
        standard                   approved
        drawing/schedule & ISS/REC.
    3   Stringing of AAA conductor (55        Km   3.09               To be issued by NESCO                                                               0                  0                  0
        Sq.mm) as per sag-Tension chart
        (including sag, binding, jumpering,
        laying of insulator, clamps,
        hardwares etc. required to
        complete the work (3 phases).




Name of the Bidder                                                                            Page No. ______                                                                    Stamp / Signature Date
                                                                               Supply                                             Installation                                     Total




                                                                                                                                                                         Total Unit
                                                                                                                                                                        charges for
                                                                                                                                                                    execution (Supply
                                                                                                                                                                     of material with
                                                                             Unit Freight,                      Unit Erection,                   Total Unit charges     Erection &
                                                         Unit Supply price    Insurance       Total Unit price   Handling &                       FOR Erection &     Commissioning
                                                          with all Taxes     charges for      of material FOR Commissioning                       Commissioning           Charges)     Total Cost of the
   Sl.                                                      and Duties        Transit &         destination    charges/ Labour Service tax* on    (with all taxes)    (with all taxes)       Item
   No.          Item-Description           Unit   Qty.        (In Rs.)       storage etc.          (5+6)           charges      Column No. 8            (8+9)              (7+10)           (4*11)
    1                  2                    3      4             5                 6                 7                8               9                   10                 11                12
    4 Provision of Stay for structure in Nos       8                                                 0                                                    0                  0                 0
       Complete (20 X 1800 mm) as per
       standard approved drawing &
       ISS/REC.
       Total Price for 11 KV line, 3 Per           1                                                0                                                    0                  0                  0
       phases (as breaked up above KM
       under SL. No. 1, 2, 3, 4 of section               Total Value (In Words) :
       B) per KM.

       NOTE :-
       1. All the materails required to complete the line works as detailed above are to be supplied by the bidder except (16 KVA Transformer, AAA Conductor, LT service distribution box)
       to be supplied by the owner at free of cost to the bidder for installation at site.

       2. Bidder shall quote price for the above items as per the heads mentioned. Supply as well as erection prices of all the other accessories, assemblies, components, part etc associated
       with these items, not mentioned separately but required for completion of whole work & its commissioning as defined in Technical Specification and Volume of Work, are to be included in
       the prices of corresponding item mentioned in the price schedule.

       3. The quantity break up for standatd condition of work is indicative only for the purpose of tender quoting by the bidder. The actual quantity shall be as per site condition and accordingly
       payment shall be made after certification by Engineer In Charge.




Name of the Bidder                                                                           Page No. ______                                                                    Stamp / Signature Date
                                                                      UNIT BREAK UP PRICE SCHEDULE -      ANNEXURE - 2 - WESCO ( Bargarh )
                                                                      CONSTRUCTION OF 11 KV NEW FEEDER :- (Including Supply of Material)

                                                                                  Supply                                             Installation                                        Total




                                                                                                                                                                          Total Unit charges
                                                                                                                                                                            for execution
                                                                                                                                                                         (Supply of material
                                                                                Unit Freight,                     Unit Erection,                    Total Unit charges     with Erection &
                                                                                 Insurance      Total Unit price   Handling &                        FOR Erection &        Commissioning
                                                            Unit Supply price   charges for     of material FOR Commissioning                        Commissioning            Charges)       Total Cost of the
   Sl.                                                       with all Taxes      Transit &        destination    charges/ Labour Service tax* on     (with all taxes)      (with all taxes)        Item
   No.               Item-Description        Unit Qty.         and Duties       storage etc.         (5+6)           charges      Column No. 8             (8+9)                (7+10)            (4*11)
    1                       2                 3    4                5                 6                7                8               9                   10                    11                 12
         Construction of 11 KV New Line with
         55 / 100 sq.mm AAA Conductor (With
         following break up as per Standard
         condition).

    1    Single Pole intermediate structure     No.   10                                              0                                                     0                    0                    0
         on 8.0 M / 200 Kg PSC Pole & its
         erection including fitting of all
         accessories (V X-arm, insulator,
         fitting, earthing, grouting, danger
         board, anticlimbing etc. complete)
         as      per    standard    approved
         drawing/schedule & ISS / REC.
    2    Single Pole Cut point structure on     No    1                                               0                                                     0                    0                    0
         8.0 M / 200 Kg PSC Pole due to
         Light angle of deviation & its
         erection including fitting of all
         accessories (V X-arm, insulator,
         fitting, earthing, grouting, danger
         board, anticlimbing etc. complete
         as      per    standard    approved
         drawing/schedule & ISS / REC.
    3    Double Pole structure on 9.0 M /       No.   1                                               0                                                     0                    0                    0
         300 Kg PSC Pole due to medium
         angle of deviation & its erection
         including fitting of all accessories
         (Straight X-arm, insulator, fitting,
         earthing, grouting, danger board,
         anti climbing etc. complete as per
         standard       approved     drawing/
         schedule & ISS / REC.
    4    Stringing of AAA conductor (55 /       Km.   3.1               To be issued by WESCO                                                               0                    0                    0
         100 Sq.mm) as per sag-Tension
         chart in 3 phases including sag,
         binding, jumpering, laying of
         insulator, clamps, hardwares etc.
         required to complete the work.




Name of the Bidder                                                                                 Page No. ______                                                                               Stamp / Signature Date
                                                                  UNIT BREAK UP PRICE SCHEDULE -      ANNEXURE - 2 - WESCO ( Bargarh )
                                                                  CONSTRUCTION OF 11 KV NEW FEEDER :- (Including Supply of Material)

                                                                              Supply                                             Installation                                        Total




                                                                                                                                                                      Total Unit charges
                                                                                                                                                                        for execution
                                                                                                                                                                     (Supply of material
                                                                            Unit Freight,                     Unit Erection,                    Total Unit charges     with Erection &
                                                                             Insurance      Total Unit price   Handling &                        FOR Erection &        Commissioning
                                                        Unit Supply price   charges for     of material FOR Commissioning                        Commissioning            Charges)       Total Cost of the
   Sl.                                                   with all Taxes      Transit &        destination    charges/ Labour Service tax* on     (with all taxes)      (with all taxes)        Item
   No.             Item-Description         Unit Qty.      and Duties       storage etc.         (5+6)           charges      Column No. 8             (8+9)                (7+10)            (4*11)
    1                     2                  3    4             5                 6                7                8               9                   10                    11                 12
    5 Provision of Stay for structure       Nos. 8                                                 0                                                     0                    0                  0
       Complete (20 X 1800 mm) as per
       standard approved drawing & ISS/
       REC.
       Total Price for construction of      Per    1                                              0                                                     0                    0                    0
       New 11 KV line, 3 phases (as         Km.         Total value in words :-
       breaked up above under SL. No.
       1, 2, 3, 4, 5) per KM.
       NOTE :-
       1. All the materails required to complete the line works as detailed above are to be supplied by the bidder, except AAA Conductor, to be supplied by the owner at free of cost to the bidder
       for installation at site.
       2. Bidder shall quote price for the above items as per the heads mentioned .Supply as well as erection prices of all the other accessories, assemblies, components, part etc associated with
       these items, not mentioned separately but required for completion of whole work & its commissioning as defined in Technical Specification and Volume of Work, are to be included in the
       prices of corresponding item mentioned in the price schedule.

       3. The quantity break up for standatd condition of work is indicative only for the purpose of tender quoting by the bidder. The actual quantity shall be as per site condition and accordingly
       payment shall be made after certification by Engineer In Charge.




Name of the Bidder                                                                             Page No. ______                                                                               Stamp / Signature Date
                                                                       UNIT BREAK UP PRICE SCHEDULE -      ANNEXURE - 3 - WESCO ( Bargarh)
                                                                          UPGRADATION OF 11 KV FEEDER :- (Including Supply of Material)

                                                                                    Supply                                             Installation                                   Total




                                                                                                                                                                            Total Unit
                                                                                                                                                                           charges for
                                                                                                                                                                            execution
                                                                                                                                                                           (Supply of
                                                                                                                                                                          material with
                                                                                                                      Unit Erection,                Total Unit charges     Erection &
                                                             Unit Supply         Unit Freight,  Total Unit price of    Handling &                    FOR Erection &      Commissioning
                                                             price with all   Insurance charges   material FOR       Commissioning                   Commissioning       Charges) (with Total Cost of the
    Sl.                                                       Taxes and          for Transit &     destination      charges/ Labour Service tax* on  (with all taxes)       all taxes)        Item
    No.         Item-Description              Unit   Qty.        Duties           storage etc.         (5+6)            charges      Column No. 8          (8+9)              (7+10)         (4*11)
     1                   2                     3      4            5                   6                 7                  8              9                10                  11              12
       Upgradation of 11 KV Line
       with 55 / 100 sq.mm AAA
       Conductor With following
       break up as per Standard
       condition.
     1 Single       Pole      Interposing     No.     4                                                0                                                    0                  0                  0
       structure on 8.0 M / 200 Kg
       PSC Pole & its erection
       including      fitting    of     all
       accessories (X-arm, insulator,
       fitting,    earthing,     grouting,
       danger board, anticlimbing etc.
       complete) as per standard
       approved drawing/schedule &
       ISS/REC.
     2 Single Pole Interposing Cut            No.     1                                                0                                                    0                  0                  0
       point structure on 8.0 M / 200
       Kg PSC Pole due to Light
       angle of deviation & its
       erection including fitting of all
       accessories X-arm, insulator,
       fitting,    earthing,     grouting,
       danger board, anticlimbing etc.
       complete as per standard
       approved drawing/schedule &
       ISS / REC.
     3 Stringing of AAA conductor (55         Km.    3.09                To be issued by WESCO                                                              0                  0                  0
       / 100 Sq.mm) as per sag-
       Tension chart, 3 phases
       including       sag,       binding,
       jumpering, laying of insulator,
       clamps,       hardwares        etc.
       required to complete the work.

     4 Provision of Stay for structure Nos.           2                                                0                                                    0                  0                  0
       Complete (20 X 1800 mm) as
       per standard approved drawing
       & ISS/REC.
       Total Price for construction Per               1                                                0                                                    0                  0                  0
       of 11 KV line, 3 phases as Km.                       Total value in words :-
       breaked up above under
       SL.No. 1, 2, 3, 4 of section A)
       per KM.




Name of the Bidder                                                                                  Page No. _____                                                                            Stamp / Signature Date
                                                                    UNIT BREAK UP PRICE SCHEDULE -       ANNEXURE - 3 - WESCO ( Bargarh)
                                                                       UPGRADATION OF 11 KV FEEDER :- (Including Supply of Material)

                                                                                 Supply                                             Installation                                   Total




                                                                                                                                                                         Total Unit
                                                                                                                                                                        charges for
                                                                                                                                                                         execution
                                                                                                                                                                        (Supply of
                                                                                                                                                                       material with
                                                                                                                   Unit Erection,                Total Unit charges     Erection &
                                                          Unit Supply         Unit Freight,  Total Unit price of    Handling &                    FOR Erection &      Commissioning
                                                          price with all   Insurance charges   material FOR       Commissioning                   Commissioning       Charges) (with Total Cost of the
    Sl.                                                    Taxes and          for Transit &     destination      charges/ Labour Service tax* on  (with all taxes)       all taxes)        Item
    No.         Item-Description           Unit   Qty.        Duties           storage etc.         (5+6)            charges      Column No. 8          (8+9)              (7+10)         (4*11)
     1                  2                   3      4            5                   6                 7                  8              9                10                  11              12
     5 Dismantling of conductors &
        other line materials, if any,
        redrum of conductor, and
        return of the dismantled items
        to designated nearest WESCO
        stores with proper devaluation
        note.
        a) Dismentalling of PSC poles /    Nos.    4                                                0                                                    0                  0                  0
        RS Joist / Rail poles of various
        sizes & return of same to
        nearest designated store of
        WESCO.
        b) Dismentalling, redrum of        Km.     1                                                0                                                    0                  0                  0
        conductors & other associated
        line materials and return of the
        same to the nearest WESCO
        stores.
        Total Price for dismantling of     Per     1                                                 0                                                   0                  0                  0
        conductors & other line            Km.
        materials,       redrum       of
        conductor and return of the
        dismantled items to Burla                        Total value in words :-
        stores of WESCO with proper
        devaluation      note    (    as
        breaked up above under
        SL.No.5 - a, 5-b).
        Grand Total                        Per     1                                                 0                                                   0                  0                  0
                                           Km.           Total value in words :-



        NOTE :-
        1. All the materails required to complete the line works as detailed above are to be supplied by the bidder, except AAA Conductor which will be supplied by the owner at free of cost
        to the bidder for installation at site.
        2. Bidder shall quote price for the above items as per the heads mentioned. Supply as well as erection prices of all the other accessories, assemblies, components, part etc
        associated with these items, not mentioned separately but required for completion of whole work & its commissioning as defined in Technical Specification and Volume of Work, are
        to be included in the prices of corresponding item mentioned in the price schedule.

        3. The quantity break up for standatd condition of work is indicative only for the purpose of tender quoting by the bidder. The actual quantity shall be as per site condition and
        accordingly payment shall be made after certification by Engineer In Charge.




Name of the Bidder                                                                               Page No. _____                                                                            Stamp / Signature Date
                                                                UNIT BREAK UP PRICE SCHEDULE -      ANNEXURE - 4 - WESCO ( Bargarh)
                                                                CONSTRUCTION OF NEW 33 KV FEEDER :- (Including Supply of Material)
                                                                          Supply                                             Installation                                      Total




                                                                                                                                                                    Total Unit
                                                                                                                                                                   charges for
                                                                                                                                                                    execution
                                                                                                                                                                   (Supply of
                                                                                                                                                                  material with
                                                                                                              Unit Erection,                Total Unit charges     Erection &
                                                                         Unit Freight,  Total Unit price of    Handling &                    FOR Erection &      Commissioning
                                                    Unit Supply price Insurance charges   material FOR       Commissioning                   Commissioning           Charges)          Total Cost of
      Sl.                                            with all Taxes      for Transit &     destination      charges/ Labour Service tax* on  (with all taxes)    (with all taxes)        the Item
      No.           Item-Description      Unit Qty.    and Duties         storage etc.         (5+6)            charges      Column No. 8          (8+9)              (7+10)              (4*11)
       1                     2             3    4          5                   6                 7                  8              9                10                  11                  12
       A Construction of New 33 KV
          Line with 100 sq.mm AAA
          Conductor, 3 phase with
          following break up as per
          Standard condition.
       1 Single Pole structure on 9.0 M / No.    12                                             0                                                   0                   0                   0
          415 Kg PSC Pole & its erection
          including       fitting   of     all
          accessories (X-arm, insulator,
          fitting,     earthing,    grouting,
          danger board, anticlimbing etc.
          complete as per standard
          approved drawing/schedule &
          ISS/REC.
       2 Single Pole Cut point structure No.     1                                              0                                                   0                   0                   0
          on 9.0 M / 415 Kg PSC Pole
          due to Light angle of deviation
          & its erection including fitting of
          all      accessories       (X-arm,
          insulator,     fitting,   earthing,
          grouting,       danger       board,
          anticlimbing etc. complete) as
          per       standard       approved
          drawing/schedule & ISS / REC.


       3 Double Pole structure on 10.0 No.       1                                              0                                                   0                   0                   0
         M / 425 kg PSC Pole due to
         medium angle of deviation & its
         erection including fitting of all
         accessories (X-arm, insulator,
         fitting,  earthing,     grouting,
         danger board, anti climbing etc.
         complete) as per standard
         approved drawing / ISS / REC.

       4 Stringing of AAA conductor Km. 3.1                       To be issued by WESCO                                                             0                   0                   0
         (100 Sq.mm) as per sag-
         Tension     chart,   3    phase
         including     sag,      binding,
         jumpering, laying of insulator,
         clamps,      hardwares      etc.
         required to complete the work.




Name of Bidder                                                                            Page No. _____                                                                            Stamp / Signature Date
                                                                    UNIT BREAK UP PRICE SCHEDULE -      ANNEXURE - 4 - WESCO ( Bargarh)
                                                                    CONSTRUCTION OF NEW 33 KV FEEDER :- (Including Supply of Material)
                                                                              Supply                                             Installation                                        Total




                                                                                                                                                                          Total Unit
                                                                                                                                                                         charges for
                                                                                                                                                                          execution
                                                                                                                                                                         (Supply of
                                                                                                                                                                        material with
                                                                                                                    Unit Erection,                Total Unit charges     Erection &
                                                                               Unit Freight,  Total Unit price of    Handling &                    FOR Erection &      Commissioning
                                                          Unit Supply price Insurance charges   material FOR       Commissioning                   Commissioning           Charges)          Total Cost of
      Sl.                                                  with all Taxes      for Transit &     destination      charges/ Labour Service tax* on  (with all taxes)    (with all taxes)        the Item
      No.            Item-Description           Unit Qty.    and Duties         storage etc.         (5+6)            charges      Column No. 8          (8+9)              (7+10)              (4*11)
       1                      2                  3    4          5                   6                 7                  8              9                10                  11                  12
       5    Provision of Stay for structure Nos. 8                                                     0                                                   0                  0                    0
            complete (20 X 1800 mm) as
            per standard approved drawing
            & ISS/REC.
            Total Price for construction of Per 1                                                      0                                                   0                  0                   0
            33 KV line with 100 sq. mm Km.
            AAA Conductor, 3 phase as                     Total value in words :-
            breaked up above under
            SL.No. 1, 2, 3, 4, 5 of section
            A per KM.
       B    Construction of New 33 KV
            Line with 232 sq.mm AAA
            Conductor, 3 phases with
            following break up as per
            Standard condition.
       1    Single Pole structure on 9.0 M / No. 16                                                    0                                                   0                  0                   0
            415 Kg PSC Pole & its erection
            including      fitting   of     all
            accessories (X-arm, insulator,
            fitting,    earthing,    grouting,
            danger board, anticlimbing etc.
            complete as per standard
            approved drawing/schedule &
            ISS/REC.
       2    Double Pole Cut point structure No. 1                                                      0                                                   0                  0                   0
            on 10.0 M / 425 kg PSC Pole
            due to medium angle of
            deviation     &      its  erection
            including      fitting   of     all
            accessories (X-arm, insulator,
            fitting,    earthing,    grouting,
            danger board, anti climbing etc.
            complete as per standard
            approved drawing / ISS / REC.
       3    Stringing of AAA conductor Km. 3.1                          To be issued by WESCO                                                              0                  0                   0
            (232 Sq.mm) as per sag-
            Tension chart, 3 phases
            including        sag,     binding,
            jumpering, laying of insulator,
            clamps,       hardwares       etc.
            required to complete the work.




Name of Bidder                                                                                 Page No. _____                                                                             Stamp / Signature Date
                                                                   UNIT BREAK UP PRICE SCHEDULE -    ANNEXURE - 4 - WESCO ( Bargarh)
                                                                   CONSTRUCTION OF NEW 33 KV FEEDER :- (Including Supply of Material)
                                                                             Supply                                             Installation                                    Total




                                                                                                                                                                     Total Unit
                                                                                                                                                                    charges for
                                                                                                                                                                     execution
                                                                                                                                                                    (Supply of
                                                                                                                                                                   material with
                                                                                                                    Unit Erection,                Total Unit chargesErection &
                                                                               Unit Freight,  Total Unit price of    Handling &                    FOR Erection & Commissioning
                                                          Unit Supply price Insurance charges   material FOR       Commissioning                   Commissioning      Charges)     Total Cost of
      Sl.                                                   with all Taxes     for Transit &     destination      charges/ Labour Service tax* on                 (with all taxes)
                                                                                                                                                   (with all taxes)                  the Item
      No.            Item-Description          Unit Qty.     and Duties         storage etc.         (5+6)            charges      Column No. 8          (8+9)         (7+10)         (4*11)
       1                     2                  3    4            5                  6                 7                  8              9                10             11             12
       4    Provision of Stay for structure Nos. 6                                                     0                                                   0             0               0
            Complete (20 X 1800 mm) aAs
            per standard approved drawing
            & ISS/REC.
            Total Price for construction of Per 1                                                      0                                                   0           0                 0
            33 KV line with 232 sq. mm Km.
            AAA Conductor, 3 phases as                   Total value in words :-
            breaked up above under SL.
            No. 1, 2, 3, 4 of section B per
            KM.
            NOTE :-
            1. All the materails required to complete the line works as detailed above are to be supplied by the bidder except (AAA Conductor) to be supplied by the owner at free of cost to the
            bidder for installation at site.
            2. Bidder shall quote price for the above items as per the heads mentioned. Supply as well as erection prices of all the other accessories, assemblies, components, part etc
            associated with these items, not mentioned separately but required for completion of whole work & its commissioning as defined in Technical Specification and Volume of Work, are
            to be included in the prices of corresponding item mentioned in the price schedule.

            3. The quantity break up for standatd condition of work is indicative only for the purpose of tender quoting by the bidder. The actual quantity shall be as per site condition and
            accordingly payment shall be made after certification by Engineer In Charge.




Name of Bidder                                                                               Page No. _____                                                                          Stamp / Signature Date
                                                                            UNIT BREAK UP PRICE SCHEDULE -    ANNEXURE - 5 - WESCO (Bargarh)
                                                                              UPGRADATION OF 33 KV FEEDER :- (Including Supply of Material)
                                                                                  Supply                                                Installation                                         Total
                                                                                                                                                                             Total Unit charges
                                                                                                                                                                               for execution
                                                                                                                                                                            (Supply of material
                                                                                                                   Unit Erection,                      Total Unit charges     with Erection &
                                                                               Unit Freight,  Total Unit price of   Handling &                          FOR Erection &        Commissioning
                                                          Unit Supply price Insurance charges   material FOR      Commissioning                         Commissioning            Charges)         Total Cost of the
        Sl.                                               with all Taxes and   for Transit &     destination      charges/ Labour    Service tax* on    (with all taxes)      (with all taxes)          Item
        No.          Item-Description           Unit Qty.       Duties          storage etc.         (5+6)            charges         Column No. 8            (8+9)                (7+10)              (4*11)
         1                    2                  3    4            5                 6                 7                 8                  9                  10                    11                   12
         A Upgradation of 33 KV Line
            with      100      sq.mm      AAA
            Conductor, 3 phases with
            following break up as per
            standard condition.
         1 Single        Pole      interposing No.     6                                                 0                                                     0                    0                    0
            structure on 9.0 M / 415 Kg
            PSC Pole & its erection
            including      fitting    of     all
            accessories (X-arm, insulator,
            fitting,                  earthing,
            grouting,danger              board,
            anticlimbing etc. complete) as
            per       standard       approved
            drawing/schedule & ISS/REC.

         2   Single Pole Cut point structure No.       1                                                 0                                                     0                    0                    0
             on 9.0 M / 415 Kg PSC Pole
             due to Light angle of deviation
             & its erection including fitting of
             all     accessories       (X-arm,
             insulator,    fitting,   earthing,
             grouting,      danger       board,
             anticlimbing etc. complete) as
             per      standard       approved
             drawing/schedule & ISS / REC.


         3   Double Pole structure on 10.0 No.         1                                                 0                                                     0                    0                    0
             M / 425 kg PSC Pole due to
             medium angle of deviation & its
             erection including fitting of all
             accessories (X-arm, insulator,
             fitting,  earthing,     grouting,
             danger board, anti climbing etc.
             complete) as per standard
             approved drawing / ISS / REC.

         4   Stringing of AAA conductor         KM     3.1                To be issued by WESCO                                                                0                    0                    0
             (100 Sq.mm) as per sag-
             Tension chart including sag,
             binding, jumpering, laying of
             insulator, clamps, hardwares
             etc. required to complete the
             work).
         5   Provision of Stay for structure    No.    8                                                 0                                                     0                    0                    0
             complete (20 X 1800 mm) as
             per standard approved drawing
             & ISS/REC.
             Total Price for construction       Per    1                                                 0                                                     0                    0                    0
             of 33 KV line, 3 phases as         Km.
             breaked up above under                          Total value in words :-
             SL.No. 1, 2, 3, 4, 5 of section
             A) per KM.
         6   Dismantling of conductors &
             other line materials from
             existing    line,  redrum     of
             conductor and return of the
             dismantled items to nearest
             WESCO stores with proper
             devaluation note.
             a) Dismentalling of PSC poles /    Nos.   4                                                 0                                                     0                    0                    0
             RS Joist / Rail poles of various
             sizes & return of same to
             nearest designated store of
             WESCO.
             b) Dismentalling, redrum of        Km.    1                                                 0                                                     0                    0                    0
             conductors & other associated
             line materials and return of the
             same to the nearest WESCO
             stores.




Name of the Bidder                                                                                    Page No. ____                                                                                   Stamp / Signature Date
                                                                           UNIT BREAK UP PRICE SCHEDULE -    ANNEXURE - 5 - WESCO (Bargarh)
                                                                             UPGRADATION OF 33 KV FEEDER :- (Including Supply of Material)
                                                                                 Supply                                                Installation                                         Total
                                                                                                                                                                            Total Unit charges
                                                                                                                                                                              for execution
                                                                                                                                                                           (Supply of material
                                                                                                               Unit Erection,                         Total Unit charges     with Erection &
                                                                           Unit Freight,  Total Unit price of   Handling &                             FOR Erection &        Commissioning
                                                      Unit Supply price Insurance charges   material FOR      Commissioning                            Commissioning            Charges)         Total Cost of the
        Sl.                                          with all Taxes and    for Transit &     destination      charges/ Labour       Service tax* on    (with all taxes)      (with all taxes)          Item
        No.        Item-Description        Unit Qty.       Duties           storage etc.         (5+6)            charges            Column No. 8            (8+9)                (7+10)              (4*11)
         1                 2                3    4            5                  6                 7                 8                     9                  10                    11                   12
            Total Price for dismantling of Per   1                                                 0                                                           0                    0                    0
            conductors & other line Km.
            materials,      redrum      of
            conductor and return of the
                                                     Total value in words :-
            dismantled items to Burla
            stores of WESCO with proper
            devaluation note (as breaked
            up above under SL.No 5 - a,
            5-b).
            Grand Total                    Per   1                                                 0                                                          0                     0                   0
                                           Km.       Total value in words :-



         B Upgradation of 33 KV Line
           with     232     sq.mm      AAA
           Conductor, 3 phases with
           following break up as per
           Standard condition.
         1 Single     Pole      Interposing No.       12                                                0                                                     0                    0                    0
           structure on 9.0 M / 415 Kg
           PSC Pole & its erection
           including    fitting    of     all
           accessories (X-arm, insulator,
           fitting,  earthing,     grouting,
           danger board, anticlimbing etc.
           complete as per standard
           approved drawing/schedule &
           ISS/REC.

         2   Double Pole Cut point structure No.      1                                                 0                                                     0                    0                    0
             on 10.0 M / 425 kg PSC Pole
             due to medium angle of
             deviation   &      its  erection
             including    fitting   of     all
             accessories (X-arm, insulator,
             fitting,  earthing,    grouting,
             danger board, anti climbing etc.
             complete as per standard
             approved drawing / ISS / REC.

         3   Stringing of AAA conductor        Km.    3.1                To be issued by WESCO                                                                0                    0                    0
             (232 Sq.mm) as per sag-
             Tension chart (including sag,
             binding, jumpering, laying of
             insulator, clamps, hardwares
             etc. required to complete the
             work.
         4   Provision of Stay for structure   Nos.   6                                                 0                                                     0                    0                    0
             complete (20 X 1800 mm) as
             per standard approved drawing
             & ISS/REC.
             Total Price for construction      Per    1                                                 0                                                     0                    0                    0
             of 33 KV line with 232 sq. mm     Km.
             AAA Conductor as breaked                       Total value in words :-
             up above under SL.No. 1, 2,
             3, 4 of section B) per KM.

         5   Dismantling of conductors &
             other line materials from
             existing    line,  redrum     of
             conductor and return of the
             dismantled items to nearest
             WESCO stores with proper
             devaluation note.
             a) Dismentalling of PSC poles / Nos.     4                                                 0                                                     0                    0                    0
             RS Joist / Rail poles of various
             sizes & return of same to
             nearest designated store of
             WESCO.
             b) Dismentalling, redrum of Km.          1                                                 0                                                     0                    0                    0
             conductors & other associated
             line materials and return of the
             same to the nearest WESCO
             stores.




Name of the Bidder                                                                                   Page No. ____                                                                                   Stamp / Signature Date
                                                                        UNIT BREAK UP PRICE SCHEDULE -    ANNEXURE - 5 - WESCO (Bargarh)
                                                                          UPGRADATION OF 33 KV FEEDER :- (Including Supply of Material)
                                                                              Supply                                                Installation                                         Total
                                                                                                                                                                         Total Unit charges
                                                                                                                                                                           for execution
                                                                                                                                                                        (Supply of material
                                                                                                               Unit Erection,                      Total Unit charges     with Erection &
                                                                           Unit Freight,  Total Unit price of   Handling &                          FOR Erection &        Commissioning
                                                      Unit Supply price Insurance charges   material FOR      Commissioning                         Commissioning            Charges)         Total Cost of the
        Sl.                                          with all Taxes and    for Transit &     destination      charges/ Labour    Service tax* on    (with all taxes)      (with all taxes)          Item
        No.        Item-Description        Unit Qty.       Duties           storage etc.         (5+6)            charges         Column No. 8            (8+9)                (7+10)              (4*11)
         1                 2                3    4            5                  6                 7                 8                  9                  10                    11                   12
            Total Price for dismantling of Per   1                                                 0                                                        0                    0                    0
            conductors & other line Km.
            materials,      redrum      of
            conductor and return of the
            dismantled items to Burla
            stores of WESCO with proper              Total value in words :-
            devaluation note (as breaked
            up above under SL.No 5 - a,
            5-b).
            Grand Total                    Per   1                                                 0                                                       0                     0                   0
                                           Km.       Total value in words :-


            NOTE :-
            1. All the materails required to complete the line works as detailed above are to be supplied by the bidder except AAA Conductor, are to be supplied by the owner at free of cost to the bidder
            for installation at site.
            2. Bidder shall quote price for the above items as per the heads mentioned .Supply as well as erection prices of all the other accessories, assemblies, components, part etc associated with
            these items, not mentioned separately but required for completion of whole work & its commissioning as defined in Technical Specification and Volume of Work, are to be included in the prices
            of corresponding item mentioned in the price schedule.

            3. The quantity break up for standatd condition of work is indicative only for the purpose of tender quoting by the bidder. The actual quantity shall be as per site condition and accordingly
            payment shall be made after certification by Engineer In Charge.




Name of the Bidder                                                                                Page No. ____                                                                                   Stamp / Signature Date
                                                                     UNIT BREAK UP PRICE SCHEDULE -       ANNEXURE - 6 - WESCO (Bargarh)
                                                                 LT LINE OF BARE CONDUCTOR WITH AB CABLE :- (Including Supply of Material)
                                                                                  Supply                                                                                              Total




                                                                                                                                                                       Total Unit charges
                                                                                                                                                                         for execution
                                                                                                                                                                      (Supply of material
                                                                                Unit Freight,                     Unit Erection,                   Total Unit charges   with Erection &
                                                                                 Insurance      Total Unit price   Handling &                       FOR Erection &      Commissioning
                                                            Unit Supply price   charges for     of material FOR Commissioning                       Commissioning          Charges)       Total Cost of the
     Sl.                                                     with all Taxes      Transit &        destination       charges/     Service tax* on    (with all taxes)    (with all taxes)        Item
     No.           Item-Description        Unit        Qty.    and Duties       storage etc.         (5+6)       Labour charges Column No. 8              (8+9)              (7+10)            (4*11)
      1                    2                3           4           5                 6                7                8               9                   10                 11                 12
           Construction of LT line with AB
           Cable with following item break
           up as per standard condition.

      1    Installation of following Items
           a) 8 Mtr x 200 Kg PSC Pole        Nos       22                                             0                                                    0                   0                  0
           b) Coil Earthing                  Nos        5                                             0                                                    0                   0                  0
           c) LT Stay Set Complete including Nos       10                                             0                                                    0                   0                  0
           Clamp, LT Stay Insulator.

           d)     Service   Distribution   Box                                                        0                                                    0                   0                  0
           including Service Connection to
           existing consumers.
           i) 4 Way                              Nos    6              To be supplied by WESCO                                                             0                   0                  0
           ii) 8 Way                             Nos   12                                                                                                  0                   0                  0
           iii) 12 Way                           Nos    4                                                                                                  0                   0                  0
           e) Piercing Connector (AB Cable       Nos   54                                                                                                  0                   0                  0
           to SDB)
           f) Neutral Connector                  Nos   22                                                                                                  0                   0                  0
           g) Eye Hook clamp                     Nos   22                                                                                                  0                   0                  0
           h) Suspension clamp                   Nos   14                                                                                                  0                   0                  0
           i) Dead end clamp                     Nos    8                                                                                                  0                   0                  0
      2    Laying of following sizes of AB
           Cables including supply of pole
           clamps only by bidder. Other AB
           cable     accessories     shall  be
           supplied by WESCO.
           a) 3 x 95 + 1 x 55 + 1x16 MM2         Km.    1              To be supplied by WESCO                                                             0                   0                  0
           b) 3 x 50 + 1 x 35 + 1 x 16 MM2       Km.    1                                                                                                  0                   0                  0
           Total Price for construction of       Per    1                                             0                                                    0                   0                  0
           LT line with 3 x 95 + 1 x 55 +        Km.
           1x16 MM2 AB Cable, 3 phase (as
           breaked up above under SL.No.                    Total Value (In Words) :
           1 & 2) per KM
           Total Price for construction of       Per    1                                             0                                                    0                   0                  0
           LT line with 3 x 50 + 1 x 35 + 1 x    Km.
           16 MM2 AB Cable, 3 phase (as
           breaked up above under SL.No.                    Total Value (In Words) :
           1 & 2) per KM




Name of the Bidder                                                                         Page No. ____                                                                       Stamp / Signature Date
                                                                    UNIT BREAK UP PRICE SCHEDULE -       ANNEXURE - 6 - WESCO (Bargarh)
                                                                LT LINE OF BARE CONDUCTOR WITH AB CABLE :- (Including Supply of Material)
                                                                                 Supply                                                                                              Total




                                                                                                                                                                      Total Unit charges
                                                                                                                                                                        for execution
                                                                                                                                                                     (Supply of material
                                                                               Unit Freight,                     Unit Erection,                   Total Unit charges   with Erection &
                                                                                Insurance      Total Unit price   Handling &                       FOR Erection &      Commissioning
                                                           Unit Supply price   charges for     of material FOR Commissioning                       Commissioning          Charges)       Total Cost of the
     Sl.                                                    with all Taxes      Transit &        destination       charges/     Service tax* on    (with all taxes)    (with all taxes)        Item
     No.           Item-Description            Unit   Qty.    and Duties       storage etc.         (5+6)       Labour charges Column No. 8              (8+9)              (7+10)            (4*11)
      1                     2                   3      4           5                 6                7                8               9                   10                 11                 12
      3 Dismantling of conductors & other
         line materials, if any, redrum of
         conductor and return of the
         dismantled items to WESCO
         storeswith     proper devaluation
         note.
         a) Dismantlling of PSC poles / RS Nos.        2                                             0                                                    0                   0                  0
         Joist / Rail poles of various sizes &
         return of same to nearest WESCO
         stores.
         b)     Dismantlling,    redrum     of Km.     1                                             0                                                    0                   0                  0
         conductors & other associated line
         materials (3 phases) and return of
         the same to WESCO stores.

         Total Price for dismantling of Per            1                                             0                                                    0                   0                  0
         conductors (3 phases) & other Km.
         line  materials,    redrum      of
         conductor and return of the
         dismantled items to Burla stores
         of    WESCO      with     proper                  Total Value (In Words) :
         devaluation note (as breaked up
         above under SL.No. 3 - a, 3-b).

         NOTE :-
         1. All the materails required to complete the line works as detailed above are to be supplied by the bidder except AB Cable acessories (piercing connectors, suspension clamp, dead
         end clamp, eye hooks, neutral connectors only) & Service distribution box are to be supplied by the owner at free of cost to the bidder for installation at site.


         2. Bidder shall quote price for the above items as per the heads mentioned .Supply as well as erection prices of all the other accessories, assemblies, components, part etc associated with
         these items, not mentioned separately but required for completion of whole work & its commissioning as defined in Technical Specification and Volume of Work, are to be included in the
         prices of corresponding item mentioned in the price schedule.

         3. The quantity break up for standatd condition of work is indicative only for the purpose of tender quoting by the bidder. The actual quantity shall be as per site condition and accordingly
         payment shall be made after certification by Engineer In Charge.




Name of the Bidder                                                                        Page No. ____                                                                       Stamp / Signature Date
                                                UNIT BREAK UP PRICE SCHEDULE -     ANNEXURE - 7 - WESCO ( Bargarh)

                 TENTATIVE EXTRA ITEMS OVER & ABOVE ITEMS UNDER ANNEXURE -( 1,2,3,4,5,6) AS PER SITE REQUIREMENT :- (Including Supply of Material)

                                                                                    Supply                                                       Installation




                                                                                                                                                       Total Unit
                                                            Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                           price with all  Insurance       price of                    Handling &                      Erection &
                                                             Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                          Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.               Item-Description             Unit Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                       2                      3    4          5            6              7               8             9               10             11                 12
   A Construction of 11 KV Link Line for
      HVDS System (Extra items other than
      that of Annexure - 1).
   1 Provision of 11 KV AB Switch (3 pole) in Set       25                                    0              0                                                  0              0
      line at desired locations for group control
      of HVDS system & its installation
      complete including earthing with GI flat &
      1 no. of earth electrode aAs per standard
      approved drawing & ISS/REC.

   2   Provision of 11 KV LA in 3 phase line at Set     25                                    0              0                                                  0              0
       desired locations & its installation
       complete including earthing with GI flat &
       2 nos. earth electrode as per standard
       approved drawing & ISS/REC.
   3   Single Pole Cut point structure on 8.0 M / Set   25                                    0              0                                                  0              0
       200 Kg PSC Pole due to Light angle of
       deviation & its erection including fitting of
       all accessories (V X-arm, insulator, fitting,
       earthing,    grouting,    danger      board,
       anticlimbing etc. complete as per standard
       approved drawing/schedule & ISS / REC.

   4   Double Pole structure on 9.0 M, 300 kg No        6                                     0              0                                                  0              0
       PSC Pole due to medium angle of
       deviation & its erection including fitting of
       all   accessories      (X-arm,    X-bracing,
       insulator, fitting, coil earthing, grouting,
       danger board, anticlimbing etc. complete)
       as       per        standard       approved
       drawing/schedule & ISS/REC.
   5   Single Pole structure on 11.0 M, 330 Kg No       11                                    0              0                                                  0              0
       PSC Pole & its erection including fitting of
       all accessories (X-arm, insulator, fitting,
       earthing,                   grouting,danger
       board,anticlimbing etc. complete) as per
       standard approved drawing/schedule &
       ISS/REC.




Name of the Bidder                                                              Page No. _____                                                                  Stamp / Signature Date
                                                                                     Supply                                                       Installation




                                                                                                                                                        Total Unit
                                                             Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                            price with all  Insurance       price of                    Handling &                      Erection &
                                                              Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                           Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.                Item-Description             Unit Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                         2                     3    4          5            6              7               8             9               10             11                 12
   6 Treated steel (M.S painted with Two coats Kg 38                                           0               0                                             0                 0
      of primer paint followed by Two coats of
      Aluminium paint) required for making
      tapping arrangement at existing 11 KV
      structure as per approved drawing / ISS /
      REC        standard.      Scope    includes
      completion of work in full including supply
      of steel, nut & bolts etc.
   7Dismantling of conductors & other line                                                     0                                                                 0
    materials, if any, after installation of HVDS
    system, redrum of conductor and return of
    the dismantled items to WESCO stores
    with proper devaluation note.
    a) Dismentalling of PSC poles / RS Joist /         Nos.   4                                0              0                                                  0              0
    Rail poles of various sizes & return of
    same to nearest WNESCO stores.
    b) Dismentalling, redrum of conductors &           Km.    1                                0              0                                                  0              0
    other associated line materiaals and
    return of the same to the nearest Discom
    store.
  B REPLACEMENT OF LT LINE WITH AB
    Cables (Extra items other than that of
    Annexure - 6)
  1 Making straight the existing tilted poles at       No. 122                                 0              0                                                  0              0
    site.
  2 Following strut including supply &
    installation with required clamps.
    a) 8 Mtr / 200 Kg PSC Pole                         No. 45                                  0              0                                                  0              0
    b) 9 Mtr / 300 Kg PSC Pole                         No. 15                                  0              0                                                  0              0
  3 Couping of existing Joist / Rail poles at          Nos. 120                                0              0                                                  0              0
    desired locations as per prior approval
    with supply of all required civil materials to
    complete the work.
  C Construction of NEW / UPGRADATION
    OF EXISTING 11 KV New Line with 55 /
    100 sq.mm AAA Conductor (Extra
    items other than that of Annexure - 3 &
    4) .
  1 Following sizes Single pole structure & its
    erection including fitting of all accessories
    (X-arm, insulator, fitting, coil earthing,
    grouting, danger board, anticlimbing etc.
    complete) as per standard approved
    drawing/schedule & ISS/REC.

       a) 9 Mtr / 300 Kg PSC Pole                      No. 350                                 0              0                                                  0              0
       b) 12 Mtr R.S Joist Pole (150x150 mm,           No. 120                                 0              0                                                  0              0
       34.6 kg/mtr.)
   2   Following sizes of Double Pole structure &
       its erection including fitting of all
       accessories (straight X-arm, X-bracing,
       insulator, fitting, coil earthing, grouting,
       danger board, anti climbing etc. complete)
       as       per        standard        approved
       drawing/schedule & ISS/REC.
       a) 9 Mtr / 300 Kg PSC Pole                      No. 200                                 0              0                                                  0              0
       b) 11 Mtr / 330 kg PSC Pole                     No. 75                                  0              0                                                  0              0
       c) 12 Mtr R.S.Joist (150x150 mm, 34.6           No. 30                                  0              0                                                  0              0
       kg/mtr.)
   3   Following Triple Pole structure & its
       erection including fitting of all accessories
       (X-arm, X-bracing, insulator, fitting, coil
       earthing, grouting, danger board, anti
       climbing etc. complete) as per standard
       approved drawing/schedule & ISS / REC.

       a) 9 Mtr / 300 kg PSC Pole                    No.      20                               0              0                                                  0              0
       b) 11 Mtr / 330 Kg PSC Pole                   No.      30                               0              0                                                  0              0
       c) 12 Mtr R.S. Joist (150x150 mm, 34.6 No.             10                               0              0                                                  0              0
       kg/mtr)
   4   Following Four Pole structure & its
       erection including fitting of all accessories
       (X-arm, X-bracing insulator, fitting, coil
       earthing, grouting, danger board, anti
       climbing etc. complete) as per standard
       approved drawing/schedule & ISS /REC.

       a) 9 Mtr / 300 kg PSC Pole                      No.    20                               0              0                                                  0              0




Name of the Bidder                                                               Page No. _____                                                                  Stamp / Signature Date
                                                                                         Supply                                                       Installation




                                                                                                                                                            Total Unit
                                                                 Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                                price with all  Insurance       price of                    Handling &                      Erection &
                                                                  Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                               Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.               Item-Description                  Unit Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                          2                        3    4          5            6              7               8             9               10             11                 12
      b) 11 Mtr / 330 Kg PSC Pole                     No. 30                                       0               0                                             0                 0
      c) 12 Mtr R.S. Joist (150x150 mm, 34.6 No. 10                                                0               0                                             0                 0
      kg/mtr)
   5 Following NBLS Tower structure & its
      erection including fitting of all accessories
      (X-arm, insulator, fitting, earthing, grouting,
      danger board, anti climbing etc. complete
      )    as      per      standard       approved
      drawing/schedule & ISS.

      a) Normal height ( 13 Mtr )                   No.    5                                       0              0                                                  0              0
      b) Normal height + 3 Mtrs                     No.    5                                       0              0                                                  0              0
      c) Normal height + 6 Mtrs.                    No.    5                                       0              0                                                  0              0




Name of the Bidder                                                                   Page No. _____                                                                  Stamp / Signature Date
                                                                                         Supply                                                       Installation




                                                                                                                                                            Total Unit
                                                                 Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                                price with all  Insurance       price of                    Handling &                      Erection &
                                                                  Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                               Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.                Item-Description                 Unit Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                        2                          3    4          5            6              7               8             9               10             11                 12
   6 Guarding for Road /11 KV / L.T. Line etc.
      crossing with supply of all materials and
      its installation as per standard approved
      drawing & ISS/REC as below.

       a) Up to span length of 50 Mtrs.               No.    5                                     0              0                                                  0              0
       b) Up to span length of 100 Mtrs.              No.    5                                     0              0                                                  0              0
   7   Following strut including supply &
       installation with required clamps &
       connectors in complete
       a) 9 Mtr / 300 kg PSC Pole                     No.    15                                    0              0                                                  0              0
       b) 11 Mtr / 330 Kg PSC Pole                    No.    10                                    0              0                                                  0              0
   8   Provision of 11 kv LA in line (3 phases)       No.    15                                    0              0                                                  0              0
       at desired locations & its installation in
       Complete including earthing with GI flat &
       2 nos. earth electrode as per standard
       approved drawing & ISS/REC.
   9   Provision of 11 kv A.B switch (3 pole) in      set    15                                    0              0                                                  0              0
       line at desired locations & its installation
       complete including earthing with GI flat &
       1 no. earth electrode as per standard
       approved drawing & ISS / REC.

  10 Provision of 11 kv H.G.Fuse (3 pole) in set             15                                    0              0                                                  0              0
     line at desired locations & its installation
     complete including earthing with GI flat &
     1 no. earth electrode as per standard
     approved drawing & ISS/REC.

  11 Installation of 300 sq.mm 3 core, 11 KV,         Mtrs 200                 To be issued by WESCO                                                                 0              0
     XLPE cable at desired location with its
     earthing as per standard approved
     drawing & ISS / REC.
  12 Installation of Out door type 300 sq.mm, 3       Nos.   8                 To be issued by WESCO                                                                 0              0
     core, XLPE end jointing.
  13 Making straight the existing tilted poles at     No.    50                                    0              0                                                  0              0
     site
  14 Couping of existing Joist / Rail poles at        Nos. 50                                      0              0                                                  0              0
     desired locations as per prior approval
     with supply of all required civil materials to
     complete the work
  15 Replacement of damaged Disc insulator            set    20                                    0              0                                                  0              0
     with hardware fitting at required existing
     structures (PSC Pole / RS Joist / Rail
     Pole) of 11 KV transmission line.




Name of the Bidder                                                                   Page No. _____                                                                  Stamp / Signature Date
                                                                                       Supply                                                       Installation




                                                                                                                                                          Total Unit
                                                               Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                              price with all  Insurance       price of                    Handling &                      Erection &
                                                                Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                             Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.                Item-Description               Unit Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                         2                       3    4          5            6              7               8             9               10             11                 12
  16    Replacement of damaged Pin insulator set 20                                              0               0                                             0                 0
        with GI Pin at required existing structures
        (PSC Poles / RS Joist / Rail pole) of 11
        KV transmission line.
  17    Replacement of V Cross arms with back set 20                                             0              0                                                  0              0
        clamp, nut & bolts etc at required existing
        structures (PSC Poles / RS Joist / Rail
        pole) of 11 KV transmission line.

  18 Replacement of Pole top bracket with set               20                                   0              0                                                  0              0
     back clamp, nut & bolts etc at required
     existing structures (PSC Poles / RS Joist /
     Rail pole) of 11 KV transmission line.

  D Construction of NEW / UPGRADATION
    OF EXISTING 33 KV New Line with 100
    / 232 sq.mm AAA Conductor (Extra
    items other than that of Annexure - 5 &
    6).
  1 Following Single pole structure & its
    erection including fitting of all
    accessories (X-arm, insulator, fitting,
    earthing, grouting, danger board,
    anticlimbing etc. complete) as per
    standard approved drawing/schedule
    & ISS/REC.
    a) 10 Mtr / 425 kg PSC Pole                   No.       40                                   0              0                                                  0              0
    b) 13 Mtr RS Joist Pole (150x150 mm, No.                7                                    0              0                                                  0              0
    34.6 kg/mtr).
  2 Following Double Pole structure & its
    erection including fitting of all accessories
    (X-arm, X-bracing, insulator, hardware
    fitting, coil earthing, grouting, danger
    board, anti climbing etc. complete) as per
    standard approved drawing/schedule &
    ISS /REC.

        a) 9 Mtr / 300 kg PSC Pole                    No.   15                                   0              0                                                  0              0
        b) 13 Mtr R.S. Joist (150x150 mm, 34.6 No.          8                                    0              0                                                  0              0
        kg/mtr)
   3    Following Triple Pole structure & its
        erection including fitting of all accessories
        (X-arm, X-bracing, insulator, hardware
        fitting, coil earthing, grouting, danger
        board, anti climbing etc. complete) as per
        standard approved drawing/schedule &
        ISS.




Name of the Bidder                                                                 Page No. _____                                                                  Stamp / Signature Date
                                                                                               Supply                                                       Installation




                                                                                                                                                                  Total Unit
                                                                       Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                                      price with all  Insurance       price of                    Handling &                      Erection &
                                                                        Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                                     Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.                  Item-Description                   Unit   Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                           2                           3      4          5            6              7               8             9               10             11                 12
        a) 9 Mtr , 300 Kg PSC Pole                        No.     5                                      0               0                                             0                 0
        b) 10 Mtr / 425 kg PSC Pole                       No.     5                                      0               0                                             0                 0
        c) 13 Mtr R.S. Joist (150x150 mm, 34.6            No.     5                                      0               0                                             0                 0
        kg/mtr).
   4    Following Four Pole structure & its
        erection including fitting of all accessories
        (X-arm, X-bracing insulator, hardware
        fitting,clamps, coil earthing, grouting,
        danger board, anti climbing etc. complete)
        as         per      standard        approved
        drawing/schedule & ISS /REC.

        a) 9 Mtr , 300 Kg PSC Pole                        No.     5                                      0              0                                                  0              0
        b) 10 Mtr / 425 kg PSC Pole                       No.     5                                      0              0                                                  0              0
        c) 13 Mtr R.S. Joist (150x150 mm, 34.6            No.     5                                      0              0                                                  0              0
        kg/mtr)
   5    Following NBLS Tower structure & its
        erection including fitting of all accessories
        (X-arm, insulator, fitting, earthing, grouting,
        danger board, anti climbing etc. complete)
        as        per      standard          approved
        drawing/schedule & ISS.
        a) Normal height ( 13 Mtr )                       No.     5                                      0              0                                                  0              0
        b) Normal height + 3 Mtrs                         No.     5                                      0              0                                                  0              0
        c) Normal height + 6 Mtrs.                        No.     5                                      0              0                                                  0              0
   6    Guarding for Road/11 KV/L.T. Line etc.
        crossing with supply of all materials and
        its installation as per standard approved
        drawing & ISS / REC as below.

        a) Up to span length of 50 Mtrs.                  No.     5                                      0              0                                                  0              0
        b) Up to span length of 100 Mtrs.                 No.     5                                      0              0                                                  0              0
   7    Following strut including supply &
        installation with required clamps
        a) 9 Mtr , 415 Kg PSC Pole                        No.    10                                      0              0                                                  0              0
        b) 10 Mtr / 425 kg PSC Pole                       No.    10                                      0              0                                                  0              0
   8    Provision of 33 kv LA in line (3 Phases)          no     5                                       0              0                                                  0              0
        at desired locations & its installation in
        Complete including earthing with GI flat &
        2 nos. of electrode as per standard
        approved drawing & ISS/REC.
   9    Provision of 33 kv A.B switch in line (3          no      5                                      0              0                                                  0              0
        phases) at desired locations & its
        installation in Complete including earthing
        with GI flat & 1 no.of earth electrode as
        per standard approved drawing &
        ISS/REC.




Name of the Bidder                                                                         Page No. _____                                                                  Stamp / Signature Date
                                                                                        Supply                                                       Installation




                                                                                                                                                           Total Unit
                                                                Unit Supply Unit Freight,     Total Unit                  Unit Erection,                  charges FOR
                                                               price with all  Insurance       price of                    Handling &                      Erection &
                                                                 Taxes and    charges for    material FOR                Commissioning                   Commissioning
  Sl.                                                              Duties      Transit &     destination    Total Supply    charges/     Service tax* on (with all taxes) Total Installation
  No.                 Item-Description               Unit Qty.    ( In Rs:)   storage etc.      (5+6)       Value (4*7) Labour charges Column No. 9          (9+10)         Value (4*11)
   1                         2                        3    4          5            6              7               8             9               10             11                 12
  10    Provision of 33 kv H.G.Fuse in line (3 no          5                                      0               0                                             0                 0
        phase) at desired locations & its
        installation complete including earthing
        with GI flat & 1 no. of electrode as per
        standard approved drawing & ISS/REC.
  11    Making straight the existing tilted poles at No. 30                                       0              0                                                  0              0
        site
  12    Replacement of damaged Disc insulator set 25                                              0              0                                                  0              0
        with hardware fitting at required existing
        structures (PSC Pole / RS Joist / Rail
        Pole) of 33 KV transmission line.

  13 Replacement of damaged Pin insulator set             25                                      0              0                                                  0              0
     with GI Pin at required existing structures
     (PSC Poles / RS Joist / Rail pole) of 33
     KV transmission line.
  14 Replacement of V Cross arms with back set            25                                      0              0                                                  0              0
     clamp, nut & bolts etc at required existing
     structures (PSC Poles / RS Joist / Rail
     pole) of 33 KV transmission line.

  15 Replacement of Pole top bracket with set             25                                      0              0                                                  0              0
     back clamp, nut & bolts etc at required
     existing structures (PSC Poles / RS Joist /
     Rail pole) of 33 KV transmission line.

  16 Couping of existing Joist / Rail poles at No.        70                                      0              0                                                  0              0
     desired locations as per prior approval
     with supply of all required civil materials to
     complete the work.
                                       Total value                                                               0                                                                 0
                           Total value in words




Name of the Bidder                                                                  Page No. _____                                                                  Stamp / Signature Date
                           ABSTRACT PRICE SCHEDULE - ANNEXURE - 8 WESCO (Bargarh)

                                                                   Unit Price of material for
                                                                    Destination (In Rs) & its
                                                                   installation as estimated
                                                                  in break up Annexure - 1,
                                                                          2, 3, 4, 5, 6, 7
                                                        Tender                                             Unit Break up
  SL.                                                   Quantit Suppl Installa                 Total Cost price schedule
  No.              Item Description                Unit   y       y     tion          Total     of Item       details
                                                                                   (vii)=(v+vi (vii)=(iv x
  (i)                      (ii)                    (iii)   (iv)    (v)      (vi)
                                                                                         )         vii)
   1    HVDS System with 16 KVA, 11/0.25 KV                                                                   Details
        Distribution Transformer & 11 kv Link                                                               enclosed in
        line to substation with 55 sq.mm                                                                   Annexure - 1
        AAAC                                                                                                  WESCO
        a) Construction of Single Pole mounted No          125      0        0          0           0
        16 KVA, 11/0.25 KV Substation
        b) 11 KV link line ( 3 phase) to substation Km.    25       0        0         0          0
        with 55 sq.mm AAA Conductor

   2    New 11 kv Feeder (3 phase) with 100 Km.             5       0        0         0          0       Enclosed as
        Sq.mm AAA Conductor                                                                              Annexure - 2
                                                                                                            WESCO
   3    Upgradation of existing 11 KV Feeder       Km.     143      0        0         0          0       Enclosed as
        (3 phases) with 100 sq.mm AAA                                                                    Annexure - 3 -
        Conductor                                                                                           WESCO
   4    New 33 KV Feeder (3 phase) with                                                                   Enclosed as
        following sizes of AAA Conductor                                                                 Annexure - 4 -
        a) with 100 sq.mm AAA Conductor            Km.      7       0        0         0          0         WESCO
        b) with 232 sq.mm AAA Conductor            Km.      0       0        0         0          0
   5    Upgradation of existing 33 KV Feeder                                                              Enclosed as
        (3 phases) with following size of AAA                                                            Annexure - 5 -
        Conductor                                                                                           WESCO
        a) with 100 sq.mm AAA Conductor            Km.     90       0        0         0          0
        b) with 232 sq.mm AAA Conductor            Km.      0       0        0         0          0
   6    Provision of LT LINE WITH AB Cables                                                               Enclosed as
        with cable accessories of following                                                               Annexure - 6
        sizes.                                                                                              WESCO
        a) 3 x 95 + 1 x 55 + 1x16 MM2              Km.     69       0        0         0          0
        b)3 x 50 + 1 x 35 + 1 x 16 MM2             Km.     53       0        0         0          0
        Dismentalling of existing bare conductor   Km.     122      0        0         0          0
        with accessories of LT Line
   7    TENTATIVE EXTRA ITEMS OVER &               Lot Qty. as      0        0         0          0       Enclosed as
        ABOVE ITEMS UNDER ANNEXURE -                   per                                               Annexure - 7 -
        (1, 2, 3, 4, 5, 6) AS PER SITE                 Annexu                                               WESCO
        REQUIREMENT                                    re
        Grand Total Value of Tender                                 0        0         0          0

        Value in Words




Name of the Bidder                                   Page No. _____                             Stamp / Signature Date

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:10
posted:8/13/2011
language:English
pages:23
Description: Taxes an the Labour Supply document sample