Contractors Paint Invoice - Excel

Description

Contractors Paint Invoice document sample

Shared by: sdk14129
Categories
Tags
-
Stats
views:
73
posted:
8/12/2011
language:
English
pages:
4
Document Sample
scope of work template
							 Date No. Question                                                            Response
5/14/09 1 Will there be area within close proximity of the project for:       See Below

                                                                              There is no office space available on the entire campus.
                                                                              Former housekeeping and storage closet spaces are
                                                                              available for contractors use but these are extremely
                           a.    Office trailer                               small (approximately 50 square feet). If the contractor
                                                                              wishes to use such a space, one closet will be made
                                                                              available for contractors use.
                                                                              A location for a dumpster will be provided in the south
                           b.    Dumpster
                                                                              parking lot, south side of Bldg 1D.
                                                                              A 4’X20’ section of the mechanical room to the west of
                                                                              the pharmacy on the 1st floor will be available for
                                                                              material staging. Contractor will need to schedule
                           c.    Material staging                             delivery of the air handler in such a manner that the unit
                                                                              is set on the roof the same day it arrives at the site. On
                                                                              site storage of the air handler will not be provided.

          2                                                                   Yes. The restrooms to the south of the mechanical room
                                                                              on the first floor will be available for contractor use.
              Will we be able to use the Hospital restrooms                   Contractor will be expected to practice good
                                                                              housekeeping or lose the privilege.

          3                                                                   Yes. As indicated in Section 01 00 00 of the General
              Will we be required to create a negative air condition during   Requirements in the Specifications and as defined in the
              demolition?                                                     ICRA..

          4                                                                   Contractor will be limited to use of stairwell and one
                                                                              elevator for use. Contractors designated stairwell is the
                                                                              one on the southwest corner of the campus in Building
                                                                              1D. Use of stairwell by contractor will not be limited.
              What is the closest exit for removing demo material             Contractor's elevator will be one of the two "Blue
                                                                              Elevators" in Building 1D. Use of the elevator will be
                                                                              limited to after hours only (anytime other than 7:00 AM to
                                                                              5:00 PM on Monday through Friday).
          5                                                                   Yes. A crane can be staged in the parking lot to the
                                                                              south of Bldg 1D. The crane staging will be required to
              Can we stage a crane in the parking lot on the south side       be completed on a Saturday or Sunday. Contractor will
                                                                              be required to deliver the air handler to the site on the
                                                                              same day it is mounted on the roof.
 Date     No. Question                                                         Response
           6                                                                   Section 01 00 00 of the General Requirements clarifies
              Will there be badging or security check in daily?                the badging requirements.
           7                                                                   Gang boxes can be left in the construction zone once
                                                                               the construction area is established. Until a construction
                                                                               zone has been established, gang boxes can be left in
               Can we leave gang boxes in the mechanical room                  the mechanical room as long as they are locked.



5/15/09    1 Detail 2/AS-101 shows work on the 2nd floor. Is this area         See new detail 3/AS-101 for reference of the vicinity of
             accessible? is it a clean room? Is it after hours work? Do we     this area. The area is accessible. This is a Mech.
             have to vacate the area. Please clarify the finish on the         Room. Work can occur during government occupied
             drywall? Is it painted?                                           hours. VA will vacate the area. Finish: Paint, see Key
                                                                               Note 36.
           2 Detail 3/AS-102 shows work in the ground floor. Is it             See new destail 2/AS-102 for reference of the vicinity of
             available, accessible any time? What type of ceiling texture is   this area. Accessibilitly/work in this area has to be co-
             required. Is there a spec on the access doors? Is this            ordinated with VA. Provide "Orange Peel" ceiling texture,
             weekend work?                                                     finish: Paint. See specification section 08 31 13 for
                                                                               specification regarding the access door. This work is to
                                                                               be accomplished during government un-occupied hours
                                                                               (weekend is acceptable).
 Date No. Question                                                          Response
5/18/09 1 Contract Duration of 135 calendar Days – Solicitation             The 135 calendar day schedule is intended to be on site
          documents indicates a 135 calendar day construction               work duration. A separate Notice To Proceed Letter will
          schedule after the issuance of NTP. The NTP will not be           be issued for Materials so that the Contractor may
          issued until all submittals and equipment are                     proceed with obtaining approval of all submittals and
          delivered/available on site. In order to proceed with shop        procurement of critical equipment items. The
          drawings and submittals a NTP will need to be issued.             Government will provide payment for selected pieces of
          Furthermore, in order to receive the new roof-top AHU, which      equipment once contractor obtains title to the equipment
          is to be installed during Phase I, the new structural steel       even if installation is scheduled to occur in the future as
          support system will need to be in installed in order to do so.    long as the equipment is stored in a properly secure and
          This will require field measuring and shop drawing approval       bonded warehouse. Once all items are received and the
          before ordering the steel and the subsequent erection of it.      Contractor is ready to proceed with work on site, a Pre-
          We strongly encourage consideration be given to an                Con meeting will be held to go over all the site issues
          extension of contract duration, or redefine the NTP process in    and a Notice to Proceed with construciton will be issued.
          a manner that will sufficiently accommodate the work
          required, as designed and phased. Specifically the submittal
          and installation of roof-top AHU steel structure.

            See attached rough preliminary schedule reflecting 252 days
            from NTP, please note that the 60 days of lead time
            associated with the fabrication of the AHU is a guess and
            could easily be longer, based on recent projects. This
            schedule merely highlights the difficulty in time associated
            with the acquisition of the new AHU.


         2 Special Inspections – Spec section 01 45 29 Testing Lab          The VA will select a qualified testing agency to perform
           Services indicates that Special Inspections are to be Retained   all tests required by the contract. The VA will scheduled
           by the VA but Paid by Contractor? How does that work?            the testing agency on site as necessary in order to
           Please clarify as it does not appear possible to quantify a      perform all required tests. Invoice for all tests will be
           service that the VA is going to coordinate.                      forwarded to the contractor for payment. Contractor is to
                                                                            review the list of tests as required in the contract
                                                                            documents and assure costs for performing these tests
                                                                            are included in his bid price.

         3 QCM – Spec section 01 45 00 requires the contractor to           The contractor's QCM must be a person with experience
           provide a Quality Control Manager, with very specific and        and background capable of assuring that all work
           significant background and experience. However, the spec         performed is in accordance with the contract documents.
           specifies this QCM cannot serve as the project                   This person cannot be the superintendent as described
           superintendent. Please confirm the role & qualifications of      in Spec section 01 45 00.
           the QCM under this contract?
 Date     No. Question                                                          Response
           4 Certified Industrial Hygienist/Certified Safety Professional –     The Government confirms that the superintendent, QCM
              Spec section 01 52 50 Safety Requirements indicates that a        and CIH/CSP are to be distinct people.
              CIH or CSP must be retained by the Contractor to prepare the
              HASP, conduct hazard analyses and prepare detailed plan for
              demo/removal & disposal of materials. It appears that a
              clear distinction between the Superintendent, QCM &
              CIH/CSP is made. Please confirm this requirements is
              required under this contract.
           5 Infectious Control Classification Determination – Spec section     Enclosure (3) of the amendment is provided in response
              01 52 50 requires the Contractor to determine the correct         to this question.
              Infectious Control Classification for this project based on the
              Matrix provided in the spec section. Concern exists about the
              qualifications of Contractors to make this determination or
              assessment. To remove any uncertainty, could the VA
              confirm the level of Infectious Control required for this
              contract?
           6 Guarantee Period Services Cost – Bid Schedule indicates            The requirements for Extended Guarantee Period
              cost associated with Guarantee Period Services but unclear        Services are identified in Section 22 05 11, starting in
              as to the extent of this Guarantee Period. Reference to this      paragraph 1.3 E and throughout this section and in
              Guarantee Period are made in VAAR 852.236-82 Payment              Section 23 09 23 paragraph 1.7.
              Under Fixed Price Construction Contracts (6) ii; and VAAR
              852.246-75 Warranty for Construction – Guarantee Period
              Services, but again no real understanding as to what the
              Guarantee Period Services is. Please clarify.

5/18/09    1 Has an asbestos survey been done? According to Washoe              Answer: An asbestos survey has been completed and
             County Board of Health Regulations Governing Air Quality           there is no asbestos in the area. The VA will obtain the
             Management an asbestos survey and acknowledgement of               asbestos sign-off from Washoe County. There can
             asbestos assessment sign-off must be obtained from                 never be an absolute guarantee. If a contractor does
             Washoe County AQMD. According to Region IX, US EPA,                encounter what appears to be asbestos, they are
             No commercial facility or residential structure the will become    expected to stop work and notify the Contracting Officer.
             a commercial enterprise regardless of the age of the building,
             is exempt from this requirement.

						
Related docs
Other docs by sdk14129
Contractors Progress Report
Views: 5  |  Downloads: 0
Contractors Guide to Environmental Protection
Views: 30  |  Downloads: 0
Contractors Demand for Payment
Views: 6  |  Downloads: 0
Contractors Demand for Payment
Views: 8  |  Downloads: 0
Contractors Services and Repairs
Views: 14  |  Downloads: 0
Contracts Concept Map
Views: 6  |  Downloads: 1
Contractors Data Brief
Views: 21  |  Downloads: 0
Contractors Payment Application Status
Views: 11  |  Downloads: 0
Contractors Refferal Fee
Views: 8  |  Downloads: 0