Scope of Work Data Cabling - PDF

					PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                                                     Scope of Work

Total Project Summary
Labor and materials will be provided to install the following:

        - (5028) blue plenum Cat 6 cables for data applications.
        - (1814) white plenum Cat 6 cables for voice applications.
        - (25) racks, (1) wall rack, (19) ladder runway sections, and related equipment for (7)
        Telecommunications Rooms.
        Telecommunications Rooms will be connected with the following backbone cables:

                  Server Room to 1st Floor West IDF
                  - 0 pairs of plenum Cat 3 cable.
                  - (1) 12 strand 50/125 OM4 plenum armored cable .
                  Server Room to 1st Floor East IDF
                  - (1) 12 strand 50/125 OM4 plenum armored cable .
                  Server Room to 2nd Floor Central IDF
                  - (1) 12 strand 50/125 OM4 plenum armored cable .
                  Server Room to 2nd Floor West IDF
                  - (0) blue plenum Cat 5e 4 pair cable.
                  - (1) 12 strand 50/125 OM4 plenum armored cable .
                  Server Room to 2nd Floor East IDF
                  - (1) 12 strand 50/125 OM4 plenum armored cable .
                  Server Room to MPOP
                  - (1) 6 strand single mode plenum armored cable .


Installation Practices
Cable Pathways and Support
        Wherever practical, all cables will be installed running square with building structure.
        Cable bundles will run down hallways or other accessible routes.
        Cables will be supported at a maximum of 5 foot intervals using J-hooks, cable straps,
        conduit, trapeze, or cable tray depending upon the cable quantities and pathway
        conditions. See materials list for proposal details.
        Cable support will be attached to the building structure using hanger wire or all thread
        dedicated for the purpose.


Project Summary
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Labeling
        Each cable will be labeled within 6" of each end with a self-adhesive, machine printed
        label. This label will corresponding to the port labeling scheme at the workstation outlet.
        Each workstation jack will be identified with a distinct identifier using a machine printed
        label. The preferred labeling scheme will identify where the cable terminates at the
        Telecommunications Room end. {ie. Room. ID - Rack ID - Patch Panel ID - Port
        Number} Labeling method will be verified with the customer prior to installation.
        Floor plan locations will be marked with the corresponding jack numbers.

Cable Testing
        All Cat 6 workstation cables will be tested for Cat 6 compliance. A soft copy of test
        results will be provided upon completion of the project.
        All multimode fibers will be measured for attenuation using an Optical Power Meter
        and OTDR. Tests will be done at both 850nm and 1300nm wavelengths. A soft copy of
        test results will be provided upon completion of the project.
        All single mode fibers will be measured for attenuation using an Optical Power Meter
        and OTDR. Tests will be done at both 1320nm and 1550nm wavelengths. A soft copy of
        test results will be provided upon completion of the project.


Grounding
        Racks and related equipment will be connected to grounding busbar using a #6 CU green
        insulated ground wire.
        Busbars in the intermediate communications rooms will be connected to the Main
        Telecommuncations Grounding Busbar in the Server Room with the following
        grounding backbone cable:
                  - #3/0 CU
        Refer to full scope of work for additional details. Customer should request an electrician
        to connect the grounding busbar to the building electrical ground.

As Built Drawings
        A hard and soft copy of floorplans in AutoCAD with workstation locations and numbers
        labeled will be provided upon completion of the project.




Project Summary
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Scope Details

Horizontal Cabling

        data Workstation Cabling
                 Workstation ports for data will be supported by blue plenum Cat 6 cables.
                 Cables for data workstations will terminate on:
                                 - data jack 1 - blue Cat 6 RJ-45 jacks
                                 - data jack 2 - yellow Cat 6 RJ-45 jacks
                                 - data jack 3 - orange Cat 6 RJ-45 jacks
                           and on flat 110 style patch panels in the telecommunications
                           rooms.


        voice Workstation Cabling
                 Workstation ports for voice will be supported by white plenum Cat 6 cables.
                 Cables for voice workstations will terminate on:
                                 - voice jack - gray Cat 6 RJ-45 jacks
                           and on flat 110 style patch panels in the telecommunications
                           rooms.


        Service Loops for Horizontal Cabling at Telecommunications Rooms
                 At the Telecommunications Rooms, 10 foot service loops will be coiled in
                 the ceiling.
        Service Loops for Horizontal Cabling at the Workstation
                 At workstations, 10 foot service loops will be coiled in the ceiling.




Horizontal Cabling Description
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Workstation Outlet Count for Cables Terminating in the Server Room

        At hardwalled office locations, jacks will be installed in white faceplates.
        Qty                      Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
        (25)                   - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




        (20)                   - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) gray Cat 6 RJ-45 jack for voice jack




        (5)                    - wallphones




        At modular furniture locations, jacks will be installed in black snap in furniture faceplates.
        Qty                         Jacks at this outlet
                                     - (1) blue Cat 6 RJ-45 jack for data jack 1
                                     - (1) yellow Cat 6 RJ-45 jack for data jack 2
        (200)
                                     - (1) orange Cat 6 RJ-45 jack for data jack 3
                                     - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (2) blue Cat 6 RJ-45 jacks for data jack 1
        (15)                          - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (1) black blank insert

        At locations where the cable is fed from below the floor, jacks will be installed in white 106
        mounting frames.
        Qty                      Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
        (3)                    - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




Outlet Configuration and Count for Cables Originating in the Server Room
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




        At locations at or above the ceiling, jacks will be installed in white faceplates.
        Qty                      Jacks at this outlet


                               - (1) orange Cat 6 RJ-45 jack for data jack 3
        (5)
                               - (1) white blank insert




Outlet Configuration and Count for Cables Originating in the Server Room
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Workstation Outlet Count for Cables Terminating in the 1st Floor West IDF

        At hardwalled office locations, jacks will be installed in white faceplates.
        Qty                      Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (25)                  - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (5)                   - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (1)                   - wallphone




         At modular furniture locations, jacks will be installed in black surface mount boxes.
         Qty                         Jacks at this outlet
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
                                      - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (237)
                                      - (1) orange Cat 6 RJ-45 jack for data jack 3
                                      - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
         (43)                         - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (2) black blank inserts

         At locations where the cable is fed from below the floor, jacks will be installed in white 106
         mounting frames.
         Qty                     Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (3)                   - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




Outlet Configuration and Count for Cables Originating in the 1st Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




         At locations at or above the ceiling, jacks will be installed in white faceplates.
         Qty                      Jacks at this outlet


                               - (1) orange Cat 6 RJ-45 jack for data jack 3
         (5)
                               - (1) white blank insert




Outlet Configuration and Count for Cables Originating in the 1st Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Workstation Outlet Count for Cables Terminating in the 1st Floor East IDF

        At hardwalled office locations, jacks will be installed in white faceplates.
        Qty                       Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (19)                  - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (2)                   - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (1)                   - wallphone




         At modular furniture locations, jacks will be installed in black surface mount boxes.
         Qty                         Jacks at this outlet
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
                                      - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (321)
                                      - (1) orange Cat 6 RJ-45 jack for data jack 3
                                      - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
         (32)                         - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (2) black blank inserts

         At locations where the cable is fed from below the floor, jacks will be installed in white 106
         mounting frames.
         Qty                     Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (5)                   - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




Outlet Configuration and Count for Cables Originating in the 1st Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




         At locations at or above the ceiling, jacks will be installed in white faceplates.
         Qty                      Jacks at this outlet


                               - (1) orange Cat 6 RJ-45 jack for data jack 3
         (8)
                               - (1) white blank insert




Outlet Configuration and Count for Cables Originating in the 1st Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Workstation Outlet Count for Cables Terminating in the 2nd Floor Central IDF

        At hardwalled office locations, jacks will be installed in white faceplates.
        Qty                      Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (28)                  - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (3)                   - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (5)                   - wallphones




         At modular furniture locations, jacks will be installed in black surface mount boxes.
         Qty                         Jacks at this outlet
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
                                      - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (236)
                                      - (1) orange Cat 6 RJ-45 jack for data jack 3
                                      - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
         (26)                         - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (2) black blank inserts

         At locations at or above the ceiling, jacks will be installed in white faceplates.
         Qty                      Jacks at this outlet



         (7)                   - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) white blank insert




Outlet Configuration and Count for Cables Originating in the 2nd Floor Central IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Workstation Outlet Count for Cables Terminating in the 2nd Floor West IDF

        At hardwalled office locations, jacks will be installed in white faceplates.
        Qty                      Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (34)                  - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (6)                   - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (5)                   - wallphones




         At modular furniture locations, jacks will be installed in black surface mount boxes.
         Qty                        Jacks at this outlet
                                     - (1) blue Cat 6 RJ-45 jack for data jack 1
                                     - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (187)
                                     - (1) orange Cat 6 RJ-45 jack for data jack 3
                                     - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
         (56)                         - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (2) black blank inserts

         At locations where the cable is fed from below the floor, jacks will be installed in white 106
         mounting frames.
         Qty                     Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (5)                   - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




Outlet Configuration and Count for Cables Originating in the 2nd Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




         At locations at or above the ceiling, jacks will be installed in white faceplates.
         Qty                     Jacks at this outlet


                               - (1) orange Cat 6 RJ-45 jack for data jack 3
         (15)
                               - (1) white blank insert




Outlet Configuration and Count for Cables Originating in the 2nd Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Workstation Outlet Count for Cables Terminating in the 2nd Floor East IDF

        At hardwalled office locations, jacks will be installed in white faceplates.
        Qty                      Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (23)                  - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (6)                   - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) gray Cat 6 RJ-45 jack for voice jack




         (5)                   - wallphones




         At modular furniture locations, jacks will be installed in black surface mount boxes.
         Qty                         Jacks at this outlet
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
                                      - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (221)
                                      - (1) orange Cat 6 RJ-45 jack for data jack 3
                                      - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (1) blue Cat 6 RJ-45 jack for data jack 1
         (14)                         - (1) gray Cat 6 RJ-45 jack for voice jack
                                      - (2) black blank inserts

         At locations where the cable is fed from below the floor, jacks will be installed in white 106
         mounting frames.
         Qty                     Jacks at this outlet
                               - (1) blue Cat 6 RJ-45 jack for data jack 1
                               - (1) yellow Cat 6 RJ-45 jack for data jack 2
         (5)                   - (1) orange Cat 6 RJ-45 jack for data jack 3
                               - (1) gray Cat 6 RJ-45 jack for voice jack




Outlet Configuration and Count for Cables Originating in the 2nd Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




         At locations at or above the ceiling, jacks will be installed in white faceplates.
         Qty                      Jacks at this outlet


                               - (1) orange Cat 6 RJ-45 jack for data jack 3
         (5)
                               - (1) white blank insert




Outlet Configuration and Count for Cables Originating in the 2nd Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Backbone Cabling

        Server Room to 1st Floor West IDF
                Fiber Backbone - A 12 strand 50/125 OM4 plenum armored fiber cable
                cable armored will be installed between the Server Room and the 1st Floor
                West IDF.
                The fiber cable will terminate with LC simplex connectors in a fiber
                enclosure on a floor rack at both ends.

                Telecommunication Grounding Backbone Conductor - A copper
                grounding cable will be installed between the Server Room and the 1st Floor
                West IDF. The cable will be bonded to a telecommunications bus bar
                provided and installed as part of this proposal in the Server Room and the 1st
                Floor West IDF. Refer to the materials list for size of grounding conductors
                that will be used.


        Server Room to 1st Floor East IDF
                Fiber Backbone - A 12 strand 50/125 OM4 plenum armored fiber cable
                cable armored will be installed between the Server Room and the 1st Floor
                East IDF.
                The fiber cable will terminate with LC simplex connectors in a fiber
                enclosure on a floor rack at both ends.

                Telecommunication Grounding Backbone Conductor - A copper
                grounding cable will be installed between the Server Room and the 1st Floor
                East IDF. The cable will be bonded to a telecommunications bus bar
                provided and installed as part of this proposal in the Server Room and the 1st
                Floor East IDF. Refer to the materials list for size of grounding conductors
                that will be used.


        Server Room to 2nd Floor Central IDF
                Fiber Backbone - A 12 strand 50/125 OM4 plenum armored fiber cable
                cable armored will be installed between the Server Room and the 2nd Floor
                Central IDF.
                The fiber cable will terminate with LC simplex connectors in a fiber
                enclosure on a floor rack at both ends.

                Telecommunication Grounding Backbone Conductor - A copper
                grounding cable will be installed between the Server Room and the 2nd
                Floor Central IDF. The cable will be bonded to a telecommunications bus
                bar provided and installed as part of this proposal in the Server Room and the
                2nd Floor Central IDF. Refer to the materials list for size of grounding

Backbone Cable Description
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                conductors that will be used.


        Server Room to 2nd Floor West IDF
                Fiber Backbone - A 12 strand 50/125 OM4 plenum armored fiber cable
                cable armored will be installed between the Server Room and the 2nd Floor
                West IDF.
                The fiber cable will terminate with LC simplex connectors in a fiber
                enclosure on a floor rack at both ends.

                Telecommunication Grounding Backbone Conductor - A copper
                grounding cable will be installed between the Server Room and the 2nd
                Floor West IDF. The cable will be bonded to a telecommunications bus bar
                provided and installed as part of this proposal in the Server Room and the
                2nd Floor West IDF. Refer to the materials list for size of grounding
                conductors that will be used.


        Server Room to 2nd Floor East IDF
                Fiber Backbone - A 12 strand 50/125 OM4 plenum armored fiber cable
                cable armored will be installed between the Server Room and the 2nd Floor
                East IDF.
                The fiber cable will terminate with LC simplex connectors in a fiber
                enclosure on a floor rack at both ends.

                Telecommunication Grounding Backbone Conductor - A copper
                grounding cable will be installed between the Server Room and the 2nd
                Floor East IDF. The cable will be bonded to a telecommunications bus bar
                provided and installed as part of this proposal in the Server Room and the
                2nd Floor East IDF. Refer to the materials list for size of grounding
                conductors that will be used.


        Server Room to MPOP
                Fiber Backbone - A 6 strand single mode plenum armored fiber cable cable
                armored will be installed between the Server Room and the MPOP.
                The fiber cable will terminate with LC simplex connectors in a fiber
                enclosure on a floor rack in the Server Room and on LC simplex connectors
                in a fiber enclosure on a wall rack in the MPOP.

                Telecommunication Grounding Backbone Conductor - A copper
                grounding cable will be installed between the Server Room and the MPOP.
                The cable will be bonded to a telecommunications bus bar provided and
                installed as part of this proposal in the Server Room and the MPOP. Refer to
                the materials list for size of grounding conductors that will be used.

Backbone Cable Description
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Backbone Cable Description
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Configuration of the Server Room
      The following support hardware will be installed in the Server Room:
             (4) - black 19" x 7' equipment racks.
             (3) - vertical cable managers installed between racks.
             (2) - vertical cable managers installed on the ends of racks.
             (3) - sections of black 12" wide ladder runway.
                    The ladder runway will be installed with overhead supports attached to the building
                    structure. The bottom of the runway will be 7' 6" above the floor.

      The racks will be arranged as shown below.




      The following wall mounted support hardware will be installed:
             (1) - grounding bus bar.
             The location of wall mounted support hardware will be determined based upon site conditions
             and discussion with the customer's representative.

      All racks and ladder runway will be grounded to the grounding bus bar with #6 CU ground wire.
      Termination Panels on Floor Racks
      The following termination panels will be installed on 19" x 7' equipment racks in the Server Room:


             Rack 1 will have the following panels installed starting at the top.
                    No termination panels will be installed here

                    (1) - 1RU horizontal cable manager
                    (6) - 48 port Cat 6 patch panels for data cables
                    Alternating with
                    (6) - 2RU horizontal cable managers

             Rack 2 will have the following panels installed starting at the top.

                    (1) - 8 panel 2RU rack mount fiber enclosure loaded with the following adapter
                    panels:
                              (1) - 12 strand LC multimode fiber adapter panel for fiber to the 1st
                              Floor West IDF

Room Layout for Server Room
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                              (1) - 12 strand LC multimode fiber adapter panel for fiber to the 1st
                              Floor East IDF
                              (1) - 12 strand LC multimode fiber adapter panel for fiber to the 2nd
                              Floor Central IDF
                              (1) - 12 strand LC multimode fiber adapter panel for fiber to the 2nd
                              Floor West IDF
                              (1) - 12 strand LC multimode fiber adapter panel for fiber to the 2nd
                              Floor East IDF
                              (1) - 12 strand LC single mode fiber adapter panel for fiber to the MPOP
                              (2) - blank panels
                    (1) - 1RU horizontal cable manager
                    (5) - 48 port Cat 6 patch panels for data cables
                    Alternating with
                    (5) - 2RU horizontal cable managers

             Rack 3 will have the following panels installed starting at the top.
                    No termination panels will be installed here

                    (1) - 1RU horizontal cable manager
                    (5) - 48 port Cat 6 patch panels for data cables
                    Alternating with
                    (5) - 2RU horizontal cable managers

             Rack 4 will have the following panels installed starting at the top.
                    No termination panels will be installed here

                    (1) - 1RU horizontal cable manager
                    (6) - 48 port Cat 6 patch panels for voice cables
                    Alternating with
                    (6) - 2RU horizontal cable managers



      Open termination ports for additional cables
             There are (29) open ports for additional data cables.
             There are (20) open ports for additional voice cables.




Room Layout for Server Room
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




RACK ELEVATION - Server Room




      RACK 1                  RACK 2                  RACK 3     RACK 4
  Cable managers provided may look different than those shown. Refer to the bill of materials for
  managers that will be provided.




Room Layout for Server Room
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Configuration of the 1st Floor West IDF
      The following support hardware will be installed in the 1st Floor West IDF:
             (4) - black 19" x 7' equipment racks.
             (2) - vertical cable managers installed between racks.
             (4) - vertical cable managers installed on the ends of racks.
             (3) - sections of black 12" wide ladder runway.
                     The ladder runway will be installed with overhead supports attached to the building
                     structure. The bottom of the runway will be 7' 6" above the floor.

      The racks will be arranged as shown below.




      The following wall mounted support hardware will be installed:
             (1) - grounding bus bar.
             The location of wall mounted support hardware will be determined based upon site conditions
             and discussion with the customer's representative.

      All racks and ladder runway will be grounded to the grounding bus bar with #6 CU ground wire.
      Termination Panels on Floor Racks
      The following termination panels will be installed on 19" x 7' equipment racks in the 1st Floor West IDF:


             Rack 1 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

             Rack 2 will have the following panels installed starting at the top.
Room Layout for 1st Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




             Rack 2 will have the following panels installed starting at the top.

                     (1) - 4 panel 1RU rack mount fiber enclosure for fiber backbone to the Server
                     Room The enclosure will be loaded with (1) 12 strand LC multimode fiber adapter
                     panel and (3) blank panels
                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

             Rack 3 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

             Rack 4 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (7) - 48 port Cat 6 patch panels for voice cables
                     Alternating with
                     (7) - 2RU horizontal cable managers



      Open termination ports for additional cables
             There are (16) open ports for additional data cables.
             There are (22) open ports for additional voice cables.




Room Layout for 1st Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




RACK ELEVATION - 1st Floor West IDF




      RACK 1                    RACK 2                           RACK 3    RACK 4
  Cable managers provided may look different than those shown. Refer to the bill of materials for
  managers that will be provided.




Room Layout for 1st Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Configuration of the 1st Floor East IDF
        The following support hardware will be installed in the 1st Floor East IDF:
                 (5) - black 19" x 7' equipment racks.
                 (4) - vertical cable managers installed between racks.
                 (2) - vertical cable managers installed on the ends of racks.
                 (4) - sections of black 12" wide ladder runway.
                          The ladder runway will be installed with overhead supports
                          attached to the building structure. The bottom of the runway will
                          be 7' 6" above the floor.

        The following wall mounted support hardware will be installed:
                 (1) - grounding bus bar.
                 The location of wall mounted support hardware will be determined based
                 upon site conditions and discussion with the customer's representative.

        All racks and ladder runway will be grounded to the grounding bus bar with #6 CU
        ground wire.
        Termination Panels on Floor Racks
        The following termination panels will be installed on 19" x 7' equipment racks in the 1st
        Floor East IDF:


                 Rack 1 will have the following panels installed starting at the top.
                          No termination panels will be installed here

                          (1) - 1RU horizontal cable manager
                          (6) - 48 port Cat 6 patch panels for data cables
                          Alternating with
                          (6) - 2RU horizontal cable managers

                 Rack 2 will have the following panels installed starting at the top.

                          (1) - 4 panel 1RU rack mount fiber enclosure for fiber backbone
                          to the Server Room The enclosure will be loaded with (1) 12
                          strand LC multimode fiber adapter panel and (3) blank panels
                          (1) - 1RU horizontal cable manager
                          (6) - 48 port Cat 6 patch panels for data cables
                          Alternating with
                          (6) - 2RU horizontal cable managers

                 Rack 3 will have the following panels installed starting at the top.
Room Layout for 1st Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                 Rack 3 will have the following panels installed starting at the top.
                          No termination panels will be installed here

                          (1) - 1RU horizontal cable manager
                          (6) - 48 port Cat 6 patch panels for data cables
                          Alternating with
                          (6) - 2RU horizontal cable managers

                 Rack 4 will have the following panels installed starting at the top.
                          No termination panels will be installed here

                          (1) - 1RU horizontal cable manager
                          (5) - 48 port Cat 6 patch panels for data cables
                          Alternating with
                          (5) - 2RU horizontal cable managers

                 Rack 5 will have the following panels installed starting at the top.
                          No termination panels will be installed here

                          (1) - 1RU horizontal cable manager
                          (8) - 48 port Cat 6 patch panels for voice cables
                          Alternating with
                          (8) - 2RU horizontal cable managers


        Open termination ports for additional cables
                 There are (27) open ports for additional data cables.
                 There are (5) open ports for additional voice cables.




Room Layout for 1st Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




RACK ELEVATION - 1st Floor East IDF




      RACK 1                     RACK 2               RACK 3     RACK 4    RACK 5
  Cable managers provided may look different than those shown. Refer to the bill of materials for
  managers that will be provided.




Room Layout for 1st Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Configuration of the 2nd Floor Central IDF
      The following support hardware will be installed in the 2nd Floor Central IDF:
              (4) - black 19" x 7' equipment racks.
              (3) - vertical cable managers installed between racks.
              (2) - vertical cable managers installed on the ends of racks.
              (3) - sections of black 12" wide ladder runway.
                     The ladder runway will be installed with overhead supports attached to the building
                     structure. The bottom of the runway will be 7' 6" above the floor.

      The racks will be arranged as shown below.




      The following wall mounted support hardware will be installed:
              (1) - grounding bus bar.
              The location of wall mounted support hardware will be determined based upon site conditions
              and discussion with the customer's representative.

      All racks and ladder runway will be grounded to the grounding bus bar with #6 CU ground wire.
      Termination Panels on Floor Racks
      The following termination panels will be installed on 19" x 7' equipment racks in the 2nd Floor Central
      IDF:


              Rack 1 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

              Rack 2 will have the following panels installed starting at the top.

                     (1) - 4 panel 1RU rack mount fiber enclosure for fiber backbone to the Server
                     Room The enclosure will be loaded with (1) 12 strand LC multimode fiber adapter
                     panel and (3) blank panels


Room Layout for 2nd Floor Central IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

              Rack 3 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

              Rack 4 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (7) - 48 port Cat 6 patch panels for voice cables
                     Alternating with
                     (7) - 2RU horizontal cable managers



      Open termination ports for additional cables
              There are (27) open ports for additional data cables.
              There are (40) open ports for additional voice cables.




Room Layout for 2nd Floor Central IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




RACK ELEVATION - 2nd Floor Central IDF




      RACK 1                    RACK 2                RACK 3     RACK 4
  Cable managers provided may look different than those shown. Refer to the bill of materials for
  managers that will be provided.




Room Layout for 2nd Floor Central IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Configuration of the 2nd Floor West IDF
      The following support hardware will be installed in the 2nd Floor West IDF:
             (4) - black 19" x 7' equipment racks.
             (2) - vertical cable managers installed between racks.
             (4) - vertical cable managers installed on the ends of racks.
             (3) - sections of black 12" wide ladder runway.
                    The ladder runway will be installed with overhead supports attached to the building
                    structure. The bottom of the runway will be 7' 6" above the floor.

      The racks will be arranged as shown below.




      The following wall mounted support hardware will be installed:
             (1) - grounding bus bar.
             The location of wall mounted support hardware will be determined based upon site conditions
             and discussion with the customer's representative.

      All racks and ladder runway will be grounded to the grounding bus bar with #6 CU ground wire.
      Termination Panels on Floor Racks
      The following termination panels will be installed on 19" x 7' equipment racks in the 2nd Floor West IDF:


             Rack 1 will have the following panels installed starting at the top.
                    No termination panels will be installed here

                    (1) - 1RU horizontal cable manager
                    (6) - 48 port Cat 6 patch panels for data cables
                    Alternating with
                    (6) - 2RU horizontal cable managers

             Rack 2 will have the following panels installed starting at the top.
Room Layout for 2nd Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




             Rack 2 will have the following panels installed starting at the top.

                    (1) - 4 panel 1RU rack mount fiber enclosure for fiber backbone to the Server
                    Room The enclosure will be loaded with (1) 12 strand LC multimode fiber adapter
                    panel and (3) blank panels
                    (1) - 1RU horizontal cable manager
                    (5) - 48 port Cat 6 patch panels for data cables
                    Alternating with
                    (5) - 2RU horizontal cable managers

             Rack 3 will have the following panels installed starting at the top.
                    No termination panels will be installed here

                    (1) - 1RU horizontal cable manager
                    (5) - 48 port Cat 6 patch panels for data cables
                    Alternating with
                    (5) - 2RU horizontal cable managers

             Rack 4 will have the following panels installed starting at the top.
                    No termination panels will be installed here

                    (1) - 1RU horizontal cable manager
                    (6) - 48 port Cat 6 patch panels for voice cables
                    Alternating with
                    (6) - 2RU horizontal cable managers



      Open termination ports for additional cables
             There are (13) open ports for additional data cables.
             There are (0) open ports for additional voice cables.




Room Layout for 2nd Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




RACK ELEVATION - 2nd Floor West IDF




      RACK 1                   RACK 2                            RACK 3    RACK 4
  Cable managers provided may look different than those shown. Refer to the bill of materials for
  managers that will be provided.




Room Layout for 2nd Floor West IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Configuration of the 2nd Floor East IDF
      The following support hardware will be installed in the 2nd Floor East IDF:
             (4) - black 19" x 7' equipment racks.
             (2) - vertical cable managers installed between racks.
             (4) - vertical cable managers installed on the ends of racks.
             (3) - sections of black 12" wide ladder runway.
                     The ladder runway will be installed with overhead supports attached to the building
                     structure. The bottom of the runway will be 7' 6" above the floor.

      The racks will be arranged as shown below.




      The following wall mounted support hardware will be installed:
             (1) - grounding bus bar.
             The location of wall mounted support hardware will be determined based upon site conditions
             and discussion with the customer's representative.

      All racks and ladder runway will be grounded to the grounding bus bar with #6 CU ground wire.
      Termination Panels on Floor Racks
      The following termination panels will be installed on 19" x 7' equipment racks in the 2nd Floor East IDF:


             Rack 1 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

             Rack 2 will have the following panels installed starting at the top.
Room Layout for 2nd Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




             Rack 2 will have the following panels installed starting at the top.

                     (1) - 4 panel 1RU rack mount fiber enclosure for fiber backbone to the Server
                     Room The enclosure will be loaded with (1) 12 strand LC multimode fiber adapter
                     panel and (3) blank panels
                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (6) - 2RU horizontal cable managers

             Rack 3 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (5) - 48 port Cat 6 patch panels for data cables
                     Alternating with
                     (5) - 2RU horizontal cable managers

             Rack 4 will have the following panels installed starting at the top.
                     No termination panels will be installed here

                     (1) - 1RU horizontal cable manager
                     (6) - 48 port Cat 6 patch panels for voice cables
                     Alternating with
                     (6) - 2RU horizontal cable managers



      Open termination ports for additional cables
             There are (44) open ports for additional data cables.
             There are (19) open ports for additional voice cables.




Room Layout for 2nd Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




RACK ELEVATION - 2nd Floor East IDF




      RACK 1                    RACK 2                           RACK 3    RACK 4
  Cable managers provided may look different than those shown. Refer to the bill of materials for
  managers that will be provided.




Room Layout for 2nd Floor East IDF
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Hardware and Termination Equipment for the MPOP
        The following wall mounted support hardware will be installed in the MPOP:
                (1) - 19in x 24.5in x 18in black wall rack with
                        (1) - 4 panel 1RU rack mount fiber enclosure for fiber backbone
                        to the Server Room. The enclosure will be loaded with (1) 12
                        strand LC single mode fiber adapter panel and (3) blank panels.


                (1) - grounding bus bar.
                The location of wall mounted support hardware will be determined based
                upon site conditions and discussion with the customer's representative.

        The rack will be grounded to the grounding bus bar with #6 CU ground wire.


Open termination ports for additional cables




Room Layout for MPOP
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Patch Cords and Fiber Jumpers
        The following copper patch cords will be provided.
             (2111) - 3 ft blue Cat 6 patch cords
             (3318) - 7 ft blue Cat 6 patch cords
             (1277) - 10 ft blue Cat 6 patch cords
             (576) - 5 ft blue Cat 6 patch cords
        The following fiber jumpers will be provided.
                 (22) - 3 meter duplex LC-LC 50/125 OM4 fiber jumpers
                 (22) - 1 meter duplex LC-LC 50/125 OM4 fiber jumpers




Patch Cords and Fiber Jumpers
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




Assumptions
        Plywood backboards will be provided by others.
        Poke throughs, core holes, and sleeves through brick or masonry will be provided by
        others. Sleeves required through gypsum board walls will be considered part of the
        cabling scope of work.
        Firestopping of holes or sleeves used for communications cabling on this project will be
        considered part of the cabling scope of work.
        Grounding and bonding not described in the scope of work will be done by others. It is
        recommended that connection of the grounding system to the building ground be done
        by an electrician.




Project Assumptions
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                                                                                          1st   1st   2nd   2nd   2nd
                                                                                  Server Floor Floor Floor Floor Floor
                                                                                                                       MPOP Project
     Purpose              Description              Manufacturer    Part Number    Room West East Central West East
                                                                                                                       QTY Total
                                                                                   QTY IDF      IDF   IDF   IDF   IDF
                                                                                         QTY QTY QTY QTY QTY
                              blue
   data station
                          plenum Cat CommScope/Uniprise               6504+       153638 176299 223908 174012 156964 160498   0   1046000
      cables
                             6 cable
                             white
  voice station
                          plenum Cat CommScope/Uniprise               6504+       55717 65280 78794    61538   59875 55925    0   378000
     cables
                             6 cable
                           blue Cat 6
 data jack 1 jack                     CommScope/Uniprise            UNJ600-BL      278    313    379    296    288    269     0    1823
                           RJ-45 jack
                          yellow Cat
 data jack 2 jack          6 RJ-45 CommScope/Uniprise               UNJ600-YL      228    265    345    267    226    249     0    1580
                              jack
                          orange Cat
 data jack 3 jack          6 RJ-45 CommScope/Uniprise               UNJ600-OR      233    270    353    274    241    254     0    1625
                              jack
                           gray Cat 6
 voice jack jack                      CommScope/Uniprise            UNJ600-GY      268    314    379    296    288    269     0    1814
                           RJ-45 jack
    wallphone             wall phone
                                     CommScope/Uniprise            UNF-WL-1P-IV     5      1      1      5      5      5      0     22
     faceplate             faceplate
                            white 2
    2 port wall
                              port            CommScope/Uniprise   UNF-D-2P-WH      20     5      2      3      6      6      0     42
     faceplate
                            faceplate
                            white 4
    4 port wall
                              port            CommScope/Uniprise   UNF-D-4P-WH      25    25     19     28      34     23     0    154
     faceplate
                            faceplate




Bill of Materials for Horizontal Station Cabling
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                  black 4
 4 port modular
                port snap in
    furniture                CommScope/Uniprise                    UNF-MF-4P-BK    215   280   353   262   243   235   0   1588
                 furniture
    faceplate
                 faceplate
  blank inserts
  for modular             black blank
                                      CommScope/Uniprise             UNDC-BK       15    86    64    52    112   28    0   357
    furniture                insert
    faceplates
                            white 4
   4 port floor
                           port 106
    mounted                                   CommScope/Uniprise UNF-FR106-4P-WH    3     3     5     3     5     5    0    24
                           mounting
    faceplate
                             frame
  2 port ceiling            white 2
    mounted                   port            CommScope/Uniprise   UNF-D-2P-WH      5     5     8     7    15     5    0    45
    faceplate               faceplate
  blank inserts
   for ceiling               white
                                       CommScope/Uniprise           UNDC-WH         5     5     8     7    15     5    0    45
    mounted               blank insert
    faceplates
   large (up to
   300 cables)      large
     supports      support
  for horizonal assemblies                          TBD                TBD         60    69    87    67    62    62    0   407
      cable      (up to 300
  estimated by     cables)
 BetterProposals
 medium (up to
   50 cables)     medium
    supports      support
  for horizonal assemblies                          TBD                TBD         276   322   393   311   313   284   0   1899
      cable      (up to 50
  estimated by    cables)
 BetterProposals


Bill of Materials for Horizontal Station Cabling
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




 small (up to 16
     cables)       small
    supports      support
  for horizonal assemblies                         TBD              TBD        301   337   404   329   335   301   0   2007
      cable      (up to 16
  estimated by    cables)
 BetterProposals
   RJ-45 to    3 ft blue
 RJ-45 copper Cat 6 patch CommScope/Uniprise                     UNC6-BL-3F     0     0     0     0     0     0    0   2111
 TOTAL ONLY      cords
   RJ-45 to    7 ft blue
 RJ-45 copper Cat 6 patch CommScope/Uniprise                     UNC6-BL-7F     0     0     0     0     0     0    0   3318
 TOTAL ONLY      cords
   RJ-45 to    10 ft blue
 RJ-45 copper Cat 6 patch CommScope/Uniprise                     UNC6-BL-10F    0     0     0     0     0     0    0   1277
 TOTAL ONLY      cords
   RJ-45 to    5 ft blue
 RJ-45 copper Cat 6 patch CommScope/Uniprise                     UNC6-BL-5F     0     0     0     0     0     0    0   576
 TOTAL ONLY      cords




Bill of Materials for Horizontal Station Cabling
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                                                                                       1st     1st   2nd      2nd     2nd
                                                                               Server Floor   Floor Floor    Floor   Floor
                                                                                                                           MPOP Project
     Purpose             Description       Manufacturer          Part Number   Room West      East Central   West    East
                                                                                                                           QTY Total
                                                                                QTY IDF        IDF   IDF      IDF     IDF
                                                                                      QTY     QTY QTY        QTY     QTY
                           12 strand
                            50/125
    1st Fiber                OM4
                                      CommScope/Uniprise P-012-DZ-5K-FSUAQ       0     335    420    60       363    447    0     1625
    Backbone                plenum
                           armored
                          fiber cable
                           6 strand
                            single
    1st Fiber                mode
                                      CommScope/Uniprise P-006-DZ-8W-FSUYL       0      0      0      0        0      0    189    189
    Backbone                plenum
                           armored
                          fiber cable
 #3/0 CU cable
 for grounding
                #3/0 CU
   backbone                                      TBD                TBD          0      0      0      0        0      0     0     1485
               ground wire
    TOTAL
     ONLY
 grounding lugs
  for #3/0 CU
                   #3/0
   grounding
                grounding                        TBD                TBD          0      0      0      0        0      0     0      8
   backbone
                    lug
    TOTAL
     ONLY
  taps for #3/0
 CU grounding                #3/0
    backbone              grounding              TBD                TBD          0      0      0      0        0      0     0      2
    TOTAL                     tap
     ONLY


Bill of Materials for Backbone Cabling
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




 small (up to 16
      cables)      small
     supports     support
  for backbone assemblies                        TBD                   TBD          0   53   68   3   55   70   26   275
       cable     (up to 16
   estimated by   cables)
 BetterProposals
                3 meter
                duplex
  fiber jumper  LC-LC
                                               Systimax          FEXLCLC42-MXM003   0   0    0    0   0    0    0    22
 TOTAL ONLY 50/125
               OM4 fiber
                jumper
                1 meter
                duplex
  fiber jumper  LC-LC
                                               Systimax          FEXLCLC42-MXM001   0   0    0    0   0    0    0    22
 TOTAL ONLY 50/125
               OM4 fiber
                jumper




Bill of Materials for Backbone Cabling
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




                                                                                               1st   1st   2nd  2nd     2nd
                                                                                       Server Floor Floor Floor Floor   Floor
                                                                                                                              MPOP Project
        Purpose                  Description           Manufacturer    Part Number     Room West East Central West      East
                                                                                                                              QTY Total
                                                                                        QTY IDF IDF       IDF   IDF     IDF
                                                                                              QTY QTY QTY QTY           QTY
   data termination          48 port Cat 6 patch
                                                 CommScope/Uniprise     UNP600-48       16     18   23     18    16      17    0     108
         panels                     panel
  voice termination          48 port Cat 6 patch
                                                 CommScope/Uniprise     UNP600-48        6     7     8     7      6      6     0      40
        panels                      panel
    Termination              8 panel 2RU rack
 enclosures for fiber           mount fiber        CommScope/Uniprise RFE-SLG-EMT/2U     1     0     0     0      0      0     0      1
     1 backbone                enclosure-1--1
    Termination              4 panel 1RU rack
 enclosures for fiber           mount fiber        CommScope/Uniprise RFE-SLG-EMT/1U     0     1     1     1      1      1     1      5
     1 backbone                  enclosure
                               12 strand LC
 Adapter panels for
                              multimode fiber      CommSope/Uniprise   MFA-LC12-AQ       5     1     1     1      1      1     0      10
      fiber 1
                               adapter panel
                            12 strand LC single
 Adapter panels for
                            mode fiber adapter CommScope/Uniprise      SFA-LC12-B        1     0     0     0      0      0     1      2
      fiber 1
                                    panel
  Blank panels for           blank fiber adapter
                                                                 tbd       tbd           2     3     3     3      3      3     3      20
       fiber 1                      panel
                               19 inch x 7 foot
      2 post racks                                       Chatsworth     55053-703        4     4     5     4      4      4     0      25
                               black relay rack
   vertical cable
                                vertical cable
 managers between                                        Chatsworth     30096-703        3     2     4     3      2      2     0      16
                                  manager
        racks
   vertical cable
                                vertical cable
 managers at end of                                      Chatsworth     30095-703        2     4     2     2      4      4     0      18
                                  manager
        racks
  1RU horizontal
                               1RU horizontal
 cable managers on                                       Chatsworth     30139-719        4     4     5     4      4      4     0      25
                                cable manager
      floor rack

Bill of Materials for Telecommunications Rooms
PROPOSAL FOR: BGA Inc. - Downtown Office Cabling - BY: Symacco
Proposal # P6986 - June 23,2010




  2RU horizontal
                               2RU horizontal
 cable managers on                                       Chatsworth   30130-719   22   25   31   25   22   23   0    148
                                cable manager
      floor rack
    wall mounted            19in x 24.5in x 18in
                                                             CPI      11960-718   0    0    0    0    0    0    1     1
     rackMPOP                 black wall rack
                                12 inch black
    ladder runway                                        Chatsworth   10250-712   3    3    4    3    3    3    0    19
                                ladder runway
                             12 inch black wall
  wall angle bracket           angle support             Chatsworth   11421-712   3    2    4    3    2    2    0    16
                                   bracket
   runway junction
                              junction splice kit        Chatsworth   11302-001   3    4    3    3    4    4    0    21
       splice
  runway butt splice            butt splice kit          Chatsworth   11301-001   0    0    2    0    0    0    0     2
                             protective runway
   runway end cap                                        Chatsworth   10642-001   2    2    0    2    2    2    0    10
                                  end caps
   vertical runway
                            vertical wall bracket        Chatsworth   10608-001   6    4    4    6    4    4    0    28
     wall bracket
                              threaded ladder
   runway ceiling
                             runway ceiling kit          Chatsworth   11310-001   2    2    6    2    2    2    0    16
     support kit
                               (3/8 inch rod)
 telecommunications telecommunications
                                                         Chatsworth   40153-020   1    0    0    0    0    0    0     1
  grounding bus bar   grounding busbar
 telecommunications telecommunications
                                                         Chatsworth   40153-012   0    1    1    1    1    1    0     5
  grounding bus bar   grounding busbar
 telecommunications
                    telecommunications
    grounding bus                                        Chatsworth   13622-012   0    0    0    0    0    0    1     1
                      grounding busbar
      barMPOP
  2 hole #6 ground          2 hole No.6 ground
                                                             TBD        TBD       16   16   18   16   16   16   2    100
         lug                        lug
 #6 insulated ground            No.6 insulated
                                                             TBD        TBD       60   54   58   60   54   54   10   350
         wire                    ground wire




Bill of Materials for Telecommunications Rooms

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:161
posted:8/11/2011
language:English
pages:45
Description: Scope of Work Data Cabling document sample