					Predicting the Future


  Project Scheduling
  Tools & Techniques


 Duane Webb, BioWare Corp.
Topics Discussed

 Scheduling Concepts
 Predictability
 Early Project Techniques
 Estimating Techniques
 Contingency Planning
 Managing to your Schedule
What is a Schedule for?

 Predicts a completion date
 Creates a picture of the entire project
 Breaks the work down into components
 Tool to track progress
Why do schedules fail?

 Poor estimates
 Missed or unclear requirements
 Scope changes
 Staffing issues
 Stakeholder pressure
 Poor productivity
 Inexperienced project management
 … and much more
What makes a good schedule?

 PERT / CPM ?
 Monte Carlo simulation techniques?
 Earned Value assessments?
 PMP Certified Project Managers?
 Better estimation techniques?
 More up-front planning?
 Better specifications?
What makes a good schedule?

 Good management
 Experience
       Team Leads, Producers, Project Managers,
        Developers, etc.
 Historical Data
 Flexibility, Adaptability, Realism
       Understanding the trade-offs on a project
Project Triangle

             Scope


       What about Quality?




Time                         Resources
Project Fulcrum



   Scope            Time


   Quality        Resources
Project Fulcrum



   Scope            Time


   Quality        Resources
Plan for Change

 Change is inevitable
 Scope will increase
 Requirements will be missed or forgotten


   Accept it and be prepared to adapt!
Topics Discussed

 Scheduling Concepts
 Predictability
 Early Project Techniques
 Estimating Techniques
 Contingency Planning
 Managing to your Schedule
Precision vs. Accuracy

 During initial planning, there are hundreds of
  decisions, issues and challenges which are
  yet to be made.
 An impressive-looking schedule
      with specific dates (precision)
      isn‟t close to reflecting reality (accuracy).
 Precisionis easy,
     Accuracy is difficult!
      “The Art   of Project Management” by Scott Berkun
Sample Schedules
Sample Schedules
Why make a schedule?

   Planning process helps identify risks, issues
    and requirements

   An inaccurate schedule still provides value
     Forecast for completion
     Provides a roadmap
     Management tool
Schedule Probability:

“Schedules need to be good enough for
  the team and the leaders to believe in,
  provide a basis for tracking and
  making adjustments,
  and have a probability of success!”



    “The Art   of Project Management” by Scott Berkun
                               The Art of Project Management, by Scott Berkun
“A day lost at the beginning of a
 project hurts just as much as a
      day lost at the end.”


    “The Deadline” by Tom DeMarco
Topics Discussed

 Scheduling Concepts
 Predictability
 Early Project Techniques
 Estimating Techniques
 Contingency Planning
 Managing to your Schedule
Early Project Scheduling

   You need to provide a long-term view of
    your project
       For executive producers, publishers and
        investors
   You need to provide a high probability of
    success, but do not assume accuracy.
       Be realistic!
Predict the future based on past

 Size every project, past and present
 Use common characteristics of the work
       # Models, poly counts, size of levels, etc.
   Collect historical data to derive productivity
    trends from past projects
     post-mortems
     payroll data & man-months
               Crunch time will NOT be included in this data!
       determine the „size‟ characteristics of your past
        projects
Early Project Scheduling

 Use the past to predict the future
 Estimate the „size‟ of your new project
 Compare relatively to past projects
 Factor in technology changes, engine
  maturity, available training resources

   Track the data on all new projects!
Early Project Scheduling

 Use your “Typical” project template
 Define your “Typical” project milestones
       Work backwards from release

 Identify differences for this project
 Create a staffing plan
  and establish your cost budget
Determine your “Typical” project
Determine your “Typical” project
Determine your “Typical” project
Example of a Staffing Plan
Topics Discussed

 Scheduling Concepts
 Predictability
 Early Project Techniques
 Estimating Techniques
 Contingency Planning
 Managing to your Schedule
Prototyping and Pre-production

 Address the highest risk features and
  unknowns on the project first
 Shakedown the pipeline and measure
     Measure the time to create assets and get
      them into the game
     Provides valuable data for your schedule!

   This is when most of the work is done in
    creating a schedule with a higher
    probability of success!
Estimating effort

   Estimates are inaccurate – be realistic

   Putting a lot of effort into estimating does
    not always result in more accuracy

   Experienced developers should be part
    of the process
                            Estimate Convergence Graph
                     450%

                     400%

                     350%
Estimate Precision




                     300%

                     250%

                     200%

                     150%

                     100%

                     50%

                      0%
                            Concept/Vision     Design        Prototype Specification   Pre-production       Production
                                             Specification




                                                                              Check this  Rapid Development, Steve McConnell
Estimating Techniques

 5-4-3-2-1 Method
 Planning Poker
 Developer Estimates in detail
 5-4-3-2-1 Estimating
 Size                           Factor     Effort in days
 Very Small (> 1 hour)                            1
 Small (> 1 day)                  X5              5
 Medium (> 5 days)                X4              20
 Large (> 20 days)                X3              60
 Very Large* (> 60 days)          X2             120

Measures high level feasibility, “In the ballpark” LOD

*120d = “Don‟t know”, should work to break this down
5-4-3-2-1 Estimating

 Provides quick, high level, long term scoping
 Can be done individually (then distribute)
 Estimate the size of the task, not days
          Should include QA time for acceptance tests
   Compare relative sizes with other tasks

   Then take a second pass through once you
    are complete.
Planning Poker

   Agile Development method

 Includes the customer
 Includes a number of developers


   Uses cards numbered
       1, 2, 3, 5, 8, 13, 20, 40, 100

   Numbers represent relative size, not days
“Agile   Estimating and Planning” by Mike Cohn
Planning Poker works

 Multiple „expert opinions‟ involved
 Discussion brings up missing information
  and reduces the uncertainty and variability
           Jr. staff learn from hearing Sr. staff explanations
           Feeds into group accountability

   Minimizes the time spent in estimation
    phase

 It‟s     fun!
“Agile   Estimating and Planning” by Mike Cohn
Developer Estimates

   Expert Opinions
       Utilize your most experienced staff to either
        create or review the estimates
   Utilize proven & time measured estimates
       Test out a process and measure the time it
        takes to complete a task
   Are they including QA time?
    Integration time?
    Polish phase?
Caution – Developer Estimates

 Every developer will estimate differently
 You have to agree on the primary unit of
  time
 Developer says: “5 days”
     “Ideal days” - 40 hours uninterrupted?
     5 days, with normal interruptions
     OR “bigger than a bread box” estimate
 “There are infinitely many ways
to lose a day... but not even one
      way to get one back.”


    “The Deadline” by Tom DeMarco
Topics Discussed

 Scheduling Concepts
 Predictability
 Early Project Techniques
 Estimating Techniques
 Contingency Planning
 Managing to your Schedule
Contingency Planning
   Combination of risk, confidence level,
    efficiency, scope change, etc.
       Hard to sell 30-40% contingency to
        management

   Contingency time in your schedule is for
    Project Manager, NOT the developer.
     Have the developer stick to their original
      estimates
     Parkinson‟s Law: Work expands to fill the
      time available for its completion.
Contingency: Confidence Level

   Apply a confidence level to the estimate
            High, Medium, Low
 5-4-3-2-1 System does this
 Planning Poker utilizes group discussion
 Do you have experience developing similar
  activities on previous projects?
 What is the Level of Analysis?
       Early guess, good estimate, or a detailed and
        thorough analysis
Risk Management

   Manage your project by managing the risks
       Embrace the risks!
 Create a list of risks
 Quantify the risks
     Probability of occurrence and cost if it does
     Prioritize them accordingly

 Look for early warning signs!
 Have an action plan ready for top 5 or 10
Contingency: Risk Management

 Risk is inherent in each development
  activity, task or feature
 Analyze the level of risk
       Activities that are dependant on others have a
        higher risk
   Quantify your risk tolerance on activity
       10%, 40%, 60%, … low, med, high
   Calculate your risk contingency and add it
    to your schedule
Contingency: Scope Change

 Plan for change during project
 “Rate of discovery”
       As you learn more about your project, you
        will discover new or forgotten requirements
   Apply a change factor to your estimates
     Apply a %change to each estimate
     Adds to the contingency time
More Contingency…

 Put vacation time directly into your
  schedule!
 Plan for sick time in contingency
       How many days are typical?
 HR: Training, Performance Reviews, etc.
 QA: based on your organization:
       Put QA time as separate tasks
          OR
       Allocate some contingency to QA & bug fixes
Duration vs. Effort

 Duration factors in effective work time
  during the day.
 Some studies have shown software
  developers doing only 2-3 hours task
  work in a day.
 Effective work time decreases as developer
  seniority increases
        more interruptions and guidance to others
   Knowing the team‟s efficiency is good!
       Don‟t plan for 8 hours when you only get 2-3!
Time in a day
                                3 hours of lost
Email, Phone calls,             productivity
 IM, Interruptions
                      3 hours   each day costs
     Meetings,                  4 man-months
    discussions
                                per year!
                                So plan for it!
    Task Time:
  Productive Work     5 hours
 on assigned tasks
Example

 Developer Estimate = 5 days
 Confidence Level = Medium (add 15%)
 Risk Analysis: High probability, Medium
  impact (add 15%)
 Efficiency = 5 hours/day
       What is your primary unit of time?


   What do you put in your schedule?
Example

            Duration


     5 days            3 days   ……     2 days


    Estimate                     Contingency


Start of                               End of
Milestone                            Milestone
Topics Discussed

 Scheduling Concepts
 Predictability
 Early Project Techniques
 Estimating Techniques
 Contingency Planning
 Managing to your Schedule
Managing to your schedule

   Track your progress along the way
       Collect data  your actual results
   Project Managers/Producers are responsible
     But have the team update their status
     Commitment!

   Use a tool to track task progress
     Bug databases, online databases, bulletin board
     … suited to your organization
Managing to your schedule
   Manage your milestones
       Obtain commitment from your team
       Make them deliver  do „mini-crunches”
       Every milestone (or phase) can be treated as a mini-project
   Manage to a list of tasks and priorities
       Developers hate big schedules and will ignore them
       Each person gets their own list!
            Online, at their desk, in their favorite tool…
   Early warning system
       Open and honest communication paths are essential
       Don‟t ignore the obvious signs of trouble
Example…                                     Unused
                                          Contingency

            Duration


     5 days            3 days 1 d   ……        1d


    Estimate                         Contingency


Start of                                   End of
Milestone                                Milestone
Agile Development

 Deliver early and often!
 Inspect and adapt
 Know what your efficiency is


   Always do highest risk or highest priority
    work first

   Scrums, Sprints, Releases, Backlogs, User
    Stories, Velocity …
Key Points

 Use past data to predict the future
 Create a staffing plan first based on your
  “typical” project
 Size your projects and adjust
 Prototyping should mitigate the highest risks
  and provide the data to estimate better
 Use an estimating system that your team
  supports
Key Points

   Time Scheduling must:
     Factor in efficiency and effective work time
     Factor in confidence level of estimates
     Factor in risk on the task
     Factor in change expectation
     Factor in vacation, sick time
     Factor in QA & Polish time
     Create a contingency pool for managers, not
      for the developers!
Key Points

 Use a methodology that allows for
  change such as Agile development
 Build in Quality early in the project, so it
  doesn‟t get sacrificed at the end
       Plan for QA time in each milestone and at the
        end of the project!
Key Points – Why schedule?

   Planning process helps identify risks,
    issues and requirements

   An inaccurate schedule still provides
    value
     Forecast for completion
     Provides a roadmap
     Management tool
     Predicting the Future


             Duane Webb
Director of Production, BioWare Corp.
Book References
   “The Deadline”
       by Tom DeMarco

   “Agile Estimating and Planning”
       by Mike Cohn

   “The Art of Project Management”
       by Scott Berkun

   “Rapid Development”
       Steve McConnell

				