IT PROJECTS UNDER CAO FOIS

Document Sample
IT PROJECTS UNDER CAO FOIS Powered By Docstoc
					   IT PROJECTS
  (UNDER CAO/FOIS)


PROGRESS AND CONCERNS
     AUGUST 2006




                        1
     STRUCTURE OF PRESENTATION
1.    OVERVIEW

2.    AREAS REQUIRING BOARD’S
      INTERVENTION

3.    PROJECT SPECIFIC DETAILS



                                 2
 OUR TASK - THIS YEAR
Software                    User/SRS specifications, interaction with field
                            officers and CRIS, testing and field trial.
Deployment of hardware      i) TSS equipment = 4600*
and connectivity            ii) Routers = 500* Modems = 1700* pairs
equipments
                            Lan Extenders = 1013* pairs V-SATs = 950*
Humanware                   9500 men to be trained
Connectivity and power      Sites = 1151*
supply                      Terminals = 3984*
Site identification and     Sites = 1151*
preparation
Roll out                    Hand holding and commissIoning
*Plus issues related to 569 sites, 600 routers, 1200 pairs modems, 187
Lan Extenders, 235 VSATs, 616 terminals & 1400 TSS equipments that
were commissioned till last year.
                                                                         3
GROWTH OF IT PROJECTS ON IR
 IR’s capital budget for IT is Rs. 273 crore in
 2006-07

 It is projected to increase to about Rs. 900
 crore to Rs. 1200 crore by 2010 – 2011

 To make this scale of operation possible,
 requirement of space and other facilities for
 CRIS and FOIS organization needs to be
 significantly increased

                                          4
OUTLAY FOR PROJECTS UNDER
         CAO/FOIS

       YEAR             INVESTMENT
                        (Rs. in Crores)
Last 5 years’ average        26.30
     (2001-2006)
    2006 – 2007          100 (approx.)




                                         5
 IMPORTANT PROJECTS
1. COA (Control Charting)


2. FOIS (Freight Operations Information System)


3. CMS (Crew Management System)


4. ICMS (Integrated Coach Management System)


                                                  6
MAJOR ISSUES NEEDING BOARD’s INTERVENTION

CONTROL    DATA LOGGER - INTEGRATION WITH CONTROL CHARTING
CHARTING   (COA)
           V-SAT – PERFORMANCE & EXPANSION
           DISASTER RECOVERY SITE WITH STAND BY V-SAT HUB AT SC
           POWER SUPPLY – CONNECTION FROM AT SUPPLY/STATION
           GENERATOR
  ALL
           POSTING OF OFFICERS - SUITABLE BACKGROUND, THEIR
PROJECTS
           EXCLUSIVE USE FOR PROJECTS, CONSULTAION WITH CAO
           INTEGRATED BUILDING COMPLEX(CAO & CRIS) – SANCTION
           ON OUT OF TURN BASIS
           EDs COMMITTEE - TO RESOLVE DIFFERENCE IN PRACTICE
  CMS      OVER ZONES
           INTEGRATION OF LOBBIES – BY ZONES BEFORE NOV. ‘06




                                                          7
STATUS – CONTROL CHARTING
           (COA)
  Pilot project under trial at Madurai and Trivandrum
  divisions of SR
  DOMs/SrDOMs visiting TVC/MDU and their reports
  being sent to CRIS continuously for necessary
  changes/enhancements
  Tender for customization of software for IR under
  finalization in CRIS.
  Tender for hardware and roll out to 23 divisions also
  under finalization in CRIS (Phase I)
  Strategy for roll out – In three phases
    Phase I – SR, SCR, SWR, CR, ECOR, SECR
   Phase II – WR, WCR, NCR, NR, NWR
   Phase III – SER, ER, ECR, NER. NFR
  (all detail at http://it.indianrail.gov.in)


                                                     8
CONTROL CHARTING (COA) – TYPICAL CHART
   Chart and Advance Plotting




     FOIS    COIS    NTES    CMS   9
ISSUES – CONTROL CHARTING
           (COA)
 Integration with dataloggers (1437
 already installed & number growing)
 Integration with FOIS, COIS, CMS and
 other public interface systems like
 NTES, Call centers etc
 Record keeping of Control chart
 information – policy for archival


                                        10
    IMPACT ON TARGET –
  CONTROL CHARTING (COA)
Board’s target for IR (76 locations/ 284
boards) – Mar 2007
Latest review with CRIS indicates that
software and hardware may become available
by Dec 2006
Roll out @ 7 locations per month
    Mar 2007   21 locations
    Jun 2007   42 locations
    Dec 2007   76 locations
                                       11
DECISION/ASSITANCE-
        COA
Telecom and C&IS directorates to
resolve the issue of supply of data by
datalogger vendors to enable
development of interface of COA with
networked dataloggers

Safety and C&IS directorates to help
freeze archival policy

                                         12
      ISSUES-FOIS
V-SAT INSTALLATION AT 214 TMS
SITES
EQUIPMENTS AVAILABILITY
RAILWAY’S INVOLVEMENT
CHANGED TRAFFIC PATTERN



                                13
                        FOIS TMS Module
   524* locations on IR
   (all details at http://it.indianrail.gov.in)

   214 locations on VSAT

   324 locations online covering 376 sites

   126 locations printing RR online covering 176 sites

   Around 1100 PCs and 400 printers supplied so far

   668 PCs and 612 printers under supply (within 45 days)
*(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)




                                                                                     14
 VSAT – BASIC FACTS
ON 21/12/04 BOARD (ML/MT/FC) APPROVED SETTING UP
OF RAILWAY HUB & PURCHASE OF VSATs BY IRPMU
WITH FOLLOWING FEATURES:

1.   MASTER EARTH STATION IN KU BAND WITH AUTOTRACKING
2.   200 VSAT TERMINALS WITH DATA & VOICE CAPABILITY
3.   SETTING UP OF NMS NETWORK
4.   PAYMENT TO DOT FOR COMMERCIAL/CAPTIVE VSAT SERVICES
     WITH CUG CAPABILITY
5.   HIRING OF QUARTER TRANSPONDER
6.   AMC WITH OEM FOR MAINTENANCE SUPPORT FOR HUB &
     TERMINAL
7.   CAO/FOIS TO MONITOR PROJECT & IRPMU TO NOMINATE ONE DY.
     CSTE EXCLUSIVELY
8.   HIRE VSAT WITHIN 3 MONTHS & SETTING UP OF A HUB WITHOUT
     AFFECTING FOIS TERMINAL




                                                           15
       TMS VSAT locations

214 TMS locations have to be
commissioned on VSATs by IRPMU


Railway Board’s target was June 2006.
IRPMU’s revised target is Sept 2006


74 VSATs covered upto 17.8.06


                                    16
IMPACT ON TARGET-
      FOIS
V-SAT DEPENDENT TMS SITES(214)
WILL TAKE LONGER TO STABLISE
   RESPONSE TIME ISSUES (1500 vs700
    msecs)
   CHANGE IN HUB FROM VENDOR’S TO OUR
    OWN    (Realignment of each dish)




                                     17
Problems relating to the VSAT
          Network
Response time excessive – timed out if data
packet size exceeds 1000 bytes

Voice communication yet to be provided

Video conferencing facility between CRIS,
Railway Board and zonal railway HQs
required




                                              18
 GENERAL ISSUES- V-SAT


HECL CONTRACT - 235 (± 25%)

Requirement as of now - 477

HUB CAPACITY-500 (CAN GO UPTO 1000)

TRANSPONDER HIRING ISSUE


                                19
 DECISION/ASSITANCE-
        FOIS
Board’s directive for AT/generator supply from
station to TMS site
Nomination of 2 Rates Inspectors by each
zone to CAO/FOIS for verification of
referential database and testing of software
changes due to rates circulars



                                         20
            STATUS-CMS
Detailed estimate of Rs 38.16 crores sanction
by Railway Board.

302 lobbies to be covered, out of which 259
are integrated lobbies (presently around
60%).
(all details at http://it.indianrail.gov.in)


Target for completion March 2007

                                               21
           STATUS-CMS
Application under development and testing for
  Freight module
  Coaching, shunting and pilot module
  Suburban module
Site Preparation
  Lump sum amount sanctioned @ Rs 1,31,728 for major and Rs
    82,890 for minor lobbies
  Target for readiness Aug 2006
Terminal Equipment
  Under vetting
  Target of Phase I supply - Dec 2006
Datacom Equipment
  Under vetting. Will be procured through CRIS
Training
  Core group and core implementers will be trained at CRIS
  Core group identified on all 16 zonal railways
  Training labs being set up at 5 locations


                                                               22
       ISSUES - CMS
Difference in interpretation of Board’s
circulars by zonal railways in calculation
of running allowance
Integration of lobbies




                                         23
IMPACT ON TARGET-CMS
 Board’s target – 302 sites by Mar 2007
 Latest review with CRIS indicates
 software and hardware will be available
 only by Dec 2006.
 Going by the FOIS and other roll out
 experience, commissioning of 30 sites
 per month would be a reasonable target
 March 2007   100 sites (DLI MUMBAI routes - 3)
 Dec 2007     202 sites

                                           24
DECISION/ASSITANCE-
       CMS

Nomination of Committee of ED s of
Electrical, Mechanical, Personnel &
Finance for practice to be adopted for
computation of running allowance and
other issues / business reengineering
Details of sample issues

                                         25
               STATUS-ICMS
Enhanced scope

     Punctuality Module
          Module is being tested on NDLS & MAS

     Coaching Stock Management Module
          Being implemented in three phases
          Software ready and under field trials at Nizamuddin &
           Chennai
          Ready for roll out

     Timetabling Module
          Time table simulation module’s system requirements
           under discussion


                                                                   26
                 STATUS-ICMS
Enhanced scope (contd)

     Coaching Stock Maintenance Module
          Scope of Mechanical module has been enhanced from
           capturing of coaching depot maintenance related
           activities to automation of C&W department
          It covers 154 depots & 975 coaching locations.
          It covers 331 depots & 973 electrical locations.
          Scope of Electrical Maintenance module defines only 8
           technical modules developed by NR under MIS projects.
           It also does not give assessment of hardware & user
           specifications.

                                                              27
      ICMS – Coaching Stock
       Management Module
     Phase I – 114 terminals at 41 locations
                 Target for implementation 31st Aug 2006
     Phase II - 78 terminals at 34 locations
                  Target for implementation 31st Oct 2006
     Phase III - 128 terminals at 58 locations
                   Target for implementation 31st Dec 2006
(all details at http://it.indianrail.gov.in)
     Training
       186 staff from 136 locations trained so far
       Training labs being set up to take care of additional training needs
     Equipment
       Thin clients and printers supplied to all locations
       Datacom equipment- 57 LAN extenders supplied. Rest under
         supply
       14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1
       107 locations have been provided connectivity.
       Target likely to be met
                                                                               28
          ISSUES-ICMS
  Freezing the scope of Mechanical &
  Electrical Maintenance Modules –
  Railway Board
  Supply of datacom equipment by CRIS
  & commissioning of 59 VSAT locations

450 pair modems PO placed. Supply in a month
144 pair LAN    Supply completed
extenders
112 routers     TC negotiation
                                          29
 IMPACT ON TARGET-
       ICMS
Three months delay due to supply of
UPS and datacom equipment

  Mar 2007        Phase I & II – 192
                  locations
  Jun 2007        All 320 locations



                                       30
DECISION/ASSITANCE-
       ICMS
C&IS directorate to facilitate freezing of
scope for Mechanical & Electrical
Maintenance Modules in view of
dropping of work from MIS

C&IS directorate to sanction & release
funds for time tabling module.

                                             31
  GENERAL ISSUES -
   INFRASTRUTURE
INVESTMENT

SPACE-BLDG

MANPOWER

DISASTER TOLERANCE – VSAT HUB
ISSUE
                            32
  GENERAL ISSUES -
     TRAINING
CURRICULAM IN TRAINING
INSTITUTES-
TRAFFIC,MECHANICAL,ELECTRICAL
-MPP DTE’S ROLE

ADDITIONALTRAINING CENTERS –5
(DLI,SC,BB,HWH,TPJ)

                                33
Increase in strength of FOIS and
      space requirement
                                                                    Training
                                                                      areas,
                                                   Bare              central
         Approx IT         FOIS     Manpower    seating              control   Total space
             budget    manpower      based in     space   Support      room    requirement
  Year   (Rs. Crore)      (total)        HQ      (sq m)     space       etc.         (sq m)

 2006-
 07           300          264          140      420        420        210          1050
 2007-
 08           360           317         160      480        480       240           1200
 2008-
 09           450          396          200      600        600       300           1500
 2009-
 10           540          475          240      720        720       360           1800
 2010-
 11           650          572          290      870        870       435           2175
 2011-
 12           800          704          360     1080       1080       540           2700


                                                                               34
              Projected growth of manpower in CRIS

1200                                             Trainees
1100                                             Procurement staff
1000                                             Support staff
 900                                             IT/HW
 800                                             Help Desk
 700                                             N/W
 600                                             DBA
 500                                             Implementers (full-time)
 400                                             Developers
 300                                             Managers

 200
 100
   0
       2006   2007   2008   2009   2010   2011
                        Year


                                                                 35
SPACE - CRIS location




                        36
SPACE – Area with Railways




                        37
                 Required facilities for
                      expansion




Secure areas in red
                      Restricted areas in orange
                                                   Open access in green
                                                                  38
THANK YOU


            39

				