									Toll Bridge Seismic Retrofit Program


   San Francisco-Oakland Bay Bridge
       East Span Seismic Safety
     Replacement Project Update
Toll Bridge Program Oversight Committee
                  (TBPOC)

  Steve Heminger, Chair
   Executive Director, BATA
  Cindy McKim
   Director, Caltrans
  Bimla Rhinehart, Vice Chair
   Executive Director, CTC




                                          2
Toll Bridge Program Management Team
                 (PMT)

 Stephen Maller
  Deputy Director, CTC
 Tony Anziano
  TBSRP Program Manager, Caltrans
 Andrew Fremier
  Deputy Executive Director, BATA




                                      3
Self Anchored Suspension Span
       Contract Update
SAS Construction Status
                      5
Installation of Roadway Lift 7 East
                                  6
Tower Lift 1 Installation
                        7
Tilting Apparatus for Tower Lift
                               8
Tower Lift 1
           9
Fabrication Status
                10
Tower Lift 2 Segments on Dock
                           11
Roadway Boxes in Trial Assembly Area
                                  12
Anchorage Box Lift 13W in Assembly Jig
                                    13
   East End
Anchorage Boxes
                   East End Challenges

 East End Roadway Lifts 13 and 14 are more complex than first
  11 lifts,
      Anchorage for main cable
      Hinge connection to Skyway
      On a curve with camber and super-elevation


 Considerably more heavy and more complex, requiring more
  detail sheets,
      First 11 lifts had approximately 8,000 sheets
      Lift 13 has over 3,300 sheets
      Lift 14 has an additional 1,600 sheets




                                                                 15
East End Challenges




                      16
East End Challenges




                      17
             East End Challenges
 Complexity of East End has

     put us behind schedule
     added significant costs to Contractor


 Get back on track through

     resolution of claims to date
     developing accelerated path forward




                                              18
             Dispute Resolution
 Change Order to Resolve Impact of
  Delays to Contractor

     Resolves direct and indirect costs due to East
      End impacts


 Adjusts Contract Schedule

     Requires Contractor to develop new baseline
      schedule leading to readiness for Seismic
      Safety Opening to traffic in late 2013


                                                       19
          Support for Acceleration
 Participation in Additional Costs
  Associated with Accelerated Schedule

     Additional
       • labor
       • equipment
       • transportation (shipping)
       • costs associated with changes to order of
         work




                                                     20
        Incentives and Disincentives
 Adds Incentives Shipment of East End Anchorage
  Boxes
     Incentives ranging from $200K to $350K per day if
      shipped before August 21, 2011 with a maximum cap of
      $20M.
 Adds Incentives and Disincentives for Seismic
  Safety Opening Readiness
     Incentive of $385K per day if SSO achieved before
      October 20, 2013 with a maximum cap of $20M
     Disincentive of $100K per day if SSO not achieved by
      November 30, 2013 with a maximum cap of $125M




                                                             21
                                    Seismic Safety Opening
                                   Incentives/Disincentives

                                    Seismic Safety Opening Incentive/Disincentive

                          $25,000,000
Incentive/Disincentive




                          $20,000,000
                          $15,000,000
                          $10,000,000
                           $5,000,000
                                 $-
                          $(5,000,000)
                         $(10,000,000)
                         $(15,000,000)
                                                                 10


                                                                 11


                                                                 12
                                         8/


                                                     9/




                                                                 1/


                                                                                2/


                                                                                3/
                                            1/


                                                        1/




                                                                    1/


                                                                                   1/


                                                                                   1/
                                                                    /1


                                                                    /1


                                                                    /1
                                              20


                                                          20




                                                                      20


                                                                                     20


                                                                                     20
                                                                       /2


                                                                       /2


                                                                       /2
                                                                         01


                                                                         01


                                                                         01
                                                13


                                                            13




                                                                          14


                                                                                       14


                                                                                       14
                                                                            3


                                                                            3


                                                                            3
       Change Order is Within Current
             Program Budget
 Costs
      Dispute Resolution $125 M
      Support for Acceleration $20M
      Incentives and Disincentives
        • Incentives of up to $40M to project
        • Disincentives of up to $125M to Contractor

 Cost of the Changes Will Require a Project/Contract Budget
  Increase and Require Allocation of Program Contingency
  Funds, But Remains Within Reported Contract, Project and
  Program Forecasts
 Program Remains Within Budget Established by AB 144
 Forecast Continues to Show Positive Program Contingency
  Balance


                                                               23
   Item 3A Proposed TBSRP Budget Change
                              Current                 Proposed                Difference
                              Budget                  Budget*
                               ($ millions)             ($ millions)

SFOBB East Span                  5,891                    6,184                     293
Replacement
Project
Other TBSRP                      2706                     2706                        -
Projects and
Costs
TBSRP Program                     701                      408                     (293)
Contingency


Total TBSRP                      9,298                    9,298                       -



* Does not include budget reductions for Item 3B Dumbarton Bridge Seismic Retrofit Project
25
  Item 3B Proposed TBSRP Budget Change
   Including Both SFOBB and Dumbarton
                   Current        Proposed        Difference
                   Budget          Budget
                   ($ millions)    ($ millions)

SFOBB East Span      5,891           6,184           293
Replacement
Project
Dumbarton             365             149           (216)
Bridge Seismic
Retrofit Project
Other TBSRP          2,341           2,341            -
Projects and
Costs
TBSRP Program         701             408           (293)
Contingency

Total TBSRP          9,298           9,082          (216)

								