					                              SOR FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                                 MEERUT ZONE-2

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0                                                                                Bidder Name:_____________________________
                                                                                                                                          Unit Price        Total Price
                                                                                                                                        including all      including all
   S.No.                                               Description                                                    Unit    Qty
                                                                                                                                      taxes and Duties   taxes and Duties
                                                                                                                                           in INR             in INR
    1.1     Laying in normal surface/ any unprepared surface (Kachcha Surface)
            Receiving and taking over, handling, loading, transportation and unloading of owner supplied
            MDPE pipes, fittings and other free issue items from Owner's designated stock yards to
            Contractor's own stock-yards/ workshops/ work-sites, proper storing, stacking, identification,
            providing security and insurance cover.
            Preparation and getting approval of schedules, execution procedures, drawings/ sketches/
            wherever required, making trial pits to determine the underground utilities/ services etc.
            restoration of the abandoned trial pits to original condition.
            Grading the ROU, barricading the work area as per local authorities norms & to satisfaction of
            EIC, installation of safety signs, trenching to required depth in all kinds of soil including soft and
            hard rocks, repairing of all damaged utilities if any, and payment of any compensation ( if
            claimed by owner/ other utility agencies)
            Sand padding of 75mm including supply of sand at the trench bottom
            Uncoiling stringing of pipes, clamping, jointing of the pipe ends/ fittings/ valves by qualified
            personnel using approved electro-fusion techniques as per specification.

            Excavating trench in all types of soil including soft and hard rock
            Lowering, sand padding the trench will have to filled with sand around and upto 75 mm from top
            of pipe,
            Lowering the pipeline in trench to required depths, sand padding the trench will have to filled
            with sand around and upto 75 mm from top of pipe, soft graded soil layer of 125 mm above
            layer of sand, if required insertion of carrier pipe inside the Casing pipe, Supply as per
            specification attached and placement of PE/PVC warning grid mat over the pipeline along the
            complete route, padding around pipeline with suitable approved soil, backfilling with available
            excavated material after screening, compaction with jumping jack compactor and water at
            subsequent layers of 150 mm above warning mat. All tiles/ slabs/ curb stones etc removed
            during excavation shall be placed properly. Roads, pavements, footpaths etc. to be made
            motorable wherever pipeline is laid.
            Installation and electro fusion jointing of valves, wherever required and as directed by Engineer-
            in-charge.
            Restoration of area to original condition, including cleaning the area of all unserviceable
            materials, debris, excess earth near trenches to the designated disposal area as per the
            specifications, instruction of Owner/ Engineer -in- Charge and to the complete satisfaction of
            local authorities.
            Restoration of all surrounding ground features to that existing before as detailed out in the
            specifications and as directed by Engineer-in‑ charge which would include replanting of any
            uprooted trees etc.

            Flushing, cleaning ,Pneumatic testing, purging with nitrogen and commissioning as per
            specification and approved procedures providing all tools and tackles, nitrogen, instruments,
            manpower and other related accessories and as per the instructions of the Engineer-in charge.
            Maintaining the completed pipelines / installation for any defect, failures during defect liability
            period ( i.e. 12 months from date of completion of work).
            Handing over the completed works to GGL for their operation/ use, returning of all surplus
            material to GGL stores, reconciliation of free issue material area wise and obtaining no
            objection certificate.
            Preparation and submission of Daily progress report, Laying Graphs/ PE/GI/Cu line cards on
            daily basis.
            On completion of gas charging of pipelines, preparation and submission of As built drawings,
            crossings details, termination, utility graphs and deviation statements.

            Submission of all documents required for contract closure in numbers as mentioned in contract.
            Any other activities not mentioned / covered explicitly above, but otherwise required for
            satisfactory completion /operation/ safety / statutory / maintenance of the works shall also be
            covered under the scope of work and has to be completed by the Contractor within specified
            schedule at no extra cost to GGL

     a      20 mm PE pipe                                                                                            Meters   31080
     b      32 mm PE pipe                                                                                            Meters   14700
     c      63 mm PE pipe                                                                                            Meters    8100
     d      125 mm PE pipe                                                                                           Meters    495
    1.2     Pipe Laying in a built-up surface

             Raking / Trenching of hard surface in all types of soil including rock ,metal, concrete,
            bituminous, tiled, brick lined etc. All tiles/ slabs/ curb stones etc. removed during excavation
            shall be placed properly. The other activities are as per SOR item No. 1.1 and as detailed in the
            specifications and as per the instructions of the Engineer-in-charge.

     a      20 mm PE pipe                                                                                            Meters   13468
     b      32 mm PE pipe                                                                                            Meters    6370
     c      63 mm PE pipe                                                                                            Meters    3510
     d      125 mm PE pipe                                                                                           Meters    215
    1.3     Restoration of trenches (where the above item 1.2 rates are applicable)
            Restoration of the roads, pavements, channels, footpaths, tiles stones etc. to original condition
            including supply of the approved quality material required, as per local authorities norms,
            obtaining NOC from concerned local authorities / land owners/ third party inspection agencies
            designated by GGL and to the satisfaction of the Engineer-in-charge.
                              SOR FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                                 MEERUT ZONE-2

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0                                                                                 Bidder Name:_____________________________
                                                                                                                                          Unit Price        Total Price
                                                                                                                                        including all      including all
   S.No.                                               Description                                                     Unit    Qty
                                                                                                                                      taxes and Duties   taxes and Duties
                                                                                                                                           in INR             in INR
     a      Asphalting                                                                                                Meters   1767
     b      Cement concrete                                                                                           Meters   2357
     c      Slabs/ Blocks/ Curb sloves                                                                                Meters   442
     d      Brick setting/ channels etc.                                                                              Meters   884
     e      Interlocking Tiles                                                                                        Meters   442
    1.4
     a)     Laying of 40 mm OD, 6Kg/cm2 permanently lubricated HDPE conduits, in same pipeline trench
            direct buried or through CS/ HDPE conduit, excavation as required, padding, backfilling etc.
            including cleaning and sealing of ducts at the end of laid drum lengths, jointing of HDPE
            conduit including supply of all material, coupler for jointing of HDPE Duct, HDPE conduit                 Meters   1433
            testing after laying, joint location marking all complete as per specifications provided in the bid
            document and as per direction of consultant.
     b)     Supply of HDPE Conduit
            Supply of 40 mm conduit as per relevant specification                                                     Meters   1433
     c)     Providing and laying 1200 mm dia cable blowing / jointing pit as per detail                                Nos     29
    1.5     Pipe laying using manual moling technique
    1.5.1   Pipe laying using manual moling technique (without casing) for carrier pipe sizes of:

            Survey of underground utilities, execution of the work as per specification, including excavation
            of pits moling with the hole size not exceeding 20% of the pipe dia, jointing and insertion of
            carrier pipe without casing and subsequent backfilling, compaction restoration of the pits to its
            original condition as per specifications and the instructions of Engineer-in-Charge

     a      20 mm PE pipe                                                                                             Meters   7252
     b      32 mm PE pipe                                                                                             Meters   1642
     c      63 mm PE pipe                                                                                             Meters   905
      d     125 mm PE pipe                                                                                            Meters    56
    1.5.2   Pipe laying using manual moling technique with Casing( including Supply of HDPE
            Coupler as per specification attached) for carrier pipe sizes of:
            Survey of underground utilities, execution of the work as per specification, including excavation
            of pits moling with the hole size not exceeding 20% of the pipe dia, jointing and insertion of
            carrier pipe with casing and subsequent backfilling, compaction restoration of the pits to its
            original condition as per specifications and the instructions of Engineer-in-Charge

     a      32 mm PE pipe                                                                                             Meters   821
     b      63 mm PE pipe                                                                                             Meters   453
      c     125 mm PE Pipe                                                                                            Meters    28
    1.6.1   Pipe laying using Moling Technique with Machine ( without casing) for carrier pipe sizes
            of:
            Survey of underground utilities, execution of the work as per standard procedure attached,
            including excavation of pits and subsequent backfilling, compaction, jointing and insertion of
            casing pipe, restoration of the pits to original condition, submission of As built graphs as per
            specifications and the instructions of EIC

     a      32 mm PE pipe                                                                                             Meters   329
     b      63 mm PE pipe                                                                                             Meters   181
     c      125 mm PE Pipe                                                                                            Meters   12
    1.6.2   Pipe laying using Moling Technique with Machine( including Supply of HDPE Coupler)
            with casing for carrier pipe sizes of:
            Survey of underground utilities, execution of the work as per standard procedure attached,
            including excavation of pits and subsequent backfilling, compaction, jointing and insertion of
            casing pipe, restoration of the pits to original condition, submission of as built graphs as per
            specifications and the instructions of EIC
     a      32 mm PE pipe                                                                                             Meters   165
     b      63 mm PE pipe                                                                                             Meters    91
     c      125 mm PE Pipe                                                                                            Meters    6
    1.7.1   Pipe laying using Directional Drilling technique ( without casing):
            Survey of U/G utilities, submission of profile for approval, execution of the work as per standard
            procedure attached, including excavation of pits and subsequent backfilling compaction,
            jointing and insertion of carrier pipe restoration of the pits to original condition, submission of As-
            Built Graph as per specifications and the instruction of Engineer-in-Charge.


     a      For Carrier pipes 32 / 63 mm                                                                              Meters   510
     b      For Carrier pipes 125 mm                                                                                  Meters   12
    1.7.2   Pipe laying using Directional Drilling technique( including Supply of HDPE Coupler) with
            casing for carrier pipe size of :
                              SOR FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                                 MEERUT ZONE-2

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0                                                                              Bidder Name:_____________________________
                                                                                                                                       Unit Price        Total Price
                                                                                                                                     including all      including all
   S.No.                                               Description                                                  Unit    Qty
                                                                                                                                   taxes and Duties   taxes and Duties
                                                                                                                                        in INR             in INR

            Survey of U/G utilities, submission of profile for approval, execution of the work as per standard
            procedure attached including excavation of pits and subsequent backfilling compaction, jointing
            and insertion of casing pipe and carrier pipe, restoration of the pits to original condition,
            submission of As-Built Graph as per specifications and the instruction of Engineer-in-Charge.

     a      For Carrier pipes 32 / 63 mm                                                                           Meters   256
     b      For Carrier pipes 125 mm                                                                               Meters    6
    1.8     Supply of HDPE Casing Pipe as per Specification

     a      HDPE Casing Pipe 50 MM Dia                                                                             Meters   1242
     b      HDPE Casing Pipe 90 MM Dia                                                                             Meters   544
     c      HDPE Casing Pipe 200 MM Dia                                                                            Meters    40
    1.9     Supply of GI/MS/Concrete Sleeves
            Supply, installation of sleeve, insertion of pipe, sealing the annuals, firm fixing of sleeves with
            concrete mix. Breaking through any obstructions and their subsequent restoration, as per
            specifications and instructions of the Engineer-in-charge.
     a)     GI Sleeves ( in Nos)
     i.     1" NB, 1 Ft. Length                                                                                     Nos     6125
     ii     1-1/2" NB, 1 ft. Length                                                                                 Nos     172
     b)     MS Enamel Coated
     i.     2" NB                                                                                                   RM      172
     ii.    4" NB                                                                                                   RM      172
     c)     Concrete
     i.     4" NB                                                                                                   RM      172
     ii     6" NB                                                                                                   RM      172
     III    8" NB                                                                                                   RM      172
     iv     10" NB                                                                                                  RM      172
   1.10.1   Preparation and Installation of valve pit (Extended Stem)
            All civil works including supply of all material, excavation of pit, piping supports including all
            PCC and RCC works for valves pit, pedestals with insert plates as required sealing of pipe at
            valve pits, providing cover etc and finishing, clean up and restoration of site, filling and grading    Nos     20
            of area around the valve station to avoid any local flooding of area, as per typical drawing and
            specification enclosed and instruction of Engineer-in-Charge.
   1.10.2   Preparation and Installation of valve pit (Normal Stem)
            All civil works including supply of all material, excavation of pit, piping supports including all
            PCC and RCC works for valves pit, pedestals with insert plates as required sealing of pipe at
            valve pits, providing cover etc and finishing, clean up and restoration of site, filling and grading    Nos     19
            of area around the valve station to avoid any local flooding of area, as per typical drawing and
            specification enclosed and instruction of Engineer-in-Charge.
    1.11    Fabrication & Installation of Markers
     a      RCC Route Markers as per Sketch
            Supply, fabrication and installation of RCC route markers as per the attached drawings, along
            the route including all associated civil works such as excavation and construction in all types of
            soils, construction and pedestals and grouting with concrete, clearing , supply and application
            of approved color and quality of primer and paint, stencil letter cutting of numbers, direction,        Nos     195
            chainage etc. restoration of area to original condition and performing all works as per drawings,
            specification and instruction of EIC.
     b      Plate Markers As per Sketch

            Supply, fabrication and installation of plate markers as per the attached drawings, including all
            associated works and complete as per the Instructions of EIC.                                           Nos.    195
     c      Warning Sign Markers
            Supply, fabrication and installation of plate markers as per the attached drawings,including all
            associated civil works such as excavation and construction in all types of soil,construction and
            pedestals and grouting with concrete ,cleaning,stencil, letter cutting and painting of numbers
                                                                                                                    Nos.    195
            ,direction,chainage etc. restoration of area to original condition as per the instruction of EIC

    1.12    Supply and installation of RCC Half round crimp guard and 50 NB PVC Sleeve bend to protect
            vertical service pipe and Transition fitting                                                            Nos.    7350
     2      GI/ Cu Pipe installation
    2.1
            Supply and Installation of GI Service Pipes with GI Fittings and GI valves i.e. Elbow, Tees,
            Cross, union, Socket, Reducer, Nipple, End Cap, tapes, End Plug, Flexible hoses , all other
            require fittings, Isolation valve and appliance valve ) of NPT Thread
            Preparation and approval of schedules , execution procedures, sketches.
            Finalization of optimum route with consent of customer, from transition fitting to cooking oven/
            appliance.
            Making temporary but stable platforms/ scaffolding / rope ladders and all other safety devices.

            Supply and Installation of GI Pipes , Fittings and Valves including NPT threading, painting as
            specified.
                               SOR FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                                  MEERUT ZONE-2

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0                                                                              Bidder Name:_____________________________
                                                                                                                                        Unit Price        Total Price
                                                                                                                                      including all      including all
   S.No.                                              Description                                                   Unit    Qty
                                                                                                                                    taxes and Duties   taxes and Duties
                                                                                                                                         in INR             in INR
            Installation of owner supplied regulators etc.
            Supply & Fixing of approved, clamps, Dowell Plugs with screws, grout material, suitable thread
            sealant I.e. Teflon Tape/ lock tight, drilling of holes through tiles / wood/ marble/ Granite etc
            jointing of PE to aboveground service GI pipes, testing, purging and commissioning of the
            complete installation.
            Painting of entire length of pipe along with fittings after proper surface finish by one coat of
            approved primer paint and two coats of approved synthetic enamel paint complete as per
            specification & direction of EIC. Restoring the wall surface to original by cleaning/ touching of
            corresponding paint to original as per instructions & to satisfaction of the owner. Preparation of
            laying records, meter reading etc. Reconciliation of free issue material.

            Drilling of holes through walls with proper heavy duty hammer drill Machine, tools & tackles,
            using proper sealant/ grout material & colours to match original, replacement of damages
            during drilling, restoring the area to original condition to the satisfaction of Owner/ EIC & as per
            specification for 1/2"/3/4” NB in brick wall
            All above activities to be carried out as per specification to the complete satisfaction of
            consumer & as directed by EIC.

            Any other activity not mentioned / covered, explicitly above, but otherwise required for
            satisfactory completion/ safety/ statutory/ maintenance of works shall also be covered under
            scope of work and has to be completed by contractor within specified schedule at no extra cost
            to GGL.
            Supply of all tools, tackles and consumables required to execute the work in an efficient
            manner.
     a      1/2" All Floors                                                                                        Meters   2573
     b      3/4" All Floors                                                                                        Meters   24010
     c      1" all Floor                                                                                           Meters   150
     d      1" / 1 1/2" all Floor                                                                                  Meters   100
    2.2     Supply and Installation of Copper Service Pipes including Supply of Copper Pipes and
            Copper Fittings and GI appliance valve i.e. Elbow, Tees, Cross, Socket, Reducer, End
            Cap, End Plug, Disconnect union, adopter for appliance valves, all soldering
            consumables , flux application and all other required fittings)

            Preparation and approval of schedules , execution procedures, sketches.

            Finalization of optimum route with consent of customer, from transition fitting to cooking oven/
            appliance.
            Making temporary but stable platforms/ scaffolding / rope ladders and all other safety devices.
            Supply and Installation of Copper Pipes , Copper Fittings etc
            Supply and Installation of GI appliance Valves etc.
            Supply & Fixing of approved, clamps, Dowell Plugs with screws, grout material, suitable thread
            sealant I.e. Teflon Tape/ lock tight, drilling of holes through tiles / wood/ marble/ Granite etc
            jointing of PE to aboveground service GI pipes, testing, purging and commissioning of the
            complete installation.
            Painting of GI fittings after proper surface finish by one coat of approved primer paint and two
            coats of approved synthetic enamel paint complete as per specification & direction of EIC.
            Restoring the wall surface to original by cleaning/ touching of corresponding paint to original as
            per instructions & to satisfaction of the owner. Preparation of laying records, meter reading etc.
            Reconciliation of free issue material.
            All above activities to be carried out as per specification to the complete satisfaction of
            consumer & as directed by EIC.
            Any other activity not mentioned / covered, explicitly above, but otherwise required for
            satisfactory completion/ safety/ statutory/ maintenance of works shall also be covered under
            scope of work and has to be completed by contractor within specified schedule at no extra cost
            to GGL.
            Drilling of holes through walls with proper heavy duty hammer drill Machine, tools & tackles,
            using proper sealant/ grout material & colours to match original, replacement of damages
            during drilling, restoring the area to original condition to the satisfaction of Owner/ EIC & as per
            specification for 1/2"/3/4” NB in brick wall
            Supply of all tools, tackles and consumables required to execute the work in an efficient
            manner.
     a      12 mm dia X 0.6mm Thick (Inside kitchen only) Ground to 2nd Floor as per BS EN 1057                    Meters 30,625
    2.3     (Installation of Meter) : Fixing of meters with associated inlet and outlet connections/ fittings,
            supply & fixing of approved meter brackets and other supports by proper scaffolding/ grouting,
            Restoring the area to original complete as per specification and to complete satisfaction of
            consumer and EIC.
     a      Domestic meter                                                                                          Nos.    6125
     b      Non Domestic Meters                                                                                     Nos.     20
    2.4     Conversion of Domestic Appliance
            Conversion of all types of LPG kitchen appliances to NG based appliances, supply & changing
            of nozzles, jets and associated controls for domestic & imported appliances with proper tools &
            tackles.
                               SOR FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                                  MEERUT ZONE-2

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0                                                                            Bidder Name:_____________________________
                                                                                                                                      Unit Price        Total Price
                                                                                                                                    including all      including all
   S.No.                                              Description                                                 Unit     Qty
                                                                                                                                  taxes and Duties   taxes and Duties
                                                                                                                                       in INR             in INR
            Cleaning and performing minor maintenance, greasing etc of appliance, testing/ showing
            performance to the customer, signing of joint meter records (JMR) and instructing customer on
            use & safety norms, complete as per specifications & to satisfaction of Owner/ EIC.


     a      Hot plate/ bumer                                                                                      Nos.     6125
    2.5     Regulator Boxes: supply Including painting of approved make of regulator boxes, installing
            them firmly by grouting using approved bracket/clamps as per drawings enclosed and as per
            specifications, cleaning the area complete to the satisfaction of the owner/ EIC.
                                                                                                                  Nos.     3675

            DRS/MRS/ Metering Station works
     3      Installation of DRS/MRS/ Metering Skid with RCC pedestal and foundation.
            Receiving and taking over, handling, loading, transportation and unloading of DRS/MRS/
            Metering Skid from Owner's designated stockyards to site, installation and hooking up with
            MDPE pipe.
            Providing and laying reinforced cement concrete of grade M-20 with 20 mm and down grade
            crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases,
            pipe supports, sleepers, columns, equipment, foundat5ion, etc. including providing fencing with
            gate wherever required.
            Note: -
            Rate to include cost of all labour, tools, tackels, equipment, hire charged.
            This is a lump sum item rate however payment for all civil and structural works shall be made
            based on approved quantity executed at site as per item listed elsewhere in the SOR.

            Bolts, nuts, washer, U-clamps, gaskets etc. if required during installation shall be procured and
            supplied by the Contractor within the rate quoted. These items shall not be separately
            measured and paid.
     a      Above 2000 Kg MRS/ DRS Skid                                                                           Nos.     5
     b      Up to 2000 Kg MRS/ DRS Skid                                                                           Nos.     10
     4      SUPPLY OF FOLLOWING ITEMS AS SPECIFICATION AND DATA SHEET ENCLOSED
            WITH THE TENDER
     a)     PE to Steel Transition Fitting 20 mm to 1/2" as per specification                                     No.      100
     b)     PE to Steel Transition Fitting 32 mm to 1" as per specification                                       No.       20
     c)     PE to Steel Transition Fitting 63 mm to 2" as per specification                                       No.       20

            Note: -
     i)     The quantities mentioned above are tentative.
     ii)    For all the supply items mentioned above, procurement shall be made as per specification after
            due approval of Engineer-in- Charge.
     5      STRUCTURAL WORKS
            Supply & erection of double leaf mild steel gate 2.5 m high with mesh upto 2 m height and 4 m
    5.1     wide complete in all respect including painting as per TS on all MS items, all works excluding         No       5
            foundations and RCC beams as per drawing and specifications.
            Supply and erection of single leaf mild steel gate 2.5 m high with mesh upto 2 m height and 2
    5.2     m wide complete in all respect including painting as per TS on all MS items, all works excluding       No      10
            foundations and RCC beams

            Supply of all materials , fabrication and erection of chain link fencing 2.5 m high with mesh upto
    5.3     2 m height and barbed wire fencing complete in all respect including painting as per TS on all        RM       200
            MS items, all works as per specification excluding foundations and RCC beams

    5.4     Pipe Supports, Valve supports & Other Structures
    a)      Supply fabrication and erection of all types of pipe supports like clamps, saddle, guide, stops,
            cradles, Neoprene sheet, turn buckles, anchors, Tposts, stockade/trestle and pipe bridge for
            overhead piping , frames for canopy , approach ladders and platforms, crossover, cable tray
            supports etc, including painting suitable for highly corrosive area as per specification labour
            and supervision & complete work as per drawing, specifications and instructions of Engineer-in-      M. Ton.    1
            charge (bolts, nuts, washers, u-clamps etc for supporting shall be supplied by the Contractor
            within the rates quoted. These items will not be measured and paid separately) The work is to
            be completed in all respect as per scope of work and specification.

     b)     Supply, transportation and delivery at site, erection of Pre-Coated GI sheets for roof and walls,
            flushing of GI sheets, corners ridges, galvanized fittings and fixtures including cutting, bending
            of sheets to required shapes and sizes and erecting them in position with all labour, materials        M2      25
            as per specification and drawings, if required (Net laid area to be measured)

            Note: -
      I     The quantities indicated are estimated values and hence are approximate. Final Payment will
            be made based on actual quantities to be certified by the Purchaser
     ii     The cost of MS bolts (permanent and service( washers, electrodes, putty, gases, cost of
            starigtening the raw materials, cutting of flats from plated and providing splices, paints, tools,
            plants etc., as per required for the work shall be deemed to be included in the quoted rates.

     iii    All handling and transport charges of raw materials and fabricated structures including double
            handling, as required, for
            completion of work in accordance with time schedule, are deemed to be included in the quoted
            rates.
     6      CIVIL WORKS
                              SOR FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                                 MEERUT ZONE-2

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0                                                                                 Bidder Name:_____________________________
                                                                                                                                          Unit Price        Total Price
                                                                                                                                        including all      including all
   S.No.                                               Description                                                     Unit   Qty
                                                                                                                                      taxes and Duties   taxes and Duties
                                                                                                                                           in INR             in INR
    6.1     Site Grading
            Earth work inexcavation and filling to the grades and levels shown in the approved drawings in
            all kinds of soil including for Road embankments, using approved quality good earth from
            designated borrow area, for all heights and depths including clearing and stripping (Min. 150
            mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil
            surface, excavating the earth from borrow area loading, transporting & unloading, spreading in
            layers not exceeding 150 mm thickness, breaking clods, watering (if reqd.), ramming and                    M3      20
            compacting by manual/mechanical means to give minimum 95% of modified Proctor's density of
            earth, testing & dressing including disposal of all unserviceable material all complete as per
            specifications and directions of Engineer-in-Charge

            (Rate to include cost of labour, tools, tackles, equipment, hire charges, cost of borrow earth by
            way of realities, right of way, cess etc., as applicable with all bye works and sundry works).

    6.2     Plain Cement Concrete
            Supplying and laying plain cement concrete (including shuttering of required) in all types of
            concrete works including leveling courses below foundation, substructure, superstructure,
            chambers, cable trench, under floors and any other locations, at all levels as per drawings,
            specifications and directions of EIC
     i)     PCC 1:2:4
            1 Cement: 2 Coarse sand: 4 stone aggregate 20 mm nominal size                                              M3      20
     ii)    PCC 1:4:8
            1 Cement: 4 Coarse sand: 8 stone aggregate 40 mm nominal size                                              M3      20
            (Rate to include cost of all labour, tools ,tackles, equipment , hire charges, supply of all
            materials, shuttering , earth work in excavation and backfilling using approved earth in all
            conditions etc. with all bye works and sundry works.)
    6.3     Reinforced Cement Concrete
            Providing and laying reinforced cement concrete of grade M-20 with 20 mm and down grade
            crushed stone aggregate in all types of structures like foundations, pedestals, pedestal bases,
            pipe supports, sleepers cable trench including construction joints, bitumen painting on surface
            in contact with soil, providing and fixing reinforcing steel, shuttering, inserts, finishes etc. at all
                                                                                                                       M3      20
            depths and heights complete as per drawings , specifications and direction of the Engineer-in-
            Charge.
            Rate to include cost of all labour, tools, tackles, equipment , hire charges, supply of all
            materials, such as minimum 43 grade cement including sulphate resistant cement for sub
            structures, R/F steel, Inserts, bolts, conduits, bitumen, other minor construction materials,
            shuttering tanging, earth work in excavation and backfilling using serviceable earth in all
            conditions shorting bailing and pumping out water, testing of concrete, curing etc. will all bye
            works and sundry works.
    6.4     Concrete Pavement
            Providing and laying reinforced cement concrete (M20 Grade) with 20 mm and down grade
            crushed stone aggregate in pavement, including preparation of base (i.e. compacted sub grade,
            200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making recess,
            projections fixing inserts conduit pipes (GI,PVC,HDPE etc.) laying in alternate panels, filling the
            gaps between the panels with bitumen etc., making slopes, finishing edge, leaving bars for
            pedestals & sleepers, including providing sand fill isolation, shuttering providing and fixing
                                                                                                                       M2     100
            reinforcing steel, curing, chipping and modification works etc. as specified in any shape,
            thickness, position and finishing the top surface smooth as per requirement etc. all complete as
            per drawings, specifications and directions of the Engineer-in-Charge.

            150 mm thick (type-I)
    6.5     Brick Work
            Providing brick work with brick class designation M5.0 of IS:1077 in cm 1:5(1 cement : 5sand)
            in steps , walls, retaining walls and load bearing structures drains, or any shape with all lead,
            depths & height including curing scaffolding etc., as per specifications and drawings with all bye-        M3      20
            woks and direction of the Engineer-in-Charge
            (Rate to include cost of all labour, tools, tackles, equipment , hire charges, supply of all
            materials, such as minimum 43 grade cement bricks, finishes, bitumen, other minor construction
            materials, shuttering, staging , masonry work, plastering, painting etc. with all bye works and
            sundry works)
     7      Electrical
    7.1     Supply, Installation and testing of Galvanised Iron earth electrode with 3 mts long 65 mm dia GI
            perforated pipe Class B,Complete withh GI earth bus,test link in RCC/Brick earth                           Nos     30
            pit,charcoal,salt,funnel and earth pit cover as per IS:3043,(as per drg. enclosed)
    7.2     Supply and installation of GI earthing conductor of the following sizes:-
            Above ground/Buried under ground
     a)     25X 6 mm GI Strip                                                                                          Mtrs   375
     b)     2.5 sq.mm Cu PVC wire                                                                                      Mtrs   375
     c)     10 Sq.mm Cu PVC insulated cable                                                                            Mtrs   150
                                                                                                                        Grand Total
                                    STATEMENT OF TAXES & DUTIES
                                                FOR
                             MDPE PIPE LAYING AND DOMESTIC CONNECTIONS
                                         FOR MEERUT ZONE - 2

BIDDER NAME:_________________________________________

BID DOC.NO. 110290/WGI/GAIL GAS/33-R0

                                                                                         TOTAL AMOUNT OF
                                           BASE CEILING PRICE ON       PERCENTAGE (%)
                                                                                              TAXES
 Sl.No.            DESCRIPTION              WHICH TAXES/DUTIES            RATE OF
                                                                                                &
                                            SHALL APPPLY (in INR)       TAXES/DUTIES
                                                                                           DUTIES (in INR)


   1      TOTAL EXCISE DUTY                                                  --------%


   2      TOTAL SERVICE TAX                                                  --------%

   3      TOTAL VAT                                                          --------%

   4      TOTAL CENTRAL SALES TAX                                            --------%




          NOTES:

   1      Variation in taxes & duties shall be dealt with as per Tender Clause

   2      Taxes & Duties considered & included quoted price in SOR


                                                                             STAMP & SIGNATURE OF BIDDER
                                STATEMENT OF EXTENDED STAY COMPENSATION
                            FOR MDPE PIPE LAYING AND DOMESTIC CONNECTIONS FOR
                                              MEERUT ZONE - 2


Tender No - 110290/WGI/GAIL GAS/33-R0                                        Bidder Name -

                                            EXTENDED STAY COMPENSATION
                                                                                                 RATE
 Sl.No.                                 ITEM
                                                                                             (CURRENCY INR)

          Rate of Extended Stay Compensation per week beyond the Time
  1.0     Schedule and grace period mentioned in Bidding Document for                 ________________ (Per Week)
          reasons solely attributable to Owner.


 Note:

   1      Extended stay compensation shall be loaded on the quoted prices as per clause no. 61.0 of SCC

          In case no rate for extended Stay Compensation is stipulated,it will be considered that Extended Stay Compensation is
   2
          not required by the Bidder and the rates quoted by them shall be valid till completion of works in all respects.



                                                                                           STAMP & SIGNATURE OF BIDDER

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:11
posted:7/26/2011
language:English
pages:8