Quantitative Project Risk Analysis

Document Sample
Quantitative Project Risk Analysis Powered By Docstoc
					RiskyProject
Project Risk Management Software



 Intaver Institute Inc.
 303, 6707, Elbow Drive S.W, Calgary, AB, Canada
 Tel: +1(403)692-2252
 Fax: +1(403)459-4533
 www.intaver.com
What Is RiskyProject?




                                                                 7/25/2011
RiskyProject is Windows-based project risk
management software.

  •   Project Scheduling
  •   Risk Register




                                                                 2011 Intaver Institute
  •   Quantitative risk analysis using Monte Carlo simulations
  •   Project performance measurement


Risky Project gives you a simple answer to a common
question: What will happen to your project if certain
risks occur?
                                                                         2
The Project Management Problem




                                    7/25/2011
                 • Budget
                 • Schedule
   Projects      • Quality




                                    2011 Intaver Institute
 consistently
 fail to meet:   • Safety
                 • Technology
                 • Other measures

                                          3
The Project Management Problem




                                 7/25/2011
    Reasons




                                 2011 Intaver Institute
•   Human psychological limits
•   Inadequate training
•   Poor processes
•   others

                                       4
The Project Management Problem




                                                  7/25/2011
  Key Project Management Issues

• How to estimate project duration or cost?




                                                  2011 Intaver Institute
• What are the most critical risks and how to
  mitigate them?
• How to measure project performance?
• How to make an informed decision about future
  course of the project?
                                                        5
The RiskyProject Solution




                                                             7/25/2011
Project risk management made simple

• RiskyProject is consistent with PMI PMBOK. Risky
  Project supports the full project risk management




                                                             2011 Intaver Institute
  process.
• RiskyProject is very easy to use. RiskyProject is uses a
  scheduling interface similar to other project popular
  project management tools. This will allow project
  managers to easily integrate powerful risk management
  capabilities into their project planning
• RiskyProject has low implementation and support costs.           6
  Compared with the comparative products, RiskyProject
  provides unmatched value
The RiskyProject Solution




                                                              7/25/2011
Project risk management for Project
Managers




                                                              2011 Intaver Institute
• Provide state of art quantitative project risk management
  tools
• Low cost
• Ease of implementation
• Limited initial training required
• Scalable
                                                                    7
RiskyProject Features




                                                                  7/25/2011
•   Full scheduling engine with costs and resources
•   Full risk register that links to project schedules
•   Quantitative and qualitative analysis
•   Easy to use quantitative schedule risk analysis based on
    risk events




                                                                  2011 Intaver Institute
•   Probabilistic cash flow analysis
•   Project tracking with risks and uncertainties
•   Integration with Microsoft Project, Primavera, or other
    project management software
•   Optional decision tree analysis
•   Analysis of critical risk events which need to be mitigated
    first
                                                                        8
RiskyProject Features




                                                                  7/25/2011
•   Product lifecycle management
•   Risk templates
•   Probabilistic and conditional branching
•   Managing mitigation plans




                                                                  2011 Intaver Institute
•   “What if “ analysis
•   Advanced reporting tools
•   Risk event correlations
•   Multiple statistical distributions and distribution fitting


                                                                        9
RiskyProject Workflow




                                   7/25/2011
 RiskyProject uses common PM
 artifacts




                                   2011 Intaver Institute
 •   WBS
 •   Resources
 •   Costs
 •   Risk Register or Risk Lists
                                   10
Basic RiskyProject Workflow




                                           7/25/2011
1.   Define project defaults
2.   Define risk categories and outcomes
3.   Create or import project schedule




                                           2011 Intaver Institute
4.   Define and assign project risks
5.   Run Simulations
6.   Analyze results
7.   Monitor performance with risks and
     uncertainties
                                           11
                                          RiskyProject Workflow




     2011 Intaver Institute   7/25/2011
12
 Define Project Schedule

               Enter resources, cost and
                   income for each task
                                                              Enter complete WBS,




                                                                                        7/25/2011
                                                               as it is done in other
                                                              project management
                                                                            software




                                                                                        2011 Intaver Institute
You may also import project schedules from other scheduling tools, such as Microsoft
Project or Primavera.                                                                   13
                         Risk Register
     Risk register
     view




                                                                        7/25/2011
                                                                        2011 Intaver Institute
Separate
opened and                           Pre mitigation   Post mitigation
closed risk and                      Probability,
                     Separate                         Probability,
issues                               Impact, and
                     threats or                       Impact, and
                                     Score            Score
                     opportunities                                      14
    Risk Form
       Double-click on a risk to view or modify Risk Information




                                                                   7/25/2011
Risk description
and status



Management




                                                                   2010 Intaver Institute
Strategy


Cost of Risk




Review Timeline

                                                                     15
Qualitative and Quantitative Risk Assessment
  If no schedule is attached, qualitative risk assessments can be




                                                                          7/25/2011
  performed




                                                                          2010 Intaver Institute
                         Outcome Types are
                         now qualitative     Outcomes for risk
                                             categories are qualitative
                                             and are based on risk
                                             matrix settings

                                                                            16
Mitigation Plans
  Add mitigation or risk response plans (cost, expected
  reduction in probability and impact, an descriptions.
  Plans can have sub-plans




                                                          7/25/2011
                                                          2010 Intaver Institute
                                                            17
Mitigation Waterfall Chart
   Track total cost and expected reductions in probability
   or impact and dates for mitigation plans




                                                             7/25/2011
                                                             2010 Intaver Institute
                                                               18
Risk Reviews
  All risk reviews with details can be saved and tracked




                                                           7/25/2011
  in system




                                                           2010 Intaver Institute
                                                             19
                                          Risk History




     2010 Intaver Institute   7/25/2011
20
  Risk Assignment
Risks can be global (for
all tasks or resources)
or local (for specific
tasks or resources)




                                       7/25/2011
                                       2011 Intaver Institute
     Define risk chance, outcome and
     result. Risks can have mutually
     exclusive outcomes, different
     outcomes of the same risk         21
Statistical Distribution for Risk impacts




                                                          7/25/2011
                              Statistical Distributions
                                  are enabled in Risk
                              Options. Description of
                                   feature to the left.




                                                          2010 Intaver Institute
                                Enter Base, Low,
                               and High Impacts
                                       and select           22
                                distribution type
 Statistical Distributions

                                  In addition to risk events
                                  you may define




                                                                 7/25/2011,
                                  uncertainties as statistical
                                  distributions for:
                                   task cost




                                                                 2011 Intaver Institute
                                   task start time
                                   task duration
                                   income associated with
If you enter only the low, base   task
and high cost, duration, start
time and income, RiskyProject
will generate statistical
distribution based on this data

                                                                 23
Monte Carlo Simulation




                                        7/25/2011
      When your project schedule
      and risk breakdown structure is
      ready, click here to perform
      Monte Carlo simulations




                                        2011 Intaver Institute
                                        24
Result Gantt Chart
   Compare original project schedule and result of analysis




                                                                               7/25/2011
                                                     White bars represent
                                                          original project
                                                      schedule (no risks)




                                                                               2011 Intaver Institute
                                                        Blue bars represent
                                                      project schedule with
                                                                       risks



                                                                               25
Results of Risk Analysis

                                                           Project Summary:
                                                            project duration,




                                                                                  7/25/2011
                                                         cost, and finish time
                                                            with and without
                                                                          risks




                                                                                  2011 Intaver Institute
                                                           Results of analysis
                                                             for project cost,
                                                             finish time, and     26
Double click on any chart to view detailed information               duration
  Detailed Results of Analysis
Detailed results can be shown for each task
or project for cost, duration, start time, finish
                                                    Move the slider to determine
time, and income.
                                                     the chance that project will
                                                                be within budget




                                                                                    7/25/2011
                                                                                    2011 Intaver Institute
                                                          Data can be exported
                                                            as an image or text
Get detailed
statistical data


                                                                                    27
Cost, Income and Revenue




                                                               7/25/2011
                                                               2011 Intaver Institute
                                      Compare forecasted
                                    project costs with (blue
                                     line) and without (red
 Cost chart is generated based on           line) risks
   fixed and variables cost and
income associated with tasks and
             resources                                         28
Probabilistic Cash Flow Analysis




                                                          7/25/2011
                                                          2011 Intaver Institute
                                    Compare cash flows
 Cash flow is generated based on    with (blue bars) and
   fixed and variables cost and    without (red line) risks
income associated with tasks and
             resources
                                                          29
Sensitivity Analysis




                                                          7/25/2011
                                                          2011 Intaver Institute
       Prioritize critical risks




                    Tornado chart shows risks or other
                   parameters that have the most affect
                         on the project schedule

                                                          30
Crucial Tasks


                Crucial tasks for project cost and




                                                     7/25/2011
                   duration can be different




                                                     2011 Intaver Institute
                Crucial tasks have the
                 most affect on the
                  project schedule
                                                     31
Risk Chart
Risk chart shows task duration and versus risk, associated with task




                                                                                7/25/2011
                                                                                2011 Intaver Institute
                                                            This task has low
                                                            duration but high
                                                            risk




               These tasks have
              balanced risk versus
                                                                                32
                 duration ratio.
Risk Matrix




                             7/25/2011
                             2011 Intaver Institute
        Risk Probability,
      Impact and Score for
      the current schedule

                             33
   Project Dashboard 3x3

Project Dashboard 3x3
is a condensed view of      3 most important project




                                                            7/25/2011
  the most important       parameters (cost, duration,
   results of analysis          and finish time)




                                                            2011 Intaver Institute
                                    3 most crucial tasks



                                    3 most critical risks


                                                            34
    Project Tracking
For each task at any moment you may enter how much work has been completed
                                                       This task is 100%
                                                     completed (green bar)




                                                                                    7/25/2011
                                                                                    2011 Intaver Institute
                                                           This task is partially
                                                           completed (yellow
                                                                   bar)
           Risky project automatically
         adjusts the probability of risks
          for partially completed tasks                                             35
 Tracking Results
New project forecast is done each time actual project data is entered




                                                                            7/25/2011
                                                           Low, base, and
                                                            high forecast




                                                                            2011 Intaver Institute
                  Original (baseline)
                   project duration                   Actual project
                                                        duration




                                                                            36
Advanced Project Risk Management
   Risk Mitigation




                                                           7/25/2011
   • Create multiple baselines that model mitigation
     efforts
   • View results of mitigation efforts in risk register




                                                           2011 Intaver Institute
   • Select project schedule based on criteria (cost,
     duration, start time, finish time)




                                                           37
Advanced Project Risk Management

   Create baselines that model mitigation efforts

   • Mitigation can include additional activities, costs, and risks




                                                                      7/25/2011
   • Baselines can be based on any result type




                                                                      2011 Intaver Institute
                                                                      38
Advanced Project Risk Management
   View mitigation efforts

   • Risk register allows you to compare pre and post mitigation risk
     scores




                                                                                      7/25/2011
                                                                                      2011 Intaver Institute
                                                                    Pre and post
                                                                    mitigation risk
                                                                        scores

                                      Select pre and post
                                      mitigation baselines
                                        to view on risk
                                                                                      39
                                            register
Mitigation Plans
  Add mitigation or risk response plans (cost, expected
  reduction in probability and impact, an descriptions.
  Plans can have sub-plans




                                                          7/25/2011
                                                          2010 Intaver Institute
                                                            40
Mitigation Waterfall Chart
   Track total cost and expected reductions in probability
   or impact and dates for mitigation plans




                                                             7/25/2011
                                                             2010 Intaver Institute
                                                               41
Advanced Project Risk Management
   View mitigation efforts

   • For each risk




                                                  7/25/2011
                                                  2011 Intaver Institute
                             Waterfall diagram
                             charts changes in
  See risk scores for          risk scores for
    each baseline            selected baselines


                                                  42
Advanced Project Risk Management




                                              7/25/2011
                                              2011 Intaver Institute
                        Compare results for
   Select the current     each baseline
       schedule




                                              43
Advanced Project Risk Management




                                             7/25/2011
                                             2011 Intaver Institute
                          Run alternative
                         project branches
                         probabilistically




                                             44
Integration with MS Project 2010
 Risk tab installed on MSProject ribbon allows users move projects
 seamlessly into RiskyProject




                                                                     7/25/2011
                                                                     2010 Intaver Institute
                                                                       45
Integration With PM Software
     RiskyProject can export original project schedules and results of analysis
 to other project management software include Microsoft Project and Primavera




                                                                                  7/25/2011
                           Project schedule
                          can be visualized as
                          WBS or PERT chart




                                                                                  2011 Intaver Institute
                                                    These software tools,
                                                     including Microsoft
                                                  Project, can be executed
                                                  directly from RiskyProject


                          RiskyProject schedule
                           can be converted to
                              decision tree
                                                                                  46
Intaver Institute’s Services
Intaver Institute performs project risk management, risk




                                                                     7/25/2011
analysis, and decision analysis training and consulting

Popular Intaver’s training courses include:




                                                                     2011 Intaver Institute
•   Project management: theory and best practices
•    Introduction to project risk management: theory and case
    studies
•   Project decision analysis
•   Quantitative methods in project management
•    Introduction to RiskyProject: basic RiskyProject workflow and
    features                                                         47


•   Advanced features of RiskyProject Professional

				