August 19, 2009 
 
 
 
 
 
Alpha Psi Chapter Theta Chi Fraternity Alumni Association 
1707 Ritchie Highway 
Annapolis, Maryland 21409 
 
 
RE:  Theta Chi Renovation and Expansion 
        College Park, Maryland 
 
 
Gentlemen: 
 
Attached please find Field Observation Report #31 dated August 19, 2009. 
 
If you have any question or comments regarding anything in the attached report, please feel free to contact me. 
 
 
Sincerely, 
 
 
Bill Sawicki 
(301) 922‐5825 
whsaw@aol.com 
                                                        FIELD OBSERVATION REPORT #31 
                                           Theta Chi Renovation and Expansion – College Park, Maryland 
                                                                 August 19, 2009 
                                                                         
                                                                         
                                                                         
1.     PURPOSE 
       This report is an update of construction‐related activities as of this date, including current photographs from the site. 
        
2.     CONSTRUCTION PROGRESS 
       a) Close‐in inspections have been received for all floors except the basement. Drywall installation and finishing continues. Wall tile is being 
          installed in the second‐floor bathrooms. 
       b) HVAC equipment is on site and is being installed. 
       c) Theta Chi has indicated to DesBuild that the stair/step lifts are not an acceptable solution for ADA access. Original lift shaft has been 
          capped at the basement and is in the process of being converted to a closet. 
       d) The northeast bedroom on the second floor of the addition has not been modified in accordance with the directive given at the August 
          10 progress meeting. It would appear the options are to:  accept the room as is; move and/or reduce the size of the clothes closet such 
          that a desk could fit between this closet and the HVAC unit; wait until the project is completed and rebuild the room using a new HVAC 
          unit with a front‐facing return grill, and relocate the clothes closet next to the HVAC closet. 
       e) Mike Miller has been directed NOT to paint the exterior doors red, as it is not the appropriate red. 
        
3.     CRITICAL CONSTRUCTION ISSUES 
       a) DesBuild needs to finalize:  how the water will be ejected from the waterproofing sumps (this is outside the scope of work of the 
          waterproofing contractor); selections for apartment kitchens and brothers’ pantry (cabinets and counters) and stair tread covering; a 
          keying schedule for Theta Chi approval; layout modifications to the northeast bedroom on the second floor to allow for a desk. 
       b) Theta Chi to:  make applications for cable television and internet service; and make selections for cabinets and counters for the 
          apartment kitchens and the brothers’ pantry; advise on the current layout of the northeast bedroom on the second floor. 
        
 
End of Report 
 
Respectfully submitted, 
Bill Sawicki 
 
Attachments  –  Site Photographs 
                                                                  PHOTOGRAPHS 
                                                                         
                                                                         
                                                                         
                                                                         
Lift shaft has been capped and is being converted to a closet:         Fireplaces have been sealed, but brick is not recessed as directed: 
 




                                                                                                                                               
 
 
 
 
Existing passageway at the bottom of the existing stairs is being filled in order to accommodate the stair lift, which will extend well beyond the 
bottom riser of the stairs. A new passageway had been added beyond the run of the stair lift: 
 




                                                                                                                                                       
 
 
                           Existing passageway being filled.                                      New passageway has been added.
Wall tile has commenced in second‐floor bathrooms: 
 




                                                                         
 
 
 
Passageway adjacent to lift shaft in basement has been added:            Main‐floor drywall installation has commenced: 
 




                                                                                                                            
 
 
 
 
          Living room:         
 




                                   
 
 
 
 
 
Dining room: 
 




                         
 
 
 
 
 
Kitchen:     
 




                            
         Main entry hall: 
 
Second‐floor, northeast bedroom is being completed as it was framed, making it difficult to utilize the room as intended, as previously noted to 
DesBuild. HVAC unit is about to be installed: 
 




                                                                                                                                                     

				