					                                                                 STATE UNIVERSITY OF NEW YORK
                                                         COLLEGE OF TECHNOLOGY AT ALFRED
                                                                     2010 CAMPUS STATEMENT

Alfred State College is located in Alfred, NY, a scenic village in Allegany County, surrounded by lakes, ponds, wetlands, and state parks. Hike 15 minutes from campus
and you arrive at the beautiful Alfred State Lake Lodge, a recreational complex where you can paddleboat, fish, swim, or camp. ASC is 15 miles north of the
Pennsylvania border, 70 miles south of Rochester, and 90 miles southeast of Buffalo. Alfred, NY, is a vibrant community with a permanent population of about 2,000
residents and nearly 6,000 students enrolled in three colleges.

The Alfred State campus consists of 260 acres with academic and residential buildings, and is in close proximity to our 800-acre working college farm. ASC’s second
campus, which houses the School of Applied Technology, in nearby Wellsville, NY, (a 15-20 minute drive) is situated on 21 acres and is comprised only of academic
and administrative buildings.

The College of Technology at Alfred (“Alfred State College”) had its beginning as a State School of Agriculture in 1908 when it was created by an act of the State
Legislature. An important milestone in the history of the College occurred in 1948 when it was incorporated into the newly organized State University of New York
system. In 1951, the College was authorized by SUNY to award the degree of associate in applied science; the associate in science and associate in arts degrees were
authorized 1967, and an associates occupational studies was approved in 1973. Bachelor degrees were added to the College’s offerings in 1991. Today, the College has
53 associate degrees, 18 bachelor degrees, and three certificate programs. The College enrolls approximately 3,800 students and has residential facilities for more than
2,500 students.

Recent capital improvements include a completed multi-million dollar rehabilitation of the Central Dining Hall, Phase II which included renovations to the kitchen,
serving area, and seating area; renovations to the library basement to facilitate the Technology Services relocation for the Allied Health rehab project; renovations to the
library entrance; installation of the new athletic field gateway buildings which consist of two buildings for concession and ticket sales, restrooms, and storage of athletic
field equipment; and rehabilitation of the campuses high temp/hot water loop from the heating plant to CDH. Regular on-going maintenance includes roof replacement
on various buildings, concrete and black-top repair, and classroom upgrades. In addition, a variety of minor rehab projects are nearing completion in the library, EJ
Brown, Motorsports, and several residence halls. Capital improvements are underway for critical maintenance and renovation to Allied Health. Recent residential
improvements include a public space interior makeover in Peet Hall (where the new color schemes and décor will provide a more home-like atmosphere and a sense of
community for our residents); new white roofs on Main Gate A and Main Gate B; and fire suppression sprinkler systems were installed in Burdick and Getman Halls.

A major initiative currently in the planning stages involves the College’s century-long role in agriculture education and will include the construction of an agriculture
complex of buildings known as COSA (The Center for Organic and Sustainable Agriculture). As the College embarks upon its second century, it is positioned to reform
and expand its agriculture programs in a way that will create a unique educational niche within SUNY and the nation. Construction is expected to begin in the spring of
2011.

In addition, our new Institute for Sustainability will promote the advancement of sustainability at Alfred State College and Western New York through delivery of
training programs, as well as public outreach and partnerships.

The Student Leadership Center is a strategic initiative that completed program and schematic design in 2009-10. The center is uniquely designed to bring the best civic
engagement and student leadership development opportunities to those students struggling with how best to engage in activities that will prepare them to be the citizens
of tomorrow today. It will also offer new innovations in engaging students through the use of space and technology and as such will look nothing like any other student
center in higher education today. Construction is projected to begin in May 2011.
                                         State University of New York
                                        College of Technology at Alfred

                                         Facility Profile as of Fall 2009

                                                                           Instructional
                          Facility Profile                                                     Residential      Total
                                                                            & Support

                                             Total State Owned Acreage                                           904

                                         Total State Owned Buildings             51                35             86

                          Total State Owned Gross Square Feet (GSF)           763,413            620,317      1,383,730

                Total State Owned Net Assignable Square Feet (NASF)           555,481            402,417       957,898



                         Age of Facilities                                  < 10 Years        10 – 40 Years   > 40 Years

                                                       Gross Square Feet       62,114            537,980       783,636

                                               Percentage of Total GSF          4.5%             38.9%          56.6%



                            Net Assignable Space Distribution by Major Functional Area

Instructional       Research      Student Activities     Administration    Central Services    Residential      Total

    25%                3%               13%                   5%                12%               42%           100%
Site Utility Distribution Line Replacement             Student Leadership Center
                ($ 2.3 Million)                             ($ 26.1 Million)




          Rehab Allied Health                Repair Foundation Drainage – Engineering Tech
            ($ 19.6 Million)                               ($ 118.5 Thousand)



                        College of Technology at Alfred
                                                                            State University of New York
                                                                          2010/2011 Capital Program Plan
                                                                Major Ongoing Projects (Over $1M Construction Cost)
                                                                                 As of July 31, 2010
                                                                                         (In Thousands)

                                                                State University of New York College of Technology at Alfred

                                                                                 PROJECTS UNDER DESIGN
                                                                                                                                               Anticipated Start of Construction
                                        Capital Plan Projects                     Total        YTD Expend.       LTD Expend.   Encumbered    10/11   11/12   12/13   13/14   14/15
                                                                                Estimated         thru               thru        Amount
                                                                               Project Cost     07-31-10           07-31-10     07-31-10
Rehab Allied Health Building                                                         $19,855              $130         $695         $1,391    X
Rehab For Centennial Farm                                                             $4,900              $275         $603           $25     X
Student Union/Student Activities Center                                              $23,886              $220         $420         $2,850             X
Student Leadership Center Phase 1                                                     $7,714                $0           $0            $0     X



                                                                            PROJECTS UNDER CONSTRUCTION
                                                                                                                                                  Anticipated Completion Date
                                        Capital Plan Projects                     Total        YTD Expend.       LTD Expend.   Encumbered    10/11   11/12   12/13   13/14   14/15
                                                                                Estimated         thru               thru        Amount
                                                                               Project Cost     07-31-10           07-31-10     07-31-10
Site Utility Distribution Line Replacement - Phase 1                                  $2,413                $0        $1,832         $471     X
Rehab Central Dining Hall - Phase II                                                  $4,880              $451        $4,629          $81     X
Classroom/Labs Upgrade - Various Buildings                                            $2,400               $10         $284           $47                     X
Plumbing Upgrades - Various Buildings/ Site                                           $2,400                $0          $58            $0                              X
                                                                                               State University of New York
                                                                                             2010/2011 Capital Program Plan
                                                                                     Future Planned Projects - Over $1M Construction
                                                                                                    As of July 31, 2010
                                                                                                        (In Thousands)

                                                                                State University of New York College of Technology at Alfred

                                Capital Plan Projects                                      Total        Funds             Funds         SFY            SFY          SFY            SFY          SFY
                                                                                         Estimated     Available         Needed to     2010/11        2011/12      2012/13        2013/14      2014/15
                                                                                        Project Cost                     Complete     Phase $        Phase $      Phase $        Phase $      Phase $

Rehabilitate Agricultural Science Bldg                                                        $5,742               $0        $5,742              D       $1,148              C       $4,593




      PROJECT PHASES: A = Acquisition, D = Design, C = Construction, E = Equipment
                                                                          State University of New York
                                                                             Summary of Changes
                                                                        2010/2011 Capital Program Plan
                                                           Project Cross-Reference: Current Year Status vs. Last Year
                                                                                     (In Thousands)

                                                              State University of New York College of Technology at Alfred
                                            Capital Plan Project                                  2009                 2010           Incr./Decr.
                                                                                                Estimated            Estimated             In
                                                                                                 Project              Project          Estimate
                                                                                                  Cost                  Cost             Cost

Projects Under Design
              Rehab Allied Health Building                                                            $19,639            $19,855              $216
              Student Union/Student Activities Center                                                 $33,500            $23,886           -$9,614
              Student Leadership Center Phase 1                                                                           $7,714            $7,714


Projects Under Construction
              Site Utility Distribution Line Replacement - Phase 1                                     $2,292                $2,413           $121
              Rehab Central Dining Hall - Phase II                                                     $4,301                $4,880           $579

				