                                             CONTRACT TIME CALCULATION SHEET
                          Road:                  SR X and SR Y
                          FPID:         400000-1-52-01 and 400000-2-52-01
        Federal Aid Project No.:                       N/A
                        County:                      County
          Consultant Company:

Project Location Impact
 "Time Priority": State specific conditions and recommended number of calendar days or specific time period. Attach approval by the Deputy
 Assistant Secretary and supporting data explaining why project is a "Time Priority Project". Include method used to establish contract time.


                                                     Quantities                                                         Number of Working
                                      Lead            Goes With          Grand                                                  Days
Work Involved on Projects           400000-1          400000-2           Totals     Units         Rate/Day     Max      Time        Normal
                                                                                                                       Priority
Clearing & Grubbing                      1                 1                2         AC    @         1        (20)                   2

Earthwork                                1                 1                2         CY         See Graph                             1

Stabilization                            1                 1                2         SY    @         1        (10)                    2

Base Construction                        1                 1                2         SY         See Graph                             1

Concrete Pavement                        1                 1                2         SY    @         1                                2

Milling Existing Pavement                1                 1                2         SY    @         1         (5)                    2

Superpave                                1                 1                2         TN         See Graph                             1

Friction Course                          1                 1                2         TN         See Graph                             1

Storm Sewer, Conduit, etc…               1                 1                2         LF    @         1                                2

Curb & Gutter                            1                 1                2         LF    @         1                                2

Gravity Wall (Permanent)                 1                 1                2         LF    @         1                                2

Sidewalk                                 1                 1                2         SY    @         1                                2

Grassing                                 1                 1                2         SY    @         1         (5)                    2

Guardrail                                1                 1                2         LF    @         1                                2

Final Striping                           1                 1                2         MI    @         1                                2

                                                                                                Sub-Total Work Days                    26

Factors
1.48 = 5 day work week + holidays                    1.29 = 6 day work week + holidays
1.40 = 5 day work week, No holidays                  1.00 = 7 day work week, No holidays

                                 Sub-Total Work Days for Contract          26       WD      X        1.4     Factor                    36

                                                                                                  Utility Operations                   0

                                             General Time (5 calendar days plus 14 calendar days Striping Cure)                        19

                                                                Total Estimated CONTRACT TIME Calendar Days                            55

                                                                                                                          Use          60

Special Acquisition Period allowed prior to
charging of CONTRACT TIME (Lead Time)                                 Calendar Days
                                                                                                           Signature and Date
                                                                                                       Name, Phone Number and E-mail

								