Docstoc

Project Test Management

Document Sample
Project Test Management Powered By Docstoc
					Software Project
Management Plan (SPMP)
For the Test Management
Tool (TMT)
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 2 of 60
                                
                                                                         Test Management Tool (TMT)
                                                            Software Project Management Plan (SPMP)
                                                                                     TMT-SPMP-1.2
                                                                                       27-Sep-2010




                                 SIGNATURE PAGE
This page shows signatures of applicable team members indicating that the content of this
document has been carefully reviewed and concurred.



_________________________________                   __________________
Jagati Vempaty                                      Date
Lead Requirements Analyst



_________________________________                   __________________
Harish C. Sreenivas                                 Date
Lead Architect/Designer



_________________________________                   __________________
Adam Scott                                          Date
Lead Developer



_________________________________                   __________________
Seth Zaah                                           Date
Lead QA / Tester



_________________________________                   __________________
Tom Q. Le                                           Date
Project Manager



_________________________________                   __________________
Frank Tsui                                          Date
Project Advisor




                                          Page 3 of 60
                                                 
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 4 of 60
                                
                                                                         Test Management Tool (TMT)
                                                            Software Project Management Plan (SPMP)
                                                                                     TMT-SPMP-1.2
                                                                                       27-Sep-2010



                               REVISION HISTORY
The following table lists a history of changes made to this document. When a change is made,
the following attributes are updated: Version, date, A/M/D, description, and CRN. The version
indicates major and minor changes; 9 minor changes make up 1 major. The A/M/D indicates if
the change is a modification, addition, or deletion. The CRN is the change request number, if
applicable. The description briefly describes the changes.

Version    Date     A/M/D                   Description                                   CRN
  1.0   08-Sep-2010   A   Initial Draft                                                   N/A
  1.1   20-Sep-2010 A,M Baseline                                                          N/A
  1.2   27-Sep-2010   M   Baseline updated after peer review                              N/A




                                          Page 5 of 60
                                                 
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 6 of 60
                                
                                                                           Test Management Tool (TMT)
                                                              Software Project Management Plan (SPMP)
                                                                                       TMT-SPMP-1.2
                                                                                         27-Sep-2010



                                        PREFACE
The purpose of this Software Project Management Plan (SPMP) is to provide guidance on the
management of the Test Management Tool (TMT) that is a part of the Southern Polytechnic
State University (SPSU) Testing System (STS) software development project. The template of
this plan conforms to the Institute of Electrical and Electronics Engineers (IEEE) Standard for
Software Project Management Plans, IEEE Std. 1058-1998, for format and content. The template
and its standard were selected as they are flexible and applicable to any type of project, well-
known to and accepted by many software companies, as well as common to the software
engineering department at SPSU. The TMT Project Manager (PM) assumes responsibility for
this document and updates it as required to meet the needs of the project. Updates to this
document are performed in accordance with the configuration management process defined
within this document, reviewed and concurred by applicable team members listed in the
signature page of this document.

This document relates to other documents as depicted in the following project document tree:

                       Software Project Management Plan
                                  (TMT-SPMP)

                POMA        Software Requirements Specification
                                        (TMT-SRS)

                POMA             Software Design Description
                                         (TMT-SDD)

                POMA                  Software Test Plan
                                          (TMT-STP)

                POMA              Software Test Description
                                         (TMT-STD)

                POMA                 Software Test Report
                                          (TMT-STR)

                POMA             Software Version Description
                                         (TMT-SVD)

                POMA                Software User Manual
                                         (TMT-SUM)

                            Software Development Status Report
                                       (TMT-SDSR)
                               Figure 1.1-1: Project Document Tree




                                          Page 7 of 60
                                                 
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 8 of 60
                                
                                                                                                       Test Management Tool (TMT)
                                                                                          Software Project Management Plan (SPMP)
                                                                                                                   TMT-SPMP-1.2
                                                                                                                     27-Sep-2010



                                              TABLE OF CONTENTS
SIGNATURE PAGE ...................................................................................................................... 3 
LIST OF FIGURES ...................................................................................................................... 12 
LIST OF TABLES ........................................................................................................................ 13 
1. OVERVIEW ............................................................................................................................. 15 
   1.1. Project Summary ................................................................................................................ 15 
       1.1.1. Purpose, Scope, and Objectives .................................................................................. 16 
       1.1.2. Assumptions and Constraints...................................................................................... 16 
       1.1.3. Project Deliverables .................................................................................................... 17 
       1.1.4. Schedule and Budget Summary .................................................................................. 17 
   1.2. Evolution of the Plan ......................................................................................................... 18 
   1.3. Document Overview .......................................................................................................... 19 
2. REFERENCES ......................................................................................................................... 21 
   2.1. Standards, Documents, and Other Material ....................................................................... 21 
   2.2. Deviations and Waivers ..................................................................................................... 21 
3. DEFINITIONS.......................................................................................................................... 23 
4. PROJECT ORGANIZATION .................................................................................................. 25 
   4.1. External Interfaces ............................................................................................................. 25 
   4.2. Internal Structure ............................................................................................................... 26 
   4.3. Roles and Responsibilities ................................................................................................. 26 
5. MANAGERIAL PROCESS PLANS........................................................................................ 29 
   5.1. Start-up Plan....................................................................................................................... 29 
       5.1.1. Estimation Plan ........................................................................................................... 29 
       5.1.2. Staffing Plan................................................................................................................ 29 
       5.1.3. Resource Acquisition Plan .......................................................................................... 30 
       5.1.4. Project Staff Training Plan.......................................................................................... 31 
   5.2. Work Plan .......................................................................................................................... 31 
       5.2.1. Work Activities ........................................................................................................... 31 
       5.2.2. Schedule Allocation .................................................................................................... 31 
       5.2.3. Resource Allocation .................................................................................................... 31 
       5.2.4. Budget Allocation ....................................................................................................... 31 
   5.3. Control Plan ....................................................................................................................... 31 
       5.3.1. Requirements Control Plan ......................................................................................... 32 

                                                               Page 9 of 60
                                                                        
                                                                                                         Test Management Tool (TMT)
                                                                                            Software Project Management Plan (SPMP)
                                                                                                                     TMT-SPMP-1.2
                                                                                                                       27-Sep-2010


       5.3.2. Schedule Control Plan................................................................................................. 32 
       5.3.3. Budget Control Plan .................................................................................................... 33 
       5.3.4. Quality Control Plan ................................................................................................... 33 
       5.3.5. Reporting Plan ............................................................................................................ 34 
       5.3.6. Metrics Collection Plan............................................................................................... 35 
   5.4. Risk Management Plan ...................................................................................................... 35 
   5.5. Closeout Plan ..................................................................................................................... 36 
6. TECHNICAL PROCESS PLANS ............................................................................................ 37 
   6.1. Process Model .................................................................................................................... 37 
   6.2. Methods, Tools, and Techniques ....................................................................................... 38 
       6.2.1. Requirements Methods & Techniques ........................................................................ 38 
       6.2.2. Design Models ............................................................................................................ 38 
       6.2.3. Testing Methods & Techniques .................................................................................. 38 
       6.2.4. Programming Languages ............................................................................................ 38 
       6.2.5. Tools ........................................................................................................................... 39 
   6.3. Infrastructure Plan .............................................................................................................. 39 
   6.4. Product Acceptance Plan ................................................................................................... 39 
7. SUPPORTING PROCESS PLANS .......................................................................................... 41 
   7.1. Configuration Management Plan ....................................................................................... 41 
   7.2. Verification and Validation Plan ....................................................................................... 41 
   7.3. Documentation Plan ........................................................................................................... 42 
   7.4. Quality Assurance Plan ...................................................................................................... 42 
   7.5. Reviews and Audits ........................................................................................................... 43 
   7.6. Problem Resolution Plan.................................................................................................... 44 
   7.7. Subcontractor Management Plan ....................................................................................... 44 
   7.8. Process Improvement Plan ................................................................................................. 44 
8. ADDITIONAL PLANS ............................................................................................................ 45 
APPENDIXES .............................................................................................................................. 47 
   Appendix A: Requirements Review Checklist ......................................................................... 47 
   Appendix B: Design Review Checklist .................................................................................... 48 
   Appendix C: Code Review Checklist ....................................................................................... 49 
   Appendix D: Test Review Checklist......................................................................................... 50 
   Appendix E: Defect Report Form ............................................................................................. 51 

                                                               Page 10 of 60
                                                                         
                                                                                               Test Management Tool (TMT)
                                                                                  Software Project Management Plan (SPMP)
                                                                                                           TMT-SPMP-1.2
                                                                                                             27-Sep-2010


Appendix F: Review Kickoff Form .......................................................................................... 52 
Appendix G: Review Closeout Form ........................................................................................ 53 
Appendix H: Defect Resolution Form ...................................................................................... 54 
Appendix I: Data Collection Point ............................................................................................ 55 
Appendix K: Defect Severity Levels ........................................................................................ 56 
Appendix L: Defect Types ........................................................................................................ 57 




                                                       Page 11 of 60
                                                                 
                                                                                                Test Management Tool (TMT)
                                                                                   Software Project Management Plan (SPMP)
                                                                                                            TMT-SPMP-1.2
                                                                                                              27-Sep-2010




                                              LIST OF FIGURES
Figure 1.1-1: Project Document Tree ............................................................................................. 7 
Figure 1.1-1: System Context Diagram ........................................................................................ 15 
Figure 4.1-1: Project External Organization Interfaces ................................................................ 25 
Figure 4.2-1: Project Internal Organization Structure .................................................................. 26 
Figure 6.1-1: TMT Software Development Life Cycle (SDLC) .................................................. 37 
Figure 6.2-1: TMT Requirements Process Flow........................................................................... 38 
Figure 7.1-1: TMT Configuration Management Flow .................................................................. 41 
Figure 7.4-1: Peer Review Process ............................................................................................... 42 
Figure 7.4-2: Walkthrough Review Process ................................................................................. 43 




                                                         Page 12 of 60
                                                                   
                                                                                                   Test Management Tool (TMT)
                                                                                      Software Project Management Plan (SPMP)
                                                                                                               TMT-SPMP-1.2
                                                                                                                 27-Sep-2010



                                                 LIST OF TABLES
Table 1.1-1: Project Deliverables ................................................................................................. 17 
Table 1.1-2: Master Build Schedule ............................................................................................. 17 
Table 1.1-3: Project Budget Summary.......................................................................................... 17 
Table 4.1-1: Programmatic Roles and Responsibilities ................................................................ 25 
Table 4.3-1: Project Roles and Responsibilities ........................................................................... 26 
Table 5.1-1: TMT Team Member Skill Levels ............................................................................. 30 
Table 5.1-2: Non-Staff Resource Acquisition .............................................................................. 30 
Table 5.3-1: TMT Team Member Contact Information ............................................................... 34 
Table 5.3-2: TMT Metrics ............................................................................................................ 35 
Table 6.2-1: TMT Programming Languages ................................................................................ 39 




                                                           Page 13 of 60
                                                                     
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 14 of 60
                                
                                                                                                     Test Management Tool (TMT)
                                                                                        Software Project Management Plan (SPMP)
                                                                                                                 TMT-SPMP-1.2
                                                                                                                   27-Sep-2010




                                                     1. OVERVIEW
1.1. Project Summary

The SPSU Testing System (STS) is a suite of software testing tools developed by SPSU students
majoring in Computer Science and/or Software Engineering to provide services to businesses
that need software testing. The STS aims to enhance manual software testing (via better defined
process, automatic test case generation, and improve on test cycle speed), improve test
management and control, and improve software product quality (via early defect detection). The
STS is a web-based system operating on a dedicated server which businesses can register to gain
access to different testing tools as described in the following system context diagram:


   Req. Spec.,
  Design Spec.,
    Or Code                              SPSU Testing System (STS)




                  Defines test              Test Case
                                          Generation Tool                               Test Execution
                    model                                                                    Tool

                                                                    Test result info

   Test Analyst
                                                      Test cases             Get test cases
                                                                                                               Run test cases
                                                 Errors                                  Test cases

                      Updates                                  Test Management
                     test cases                                      Tool




                                                      Queries
                                                      test info                         Test case
                                          Test reports          Test info
                                                                                       assignments
                                   Generate
                                                                    Assigns
                                  test reports
                                                                   test cases


                                                                                                             Testers




                                                   Lead Tester

                                            Figure 1.1-1: System Context Diagram




                                                            Page 15 of 60
                                                                     
                                                                           Test Management Tool (TMT)
                                                              Software Project Management Plan (SPMP)
                                                                                       TMT-SPMP-1.2
                                                                                         27-Sep-2010



1.1.1. Purpose, Scope, and Objectives

This project involves in the evolutionary development of the STS, a software test suite that
consists of the following test tools:

   1. Test Generation Tool (TGT): The purpose of this tool is to provide a test analyst the
      capability to define a test model and generate test cases based on the inputs of
      requirements specification, design specification, or source code via auto or manual
      conversion. The tool converts the inputs into test cases; however, if the conversion fails,
      the tool captures the errors. Both test cases and errors are then sent to the Test
      Management Tool.

   2. Test Management Tool (TMT): The purpose of this tool is to manage test cases, test error
      forms, test results, test case assignments, test information queries, and test reports. This
      tool also allows the test analyst to update the generated test cases.

   3. Test Execution Tool (TET): The purpose of this tool is to allow testers run test cases and
      produce test results. The test results are sent to the TMT for review and approval.

The development effort of the STS is divided and distributed to multiple teams (e.g., under-
graduates and graduates) at SPSU. The TMT Team is responsible for the development of the
Test Management Tool and integration of other test tools into the STS.

1.1.2. Assumptions and Constraints

This SPMP will state the general plans, policies, and processes applicable to the TMT Team.
Both TGT and TMT tools must be completed and integrated by no later than 28-Nov-2010. This
plan assumes the following:

   1. Schedule: 30-Aug-2010 - 12-Dec-2010.
   2. Budget: This plan will state cost estimation based on $100.00 per a person-hour, 20
      person-hours per week, and team size of 5 persons. The total budget is: $100.00 x 20
      person-hours x 5 persons x 14 weeks = $140,000.00.
   3. Resources:
          a. Staffing: The staffing information in this plan is pre-assigned not by selective hire.
          b. Tools: The TMT Team will only be responsible to acquire tools and software
             needed for development, testing, and demos. At post-development, SPSU will be
             responsible for deployment to production and maintenance.




                                           Page 16 of 60
                                                  
                                                                              Test Management Tool (TMT)
                                                                 Software Project Management Plan (SPMP)
                                                                                          TMT-SPMP-1.2
                                                                                            27-Sep-2010



1.1.3. Project Deliverables

The TMT Team is responsible for the following deliverables:

                                   Table 1.1-1: Project Deliverables

                   Item                          Date    Quantity Acquirer               Media
Plans (i.e., SPMP & STP)                     28-Nov-2010    2      SPSU                 Document
Requirements (i.e., SRS)                     28-Nov-2010    1      SPSU                 Document
High-Level design (i.e., SDD)                28-Nov-2010    1      SPSU                 Document
Source codes & executable                    28-Nov-2010    1      SPSU                 DVD-ROM
Test info (i.e., STD & STR)                  28-Nov-2010    2      SPSU                 Document
Code listing and version (i.e., SVD)         28-Nov-2010    1      SPSU                 Document
Install/user guide (i.e., SUM)               28-Nov-2010    1      SPSU                 Document
Project status data (i.e., SDSR)             28-Nov-2010    1      SPSU                 Document
EV presentations                                Weekly     14      SPSU                Power Point
IAB presentations                            28-Nov-2010   10      SPSU                Power Point
***Note: The above deliverables are incrementally delivered for reviews. The date specified is
for the final deliverable.

1.1.4. Schedule and Budget Summary

The TMT Team uses MS Excel (as a part of the TMT Team’s Metric Program) to track and
manage tasks, resources, schedule, and budget; therefore, the detail Work Breakdown Structure
(WBS), cost, schedule, and staffing resources are defined there. The following tables show the
high-level master build schedule and program budget summary:

                                 Table 1.1-2: Master Build Schedule

   Date           Build                                    Description
20-Sep-2010   Increment   01   Demo of overall system architecture & design.
27-Sep-2010   Increment   02   Demo of Test Case Management Feature.
04-Oct-2010   Increment   03   Demo of TGT & TMT Integration #1.
11-Oct-2010   Increment   04   Demo of Req. Info. Management Feature.
18-Oct-2010   Increment   05   Demo of TGT & TMT Integration #2.
25-Oct-2010   Increment   06   Demo of Test Resource Management Feature.
01-Nov-2010   Increment   07   Demo of Test Result Management Feature.
08-Nov-2010   Increment   08   Demo of Report Generation Feature.
15-Nov-2010   Increment   09   Demo of Data Query Feature.
22-Nov-2010   Increment   10   Demo of TMT full functionality.
29-Nov-2010   Increment   11   Final integration of full functionality for TMT & TGT into STS.
06-Dec-2010   Increment   12   IAB Demo.

                                Table 1.1-3: Project Budget Summary

   Date      Budget                             Description
06-Sep-2010 5000.00 Organize development team and develop project plans.
13-Sep-2010 10,000.00 System analysis and planning.
20-Sep-2010 10,000.00 Increment 01: Overall system architecture & design.

                                            Page 17 of 60
                                                    
                                                                           Test Management Tool (TMT)
                                                              Software Project Management Plan (SPMP)
                                                                                       TMT-SPMP-1.2
                                                                                         27-Sep-2010


   Date      Budget                                     Description
27-Sep-2010 10,000.00 Increment      02:   Test Case Management Feature.
04-Oct-2010 10,000.00 Increment      03:   TGT & TMT Integration #1.
11-Oct-2010 10,000.00 Increment      04:   Req. Info. Management Feature.
18-Oct-2010 10,000.00 Increment      05:   TGT & TMT Integration #2.
25-Oct-2010 10,000.00 Increment      06:   Test Resource Management Feature.
01-Nov-2010 10,000.00 Increment      07:   Test Result Management Feature.
08-Nov-2010 10,000.00 Increment      08:   Report Generation Feature.
15-Nov-2010 10,000.00 Increment      09:   Data Query Feature.
22-Nov-2010 10,000.00 Increment      10:   TMT full functionality.
29-Nov-2010 10,000.00 Increment      11:   Final integration of full functionality for TMT & TGT
                      into STS.
06-Dec-2010 15,000.00 Increment      12: IAB Demo.

1.2. Evolution of the Plan

The purpose of this SPMP is to provide a documented plan for the management and control of
the organizational, developmental, and supporting processes necessary to the successful
implementation of the STS project. The development of TMT follows an agile development
methodology and therefore the detailed WBS and schedules can be changed; these changes are
managed separately from this plan (via TMT Team’s Metric Program developed in MS Excel).
This document, however, subject to revision based on sudden changes in project or product
requirements, risk events, or unexpected deviation from the planned course of action. The initial
version of this SPMP is placed under configuration management; changes made to this document
will be controlled and tracked section 7.1 of this document.




                                           Page 18 of 60
                                                  
                                                                            Test Management Tool (TMT)
                                                               Software Project Management Plan (SPMP)
                                                                                        TMT-SPMP-1.2
                                                                                          27-Sep-2010



1.3. Document Overview

This plan is organized as follows:

   1. Section 1: Project Overview. This section provides an overview of the scope and
      objectives of the project, project's assumptions and constraints, deliverables, schedule and
      budget, and evolution of the plan.

   2. Section 2: References. This section provides a list of documents, standards, policies,
      templates, processes, and other material referenced within this plan.

   3. Section 3: Definitions. This section contains the abbreviations, acronyms, and definitions
      of terminologies used within the plan.

   4. Section 4: Project Organization. This section identifies interfaces to organizational
      entities external to the project, describes the project's internal organization structure, and
      defines roles and responsibilities for the project.

   5. Section 5: Management Process. This section specifies the project management processes
      for the project; i.e., planning, measurement, tracking, reporting, risk control mechanisms,
      and project initiation and closeout procedures.

   6. Section 6: Technical Process. This section specifies the development process model, the
      technical methods, tools, and techniques to be used to develop the various work products,
      plans for establishing and maintaining the project infrastructure, and the product
      acceptance.

   7. Section 7: Supporting Process. This section contains plans for supporting processes that
      span the duration of the software project; including, but not limited to, configuration
      management, verification and validation, documentation, quality assurance, reviews and
      audits, problem resolution, and process improvement.

   8. Section 8: Addition Plans. This section contains additional plans required to satisfy
      product requirements, safety requirements, privacy and security requirements, as well as
      any other plans.

   9. Appendixes. This section contains addition material that helps the understanding of this
      plan.




                                           Page 19 of 60
                                                   
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 20 of 60
                                
                                                                               Test Management Tool (TMT)
                                                                  Software Project Management Plan (SPMP)
                                                                                           TMT-SPMP-1.2
                                                                                             27-Sep-2010




                                       2. REFERENCES
2.1. Standards, Documents, and Other Material

The standards and documents listed below are referenced in this document:

 [1]   Institute of Electrical and Electronics Engineers (IEEE) Standard for Software Project
       Management Plans, IEEE Standard 1058-1998, IEEE, December 1998.

 [2]   Model-Based Testing - Next Generation Functional Software Testing. STN 12-4 January 2010:
       Model-Driven Development, January 2010.


2.2. Deviations and Waivers

N/A




                                              Page 21 of 60
                                                     
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 22 of 60
                                
                                                                           Test Management Tool (TMT)
                                                              Software Project Management Plan (SPMP)
                                                                                       TMT-SPMP-1.2
                                                                                         27-Sep-2010




                                   3. DEFINITIONS
The abbreviations, acronyms, and terminologies used throughout this document are listed below:

         Term                                         Definition
 ACWP                 Actual Cost of Work Performed
 A/M/D                Added/Modified/Deleted
 ASP                  Active Server Page
 BCWP                 Budgeted Cost of Work Performed
 BCWS                 Budgeted Cost of Work Scheduled
 CRN                  Change Request Number
 CSS                  Cascade Style Sheet
 EDR                  Effectiveness of Defect Removal
 EV                   Earned Value
 GQM                  Goal Question Measurement
 HTML                 Hyper-Text Markup Language
 IAB                  Industrial Advisory Board
 IDE                  Integrated Development Environment
 IE                   Internet Explorer
 IEEE                 Electrical and Electronics Engineers
 IIS                  Internet Information Service
 MS                   Microsoft
 MTBF                 Mean Time Between Failures
 N/A                  Not Applicable
 PM                   Project Manager
 POMA                 Plan, Organize, Monitor, Adjust
 QA                   Quality Assurance
 SDD                  Software Design Description
 SDLC                 Software Development Life Cycle
 SDSR                 Software Development Status Report
 SPMP                 Software Project Management Plan
 SPSU                 Southern Polytechnic State University
 SQL                  Structural Query Language
 SRS                  Software Requirements Specification
 STD                  Software Test Description
 STP                  Software Test Plan
 STR                  Software Test Report
 STS                  SPSU Testing System
 SUM                  Software User Manual
 SVD                  Software Version Description
 SWE                  Software Engineering
 TBD                  To be decided
 TET                  Test Execution Tool
 TGT                  Test Generation Tool
 TMT                  Test Management Tool

                                           Page 23 of 60
                                                  
                                                                 Test Management Tool (TMT)
                                                    Software Project Management Plan (SPMP)
                                                                             TMT-SPMP-1.2
                                                                               27-Sep-2010


        Term                                  Definition
T-SQL          Transact-Structural Query Language
WBS            Work Breakdown Structure




                                   Page 24 of 60
                                          
                                                                              Test Management Tool (TMT)
                                                                 Software Project Management Plan (SPMP)
                                                                                          TMT-SPMP-1.2
                                                                                            27-Sep-2010




                          4. PROJECT ORGANIZATION
4.1. External Interfaces

External organizational interfaces and chain-of-command for the STS project are defined in the
following figure. All organizations defined in the figure are located within the Fall 2010-SWE-
7903 Capstone Course at SPSU.




                        Figure 4.1-1: Project External Organization Interfaces

The responsibilities of the organizational entities and key positions shown in figure above are
defined in the following table:

                         Table 4.1-1: Programmatic Roles and Responsibilities

              Position                                   Roles/Responsibilities
 SPSU Software Engineering               Project Review Board to provide final review on the
 Department                              completion of the project.
 Project Advisor (Dr. Frank Tsui)        Project advisor to professional consultant to the
                                         development processes and audits the progress of
                                         the project.
 Test Generation Tool Team               A team of 8 undergraduates to develop the TGT.
 Test Management Tool Team               A team of 5 graduates to develop the TMT and
                                         integration of the STS for demos.
 TGT Project Manager (Stephen E.         To lead the development effort of the TGT team.
 Fyffe)
 TMT Project Manager (Tom Q. Le)         To lead the development effort of the TMT team.


                                            Page 25 of 60
                                                    
                                                                             Test Management Tool (TMT)
                                                                Software Project Management Plan (SPMP)
                                                                                         TMT-SPMP-1.2
                                                                                           27-Sep-2010



4.2. Internal Structure

The TMT project team organizational structure is defined in the following figure:




                        Figure 4.2-1: Project Internal Organization Structure

4.3. Roles and Responsibilities
                           Table 4.3-1: Project Roles and Responsibilities

             Position                                  Roles/Responsibilities
 TMT Project Manager                       Organize and manage the project team.
                                           Define project goals and establish measurements.
                                           Develop project plans and processes.
                                           Define, assign, and monitor tasks.
                                           Monitor work progress and report statuses.
                                           Calculate earned values.
                                           Develop, review, and approve all documents.
                                           Coordinate with all team members for risk
                                            management and issue control.
                                           Manage configurations, builds, and releases.
                                           Review and approve requirements, designs,
                                            codes, test scripts, and test reports.
 TMT Project Manager - Deputy              Assist and be TMT PM's backup.
 TMT Requirements Lead                     Work in parallel with the TMT PM in understanding
                                            the project scope.
                                           Initiate and lead the requirements elicitation,
                                            prototyping, and specification.
                                           Coordinate with the Design Lead to ensure the
                                            designs satisfy requirements.
                                           Review requirements, designs, codes, and test

                                            Page 26 of 60
                                                   
                                                                       Test Management Tool (TMT)
                                                          Software Project Management Plan (SPMP)
                                                                                   TMT-SPMP-1.2
                                                                                     27-Sep-2010


           Position                                  Roles/Responsibilities
                                     cases.
TMT Requirements Lead - Backup      Assist and be the Requirements Lead's backup.
TMT Requirements Engineers          Involve in requirements elicitations, prototyping,
                                     modeling, specification, and review.
TMT Design Lead                     Work in parallel with the TMT Requirements Lead
                                     to design the system architecture and software
                                     designs.
                                    Initiate and lead the design processes.
                                    Coordinate with the TMT Development Lead to
                                     ensure codes satisfy the design and requirements.
                                    Involve in design and code reviews.
TMT Design Lead - Backup            Assist and be the TMT Design Lead's backup.
TMT Designers                       Involve in designs, modeling, and reviewing
                                     designs, and codes.
TMT Development Lead                Work in parallel with the TMT Design Lead to
                                     ensure codes developed in accordance to the
                                     designs.
                                    Initiate and lead the coding efforts.
                                    Coordinate with the developers and testers.
                                    Involve in software reviews.
TMT Development Lead - Backup       Assist and be the TMT Development Lead's
                                     backup.
TMT Developers                      Involve in coding and other reviews.
TMT Test Lead                       Work in parallel with the Requirements Lead and
                                     Development Lead to develop test plans and test
                                     cases.
                                    Initiate and lead the test process.
                                    Involve in other software reviews.
TMT Test Lead - Backup              Assist and be the TMT Test Lead's backup.
TMT Testers                         Involve in developing test cases in executing test
                                     cases and collect test results.
                                    Involve in other software reviews.




                                     Page 27 of 60
                                            
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 28 of 60
                                
                                                                          Test Management Tool (TMT)
                                                             Software Project Management Plan (SPMP)
                                                                                      TMT-SPMP-1.2
                                                                                        27-Sep-2010




                     5. MANAGERIAL PROCESS PLANS
5.1. Start-up Plan
5.1.1. Estimation Plan

The TMT project estimation is based on the detailed work break structure defined in the TMT
Team’s Metric Program (i.e., in MS Excel). The TMT PM defines the high-level tasks based on
the project scope and high-level requirements and then coordinates with the team leads (i.e.,
Requirements Lead, Design Lead, Development Lead, and Test Lead) to further break each high-
level task down to lower-level tasks. Each low-level task will be defined, assigned, and estimated
as follows:

    Task Name:
          The project management tasks are defined to develop the development plans and
             run the team, including team meetings, status reports, coordination, and team
             support. These tasks are mostly assigned to the project team manager.
          The test management tool tasks are defined to develop the product that is broken
             off into different product features. The project team manager provides the initial
             task effort estimation and then assigns to team members based on their skill sets;
             i.e., requirements, design, coding, testing, and documentation. On Monday of
             each week, all team members get together and re-assess initial effort estimation to
             provide more accurate effort estimation based on the previous actual efforts.
          The support tasks are defined to do miscellaneous product supports and
             maintenance during testing and customer demos.
    For each task, the project team manager provides planned task information (i.e., start
     date, finish date, duration, effort, and cost); the responsible team members record the
     actual information.
          Start Date: The date when the work begins.
          Finish Date: The date when the work finishes.
          Duration: The total number of days the work takes place.
          Effort: The total hours it takes to finish the work.
          Cost: The total of cost in dollar to complete the work.
          Resource: The responsible team member (s) to work the task.

5.1.2. Staffing Plan

The project team consists of 5 graduate students pre-assigned to the team to complete the STS
architectural framework and the TMT tool. The following table summarizes the skill levels of all
team members:




                                          Page 29 of 60
                                                  
                                                                            Test Management Tool (TMT)
                                                               Software Project Management Plan (SPMP)
                                                                                        TMT-SPMP-1.2
                                                                                          27-Sep-2010


                            Table 5.1-1: TMT Team Member Skill Levels

   Team Member                                        Skill Level
 Adam Scott             8 years at Microsoft experienced in software development involving
                        in:
                             Windows, UNIX, Linux, Mac, WP7, and Symbian platforms.
                             Client-Server and stand-alone models.
                             Visual Studio 2005 - 2010, Net Beans, and Eclipse IDEs.
                             Java, C/C++, C# 2.0 - 4.0, HTML, Silverlight, J-Query, PHP,
                                and SQL programming languages.
                             MS SQL 2005 - 2008, MySQL, DB2, Posgress SQL databases.
                             Client machines and Windows Server environment.
                             Available 20 - 30 hours per week.
 Harish Sreenivas       No work experience but involved in school projects. Good at
                        designs, UML, and requirements. Available 20 hours per week.
 Jagati Vempaty         4 months internship as business analyst and data warehouse
                        designer. Available 25 hours per week.
 Seth Zaah              More than 8 years in Field Service Support, acknowledged in
                        Windows, Java, C++, Rational Rose, MySQL, PL/SQL, HTML,
                        Process Improvement. Available 20 - 25 hours per week (Mon - Sat
                        from 10:00 AM to 7:00 PM).
 Tom Le                 Currently work at Lockheed Martin Aeronautics with more than 10
                        years experience in software project leadership and development
                        involving in:
                             Windows, Unix, and Embedded platforms.
                             Client-Server, stand-alone, and web-based models.
                             Visual Studio 2000 - 2010, J-Borland, C++ Borland, Rational
                                Apex, Ultra Edit IDEs.
                             Java, C/C++, C# 1.0 - 4.0, ADA, Visual Basics, HTML,
                                JavaScript, VBScript, SQL, T-SQL, PL/SQL, ASP, ASP.NET,
                                and JSP programming languages.
                             MS SQL 2000 - 2008, Oracle, and Access databases.
                             IIS, Tomcat, Apache, and desktop environment.
                             Available 20 - 30 hours per week.

5.1.3. Resource Acquisition Plan

In addition to the team members pre-assigned to the team, the following non-staff resources are
acquired by the project team manager for the development of the TMT product:

                            Table 5.1-2: Non-Staff Resource Acquisition

                      Description                                    Date               Cost
 Testing Environment (http://www.winhost.com), an                 30-Aug-2010        $4.95/month
 ASP.NET server used to operate the STS system. Needed                                Paid by Tom
 technology includes:
     Windows 2008 Server.
     IIS 7.0.
     MS .NET Framework 4.0.
     MS ASP.NET 4.0.
     MS SQL Server 2008.

                                          Page 30 of 60
                                                  
                                                                           Test Management Tool (TMT)
                                                              Software Project Management Plan (SPMP)
                                                                                       TMT-SPMP-1.2
                                                                                         27-Sep-2010


                      Description                                   Date                Cost
 MS Visual Studio 2010, an IDE.                                  30-Aug-2010                 Free
 Configuration Management Tool (at                               20-Sep-2010        Paid by Adam
 http://adam.404.unfuddle.com).

5.1.4. Project Staff Training Plan

There is no plan for project staff planning. It is assumed that the team members assigned to the
TMT team have already been well trained in the pre-requisites of the capstone course. Team
members are assigned with responsibilities based on their initial skill levels and re-evaluated
after each development increment as applicable.

5.2. Work Plan
5.2.1. Work Activities

The various work activities to be performed in the project are defined in the TMT Team’s Metric
Program. The work activities are decomposed from project management task, support task, and
product features into low-level tasks that expose all project risk factors and allow accurate
estimate of resource requirements and schedule duration for each work activity.

5.2.2. Schedule Allocation

After defining the various work activities, the TMT PM schedules the work activities agreeing
with the Table 1.1-2: Master Build Schedule and Table 1.1-1: Project Deliverables. The specific
schedule allocations for the detailed tasks are defined in the TMT Team’s Metric Program.

5.2.3. Resource Allocation

The TMT PM allocates the various work activities to different team members based on their skill
levels and desired roles stated in Figure 4.2-1: Project Internal Organization Structure and Table
4.3-1: Project Roles and Responsibilities. The TMT PM and technical leads re-assesses resource
allocations weekly (i.e., every Monday).

5.2.4. Budget Allocation

The Table 1.1-3: Project Budget Summary shows the budgets allocated to major work activities
in the work breakdown structure. The detailed budget allocated to various tasks as well as other
cost (e.g., travel, meeting, equipments, etc.) are specified in the TMT Team’s Metric Program.

5.3. Control Plan

The key factors that contribute to the TMT project management are the processes of planning,
scheduling, performance measurement, risk mitigation, variance analysis, and corrective action.
The TMT PM coordinates with the different technical leads to develop the detailed plans based
on established work assignments defined in the TMT Team’s Metric Program for the TMT
project. Microsoft Office 2007 software is used to document the plans. The plans are then

                                           Page 31 of 60
                                                  
                                                                            Test Management Tool (TMT)
                                                               Software Project Management Plan (SPMP)
                                                                                        TMT-SPMP-1.2
                                                                                          27-Sep-2010


reviewed by both the Project Advisor and the team members. The approved plans are posted to
the team website at http://cse.spsu.edu/ftsui/SWE7903.html. Periodic reviews, weekly status
reports, and monthly assessments (i.e., earned-value and performance) are conducted to assess
the risks, to initiate risk analysis, to establish risk mitigation as well as to provide corrective
actions to the plans. Corrective action items are documented in the TMT Team’s Metric Program
and communicated to the TMT Project Advisor and team members.

5.3.1. Requirements Control Plan

The TMT PM and Requirements Analyst are responsible for the project requirement's process.
The Requirements Team specifies all requirements in the Software Requirements Specification.
The TMT Project Advisor, PM, and all technical leads review the requirements for correctness
and ensure the integrity of the requirements specified by bi-directional traceability matrices built
in for each major document (i.e., SRS, SDD, STP, and STD). As traceability matrices are
produced, the Requirements Team is able to determine whether all requirements for each
increment are met. Any updates to the requirements cause a new revision to the SRS.

***NOTE: If time permits, it is also possible to use the newly developed TMT tool to control the
requirement traceability.

5.3.2. Schedule Control Plan

The TMT Team uses the TMT Team’s Metric Program to measure the progress or work
completed at the major and minor project milestones, to compare actual progress to planned
progress, and to implement corrective action when actual progress does not conform to planned
progress. Achievement of schedule milestones are assessed using the objective criteria to
measure the scope and quality of work products completed at each milestone as specified in
section 5.3.6: Metrics Collection Plan of this SPMP.
5.3.2.1. Schedule Tracking

Project progress is charted on a weekly basis using the TMT Team’s Metric Program. Schedule
performance data is generated at the task level and compared to the proposed schedule. Reports
are generated that provide data for incremental effort estimation adjustments and projected future
performance. The actual start dates, finish dates, task completion percentages, actual cost, and
resources used on each task are recorded in the TMT Team’s Metric Program.
5.3.2.2. Schedule Performance Reports

Project schedule status information is measured against the required/planned dates and reports on
performance up-to-date are extracted from TMT Team’s Metric Program and presented to the
weekly status meeting with the TMT Project Advisor every Monday at 7:45 PM. Microsoft
Excel is used to calculate the Actual Cost of Work Performed (ACWP), Budgeted Cost of Work
Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), and Estimate at Completion.



                                            Page 32 of 60
                                                   
                                                                            Test Management Tool (TMT)
                                                               Software Project Management Plan (SPMP)
                                                                                        TMT-SPMP-1.2
                                                                                          27-Sep-2010


5.3.2.3. Schedule Reviews

Schedule reviews are conducted by the TMT Project Advisor, PM, and technical leads on a
weekly basis (i.e., every Mondays or Wednesdays). Applicable schedule updates upon reviews
can be made to the TMT Team’s Metric Program; the updates are then notified to the client and
all team members. Schedule reviews are done for at least one incremental release ahead to have
early risk mitigation.
5.3.2.4. Progress Variance Monitoring

Actual progress can differ from the planned progress for many reasons, including but not limited
to inaccurate effort estimation, resource limitation, plan and requirement changes, and etc. The
TMT technical leads are responsible to notify the TMT PM and the PM is responsible to update
the applicable scheduled tasks on the TMT Team’s Metric Program. Deviations that are beyond
the PM’s capabilities to resolve (e.g., member drop outs, non-productive or poor performance,
etc.) are brought to the Project Advisor’s attention.
5.3.2.5. Progress Variance Resolution

The TMT PM has the authority to reallocate resources, delegate and reschedule the tasks, or
correct performance problems that are not impacting a major release. Otherwise, consultancies
from the TMT Advisor are recommended.
5.3.2.6. Follow-Up on Corrective Action

The TMT Team’s Metric Program is used to identify the initial schedule deviation and to analyze
the corrective action results. Corrective action items are closely monitored to ensure that they are
effectively recovering the schedule variance before milestone or the master build schedule is
jeopardized.

5.3.3. Budget Control Plan

The total cost of the project is $140,000.00 spreading out to 14 weeks as shown in Table 1.1-3:
Project Budget Summary. The project cost is calculated based on $100.00 per person-hour
expended for each task by each assigned resource; i.e., $100.00 * effort hour * resource. Periodic
cost analysis and reviews are conducted to assess performance and provide insight to the future
task assignments.

5.3.4. Quality Control Plan

There is no independent Quality Assurance (QA) Group under the TMT management. Instead,
the TMT PM and Testing Group are responsible for assurance of all quality and production
control requirements are being accomplished. The TMT Test Lead is responsible to conduct
various reviews on project plans, requirements, designs, codes, tests, and all other documents. In
performing these duties, the TMT Test Lead monitors adherence to all applicable policies,
processes, procedures, and plans.

                                           Page 33 of 60
                                                   
                                                                         Test Management Tool (TMT)
                                                            Software Project Management Plan (SPMP)
                                                                                     TMT-SPMP-1.2
                                                                                       27-Sep-2010



5.3.5. Reporting Plan
5.3.5.1. Status Reporting

The TMT PM generates and provides weekly project status to the TMT Project Advisor on
Monday at 7:45 PM. There are 12 weekly status reports and the detailed of each status report is
noted in the TMT Team’s Metric Program under Project Management Tasks. All team members
are required to be present in all weekly status meetings.
5.3.5.2. Internal Reviews

The TMT Team holds in-progress reviews at least once month for the purpose of monitoring and
adjusting the internal process toward meeting the scheduled milestones, reviewing problems
encountered, presenting proposed resolutions, presenting near-term plans, reviewing risks and
mitigation plans, and individual performance assessments using earned value data extracted from
the TMT Team’s Metric Program. The TMT PM is also responsible to provide internal reviews
to each team member based on individual in-progress performance and task assignments.
5.3.5.3. Meetings

As the project progress become more aggressive toward the deliverable deadline, the TMT Team
is more likely to call at least one meeting every Wednesday for the purpose of monitoring
progress, work coordination, issues and resolutions, and etc. as needed.
5.3.5.4. Information Repository

All project information needs to be submitted to the TMT PM for reviews and sign-offs. Source
codes need to be uploaded to the test environment at http://www.winhost.com for sharing
purposes among the team members as well as posted on the TMT Team’s website at
http://cse.spsu.edu/ftsui/SWE7903.html.

*** NOTE: An alternative to uploading files to http://www.winhost.com, team members can also
upload files to Google Group; however, it is not recommended to for the purpose of having one
central information repository.
5.3.5.5. Communication

In addition to the aforementioned means of reporting and project communication, the TMT
members are recommended to communicate through email and phones as needed. The following
is the listing of the TMT team members contact information:

                        Table 5.3-1: TMT Team Member Contact Information

      Name                   Email                 Phone                 Comment
 Adam Scott          ascott4@spsu.edu           770-940-0988     Busy on Wednesdays.
 Harish Sreenivas    hsreenivas@spsu.edu        678-896-0727     Work at SPSU Mon – Wed,
                                                                 11:00 – 5:00.


                                          Page 34 of 60
                                                 
                                                                              Test Management Tool (TMT)
                                                                 Software Project Management Plan (SPMP)
                                                                                          TMT-SPMP-1.2
                                                                                            27-Sep-2010


      Name                   Email                   Phone                      Comment
 Jagati Vempaty      jvempaty@spsu.edu            404-751-7896        N/A.
 Seth Zaah           sethzaah@yahoo.co.uk         678-485-8014        Work at Client Support/Real
                                                                      Estate, 9:00 AM - 7:00 PM,
                                                                      Mon - Sat.
 Tom Le              tomle75@comcast.net          404-791-3816        Work at LM Aero Mon – Fri,
                                                                      9:00 – 3:00.

5.3.6. Metrics Collection Plan

The TMT Team’s metric program follows the Goal-Question-Measurement (GQM) approach to
establish team’s goals, define goal-oriented questions, and determine measurements for the
defined goals and questions. The following table shows various metrics the TMT Team needs to
collect and report:

                                      Table 5.3-2: TMT Metrics

 Metric Category          Metric Name                                 Purpose
                       Cost per Unit              To project future cost estimation.
                       MTBF                       To collect the mean time between failures to
                                                  project product availability.
 Product Metrics       Product Size               To provide future effort estimation.
                       Performance                To provide product performance assessment
                                                  since it is an online service.
                       Quality Level              To assess the product quality level.
                       Phase-based Effort         To assess the effort by various development
                                                  phases (i.e., requirements, design, code,
                                                  test, and documentation).
                       EDR per Phase              To assess the effectiveness of defect
                                                  removal per phase.
 Process Metrics       Response Time of Fix       To assess responses to fixes, future effort
                                                  estimations, and early risk mitigations.
                       Fix Backlog                To assess future workloads and schedule
                                                  risks.
                       Fix Quality                To assess rework.
                       Defect Density             To assess defects per product size.
                       Schedule                   To identify root causes for schedule slippage
                                                  and work under-estimates.
 Project Metrics       Cost                       To identify cost variance and task allocation.
                       Productivity               To assess productivity and task reallocation.
                       Scope                      To identify changes to project scope.

***NOTE: The detailed GQM metric program is defined in a separate MS Excel file and posted
on the TMT website at http://www.cse.spsu.edu/ftsui/SWE7903.html.

5.4. Risk Management Plan

To ensure all milestones and work packages delivered on-time, within budget, at product quality,
the TMT Team’s strategy is to follow the steps below:

                                           Page 35 of 60
                                                  
                                                                         Test Management Tool (TMT)
                                                            Software Project Management Plan (SPMP)
                                                                                     TMT-SPMP-1.2
                                                                                       27-Sep-2010




   1. Identify risks a week ahead of current build schedule (i.e., Table 1.1-2: Master Build
      Schedule).
   2. Enter risks in the TMT Team’s Metric Program.
   3. PM and technical leads analyze risks, determine resolution, and implement resolution.
   4. PM and technical leads provide follow-ups on risk’s resolution results.

5.5. Closeout Plan

The TMT aims to complete the project 2 week earlier than the assigned deadline (i.e., 12-Dec-
2010). All work activities need to be finished by 28-Nov-2010. The project closeout occurs on
12-Dec-2010 with a presentation to the Industrial Advisory Board (IAB) referred by the SPSU
Software Engineering Department. Along with the written reports and final documents (i.e.,
Table 1.1-1: Project Deliverables & Figure 1.1-1: Project Document Tree), the TMT Team is
required to present the following information:

   1.   Requirements.
   2.   Designs.
   3.   Test Results.
   4.   Code/Product Demo.
   5.   Development Status.




                                          Page 36 of 60
                                                 
                                                                                                                                                                 Test Management Tool (TMT)
                                                                                                                                                    Software Project Management Plan (SPMP)
                                                                                                                                                                             TMT-SPMP-1.2
                                                                                                                                                                               27-Sep-2010




                                                                              6. TECHNICAL PROCESS PLANS
6.1. Process Model

Due to uncertainties in product requirements (i.e., product functionalities are open for market
competitiveness), small team size, no project historical data, and new product type being
developed, the TMT Team tailors the Agile process model to decompose the high-level work
packages into low-level tasks and group tasks by product feature. Each product feature is
developed, reviewed, demonstrated, and modified in an increment of 2 weeks. This process is
described in the figure below:

                                                              Activity                                                                                                         Output/Artifact

                                                                                                                            Documents,                                             SPMP & STP
                                                              Planning
                                                                                                                             Reviews




                                                                                                                                Documents,                                       SRS
                                                                    Requirements




                                                                                                                                                                                                                                                                                            Test procedures and results as planned
                                                                                                                                 Reviews




                                                                                                                                                                                                                                                   Reports the overall development status
                                                                                                                                                                                         Source code listing and versions
                                                                                                                                 Documents,                               SDD
                                                                               Design
                                                                                                                                  Reviews
 Initial Development




                                                                                                                                                                                                                            Software user manual
                                             Increment # 12
                       Increment # 1




                                                                                                                                    Documents,                    SVD & Demo
                                                                                        Code
                                                                                                                                     Reviews

                                       ...
                                                                                                                                     Documents,              STD & STR
                                                                                               Test
                                                                                                                                      Reviews




                                                                                                                                      Documents,           SUM
                                                                                                      Install/Support
                                                                                                                                       Reviews




                                                                                                                                       Documents,   SDSR
                                                                                                                Status Report
                                                                                                                                        Reviews

                                                                           Figure 6.1-1: TMT Software Development Life Cycle (SDLC)

The development of the TMT tool is broken into one initial development and 12 incremental
developments. Each incremental development spans through all activities from requirements,
design, code, test, install/support, and status reporting, except the initial development spans from
the planning activity. The purpose of the initial development is to produce the following the
following software artifacts:

                       1.              A complete project plans (=> SPMP & STP).
                       2.              Requirements specification for the overall system framework => SRS).
                       3.              Overall system architectural and high-level component designs (=> SDD).
                       4.              Source codes for the system architecture and framework (=> SVD).
                       5.              Test cases, procedures, and results for the framework (=> STD & STR).
                       6.              A draft installation and user manual (=> SUM).
                       7.              A draft development status report (=> SDSR).

                                                                                                                   Page 37 of 60
                                                                                                                                 
                                                                          Test Management Tool (TMT)
                                                             Software Project Management Plan (SPMP)
                                                                                      TMT-SPMP-1.2
                                                                                        27-Sep-2010


In all other incremental developments, steps 2 through 7 are re-iterated and correspondent
documents are updated.

6.2. Methods, Tools, and Techniques
6.2.1. Requirements Methods & Techniques

The TMT Team follows the requirements process described in the figure below:




                           Figure 6.2-1: TMT Requirements Process Flow

6.2.2. Design Models

The TMT Team models the STS using the client-server system architecture and layers logical
codes using the 3-tier software design pattern. The architectural design diagrams component
descriptions are described in the Software Design Descriptions (SDD).

6.2.3. Testing Methods & Techniques

The TMT Team provides two levels of testing: Functional Test and Integration Test. In
functional tests, the TMT Testing Group develops requirement-based test cases in accordance to
the TMT Software Test Plan. In integration tests, the TMT Testing Group needs to evaluate the
overall operating capability of the TMT and TGT tools as part of the overall STS system. All test
cases and test procedures are described in the Software Test Description (STD). The TMT
Testing Group is also responsible to capture the test results and documents them in the Software
Test Report (STR).

6.2.4. Programming Languages

To implement the TMT tool, the team uses the following programming languages:

                                          Page 38 of 60
                                                 
                                                                          Test Management Tool (TMT)
                                                             Software Project Management Plan (SPMP)
                                                                                      TMT-SPMP-1.2
                                                                                        27-Sep-2010




                              Table 6.2-1: TMT Programming Languages

    Language          Version                             Description
 C#                     4.0       Used to implement business rules and data access logics.
 ASP.NET                4.0       Used to implement web-based user interfaces.
 T-SQL                 2008       Used to implement database stored procedures, functions,
                                  and database queries.
 HTML                   4.0       Used in parallel with ASP.NET to implement web pages.
 CSS                    2.0       Used to control user interface looks and feel.
 JavaScript             1.1       Used to implement client-side codes.
 Silverlight            2.0       Used to improve the user interface.

6.2.5. Tools

The TMT Team uses the following tools for the development and testing of the STS overall
framework and the TMT tool:

       Tool          Version                               Description
 MS Visual Studio    2010 Pro     An Integrated Development Environment (IDE) used for
                                  development and software builds.
 MS SQL Server       2008 Pro     A RDBM system used to develop and test the database
                                  scripts, stored procedures, and user-defined functions.
 Microsoft Office    2007 Pro     i.e., Word, Excel, Visio, Power Point, and Outlook used for
                                  documents, metrics, designs, presentations, and
                                  communication respectively.
 MS IE Browser          7.0       Used to test the system.
 MS Firefox             8.0       Used to test the system.
 Project Manager       2010       An online tool used to manage the work activities.

6.3. Infrastructure Plan

There is no plan for the project infrastructure. The TMT Team makes use of the SPSU facilities
and home offices. The TMT Team uses an online service at http:///www.winhost.com for testing
environment.

6.4. Product Acceptance Plan

There is no plan for the product acceptance; however, the work products generated need to agree
to the planned deliverables and project basic requirements. The TMT Project Advisor has the
opportunities to incrementally evaluate the product features on a weekly basis. Changes in scope
can be negotiated and documented.




                                           Page 39 of 60
                                                  
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 40 of 60
                                
                                                                         Test Management Tool (TMT)
                                                            Software Project Management Plan (SPMP)
                                                                                     TMT-SPMP-1.2
                                                                                       27-Sep-2010




                     7. SUPPORTING PROCESS PLANS
7.1. Configuration Management Plan

All software artifacts generated by the TMT Team need to be uploaded to the Team’s website at
http://cse.spsu.edu/ftsui/SWE7903.html and at ftp.tqllearning.com. Due to decentralized work
locations of all team members, a remote configuration management is required. The TMT Team
uses http://adam404.unfuddle.com/svn/adam404_capstone/ to share and control versions of all
software product artifacts. The following figure depicts the process of configuration
management:




                        Figure 7.1-1: TMT Configuration Management Flow

7.2. Verification and Validation Plan

There is no independent verification and validation organization needed for this project. All
verifications and validations are done through peer reviews and walkthroughs. The TMT Project
Advisor plays an important role in verifying and validating the TMT's developmental plans,
processes, schedules, deliverables, and quality of the product before the IAB presentation and
demo. To assure the time for the TMT Project Advisor completing his verification and
validation, the TMT Team provides incremental submissions of project statuses, demos, and
deliverables on the weekly basis as a minimum.


                                         Page 41 of 60
                                                
                                                                            Test Management Tool (TMT)
                                                               Software Project Management Plan (SPMP)
                                                                                        TMT-SPMP-1.2
                                                                                          27-Sep-2010



7.3. Documentation Plan

The Figure 1.1-1: Project Document Tree shows all project documents needed as part of the
deliverables. The following table summarizes the different deliverable documents:

         Document Type                 Format Standard          Estimated         Review Type
                                                                  Page
                                                                  Count
 Project Management Plan                                            50         Peer Review
 Test Plan                                                          50         Peer Review
 Requirements Specification                                         50         Walkthrough
 Design Descriptions                                                50         Walkthrough
 Test Descriptions                                                  50         Peer Review
 Test Report                                                        50         Peer Review
 Version Description                                                50         Peer Review
 Development Status Report                                          50         Peer Review
 User Manual                                                        50         Peer Review

7.4. Quality Assurance Plan

To assure that the project fulfills its commitments to the process and the product as specified in
the requirements specification, the document, supporting plans, and any standards, procedures, or
guidelines to which the process or the product must adhere, the TMT PM, all Technical Leads,
and Project Advisor need to review all work products produced by the team. The TMT supports
two types of review: Peer Review and Walkthrough.




                                 Figure 7.4-1: Peer Review Process




                                          Page 42 of 60
                                                  
                                                                                     Test Management Tool (TMT)
                                                                        Software Project Management Plan (SPMP)
                                                                                                 TMT-SPMP-1.2
                                                                                                   27-Sep-2010


In a Peer Review, when the author completes a work product he/she notifies the project manager
to initiate peer review. The project manager assures that the work product is in configuration,
properly versioned, and ready for review and then initiates the review by assigning various
reviewing activities to different technical expertise. Each reviewer reviews the assigned part of
the work product to find defects and records them. Once completing the assigned review, each
reviewer submits findings/defects to the author of the work product. The author updates the work
product based on the findings submitted, if applicable. The project manager moderates the entire
review process to assure all finding being updated properly and then closes out the review.


                                                                      Find defects

                                                       Work Product
                              Completes
                               Updates



                                                            Initiates review         Reviewers
                          Notifies                     Moderates & closes review

                 Author




                                     Project Manager

                              Figure 7.4-2: Walkthrough Review Process

The process of a Walkthrough Review is similar to the Peer Review, except that all participants;
i.e., project manager, author, and reviewers, are gathering in a meeting and walk through the
work product to find defects and correct them as applicable. This type of review is more
expensive but it produces more product quality.

Appendix A is the checklist for requirements review.
Appendix B is the checklist for design review.
Appendix C is the check list for code review.
Appendix D is the checklist for test procedure/script review.
Appendix E is the template for how to record a defect.
Appendix F is the template for how to plan and kick off a review.
Appendix G is the template for how to close out a review.
Appendix H is the template for how to resolve a finding.

7.5. Reviews and Audits

The following is a listing of all work products and corresponding review types::

 Product Type        Work Product              Type of Review                      Purpose
 Documentation      SPMP                         Peer Review            To agree and follow the plans


                                                 Page 43 of 60
                                                          
                                                                           Test Management Tool (TMT)
                                                              Software Project Management Plan (SPMP)
                                                                                       TMT-SPMP-1.2
                                                                                         27-Sep-2010


 Product Type        Work Product        Type of Review                    Purpose
                                                              and established processes.
 Requirements       SRS                    Walkthrough        See appendix A.
 Test               STP                    Peer Review        See appendix D.
 Design             SDD                    Walkthrough        See appendix B.
 Code               Source Code            Peer Review        See appendix C.
 Test               STD                    Peer Review        See appendix D.
 Test               STR                    Peer Review        See appendix D.
 Documentation      SVD                    Peer Review        To assure that all source codes
                                                              produced properly listed.
 Documentation      SDSR                   Peer Review        To assure that the report
                                                              properly reflect the development
                                                              statuses.
 Documentation      SUM                     Peer Review       To assure that the manual
                                                              clearly explains how to use the
                                                              product.

7.6. Problem Resolution Plan

When a defect is found during a peer review or walkthrough, the author of work product being
reviewed is responsible to resolve the problem. If it is a major problem that seriously impact the
delivery, the author needs to consult with the project manager to plan tasks fixes in future
releases. Effort devoted to problem reporting, analysis, and resolution are separately reported and
tracked for rework and process improvement. See appendices E through H for more details.

7.7. Subcontractor Management Plan

There is no plan for subcontractors. The TMT Team will perform all work activities needed to
complete the project.

7.8. Process Improvement Plan

Both the TMT Team and the Project Advisor have the opportunities to review and sign off on all
TMT Project plans. Due to the time constraint of this project, major changes to the plans are not
supported. However, minor changes to improve the effectiveness of project management,
product quality, and productivity are promoted. The TMT PM will analyze the measurement data
collected, status report feedbacks, and then assesses the effectiveness and value of the team
processes in order to suggest and make the changes. Changes will be reviewed and signed off by
all team members and the Project Advisor.




                                           Page 44 of 60
                                                  
                                                                  Test Management Tool (TMT)
                                                     Software Project Management Plan (SPMP)
                                                                              TMT-SPMP-1.2
                                                                                27-Sep-2010




                              8. ADDITIONAL PLANS
There are no other addition plans.




                                     Page 45 of 60
                                            
                                                         Test Management Tool (TMT)
                                            Software Project Management Plan (SPMP)
                                                                     TMT-SPMP-1.2
                                                                       27-Sep-2010




This page is intentionally left blank for double-side printout.




                         Page 46 of 60
                                
                                                                     Test Management Tool (TMT)
                                                        Software Project Management Plan (SPMP)
                                                                                 TMT-SPMP-1.2
                                                                                   27-Sep-2010




                                    APPENDIXES
Appendix A: Requirements Review Checklist
Use this symbol to check  and use this  to uncheck.
 Author:
 Moderator:
 Date:
 Purpose:
       Review specification quality:
        Can each item be implemented and tested?
  
        Is the meaning of each item understood?
        Is the specification easy to read?
       Review traceability:
        Can each item in the requirements specification be traceable to product
         features?
        Is the traceability backward and forward correct?
        Has the traceability been captured in the appropriate tool?
       Review for areas of future growth:
    Have all areas of uncertainty, incompleteness, or areas of future growth been
          considered and identified?
       Review error handling:
  
        Have all error handling and recovery requirements been considered?
       Review interfaces:
  
        Do interfaces correspond to defined and coordinated interfaces?
       Review associated work products updated:
  
        Have all relevant models and specifications been updated?




                                        Page 47 of 60
                                               
                                                                     Test Management Tool (TMT)
                                                        Software Project Management Plan (SPMP)
                                                                                 TMT-SPMP-1.2
                                                                                   27-Sep-2010



Appendix B: Design Review Checklist
Use this symbol to check  and use this  to uncheck.
 Author:
 Moderator:
 Date:
 Purpose:
       Review anticipated changes:
        Is the design flexible enough to allow for anticipated and unanticipated
         changes?
        Have all reasonable anticipated changes been identified?
        Are areas of anticipated changes isolated?
       Review design considerations:
        Is the design complete?
        Have all design views been addressed?
        Does it perform the specified function?
        Does it promote information hiding and reuse?
        Is it highly cohesive/loosely coupled?
  
        Does the data item naming meet standards?
        Has persistent data been considered in the design?
        Can the design be changed without excessive impact of other items?
        Does documentation conform to standards?
        Are all assumptions valid?
        Are any assumptions missing?
       Review error handing:
    Have all error handling and recovery impacts been considered?
        Are any error conditions missing?
       Review interfaces:
        Are the interfaces specified?
        Are the interface specifications sufficient?
  
        Are they consistent with the interfaces captured in the requirements
          specification?
        Do they correspond to defined and coordinated interfaces?
       Review source product completeness:
        Are the current requirements correct?
  
        Are all requirements addressed by the design?
        Are there any open action items that might affect the design?
       Review syntactic/semantic checks:
        If the design work product is too-generated output, does this output pass the
         tool’s syntactic and semantic checks?
        If the design is represented in a programming language, does the design
          compile cleanly?
       Review traceability:
        Is each item in the design directly traceable to one or more items in the
  
          requirements?
        Has this traceability been captured in the design according to standards?




                                        Page 48 of 60
                                               
                                                                     Test Management Tool (TMT)
                                                        Software Project Management Plan (SPMP)
                                                                                 TMT-SPMP-1.2
                                                                                   27-Sep-2010



Appendix C: Code Review Checklist
Use this symbol to check  and use this  to uncheck.
 Author:
 Moderator:
 Date:
 Purpose:
       Review code considerations:
        Is the code complete?
        Does it promote information hiding and reuse?
        Is it highly cohesive/loosely coupled?
        Does the data item meet standards?
  
        Has persistent data been considered in code?
        Can it be changed without excessive impact on other items?
        Have approved methods been followed?
        Does documentation conform to standards?
        Does it compile cleanly?
       Review auto-generated code:
        Is the code work product is too-generated output, does this output pass the
  
          tool’s syntactic and semantic checks?
        Does it compile cleanly?
       Review interfaces:
        Are the interfaces specified?
  
        Are the interfaces sufficient?
        Are they consistent with the interfaces capture in the requirements and design?
       Review prologue/comments:
        Are comments meaningful and accurate?
  
        Are special cases/conditions described?
        Is all code marking requirements satisfied?
       Review source product completeness:
        Are the current requirements and design correct?
  
        Are all requirements and design aspects addressed by the code?
        Are there any open action items that might affect the code?
       Review coding standards:
        Has the approved method been followed?
  
        Does the documentation conform to standards?
        Does the code meet defined standards?
       Review traceability:
        Is each item in the code directly traceable to one or more items in the
  
          requirements and design?
        Has this traceability been captured in the coding according to standards?




                                        Page 49 of 60
                                               
                                                                     Test Management Tool (TMT)
                                                        Software Project Management Plan (SPMP)
                                                                                 TMT-SPMP-1.2
                                                                                   27-Sep-2010



Appendix D: Test Review Checklist
Use this symbol to check  and use this  to uncheck.
 Author:
 Moderator:
 Date:
 Purpose:
   Are all test cases and test procedures described and documented in the STD?
   Are the test cases followed the STP?
   Have all test results been captured and documented in the STR?
   Do all test cases test the requirements?




                                        Page 50 of 60
                                               
                                                                         Test Management Tool (TMT)
                                                            Software Project Management Plan (SPMP)
                                                                                     TMT-SPMP-1.2
                                                                                       27-Sep-2010



Appendix E: Defect Report Form
Use this form for each finding submitted.
 Review type:
 Project:
 Data collection point:
 Author:
 Moderator:
 Reviewer:
 Date:
 Purpose:
 File containing finding:
 Line in file:
 Severity code:
 Defect type:
 Comments:
 Time invested




                                            Page 51 of 60
                                                   
                                                                       Test Management Tool (TMT)
                                                          Software Project Management Plan (SPMP)
                                                                                   TMT-SPMP-1.2
                                                                                     27-Sep-2010



Appendix F: Review Kickoff Form
Use this form to kick off a new review.
 Review type:
 Project:
 Data collection point:
 Author:
 Moderator:
 Reviewers:
 Date:
 Purpose:
 File names:




                                          Page 52 of 60
                                                 
                                                                    Test Management Tool (TMT)
                                                       Software Project Management Plan (SPMP)
                                                                                TMT-SPMP-1.2
                                                                                  27-Sep-2010



Appendix G: Review Closeout Form
Use this form to close out a review.
 Review type:
 Project:
 Data collection point:
 Author:
 Moderator:
 Reviewer:
 Date:
 Purpose:
 Meeting duration:
 Number of people at meeting:
 Rework effort (author):
 Follow-up effort (moderator):
 Action item comments:
 Concluding comments:




                                       Page 53 of 60
                                              
                                                                        Test Management Tool (TMT)
                                                           Software Project Management Plan (SPMP)
                                                                                    TMT-SPMP-1.2
                                                                                      27-Sep-2010



Appendix H: Defect Resolution Form
Use this form to record resolution for findings.
 Review type:
 Project:
 Data collection point:
 Author:
 Moderator:
 Reviewer:
 Date:
 Purpose:
 File containing finding:
 Line in file:
 Severity code:
 Defect type:
 Comments:
 Time invested
 Author comments:
 Moderator comments:
 Defect resolution:




                                           Page 54 of 60
                                                    
                                                                    Test Management Tool (TMT)
                                                       Software Project Management Plan (SPMP)
                                                                                TMT-SPMP-1.2
                                                                                  27-Sep-2010



Appendix I: Data Collection Point
 Code                                  Data Collection Point
   1    Phase - Business Acquisition and Planning
   1a   Activity - Supply Process
   2    Phase - Requirements
   2a   Activity - System Requirements Analysis
   2b   Activity - System Architectural Design
   2c   Activity - Software Requirements Analysis
  2c1   Informal Software Requirements
  2c2   Formal Software Requirements
   3    Phase - Design
   3a   Activity - Software Architectural Design
   3b   Activity - Detailed Design
  3b1   Detailed Design Informal
  3b2   Detailed Design Formal
   4    Phase - Implementation
   4a   Activity - Software Coding and Testing
  4a1   Software Coding Informal
  4a2   Software Coding Formal
   5    Phase - Integration and Test
   5a   Activity - Software Integration
  5a1   Documentation
   5b   Activity - Software Qualification Testing
   5c   Activity - System Integration
   5d   Activity - System Qualification Testing
   6    Phase - Transition to Customer
   6a   Activity - Software Installation
   6b   Activity - Software Acceptance Support
   7    External to the Software Product




                                      Page 55 of 60
                                             
                                                                      Test Management Tool (TMT)
                                                         Software Project Management Plan (SPMP)
                                                                                  TMT-SPMP-1.2
                                                                                    27-Sep-2010



Appendix K: Defect Severity Levels
 Code                              Defect Description                                Level
  0     No defect found or comment.                                                  None
  1      Prevents the accomplishment of an operational or mission                   Major
            essential capability
         Jeopardizes safety
         Causes significant technical, cost, or schedule risks to the
            project or to life cycle support of the system. This is a MAJOR
            defect.
  2      Adversely affects the accomplishment of an operational or                  Major
            mission essential capability and no work-around solution is
            known
         Adversely affects technical, cost, or schedule risks to the project
            or to life cycle support of the system, no work-around solution is
            known. This is a MAJOR defect.
  3      Adversely affects the accomplishment of an operational or                  Major
            mission essential capability, but a work-around solution is
            known
         Adversely affects technical, cost, or schedule risks to the project
            or to life cycle support of the system, but a work-around
            solution is known. This is a MAJOR defect.
  4      Results in user/operator inconvenience or annoyance, but does              Minor
            not affect a required operational or mission essential capability
         Results in inconvenience or annoyance for development or
            support personnel, but does not prevent the accomplishment of
            those responsibilities. This is a MINOR defect.
  5     Any other effect not described above. Projects may define and                Minor
        assign sub-codes for this priority. This is a MINOR defect.




                                       Page 56 of 60
                                              
                                                                  Test Management Tool (TMT)
                                                     Software Project Management Plan (SPMP)
                                                                              TMT-SPMP-1.2
                                                                                27-Sep-2010



Appendix L: Defect Types
 Code           Defect Type                              Description
1a      Functionality               The definition of a functional capability desired by
                                    the customer was not clear and unambiguous, or
                                    was misinterpreted.
1b      GFE/BFE/CFE/Subcontractor   Incompatibilities or deficiencies with specification-
                                    compliant Government Furnished Equipment
                                    (GFE), Buyer Furnished Equipment (BFE),
                                    Contractor Furnished Equipment (CFE), or
                                    subcontractor supplied products in their interaction
                                    with the system.
1c      Software Engineering        The SEE, as specified, is deficient in supporting the
        Environment (SEE)           software engineering process; incompatibilities
                                    exist between SEE tools.
1d      Programmatic Requirements   Conflicting contractual requirements; problems
                                    relating to security requirements; problems
                                    relating to teaming with other companies.
1e      Test                        The test equipment/environment, as specified, is
        Equipment/Environment       deficient to support system operation.
1f      Support                     The support equipment/environment, as specified,
        Equipment/Environment       is deficient to support system operation.
1z      Documentation               Documentation does not accurately/adequately
                                    describe the planning, and categories 1a through
                                    1f are not appropriate.
2a      Subsystem/Software          Incorrect/incomplete translation or specification of
        Requirements                the lower level (subsystem/software) requirements
                                    that was not the result of category 2e. Examples
                                    include: incorrect specification at the SRS level,
                                    subsystem specification incorrect, etc.
2b      Physical Interface          An error in the definition or specification of a
                                    physical (hardware) interface.
2c      Functional Interface        Incorrect/incomplete specification of the functional
                                    interaction or communication of data with other
                                    processes or subsystems, and categories 2b and
                                    2d are not appropriate.
2d      User Interface              Incorrect/incomplete specification of the software
                                    interaction with the user.
2e      System Requirements         Incorrect/incomplete translation or specification of
                                    the customer requirements that was not the result
                                    of category 1a. Examples include: incorrect
                                    specification at the SSS level, Air Vehicle
                                    Specification, etc.
2z      Documentation               Documentation does not accurately describe the
                                    intended requirements, and categories 2a through
                                    2e are not appropriate. Format, documentation
                                    standards, typographical errors, and
                                    understandability are included in this category.
3a      Physical Interface          Incorrect/incomplete design of the software
                                    interaction with hardware.


                                    Page 57 of 60
                                           
                                                               Test Management Tool (TMT)
                                                  Software Project Management Plan (SPMP)
                                                                           TMT-SPMP-1.2
                                                                             27-Sep-2010


 Code          Defect Type                           Description
3b      Subsystem Interface     Incorrect/incomplete design of the functional
                                interaction or communication of data with other
                                subsystems or processes, and categories 3a and 3c
                                are not appropriate.
3c      User Interface          Incorrect/incomplete design of the software
                                interaction with the user.
3d      Inter-process           Incorrect/incomplete interfaces or communications
        Communication           between processes or components within a
                                product. Includes timing/scheduling anomalies as
                                well as parameter passing/ omission and other
                                inter-process defects.
3e      Data Definition         Incorrect/incomplete design of the data structures
                                to be used in the product, e.g., defects associated
                                with data precision/accuracy and data units.
3f      Unit/Procedure Design   Problem with the control flow and execution within
                                a unit/procedure. For example, errors in
                                logic/computations in algorithms,
                                incorrect/incomplete translation of requirements,
                                incorrect/incomplete sequence of operations in a
                                test procedure or installation procedure, etc.
3g      Error Handling          The checks for error detection/isolation were not
                                adequate, or the response to detected error
                                conditions was not correct.
3h      Standards               Violations of design standards that do not cause a
                                defect in the functional operation of the product.
                                This does not include documentation standards.
3i      Traceability            A known requirement was missed or a non-existing
                                requirement was introduced into the design.
3z      Documentation           Documentation does not accurately describe the
                                design or software configuration item (product)
                                test plans/procedures, and categories 3a through
                                3i are not appropriate. Format, documentation
                                standards, typographical errors, and
                                understandability are included in this category.
4a      Logic                   Incorrect/incomplete decision logic causes the
                                product not to implement the full intent of the
                                design, e.g., invalid "If-Then-Else," loop structures,
                                case statements, missing "Begin-End," wrong
                                execution sequence.
4b      Computations            Incorrect/incomplete mathematical or arithmetic
                                operations cause the product not to implement the
                                full intent of the design.
4c      Data Handling           Incorrect/incomplete definition or use of data
                                structures in accordance with the design. This
                                category includes data precision, improper
                                indexing into arrays or tables, improper scaling or
                                units of measure, and data incorrectly stored or
                                accessed.
4d      Unit Interface          Problems related to the calling, parameter


                                Page 58 of 60
                                       
                                                            Test Management Tool (TMT)
                                               Software Project Management Plan (SPMP)
                                                                        TMT-SPMP-1.2
                                                                          27-Sep-2010


 Code           Defect Type                        Description
                              definition, and termination of subprocesses. This
                              category includes incorrect order or number of
                              parameters passed, ambiguous termination value
                              for a function, incorrect parameter data types,
                              inter-process communication problems, and
                              timing/scheduling anomalies.
4e      Standards             Violations of programming standards, incorrect use
                              of the programming language, typographical errors
                              during code/text entry for source code and test
                              procedures, etc.
4f      Build/Configuration   Incorrect/incomplete software build/configuration,
                              e.g., missing code, wrong version of code,
                              incorrect placement in memory, missing test
                              procedure, etc.
4z      Documentation         Documentation does not accurately describe the
                              implementation of the design, and categories 4a
                              through 4f are not appropriate. This category also
                              includes defects in documentation format or other
                              documentation standards, typographical errors,
                              understandability, etc.
5z      Documentation         Documentation does not accurately reflect test
                              results. Format, documentation standards,
                              typographical errors, and understandability are
                              included in this category. This category does not
                              include problems with software configuration item
                              test plans, test cases, or test procedures.
6z      Documentation         Documentation generated to support the transition
                              to the customer is in error. Format, documentation
                              standards, typographical errors, and
                              understandability are included in this category.
                              This category does not include problems with
                              documentation developed in prior phases that are
                              covered by categories 1z, 2z, ... 5z.
7a      GFE/BFE               A problem caused by GFE/BFE not operating in
                              accordance with its specification.
7b      CFE/Subcontractor     A problem caused by external CFE/subcontracted
                              equipment/software not operating in accordance
                              with its specification, e.g., host computer
                              hardware, firmware, supplier errors, or
                              performance problems. This does not include
                              internally maintained reused assets.
7c      SEE                   A problem caused by the SEE not operating in
                              accordance with its specification, e.g., compiler
                              problems, linker problems, interface definition tool
                              problems, etc. This does not include internally
                              maintained reused assets.
7d      Other                 Other external problem, and no other external
                              category is appropriate. This does not include
                              internally maintained reused assets.
7e      Test                  The product under test is operating correctly, yet

                              Page 59 of 60
                                     
                                                              Test Management Tool (TMT)
                                                 Software Project Management Plan (SPMP)
                                                                          TMT-SPMP-1.2
                                                                            27-Sep-2010


 Code         Defect Type                           Description
        Equipment/Environment   the test equipment/environment is operating
                                incorrectly. This does not include internally
                                maintained reused assets.
7f      Support                 The product under test is operating correctly, yet
        Equipment/Environment   the support equipment/environment is operating
                                incorrectly. This does not include internally
                                maintained reused assets.
0       Comment                 This Finding is only a comment and does not
                                document a defect or a candidate for a defect.




                                Page 60 of 60
                                       

				
DOCUMENT INFO