					                       RECAPP Facility Evaluation Report
                                      Edmonton RCSSD #7




                              Our Lady Of Mount Carmel School
                                           B3227A
                                          Edmonton




Report run on: May 10, 2006 2:26 PM
                                                 Edmonton - Our Lady Of Mount Carmel School (B3227A)
                 Facility Details                                            Evaluation Details
   Building Name: Our Lady Of Mount Carmel S              Evaluation Company: Stephens Kozak Carr and Brown
          Address: 10524 - 76 Avenue                           Evaluation Date: November 4 2005
         Location: Edmonton
                                                               Evaluator Name: Mr. Eric Lumley
       Building Id: B3227A
 Gross Area (sq. m): 5,931.80
 Replacement Cost:   $9,189,400
  Construction Year: 0                                            Total Maintenance Events Next 5 years:        $1,816,860
                                                                  5 year Facility Condition Index (FCI):            19.77%

General Summary:
The school has a total area of 5932 sq.m. and was constructed in a number of stages as follows:
1925 - 1110 sq.m.
1948 - 840 sq.m.
1950 - 104 sq.m.
1951 - 678 sq.m.
1962 - 105 sq.m.
1968 - 3095 sq.m.
The original building and earlier additions are in poor condition because of their age. The original building has significant
structural and ventilation problems and requires immediate attention. The 1968 addition is generally in acceptable
condition but specific components such as lockers and toilet partitions are in need of replacement.

Structural Summary:
The original building is loadbearing brick with wood framed flooors and roof. The 1948/50/51/and 1962 additions are wood
framed. The 1968 addition is loadbearing concrete block with a steel/concrete second floor and a wood deck on OWSJ roof
structure. There are minor areas of slab settlement. There are also vertical cracks in the loadbearing concrete block gym
walls that require investigation. The structure is generall in acceptable condition.


Envelope Summary:
1925 and 1968 sections have a brick exterior skin. The other sections have painted stucco ecterior finish. There are
aluminum and steel windows, with some original 1925 wood windows. The 1925 window sills are concrete. The asphalt
shingle roofing and the copper covering the cupola are in need of replacement. The roofing on the 1948/50/51 and 62
sections is original and in need of replacement. The 1068 section had a new roof membrane in 1994. The older sections
have wood exterior doors in wood frames which are in need of upgrading. The envelope is generally in acceptable
condition.

Interior Summary:
The 1925/48/50/51/62 sections have painted plaster and gypsum board walls, the original lino and T-bar ceilings. Some
areas have painted tentest ceiling tiles. The T-bar ceilings and the flooring are in need of replacement. The 1968 section
is painted concrete block walls with lino and VCT flooring and T-bar ceilings. The flooring is in need of replacement. The
corridor and change room lockers are in poor condition and in need of replacement. The millwork is original and in some
areas has lino counter tops. Approximately 50% of the millwork is in need of replacement. In general the interior of the
older sections is poor and the interior of the 1968 section is marginal.


Mechanical Summary:
Original building built in 1925 with additions in 1948, 1950, 1951, 1962 and 1969. In 1990 steam heating elements in
1925 original buildings and 1948, 1950, 1951, 1962 additions were changed to hot water heating elements. Steam/water
heat exchanger was installed in 1948 addition boiler room. Existing steam boilers were utilized. Circulation pumps and
black iron piping was installed to circulate hot water to the heating elements. heating plant in 1968 addition provides hot
water to heating elements in 1968 addition. Ventilation in 1925 original school is substandard. Ventilation is by gravity
by manually opening and closing dampers. Ventilation in 1948, 1950, 1951, 1962 additions is substandard. Non heated
and non filtered air is drawn into rooms through window cracks, door ways or open windows through exhausted through
the outdoors. Built up air system provides ventilation in 1968 addition. Classrooms and administration built up air
system provides ventilation for 1968 addition gymnasium. Heating element controls are pneumatic. Andover BMCS
installed. Washroom exhaust deficient in 1925 original school. Exhaust fans expel foul odors in 1968 addition.
Plumbing fixtures and brass are commercial quality. Fire protection consists of wet standpipe, fire hose cabinets, fire
Report run on: May 10, 2006 2:26 PM                                                                              Page 2 of 51
                                                        Edmonton - Our Lady Of Mount Carmel School (B3227A)

extinguishers.

Items found during review which should be addressed are:
- Replace janitor sinks.
- Replace failed plumbing brass and fixtures.
- Video tape underground sewer in older sections of building.
- Install new heating plants.
- Install new packaged rooftop units (5).
- Install humidification.
- Upgrade control panels.
- Replace underground sanitary and storm in 1925 original building.
- Upgrade industrial arts carpentry equipment exhaust, paint spray exhaust.
- Install computer room and server room air conditioning.
- Install domestic hot water heaters.

Mechanical systems and components are in poor condition.

Electrical Summary:
Older sections of school (pre 1968) require electrical upgrading and modernization; in particular original distribution
requires replacement.

Transient voltage surge suppression should be added at the main distribution panel. Panelboards throughout lack
adequate space for additional breakers and should be replaced with larger capacity panels. Panels in pre-1968 areas
are only single phase and should be upgraded to 3 phase.

Motor starters are generally obsolete and should be replaced to restore reliability.

There is a lack of adequate circuit capacity and number of duplex receptacles throughout. Wiring in the pre-1968 areas
is likely in questionable condition and should be replaced. Receptacles should be added throughout.

Electronic ballasts and T8 lamps have been retrofitted into fluorescent fixtures. The fixtures are generally in good
condition.

Emergency lighting and exit light provisions were found acceptable.

Systems such as fire alarm, intrusion alarm, telephone, television and paging and music were found acceptable.

                                                                   Rating Guide
  Condition Rating   Performance
      1 - Critical   Unsafe, high risk of injury or critical system failure.
       2 - Poor      Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.
    3 - Marginal     Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.
   4 - Acceptable    Meets present requirements, minor deficiencies. Average operating/maintenance costs.
       5 - Good      Meets all present requirements. No deficiencies.
    6 - Excellent    As new/state of the art, meets present and foreseeable requirements.




Report run on: May 10, 2006 2:26 PM                                                                                              Page 3 of 51
                                                    Edmonton - Our Lady Of Mount Carmel School (B3227A)
S1 STRUCTURAL
A1010 Standard Foundations*

All sections have concrete foundation walls and strip footings.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          100        NOV-05

A1030 Slab on Grade*1925 Basement Floor

Concrete basement floor in 1925 section.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          100        NOV-05

A1030 Slab on Grade*1968 Main Floor

Concrete slab-on-grade main floor, 1968 section.
Rating                        Installed Design Life Updated
3 - Marginal                      0          100        NOV-05


Event:    Mudjack area of gym floor.

          Concern:
          An area of the gym floor has settled.
          Recommendation:
          Mudjack the area to bring it back to level. Repair wood gym
          floor as necessary after work to level the slab is done.

          Type                        Year   Cost                 Priority
          Repair                      2007   $10,700              Medium

          Updated: February 16 2006

A2020 Basement Walls (& Crawl Space)*1925

Cast-in-place concrete walls up to grade level.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          100        NOV-05

A2020 Basement Walls (& Crawl Space)*1948/50/51/62

Concrete foundation walls.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           0         NOV-05

B1010.01 Floor Structural Frame*1925/48/50/51/62

Wood joists on foundation walls. Second floor of 1925 section is supported on steel pipe columns and concrete beams, as
well as loadbearing brick walls. Second floor of 1951 section is wood joists.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          100        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                      Page 4 of 51
                                                 Edmonton - Our Lady Of Mount Carmel School (B3227A)

B1010.01 Floor Structural Frame*1968

Second floor of 1968 section is composite concrete topping and steel deck on OWSJ.
Rating                       Installed Design Life Updated
5 - Good                        0          100        NOV-05

B1010.02 Structural Interior Walls Supporting Floors*1925

Loadbearing brick walls.
Rating                       Installed Design Life Updated
4 - Acceptable                  0          100        NOV-05

B1010.02 Structural Interior Walls Supporting Floors*1951

Loadbearing wood stud corridor walls.
Rating                       Installed Design Life Updated
4 - Acceptable                  0          100        NOV-05

B1010.02 Structural Interior Walls Supporting Floors*1968

Loadbearing concrete block walls.
Rating                       Installed Design Life Updated
5 - Good                        0          100        NOV-05

B1010.03 Floor Decks, Slabs, and Toppings*1968

Second floor is composite slab construction with a concrete topping on steel deck.
Rating                       Installed Design Life Updated
5 - Good                        0          100        NOV-05

B1010.07 Exterior Stairs**

Exterior cast in place concrete stair to basement mechanical room in 1948 section.
Rating                       Installed Design Life Updated
4 - Acceptable                  0           40        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                        Page 5 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

B1010.09 Floor Construction Fireproofing*1925

Lath and plaster to underside of floor joists. In basement boiler room (now storage) the lath and plaster is failed and is falling
off.
Rating                           Installed Design Life Updated
2 - Poor                            0           100       NOV-05


Event:     Provide gypsum board firerating to underside of
           wood floor structure in 1925 section.

           Concern:
           Lath and plaster fireproofing to the floor assembly is falling off
           and is temporarily supported with wood shoring.
           Recommendation:
           Remove lath and plaster. Provide gypsum board fireproofing to
           underside of wood floor assembly. 100 sq.m.

           Type                         Year   Cost              Priority
           Failure Replacement          2006    $5,350           High

           Updated: February 16 2006

B1010.09 Floor Construction Fireproofing*1951

Spray texture on plaster. Spray appears to contain asbestos.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           50        NOV-05

B1010.09 Floor Construction Fireproofing*1968

Non-combustible construction.
Rating                           Installed Design Life Updated
5 - Good                            0           50        NOV-05

B1010.11 Other Floor Construction*1925

Cast-in-place concrete slab at stair landings
Rating                           Installed Design Life Updated
5 - Good                            0           100       NOV-05

B1020.01 Roof Structural Frame*1925

Wood framed roof trusses.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           100       NOV-05

B1020.01 Roof Structural Frame*1948/50/51/62

Wood decking on wood joists and purlins on glulam beams.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           100       NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                                Page 6 of 51
                                                    Edmonton - Our Lady Of Mount Carmel School (B3227A)

B1020.01 Roof Structural Frame*1968

Steel deck on OWSJ. The roof structure is supported on loadbearing concrete block walls.
Rating                       Installed Design Life Updated
3 - Marginal                     0           100        NOV-05


Event:    Install engineered steel reinforcing plate
          connectors at each beam/wall bearing location.

          Concern:
          Cracks in masonary below beams.
          Recommendation:
          Install engineered steel reinforcing plate connectors at each
          beam/wall bearing location. Secure to wall and beam at 10
          locations

          Type                        Year   Cost            Priority
          Repair                      2006   $12,840         Low

          Updated: February 16 2006

Event:    Investigate cracking of concrete block walls under
          roof beams in gymnasium.

          Concern:
          There are vertical cracks in the joints of the loadbearing
          concrete block walls at beam locations in the gymnasium.
          These cracks appear to run through the bond beams.
          Recommendation:
          Investigate and determine the reason(s) for the cracking, and
          recommend action.

          Type                        Year   Cost            Priority
          Study                       2006   $5,350          Medium

          Updated: February 16 2006

B1020.04 Canopies*

Minor canopies at entrances. Wood framed and steel framed.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           100        NOV-05

B1020.06 Roof Construction Fireproofing*1925

Plaster on lath.
Rating                       Installed Design Life Updated
4 - Acceptable                   0            25        NOV-05

B1020.06 Roof Construction Fireproofing*1948/50

Plaster on lath.
Rating                       Installed Design Life Updated
4 - Acceptable                   0            25        NOV-05



 Report run on: May 10, 2006 2:26 PM                                                           Page 7 of 51
                                                  Edmonton - Our Lady Of Mount Carmel School (B3227A)

B1020.06 Roof Construction Fireproofing*1951

Spray texture on lath and plaster to underside of roof structure. Spray appears to contain asbestos.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          25        NOV-05

B1020.06 Roof Construction Fireproofing*1962

Drywall to underside of roof structure.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          25        NOV-05

B1020.06 Roof Construction Fireproofing*1968

Non-combustible construction.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          25        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                   Page 8 of 51
                                                   Edmonton - Our Lady Of Mount Carmel School (B3227A)
S2 ENVELOPE
B2010.01.02.01 Brick Masonry: Ext. Wall Skin*

Brick skin to the 1925 original building and the 1968 addition.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           75         NOV-05

B2010.01.03 Stone Assemblies: Exterior Wall Skin*

Tyndal stone pediment with dentils over the original main entrance.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           75         NOV-05

B2010.01.06.03 Metal Siding**

Prefinished profiled vertical metal siding on original 1925 building and the 1948/50/51/62 additions where the windows have
been replaced and downsized, and in the 1968 gymnasium where the windows have been removed.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           40         NOV-05

B2010.01.06.04 Wood Siding**

Horizontal stained wood fascia and diagonal stained wood feature panels on 1968 addition.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           40         NOV-05

B2010.01.08 Cement Plaster (Stucco): Ext. Wall*

Painted stucco finish to exterior of 1948/50/51 and 62 sections.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           75         NOV-05

B2010.02.05 Wood Framing*: Ext. Wall Const.

Wood framed exterior walls to the 1948/50/51 and 62 additions.
Rating                        Installed Design Life Updated
4 - Acceptable                    0          100         NOV-05

B2010.09 Exterior Soffits*

Painted wood soffits on the 1925 and 1968 sections. Painted stucco soffits on canopies on the 1948/50 and 51 sections.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           20         NOV-05

B2020.01.01.01 Steel Windows**1948/50/51/62

Prefinished steel fixed windows and sliders installed in 1988.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           20         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                         Page 9 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

B2020.01.01.02 Aluminum Windows**1925

The majority of the original main floor wood windows in the 1925 section were replacement with aluminum windows in 1971.
These windows are now 35 years old.
Rating                           Installed Design Life Updated
2 - Poor                            0           35        NOV-05


Event:     Install new aluminum or prefinished steel
           windows.

           Concern:
           The replacement windows in 1971 are now 35 years old and
           deteriorating. Operable hardware is obsolete.
           Recommendation:
           Install new aluminum or prefinished steel windows. 28

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $18,190           Medium

           Updated: February 16 2006

B2020.01.01.02 Aluminum Windows**1968

Clear anodized aluminum windows with openers and integral venetian blinds.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           35        NOV-05

B2020.01.01.05 Wood Windows**1925

Original wood windows (fixed) and double hung windows in 1925 basement area and a few on the main floor. Some
basement windows have been blocked up with painted plywood.
Rating                           Installed Design Life Updated
2 - Poor                            0           35        NOV-05


Event:     Remove wood windows and install aluminum or
           prefinished steel windows.

           Concern:
           Original wood windows are in poor condition and a number have
           been blocked up with plywood.
           Recommendation:
           Remove original wood windows and install new aluminum or
           prefinished steel windows. 14 windows.

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $9,630            Medium

           Updated: February 16 2006

B2030.01.02 Steel-Framed Storefronts**

Hollow metal insulated doors in steel frames in 1968 section.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           15        NOV-05



 Report run on: May 10, 2006 2:26 PM                                                                      Page 10 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

B2030.01.10 Wood Entrance Door**

Original wood entrance doors on 1925/48/50 and 51 sections.
Rating                          Installed Design Life Updated
3 - Marginal                       0           30        NOV-05


Event:    Install hollow metal insulated doors and steel
          frames to exterior of 1925/84/50/51 and 1962
          sections.

          Concern:
          Original wood doors and wood frames. Various degrees of
          delamination and deterioration.
          Recommendation:
          Install hollow metal insulated doors and steel frames in the
          1925/48/50/51 and 62 sections. 11 doors and frames.

          Type                         Year   Cost              Priority
          Failure Replacement          2007   $17,120           Medium

          Updated: February 16 2006

B3010.02.01.01 Asphalt Shingles**

Shingles on sloped roof of 1925 original building. Small section of asphalt shingle roof on 1968 addition.
Rating                          Installed Design Life Updated
3 - Marginal                       0           25        NOV-05


Event:    Replace asphalt shingle roofing on 1925 section.

          Concern:
          Asphalt shingles on the 1925 section are thin and have reached
          the end of their useful life.
          Recommendation:
          Replace asphalt shingles. 850 sq.m.

          Type                         Year   Cost              Priority
          Failure Replacement          2007   $37,450           Medium

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                         Page 11 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

B3010.04.01 Built-up Bituminous Roofing**1948/50/51

Original tar and gravel roofing on 1948 section. Tar roofing on 1950 and 1951 sections with concrete pavers as ballast.
Rating                          Installed Design Life Updated
3 - Marginal                       0           25        NOV-05


Event:    Remove tar and gravel roofing and replace with 2
          ply SBS roofing.

          Concern:
          Roofing on 1948/50 and 51 sections is original.
          Recommendation:
          Remove BUR from 1948/50 and 51 sections and re-roof with 2
          ply SBS roofing. 1180 sq.m.

          Type                         Year   Cost              Priority
          Failure Replacement          2007   $126,260          Medium

          Updated: February 16 2006

B3010.04.04 Modified Bituminous Membrane Roofing (SBS)**

Roof on 1968 section replaced in 1994 with 2 ply SBS roofing.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           25        NOV-05

B3010.07 Sheet Metal Roofing**

Copper roofing to the cupola on the original building. Copper gutter flashing to the concealed gutter above the original main
entrance.
Rating                          Installed Design Life Updated
3 - Marginal                       0           40        NOV-05


Event:    Replace copper roofing to cupola.

          Concern:
          Copper roofing is thin and showing signs of deterioration.
          Recommendation:
          Replace copper roofing with new copper roofing.

          Type                         Year   Cost              Priority
          Failure Replacement          2007   $8,560            Medium

          Updated: February 16 2006

B3010.08.02 Metal Gutters and Downspouts**

Original 1925 building has metal Ogee eavestrough and metal downspouts connected to the underground storm system.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           25        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                          Page 12 of 51
                                                 Edmonton - Our Lady Of Mount Carmel School (B3227A)

B3020.02 Other Roofing Openings (Hatch,Vent, etc)*

Vertical metal ladder and roof hatch provides access to the roof of the 1968 section.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           0         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                        Page 13 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)
S3 INTERIOR
C1010.01 Interior Fixed Partitions*1925

Basement has brick partitions. Upper corridor walls are wood stud.
Rating                        Installed Design Life Updated
3 - Marginal                       0           50         NOV-05


Event:    Investigate movement between loadbearing brick
          walls and brick partitions in basement of 1925
          building.

          Concern:
          There is differential movement between the loadbearing brick
          walls in the basement of the 1925 building and the non-
          loadbearing brick partitions.
          Recommendation:
          Investigate cause and recommend remedial work (if required).
          Filling and caulking the open joint may be all that is required for
          a cost of $500.

          Type                         Year   Cost               Priority
          Study                        2007   $5,350             Medium

          Updated: February 16 2006

C1010.01 Interior Fixed Partitions*1948/50/51/62

Plaster and lath on wood studs.
Rating                        Installed Design Life Updated
4 - Acceptable                     0           50         NOV-05

C1010.01 Interior Fixed Partitions*1968

Concrete block, painted.
Rating                        Installed Design Life Updated
4 - Acceptable                     0           50         NOV-05

C1010.05 Interior Windows*1951

Georgean wired glass in wood frames.
Rating                        Installed Design Life Updated
4 - Acceptable                     0           40         NOV-05

C1010.05 Interior Windows*1968

Georgian wired glass and tempered safety glass in steel frames.
Rating                        Installed Design Life Updated
4 - Acceptable                     0           40         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                            Page 14 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

C1020.01 Interior Swinging Doors**1925/48/50/51/62

Wood doors in wood frames.
Rating                           Installed Design Life Updated
3 - Marginal                        0           50        NOV-05


Event:     Install solid core wood doors in steel frames,
           include new hardware.

           Concern:
           Wood doors and frames are delaminating and damaged.
           Hardware is obsolete and difficult to operate.
           Recommendation:
           Provide new wood doors in steel frames, complete with new
           hardware. 65 doors and frames.

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $107,000          Medium

           Updated: February 16 2006

C1020.01 Interior Swinging Doors**1968

Wood doors in steel frames.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           40        NOV-05

C1020.03 Interior Fire Doors*

Storage rooms and mechanical rooms do not have rated doors and frames. Cost to upgrade included in event C1020.01.
Rating                           Installed Design Life Updated
2 - Poor                            0           50        NOV-05

C1020.04 Interior Sliding and Folding Doors*

Sliding wood door to stage stair from gym. Only used when stage is not used.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           40        NOV-05

C1030.01 Visual Display Boards**

Whiteboard, chalkboard and tackboard throughout.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           10        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                   Page 15 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

C1030.02 Fabricated Compartments(Toilets/Showers)**

Metal prefinished toilet partitions and painted wood toilet partitions.
Rating                           Installed Design Life Updated
2 - Poor                            0           20         NOV-05


Event:     Provide new prefinished metal toilet partitions.

           Concern:
           Metal toilet partitions and painted wood toilet partitions are
           damaged and in poor condition, with some rusted.
           Recommendation:
           Provide new prefinished metal toilet partitions throughout. 30
           cubicles.

           Type                         Year   Cost               Priority
           Failure Replacement          2007   $32,100            Medium

           Updated: February 16 2006

C1030.08 Interior Identifying Devices*

Cast aluminum and engraved plastic signage mounted on doors.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           10         NOV-05

C1030.10 Lockers**

Metal lockers in corridors of 1925 and 1968 sections and in boys and girls change rooms in the 1968 section.
Rating                           Installed Design Life Updated
3 - Marginal                        0           30         NOV-05


Event:     Provide new metal lockers.

           Concern:
           The lockers are in poor condition throughout. The majority need
           to be completely replaced, with some areas where new doors
           would suffice.
           Recommendation:
           Replace 286 steel lockers. Provide new doors to 131 lockers.

           Type                         Year   Cost               Priority
           Failure Replacement          2007   $90,950            Medium

           Updated: February 16 2006

C1030.12 Storage Shelving*

Millwork shelving units in storage rooms.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           20         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                           Page 16 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

C1030.14 Toilet, Bath, and Laundry Accessories*

Miscellaneous washroom accessories throughout.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           20        NOV-05

C2010 Stair Construction*1925/1968

Concrete stairs in 1925 section. Steel pan stairs with concrete fill in 1968 section.
Rating                           Installed Design Life Updated
5 - Good                            0          100        NOV-05

C2010 Stair Construction*1948/50/51/62

Wood stringers, treads and risers.
Rating                           Installed Design Life Updated
4 - Acceptable                      0          100        NOV-05

C2020.02 Terrazzo Stair Finishes*

Terrazzo finish to landings, treads and risers in the 1925 section.
Rating                           Installed Design Life Updated
5 - Good                            0           75        NOV-05

C2020.05 Resilient Stair Finishes**

Rubber stair treads and nosings in all sections except the 1925 original building and the 1951 section which has wood
treads.
Rating                           Installed Design Life Updated
3 - Marginal                        0           20        NOV-05


Event:     Replace all stair treads with rubber treeads and
           integral nosings.

           Concern:
           Stairs have damaged or missing treads and nosings.
           Recommendation:
           Install new rubber treads and nosings to stairs. 116 treads.

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $26,750           Medium

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                    Page 17 of 51
                                                    Edmonton - Our Lady Of Mount Carmel School (B3227A)

C2020.08 Stair Railings and Balustrades*

Wood handrails and pipe handrails to the stairs in the 1925/48/50 and 51 sections. Stairs in the 1968 addition have a wood
rail on metal balusters.
Rating                       Installed Design Life Updated
3 - Marginal                     0            50        NOV-05


Event:    Modify stair balusters and landing railing to reduce
          space between uprights, and to raise railing to
          1060mm.

          Concern:
          Landing railings are too low and space between balusters in too
          much.
          Recommendation:
          Modify handrail balusters and raise landing railings to meet
          current code requirements. 4 flights of stairs and 2 top
          landings.

          Type                        Year   Cost             Priority
          Code Upgrade                2007   $17,120          High

          Updated: February 16 2006

C3010.01 Concrete Wall Finishes*

Painted concrete walls in the basement of the 1925 section and in the 1948 mechanical room.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           100        NOV-05

C3010.03 Plaster Wall Finishes*

Plaster wall finishes throughout 1925/48/50 and 51 areas.
Rating                       Installed Design Life Updated
4 - Acceptable                   0            40        NOV-05

C3010.04 Gypsum Board Wall Finishes*

Drywall finish to the 1962 classroom and in the computer room/library in the 1968 addition.
Rating                       Installed Design Life Updated
4 - Acceptable                   0            40        NOV-05

C3010.06 Tile Wall Finishes**

Ceramic wall tile to janitors rooms in the 1925 section and in the shower areas of the change rooms in the 1968 addition.
Rating                       Installed Design Life Updated
4 - Acceptable                   0            50        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                           Page 18 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

C3010.09 Acoustical Wall Treatment**

No acoustical treatment in gym. Small triangular foam rubber pieces glued to the walls of the music room.
Rating                         Installed Design Life Updated
2 - Poor                           0           20         NOV-05


Event:     Install Tectum acoustic panels to gym walls.

           Concern:
           There is no acoustic treatment to the gym.
           Recommendation:
           Install Tectum acoustic panels to the gym walls.

           Type                        Year   Cost               Priority
           Program Functional Upgrade 2007    $17,120            Medium

           Updated: February 16 2006

Event:     Install high-efficiency acoustic ceiling tiles in the T-
           bar grid in the music room.

           Concern:
           Foam rubber acoustic panels are ineffective and insufficient to
           provide adequate acoustic treatment to the music room.
           Recommendation:
           Install high-efficiency (Nubby 3) fibreglass ceiling tiles in the
           existing T-bar grid. 115 sq.m.

           Type                        Year   Cost               Priority
           Program Functional Upgrade 2007    $6,955             Medium

           Updated: February 16 2006

C3010.11 Interior Wall Painting**

Painted plaster walls and concrete block.
Rating                         Installed Design Life Updated
4 - Acceptable                     0            5         NOV-05

C3020.01 Concrete Floor Finishes (Paint)*

Painted concrete finish to the basement classrooms of the 1925 section and to mechanical rooms.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           75         NOV-05

C3020.02 Tile Floor Finishes**

VCT in the corridors of the 1968 addition. Ceramic mosaic floor tile to the washrooms throughout the school.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           30         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                           Page 19 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

C3020.04 Wood Flooring**

Resilient wood flooring in the gymnasium and wood strip flooring on both stage areas.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           25         NOV-05

C3020.07 Resilient Flooring**

Original linoleum flooring throughout classroom areas, all sections.
Rating                          Installed Design Life Updated
3 - Marginal                       0           20         NOV-05


Event:    Replace all linoleum flooring with VCT.

          Concern:
          Linoleum is original and is worn, with seams that are failing.
          Recommendation:
          Replace all linoleum flooring with new VCT and underlay where
          there is a wood subfloor. 1500 sq.m.

          Type                         Year   Cost                Priority
          Failure Replacement          2007   $112,350            Medium

          Updated: February 16 2006

C3020.08 Carpet Flooring**

The daycare and the kindegarten room in the 1948 section have carpet. The classroom in the 1950 section and the upper
floor of the 1951 area have carpet. The music room in the 1968 section is carpeted.
Rating                          Installed Design Life Updated
3 - Marginal                       0           10         NOV-05


Event:    Replace all carpet with new carpet or sheet
          flooring, except library which was new in 1999.

          Concern:
          All the carpeting will be at least 20 years old by 2010. It is
          already worn and difficult to keep clean.
          Recommendation:
          Replace the music room carpet with new carpet. Replace the
          other carpet in the school with sheet vinyl flooring. 500 sq.m.

          Type                         Year   Cost                Priority
          Lifecycle Replacement        2010   $40,660             Medium

          Updated: February 16 2006

C3020.11 Floor Painting

Painted concrete slab-on-grade to the basement of the 1925 section and the mechanical rooms throughout.
Rating                          Installed Design Life Updated
4 - Acceptable                     0            5         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                      Page 20 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

C3020.14 Other Floor Finishes**

Loose laid rubber resilient tile flooring in the fitness room in the 1928 addition.
Rating                           Installed Design Life Updated
5 - Good                            0           0         NOV-05

C3030.01 Concrete Ceiling Finishes*

Unfinished concrete in the storage rooms under the stairs in the 1925 section.
Rating                           Installed Design Life Updated
4 - Acceptable                      0          100        NOV-05

C3030.03 Plaster Ceiling Finishes*

Plaster ceiling finish in 1925 basement classrooms and storage rooms throughout the 1925/48/50 additions.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           50        NOV-05

C3030.04 Gypsum Board Ceiling Finishes*

Painted gypsum board ceiling in 1962 classroom and 1968 change rooms.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           50        NOV-05

C3030.06 Acoustic Ceiling Treatment (Susp.T-Bar)**

T-bar ceiling system throughout corridors of all sections and in most classrooms in all sections.
Rating                           Installed Design Life Updated
3 - Marginal                        0           25        NOV-05


Event:     Replace all corridor T-bar ceilings and approx.
           50% of the classroom ceiling. Remove T-bar
           ceilings from washrooms and storage rooms and
           provide drywall ceilings.

           Concern:
           T-bar ceilings are damaged and there are a significant number
           of broken and discoloured lay-in tiles. Storage rooms,
           washrooms and the 1968 mechanical rooms have T-bar
           ceilings.
           Recommendation:
           Replace all corridor T-bar ceilings and approx 50% (2300
           sq.m.) of classroom T-bar ceilings. Provide gypsum board
           ceilings in washrooms, storgae rooms and 1968 mechanical
           rooms. (200 sq.m.)

           Type                         Year   Cost               Priority
           Failure Replacement          2007   $96,300            Medium

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                        Page 21 of 51
                                                 Edmonton - Our Lady Of Mount Carmel School (B3227A)

C3030.07 Interior Ceiling Painting**

Painted plaster and gypsum board ceilings in some areas.
Rating                         Installed Design Life Updated
4 - Acceptable                     0        10         NOV-05

C3030.09 Other Ceiling Finishes*

Combination of 12 x 12 and 18 x 18 painted tentest ceiling tiles gluesd to the plaster ceiling in the 1948 section. The 18 x
18 tiles are visible in the daycare and kindergarten rooms. The 12 x 12 tiles in the corridors and classrooms are covered
with a T-bar ceiling.
Rating                         Installed Design Life Updated
4 - Acceptable                     0        10         NOV-05

D1010.02 Lifts**

Wheelchair stair lift in 1951 section.
Rating                         Installed Design Life Updated
5 - Good                           0        25         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                          Page 22 of 51
                                                        Edmonton - Our Lady Of Mount Carmel School (B3227A)
S4 MECHANICAL
D2010.01 Water Closets** - 1925

1925: Floor mounted, open front seat, flush valve and flush tank.
Rating                          Installed Design Life Updated
3 - Marginal                        0              30        NOV-05


Event:    Install new water closet flush valves.

          Concern:
          Flush valves are leaking and failing.
          Recommendation:
          Install new flush valves (total of 8).

          Type                          Year   Cost               Priority
          Failure Replacement           2007       $17,120        Medium

          Updated: February 16 2006

D2010.01 Water Closets** - 1951

1951: Floor mounted, open front seat, flush valves.
Rating                          Installed Design Life Updated
3 - Marginal                        0              30        NOV-05


Event:    Install new water closet flush valves.

          Concern:
          Flush valves are leaking and failing.
          Recommendation:
          Install new flush valves (total of 8).

          Type                          Year   Cost               Priority
          Failure Replacement           2007       $17,120        Medium

          Updated: February 16 2006

D2010.01 Water Closets** - 1968

1968: Floor mounted, open front seat, flush valve.
Rating                          Installed Design Life Updated
3 - Marginal                        0              30        NOV-05


Event:    Install new water closet flush valves.

          Concern:
          Flush valves are leaking and failing.
          Recommendation:
          Install new flush valves (total of 8).

          Type                          Year   Cost               Priority
          Failure Replacement           2007       $17,120        Medium

          Updated: February 16 2006

 Report run on: May 10, 2006 2:26 PM                                                               Page 23 of 51
                                                        Edmonton - Our Lady Of Mount Carmel School (B3227A)

D2010.02 Urinals** - 1925

1925: Stall urinal, flush tank.
Rating                            Installed Design Life Updated
3 - Marginal                         0            30        NOV-05


Event:    Install new flush valve urinals.

          Concern:
          Fixtures dated, water wastage.
          Recommendation:
          Install new flush valve urinals (2).

          Type                           Year    Cost             Priority
          Energy Efficiency Upgrade      2007    $8,560           Medium

          Updated: February 16 2006

D2010.02 Urinals** - 1951

1951: Stall urinal, flush valve.
Rating                            Installed Design Life Updated
4 - Acceptable                       0            30        NOV-05

D2010.02 Urinals** - 1968

1968: Stall urinal, flush tank.
Rating                            Installed Design Life Updated
3 - Marginal                         0            30        NOV-05


Event:    Install new flush valve urinals.

          Concern:
          Fixtures dated, water wastage.
          Recommendation:
          Install new flush valve urinals (2).

          Type                           Year    Cost             Priority
          Energy Efficiency Upgrade      2007    $8,560           Medium

          Updated: February 16 2006

D2010.03 Lavatories** - 1925

1925: countertop porcelain on steel, on/off brass.
Rating                            Installed Design Life Updated
4 - Acceptable                       0            30        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                               Page 24 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D2010.03 Lavatories** - 1951

1951: Wall hung, vitreous china, on/off brass.
Rating                          Installed Design Life Updated
3 - Marginal                       0           30          NOV-05


Event:    Replace wall hung lavatories.

          Concern:
          Wall hung lavatories require floor support to keep lavatories
          from falling off wall.
          Recommendation:
          Install millwork with stainless steel bowls and brass with
          mixing valve on hot water as kindergarten uses sinks (3).

          Type                         Year   Cost              Priority
          Failure Replacement          2007   $16,050           Medium

          Updated: February 16 2006

D2010.03 Lavatories** - 1968

1968: Wall hung, vitreous china, on/off brass.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           30          NOV-05

D2010.04 Sinks**

Stainless steel, counter top, swing spout, on/off brass.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           30          NOV-05

D2010.05 Showers** - 1968

1968: Institutional heads, on/off brass. Gang shower with control column in boys washroom. In girls individual metal
cabinets on/off brass, institutional heads.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           30          NOV-05

D2010.08 Drinking Fountains / Coolers**

Wall hung, plastic and vitreous china, non refrigerated.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           30          NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                   Page 25 of 51
                                                       Edmonton - Our Lady Of Mount Carmel School (B3227A)

D2010.09 Other Plumbing Fixtures** - 1968

1968: Raised cast iron sinks in janitor rooms, no vacuum breaker in brass.
Rating                          Installed Design Life Updated
3 - Marginal                        0            0         NOV-05


Event:    Install floor janitor sinks.

          Concern:
          Difficult to empty buckets into raised sinks.
          Recommendation:
          Remove raised janitor sink and install floor janitor sink (2).

          Type                           Year   Cost               Priority
          Operating Efficiency Upgrade 2007     $6,420             Medium

          Updated: February 16 2006

D2020.01.01 Pipes and Tubes: Domestic Water* - 1948/1925

1948/1925: Copper piping and galvanized piping and fittings.
Rating                          Installed Design Life Updated
3 - Marginal                        0            40        NOV-05


Event:    Replace galvanized domestic water piping.

          Concern:
          Galvanized piping and fittings leaking. Plumbing code does not
          allow installation.
          Recommendation:
          Remove galvanized piping and install copper pipe and fittings.

          Type                           Year   Cost               Priority
          Failure Replacement            2007   $85,600            Medium

          Updated: February 16 2006

D2020.01.01 Pipes and Tubes: Domestic Water* - 1968

1968: Copper piping and fittings.
Rating                          Installed Design Life Updated
4 - Acceptable                      0            40        NOV-05

D2020.01.03 Piping Specialties (Backflow Preventors)**

Heating system make up lines, wet standpipe.
Rating                          Installed Design Life Updated
4 - Acceptable                      0            30        NOV-05

D2020.02.02 Plumbing Pumps: Domestic Water** - 1968

1968: Inline system domestic hot water recirculation pump. Inline tank/boiler circulation pump.
Rating                          Installed Design Life Updated
4 - Acceptable                      0            20        NOV-05


 Report run on: May 10, 2006 2:26 PM                                                              Page 26 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D2020.02.02 Plumbing Pumps: Domestic Water** - 2001

2001: Inline system domestic hot water recirculation pump installed in 1925 original school.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           20         NOV-05

D2020.02.06 Domestic Water Heaters** - 1968

1968: Two coppertube boilers and large vertical storage tank.
Rating                         Installed Design Life Updated
3 - Marginal                       0           20         NOV-05


Event:    Install new domestic hot water heaters.

          Concern:
          Maintenance cost, energy inefficient.
          Recommendation:
          Install new domestic hot water heaters sized for revised
          building hot water demand.

          Type                         Year   Cost                Priority
          Operating Efficiency Upgrade 2007   $25,680             Medium

          Updated: February 16 2006

D2020.02.06 Domestic Water Heaters** - 2001

2001: Install in 1925 original school, natural draft 30,000 BTU/hr. input.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           20         NOV-05

D2020.03 Water Supply Insulation*: Domestic

Majority of domestic hot, cold, recirculation piping insulated.
Rating                         Installed Design Life Updated
3 - Marginal                       0           30         NOV-05


Event:    Insulate piping which is not insulated.

          Concern:
          Domestic piping where replaced has not been insulated.
          Recommendation:
          Insulate piping which is not insulated.

          Type                         Year   Cost                Priority
          Energy Efficiency Upgrade    2007   $16,050             Medium

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                            Page 27 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

D2030.01 Waste and Vent Piping* - 1925

1925: Cast iron.
Rating                           Installed Design Life Updated
2 - Poor                            0           50        NOV-05


Event:     Replace underground storm and sanitary sewer.

           Concern:
           On other projects of similar age underground storm and
           sanitary piping had failed and storm water and sewage was
           collecting under floor slab. Rooms throughout basement were
           noted basement be very musty. Staff have become ill
           conducting classes in basement rooms.
           Recommendation:
           Video underground sewer lines to confirm probability of failed
           lines. Replace failed sewer lines.

           Type                         Year   Cost                 Priority
           Failure Replacement          2008   $321,000             Medium

           Updated: February 16 2006

D2030.01 Waste and Vent Piping* - 1948, 1951 Additions

1948, 1951 Additions: cast iron, copper.
Rating                           Installed Design Life Updated
3 - Marginal                        0           50        NOV-05


Event:     Video underground sewer lines.

           Concern:
           Existing underground piping varies in age up to 58 years.
           Recommendation:
           Video underground sewer lines in older sections of school to
           determine condition of piping.

           Type                         Year   Cost                 Priority
           Study                        2007   $10,700              Medium

           Updated: February 16 2006

D2030.02 Waste Piping Specialties*

Solids interceptor on sink in art room in 1925 original building.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           50        NOV-05

D2030.02 Waste Piping Specialties* - 1968

1968: Two compartment sump pit in boiler room. Weeping tile pit in boiler room.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           50        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                             Page 28 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D2040.01 Rain Water Drainage Piping Systems*

Rainwater leaders connected to underground storm.
Rating                        Installed Design Life Updated
4 - Acceptable                    0            50        NOV-05

D2040.02.04 Roof Drains**

Cast iron dome, full flow and control flow.
Rating                        Installed Design Life Updated
4 - Acceptable                    0            40        NOV-05

D3010.02 Gas Supply Systems*

Gas line to hot water heating boilers, steam boilers, hot water heaters, science room.
Rating                        Installed Design Life Updated
4 - Acceptable                    0            50        NOV-05

D3020.01.01 Heating Boilers & Accessories: Steam** - 1948

1948: Two natural draft Weil McLain cast iron sectional boilers installed in 1948 addition mechanical room. Complete with
low water cut off, relief valve. Provides low pressure steam for heating system heat exchanger installed in 1990. 1,190,000
BTU/hr input each.
Rating                        Installed Design Life Updated
3 - Marginal                      0            35        NOV-05


Event:    Install new heating plant.

          Concern:
          Maintenance costs, energy inefficient.
          Recommendation:
          Install new heating plant, install energy efficient coppertube
          boilers, fan assisted, low NOX, primary and secondary pumps.

          Type                         Year   Cost             Priority
          Operating Efficiency Upgrade 2007   $342,400         Medium

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                        Page 29 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3020.01.02 Feedwater Equipment - 1968

1968: Above ground condensate tank with two condensate pumps.
Rating                          Installed Design Life Updated
3 - Marginal                       0           0          NOV-05


Event:    Install new condensate receiver.

          Concern:
          Excessive condensate leakage at condensate receiver.
          Recommendation:
          Install new condensate receiver.

          Type                         Year   Cost                 Priority
          Failure Replacement          2007   $21,400              Medium

          Updated: February 16 2006

D3020.01.03 Chimneys (&Comb. Air) : Steam Boilers**

Masonry chimney. Insulated combustion air.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           35         NOV-05

D3020.02.01 Heating Boilers and Accessories: H.W.** - 1968

1968: One (1) Peerless natural draft, cast iron sectional boiler, complete with relief valve and low water cut off, input
3,150,000 BTU/hr. input.
Rating                          Installed Design Life Updated
3 - Marginal                       0           30         NOV-05


Event:    Install new heating plant.

          Concern:
          Boiler energy inefficient, standing pilot. No standby.
          Recommendation:
          Install new heating plant. Install energy efficient coppertube
          boilers, fan assisted, low NOX, primary and secondary pumps.

          Type                         Year   Cost                 Priority
          Failure Replacement          2007   $267,500             Medium

          Updated: February 16 2006

D3020.02.02 Chimneys (&Comb. Air): H.W. Boiler**

Class A chimney. Insulated combustion air.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           30         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                       Page 30 of 51
                                                          Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3020.02.03 Water Treatment: H. W. Boiler*

Side steam filter, chemical pot feeder.
Rating                          Installed Design Life Updated
4 - Acceptable                          0           30        NOV-05

D3020.05 Auxiliary Equipment: Heat Generation* - 1948

1948: Horizontal air cushion expansion tank.
Rating                          Installed Design Life Updated
4 - Acceptable                          0           30        NOV-05

D3020.05 Auxiliary Equipment: Heat Generation* - 1990

1990: Horizontal air cushion expansion tank.
Rating                          Installed Design Life Updated
4 - Acceptable                          0           0         NOV-05

D3040.01 Air Distribution Systems - 1925

1925: Natural ventilation.
Rating                          Installed Design Life Updated
1 - Critical                            0           30        NOV-05


Event:     Install packaged rooftop unit.

           Concern:
           No conditioned air supplied into rooms. Natural ventilation
           provided via opening and closing of manual dampers. Many
           rooms are musty, have odors. Complaints of rooms being hot,
           stale. Carbon dioxide levels have been measured to 1600 ppm.
            Normal is 800 ppm.
           Recommendation:
           Install gas fired packaged rooftop unit with supply fan, return,
           fan, motorized fresh, return, exhaust dampers, indirect gas fired
           heat exchanger, high turn down burner. Medium efficiency filter
           bank, above ground supply and return ductwork, CO2 sensor to
           vary amount of fresh air, connect to BMCS.

           Type                             Year   Cost            Priority
           Indoor Air Quality Upgrade       2007   $374,500        High

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                 Page 31 of 51
                                                          Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.01 Air Distribution Systems - 1948, 1950, 1951, 1962 Additions

1948, 1950, 1951, 1962 Additions: Low velocity ductwork connected to exhaust fan in 1948 mechanical room.
Rating                          Installed Design Life Updated
2 - Poor                                0           30        NOV-05


Event:     Install gas fired packaged rooftop unit.

           Concern:
           No conditioned supply air into rooms. Indoor centrifugal
           exhaust fans draws air form rooms and expels air to outdoors.
           Air make up is drawn in through cracks and open windows. No
           filters. Air not heated. Ventilation is sub-standard.
           Recommendation:
           Install two (2) gas fired packaged rooftop unit with supply fan,
           return fan, motorized fresh, return, exhaust dampers, indirect
           fired heat exchanger, high turn down burner, medium efficiency
           filter bank, above ground supply and return air ductwork, CO2
           sensor to vary amount of fresh air. Connect to BMCS.

           Type                             Year   Cost            Priority
           Indoor Air Quality Upgrade       2007   $642,000        High

           Updated: February 16 2006

D3040.01 Air Distribution Systems - 1968

1968: No ventilation in various rooms.
Rating                          Installed Design Life Updated
3 - Marginal                            0           30        NOV-05


Event:     Install ventilation in rooms where deficient.

           Concern:
           No ventilation in gymnasium storage, no ventilation in janitor
           room.
           Recommendation:
           Install ventilation in rooms where deficient.

           Type                             Year   Cost            Priority
           Code Upgrade                     2007   $6,420          Medium

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                    Page 32 of 51
                                                         Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.01.01 Air Handling Units: Air Distribution** - 1968

1968: Classroom/administration air system is built up consisting of motorized fresh, return, exhaust dampers, roll filter
bank, supply fan, above ground supply air ductwork, ceiling return air.
Rating                         Installed Design Life Updated
3 - Marginal                           0           30        NOV-05


Event:    Install packaged rooftop unit.

          Concern:
          Use of supply fan only cannot guarantee correct differential
          between supply and return air.        Unit internals rusty at
          abandoned evaporative humidifier. Poor aseptic condition.
          Ceiling space used as return air plenum with wood deck.
          Recommendation:
          Install gas fired packaged rooftop unit with supply fan, return
          fan, motorized fresh, return, exhaust dampers, indirect fired
          heat exchanger, high turn down burner, medium efficiency filter
          bank, above ground supply and return ductwork CO2 sensor to
          vary amount of fresh air. Connect to BMCS.

          Type                             Year   Cost            Priority
          Indoor Air Quality Upgrade       2007   $449,400        Medium

          Updated: February 16 2006

D3040.01.01 Air Handling Units: Air Distribution** - 1968

1968: Gymnasium air system is built up consisting of motorized fresh, return, exhaust dampers, filter tank, pumped hot
water heating coil, supply fan, underground supply air ductwork, ducted return air.
Rating                         Installed Design Life Updated
3 - Marginal                           0           30        NOV-05


Event:    Install packaged rooftop unit.

          Concern:
          Use of supply fan only cannot guarantee correct differential
          between supply and return air. System design not suitable for
          high/low occupancy. Motorized damper motors located in
          stage ceiling space. Poor access to damper motors.
          Recommendation:
          Install gas fired packaged rooftop unit with supply fan, return,
          fan, motorized fresh, return, exhaust dampers, indirect fired
          heat exchanger, high turndown burner, medium efficiency filter
          bank, above ground supply and return ductwork, CO2 sensor to
          vary mount of fresh air, connect to BMCS complete with
          frequency drives.

          Type                             Year   Cost            Priority
          Indoor Air Quality Upgrade       2007   $214,000        Medium

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                        Page 33 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.01.02 Fans: Air Distribution*

Circulation fans installed in 1951 addition.
Rating                          Installed Design Life Updated
4 - Acceptable                     0            30         NOV-05

D3040.01.03 Air Cleaning Devices:Air Distribution* - 1968

1968: Classroom/administration air system complete with 50 mm roll filter. Gymnasium air system complete with 50 mm
throw away filters. COST INCLUDED IN D3040.01.01.
Rating                          Installed Design Life Updated
3 - Marginal                       0            30         NOV-05

D3040.01.04 Ducts: Air Distribution* - 1968

1968: Medium velocity galvanized ductwork to terminal boxes. Ceiling return air. COST INCLUDED IN D3040.01.01.
Rating                          Installed Design Life Updated
4 - Acceptable                     0            50         NOV-05

D3040.01.06 Air Terminal Units: Air Distribution**

Twenty-seven (27) constant volume terminal boxes with reheat coils.
Rating                          Installed Design Life Updated
3 - Marginal                       0            30         NOV-05


Event:    Replace terminal boxes.

          Concern:
          Operation of terminal boxes suspect.           No access door to
          inspect condition of heating coil.
          Recommendation:
          Replace terminal boxes.

          Type                         Year    Cost              Priority
          Failure Replacement          2007    $57,780           Medium

          Updated: February 16 2006

D3040.01.07 Air Outlets & Inlets:Air Distribution* - 1968

1968: Vary as to type. Square diffusers, round diffusers, egg crate and linear bar return grilles.
Rating                          Installed Design Life Updated
4 - Acceptable                     0            30         NOV-05

D3040.02 Steam Distribution Systems: Piping/Pumps** - 1990

1990: Black iron piping to heating system heat exchanger. condensate piped to condensate receiver via black iron pipe.
Rating                          Installed Design Life Updated
4 - Acceptable                     0            30         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                       Page 34 of 51
                                                          Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.03.01 Hot Water Distribution Systems** - 1968

1968: Home economics area.
Rating                          Installed Design Life Updated
3 - Marginal                            0           0         NOV-05


Event:     Install additional heating elements in home
           economics.

           Concern:
           Home economics area is cold.
           Recommendation:
           Install additional heating elements in home economics.

           Type                             Year   Cost            Priority
           Operating Efficiency Upgrade 2007       $8,560          Medium

           Updated: February 16 2006

D3040.03.01 Hot Water Distribution Systems** - 1969

1969: Two base mounted circulation pumps. Black iron piping to radiation, terminal boxes, unit heaters.
Rating                          Installed Design Life Updated
4 - Acceptable                          0           40        NOV-05

D3040.03.01 Hot Water Distribution Systems** - 1990

1990: Two base mounted circulation pumps. Black iron piping to radiation, convectors, fan coil units.
Rating                          Installed Design Life Updated
4 - Acceptable                          0           0         NOV-05

D3040.04 Special Exhaust Systems

Carpentry equipment exhaust.
Rating                          Installed Design Life Updated
1 - Critical                            0           30        NOV-05


Event:     Upgrade carpentry equipment exhaust.

           Concern:
           Carpentry equipment not provided with hook up to central dust
           collector equipment.
           Recommendation:
           Install exhaust hoods and exhaust connections to carpentry
           equipment.     Install 100% exhaust central dust collector
           equipment and make up air unit.

           Type                             Year   Cost            Priority
           Indoor Air Quality Upgrade       2007   $42,800         High

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                      Page 35 of 51
                                                          Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.04 Special Exhaust Systems

Paint spray exhaust.
Rating                          Installed Design Life Updated
1 - Critical                            0           30        NOV-05


Event:     Install paint spray exhaust hood with filtration and
           make up air.

           Concern:
           Paint spray exhaust consists of cardboard box. No exhaust,
           filtration.
           Recommendation:
           Install galvanized paint spray hood with paint arrestance filter,
           exhaust fan, make up air unit.

           Type                             Year   Cost            Priority
           Indoor Air Quality Upgrade       2007   $32,100         High

           Updated: February 16 2006

D3040.04.01 Fans: Exhaust**

Indoor centrifugal exhaust fan in 1948 addition boiler room.
Rating                          Installed Design Life Updated
4 - Acceptable                          0           30        NOV-05

D3040.04.01 Fans: Exhaust** - 1925

Washroom exhaust.
Rating                          Installed Design Life Updated
3 - Marginal                            0           30        NOV-05


Event:     Install washroom exhaust.

           Concern:
           No exhaust in lower level washrooms.
           Recommendation:
           Install exhaust fans for washrooms.

           Type                             Year   Cost            Priority
           Indoor Air Quality Upgrade       2007   $8,560          High

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                 Page 36 of 51
                                                         Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.04.01 Fans: Exhaust** - 1968

1968: Roof mounted dome exhaust fans.
Rating                          Installed Design Life Updated
3 - Marginal                           0           30        NOV-05


Event:    Replace failing exhaust fans.

          Concern:
          Three (3) exhaust fans vibrate excessively.
          Recommendation:
          Replace exhaust fans with new (3).

          Type                             Year   Cost            Priority
          Failure Replacement              2007   $9,630          Medium

          Updated: February 16 2006

D3040.04.01 Fans: Exhaust** - 1968

1968: Home economics area.
Rating                          Installed Design Life Updated
3 - Marginal                           0           30        NOV-05


Event:    Install exhaust in home economics room.

          Concern:
          No exhaust in home economics room to reduce odor migration
          from room to remainder of school.
          Recommendation:
          Install exhaust and make up air unit.

          Type                             Year   Cost            Priority
          Indoor Air Quality Upgrade       2007   $21,400         Medium

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                Page 37 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3040.04.01 Fans: Exhaust** - 1969

1969: Ranges.
Rating                        Installed Design Life Updated
3 - Marginal                      0           30         NOV-05


Event:    Install range hoods.

          Concern:
          Range hood not installed in caretakers office, staff lounge at
          ranges.

          Recommendation:
          Install range hoods where deficient.

          Type                        Year   Cost             Priority
          Code Upgrade                2007   $3,210           Medium

          Updated: February 16 2006

D3040.04.03 Ducts: Exhaust*

Low velocity exhaust air ductwork connected to exhaust air outlets and fans.
Rating                        Installed Design Life Updated
4 - Acceptable                    0              0       NOV-05

D3040.04.05 Air Outlets and Inlets: Exhaust*

Linear bar and egg crate exhaust grilles.
Rating                        Installed Design Life Updated
4 - Acceptable                    0              0       NOV-05

D3040.05 Heat Exchangers** - 1990

1990: Shell and tube steam/water heat exchanger provides heated water for heating transfer equipment installed in 1925
original building and 1948, 1950, 1951, 1962 additions.
Rating                        Installed Design Life Updated
4 - Acceptable                    0           30         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                    Page 38 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3050.01.01 Computer Room Air Conditioning Units**

Computer lab.
Rating                        Installed Design Life Updated
3 - Marginal                      0            30        NOV-05


Event:    Install air conditioning.

          Concern:
          Roof hot.
          Recommendation:
          Install ductless air conditioning unit with remote condensing
          unit.

          Type                        Year    Cost            Priority
          Operating Efficiency Upgrade 2007   $37,450         High

          Updated: February 16 2006

D3050.01.01 Computer Room Air Conditioning Units** - Server Room

Server room.
Rating                        Installed Design Life Updated
3 - Marginal                      0            30        NOV-05


Event:    Install air conditioning.

          Concern:
          Server room and equipment hot.
          Recommendation:
          Install ductless air conditioning unit with remote condensing
          unit.

          Type                        Year    Cost            Priority
          Operating Efficiency Upgrade 2007   $21,400         High

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                            Page 39 of 51
                                                         Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3050.03 Humidifiers**

No humidification.
Rating                          Installed Design Life Updated
3 - Marginal                           0           25        NOV-05


Event:    Install gas fired humidifiers.

          Concern:
          No humidification. Alberta Infrastructure Design Guidelines
          recommends humidification.
          Recommendation:
          Install five (5) low maintenance gas fired humidifiers with
          multiple steam grids for proposed new rooftop air systems.
          Install water softeners.

          Type                             Year   Cost            Priority
          Indoor Air Quality Upgrade       2007   $214,000        Medium

          Updated: February 16 2006

D3050.05.01 Convectors**

Recessed and exposed convectors.
Rating                          Installed Design Life Updated
4 - Acceptable                         0           30        NOV-05

D3050.05.02 Fan Coil Units**

Wall fin coil units installed in entrances.
Rating                          Installed Design Life Updated
4 - Acceptable                         0           30        NOV-05

D3050.05.03 Finned Tube Radiation**

Wall fin radiation installed within enclosure and millwork.
Rating                          Installed Design Life Updated
4 - Acceptable                         0           40        NOV-05

D3050.05.06 Unit Heaters** - 1968

1968: Unit heaters installed in ceiling space in entrances.
Rating                          Installed Design Life Updated
4 - Acceptable                         0           30        NOV-05

D3050.05.07 Unit Ventilators** - 1950

1950: Installed in 1950 addition classroom.
Rating                          Installed Design Life Updated
4 - Acceptable                         0           30        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                Page 40 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

D3060.02.01 Electric and Electronic Controls**

Electric thermostat cycles fan coil units and unit heaters to maintain set point.
Rating                          Installed Design Life Updated
4 - Acceptable                      0           30        NOV-05

D3060.02.02 Pneumatic Controls** - 1948

1948: Simplex air compressor, refrigerated air dryer, pneumatic room thermostats, control valves.
Rating                          Installed Design Life Updated
4 - Acceptable                      0           40        NOV-05

D3060.02.02 Pneumatic Controls** - 1968

1968: Two Simplex air compressors, refrigerated air dryer, pneumatic room thermostats, control valves, damper motors.
Rating                          Installed Design Life Updated
4 - Acceptable                      0           40        NOV-05

D3060.02.03 Pneumatic and Electric Controls

Transducers to integrate pneumatic with BMCS.
Rating                          Installed Design Life Updated
4 - Acceptable                      0           40        NOV-05

D3060.02.05 Building Systems Controls(BMCS, EMCS)** - 1990

1990: Andover BMCS. System controls equipment activation and assists in maintaining building environment.
Rating                          Installed Design Life Updated
3 - Marginal                        0           30        NOV-05


Event:    Replace control panels.

          Concern:
          BMCS parts not available. Failure imminent.
          Recommendation:
          Replace control panels.

          Type                          Year   Cost              Priority
          Failure Replacement           2006   $74,900           High

          Updated: February 16 2006

D4020 Standpipes*

Wet standpipe 40 mm angle valve, hose, fog nozzle exposed in older sections. Fire hose cabinets in newer sections.
Rating                          Installed Design Life Updated
4 - Acceptable                      0           50        NOV-05

D4030.01 Fire Extinguisher, Cabinets and Accessories**

ABC, pump style fire extinguishers installed in wall brackets and cabinets.
Rating                          Installed Design Life Updated
4 - Acceptable                      0           30        NOV-05



 Report run on: May 10, 2006 2:26 PM                                                                        Page 41 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D4090 Other Fire Protection Systems*

Flammable storage.
Rating                        Installed Design Life Updated
3 - Marginal                      0           0          NOV-05


Event:    Install metal flammable storage cabinet.

          Concern:
          Flammable storage cabinet is wood construction.
          Recommendation:
          Install metal flammable storage cabinet.

          Type                        Year   Cost             Priority
          Code Upgrade                2007   $2,140           Medium

          Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                            Page 42 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)
S5 ELECTRICAL
D5010.01 Main Electrical Transformers**

The EPCOR pad mounted transformer is located in the parking area on the north side of the building. The primary service is
routed underground from a pole located on the west side of 105 Street which is east of the building. The secondary service
is routed underground to the main electrical room of the 1968 addition.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           40        NOV-05

D5010.03 Main Electrical Switchboards (Main Distribution)**

The main distribution panel (MDP) is 1000 Amps, 3 Phase, 4 Wire, 120/208 Volts. It is located in the 1968 addition main
electrical room. There are six (6) spaces for additional breakers. The demand read from the utility meter was
approximately 240 amps. There is no transient voltage surge suppressor.
Rating                          Installed Design Life Updated
3 - Marginal                       0           40        NOV-05


Event:    Add transient voltage surge suppression
          equipment.

          Concern:
          Sensitive computer and other mircoprocessor operated
          equipment could become damaged due to a voltage surge.
          Recommendation:
          Provide a transient voltage surge suppressor and connect to
          the MDP.

          Type                         Year   Cost              Priority
          Failure Replacement          2007   $10,700           Medium

          Updated: February 16 2006

D5010.05 Electrical Branch Circuit Panelboards (Secondary Distribution)**

The panels in the 1968 addition are 3 Phase, 4 Wire, 120/208 Volts and are located throughout the areas. Most have
limited space for additional breakers. The panels in the remaining much older areas of the school are single phase,
generally full of breakers and are obsolete.
Rating                          Installed Design Life Updated
3 - Marginal                       0           25        NOV-05


Event:    Replace panels throughout the school, including
          the 1968 addition.

          Concern:
          Additional loads cannot be connected to the existing panels in
          most locations.       Replacement breakers are generally
          unavailable for the obsolete panels.
          Recommendation:
          Supply and install 40 new panels of larger capacity c/w larger
          feeder conductors.

          Type                         Year   Cost              Priority
          Lifecycle Replacement        2007   $107,000          Medium

          Updated: February 16 2006


 Report run on: May 10, 2006 2:26 PM                                                                       Page 43 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D5010.07.02 Motor Starters and Accessories**

Motor control consists of loose magnetic and manual motor starters located at equipment locations. The equipment
located in the pre-1968 areas is obsolete.
Rating                          Installed Design Life Updated
3 - Marginal                       0           0         NOV-05


Event:    Provide new combination magnetic starters and
          manual motor starters to replace existing
          equipment.

          Concern:
          The obsolete equipment parts hard to obtain could fail and
          mechanical systems would shutdown.           Emergency
          replacement would likely be required.
          Recommendation:
          Replace 40 existing magnetic and manual starters.

          Type                         Year   Cost               Priority
          Failure Replacement          2007   $26,750            Medium

          Updated: February 16 2006

D5020.01 Electrical Branch Wiring*

Wiring in the 1968 addition is in good condition. Wiring in the remaining areas is likely fair to poor with a probable lack of
adequate grounding and wiring devices in old condition. All areas require a minimum addition of four (4) duplex receptacles
in each room.
Rating                          Installed Design Life Updated
3 - Marginal                       0           50        NOV-05


Event:    Replace wiring in pre-1968 areas. Add duplex
          receptacles in all areas.

          Concern:
          Lack of adequate number of receptacles and circuit capacity
          restricts the ability to connect electrically operated educational
          aids and general purpose equipment. Old wiring can pose a
          potential safety hazard.
          Recommendation:
          In conjunction with replacing panels (D5010.05) add
          receptacles and replace wiring as indicated herein. Add 600
          new receptacles.

          Type                         Year   Cost               Priority
          Program Functional Upgrade 2007     $321,000           Medium

          Updated: February 16 2006

D5020.02.01 Lighting Accessories (Lighting Controls)*

Low voltage switching is used in the gymnasium, industrial arts and computer area. Line voltage switching in all other
areas.
Rating                          Installed Design Life Updated
4 - Acceptable                     0           30        NOV-05



 Report run on: May 10, 2006 2:26 PM                                                                           Page 44 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

D5020.02.02.01 Interior Incandescent Fixtures*

A minimal number of incandescent fixtures are installed. Locations include service, storage, mechanical and some feature
locations.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           30           NOV-05

D5020.02.02.02 Interior Florescent Fixtures**

T-bar/drywall recessed and chain or rod suspended and surface fluorescent fixtures are installed throughout. All fluorescent
fixtures were recently retrofitted with electronic ballasts and T8 lamps.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           30           NOV-05

D5020.02.03 Emergency Lighting*

Emergency battery packs and remote heads are installed. It appears that an adequate number of units has been provided.
The school indicated that regular testing is done. The units are in good condition.
Rating                         Installed Design Life Updated
4 - Acceptable                     0            0           NOV-05

D5020.02.05 Special Purpose Lighting*

Stage lighting fixtures are used for various functions.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           30           NOV-05

D5020.03.01.01 Exterior Incandescent Fixtures*

Incandescent fixtures are in minimal use at canopies and entry door.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           25           NOV-05

D5020.03.01.04 Exterior H.P. Sodium Fixtures*

HPS (high pressure sodium) wall packs are located along exterior walls near entrances.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           25           NOV-05

D5020.03.02 Lighting Accessories (Lighting Controls)*

Photo-electric control is provided for exterior fixtures.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           25           NOV-05

D5020.03.03 Emergency Lighting*

An adequate number of LED exit lights are provided. Exits are connected to the battery packs.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           30           NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                         Page 45 of 51
                                                  Edmonton - Our Lady Of Mount Carmel School (B3227A)

D5030.01 Detection and Fire Alarm**

There is a Simplex 2001 fire alarm system. Main control panel is in the general office. Annunciator is at main entrance It
appears that devices have been located in locations as required. Last test was August 18, 2005.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           25        NOV-05

D5030.02.02 Intrusion Detection**

There is a custom security system consistent with ECS standards. Motion sensors are located throughout. An LED
annunciator is at the main entrance.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           25        NOV-05

D5030.03 Clock and Program Systems**

There is an Edwards master clock and driven clocks in the 1968 area. All other areas have local electric or battery clocks.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           25        NOV-05

D5030.04.01 Telephone Systems**

There is a Nitsuko D telephone system with telephone sets in classrooms, offices, administration areas, library, etc.
Communication from classroom to classroom and to offices or administration is done via the telephone system.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           25        NOV-05

D5030.04.04 Data Systems**

Central hub and servers are in general office area. Category 5 cable is used.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           25        NOV-05

D5030.05 Public Address and Music Systems**

There is a Dukane Petcom 2200 system. Recessed speakers are used in the 1968 addition. Other areas have surface
mounted speakers.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           20        NOV-05

D5030.06 Television Systems*

Community cable television and service from a local VCR is provided to classrooms and other selected areas.
Rating                       Installed Design Life Updated
4 - Acceptable                   0           20        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                           Page 46 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)
S6 EQUIPMENT, FURNISHINGS AND SPECIAL CONSTRUCTION
E1020.03 Theater and Stage Equipment*

Spotlights and stage drapery.
Rating                        Installed Design Life Updated
4 - Acceptable                     0           25        NOV-05

E1090.04 Residential Equipment*

Home Economics room has four kitchen stations with stoves and microwaves, a fridge and a washer and dryer. Staff
kitchen areas have stoves, microwaves, fridges and dishwashers.
Rating                        Installed Design Life Updated
5 - Good                           0           25        NOV-05

E1090.07 Athletic, Recreational, and Therapeutic Equipment*

4 sidecourt basketball backstops. Main court backstops are glass.
Rating                        Installed Design Life Updated
5 - Good                           0           15        NOV-05

E2010.02.05 Educational Facility Casework*

Millwork base cabinets and perimeter shelving units throughout all areas. Some with plastic laminate tops, some with lino
tops.
Rating                        Installed Design Life Updated
3 - Marginal                       0           35        NOV-05


Event:     Provide 75m of new millwork base units.

           Concern:
           Millwork is no longer appropriate for the room function, and
           some is in marginal condition.
           Recommendation:
           Provide approx. 75m of new millwork base units with plastic
           laminate counter tops.

           Type                        Year   Cost            Priority
           Program Functional Upgrade 2007    $69,550         Low

           Updated: February 16 2006

E2010.02.07 Kitchen Casework*

Millwork base and upper cabinets. Plastic laminate counter tops.
Rating                        Installed Design Life Updated
4 - Acceptable                     0           35        NOV-05

E2010.02.09 Library Casework*

Movable millwork shelving units.
Rating                        Installed Design Life Updated
5 - Good                           0           35        NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                         Page 47 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)

E2010.03.01 Blinds**

Roller blinds in 1925/48/50/51 and 62 sections. Between glass venetian blinds in 1968 section.
Rating                           Installed Design Life Updated
3 - Marginal                        0           35        NOV-05


Event:     Replace roller blinds with new perforated roller
           blinds.

           Concern:
           A significant number of the roller blinds are broken, dmamged
           or missing.
           Recommendation:
           Replace all roller blinds with new perforated roller blinds. 70
           blinds.

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $14,980           Medium

           Updated: February 16 2006

E2020 Moveable Furnishings*

Educational and office furniture and equipment throughout.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0         NOV-05

F2020.01 Asbestos*

Textured spray to ceilings (above T-bar) in 1951 section is likely to contain asbestos.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0         NOV-05

F2020.02 PCBs*

Lighting upgraded, no PCBs.
Rating                           Installed Design Life Updated
5 - Good                            0           0         NOV-05

F2020.04 Mould*

Non evident.
Rating                           Installed Design Life Updated
5 - Good                            0           0         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                             Page 48 of 51
                                                      Edmonton - Our Lady Of Mount Carmel School (B3227A)
S8 FUNCTIONAL ASSESSMENT
K3020 Indoor Environment

Poor air quality. See Mechanical.
Rating                         Installed Design Life Updated
2 - Poor                            0           0         NOV-05

K40 Current Code Issues

There are significant code issues with respect to exiting the building. The 1925 section has a basement with single direction
exits and stairs that do not exit to the outside. The earlier sections exceed the area allowable for combustible construction
and are not compartmentalized with fire walls. There are dead end corridors and stairs from the 1951 and 1968 sections do
not have direct exterior exits. The courtyard has no means of exit. One main stair appears to have a pitch that exceeds the
building code maximum.
Rating                         Installed Design Life Updated
1 - Critical                        0           0         NOV-05


Event:     Implement a Code Analysis for the facility.

           Concern:
           There are significant code issues with respect to life safety and
           emergency evacuation of the school.
           Recommendation:
           Conduct a Building Code Analysis Study. There are several
           stairs that exit into the enclosed courtyard. The purpose of the
           study would be to establish an acceptable strategy with the
           Code Authority such as creating a "Safe Route" from the
           courtyard to the exterior. This might involve the installation of
           fire rated partitions and doors through the entrances of the
           existing building, at a cost of approximately $80,000.

           Type                         Year   Cost              Priority
           Study                        2006   $10,700           High

           Updated: February 16 2006

K4010.01 Barrier Free Route: Parking to Entrance

At grade access to main entrance.
Rating                         Installed Design Life Updated
4 - Acceptable                      0           0         NOV-05




 Report run on: May 10, 2006 2:26 PM                                                                          Page 49 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

K4010.02 Barrier Free Entrances

There are no power assist mechanisms installed on any of the entrances.
Rating                         Installed Design Life Updated
2 - Poor                           0           0         NOV-05


Event:     Install power assist at main entrance.

           Concern:
           There are no power assist mechanisms installed to facilitate
           barrier free access.
           Recommendation:
           Provide a power assist mechanism on one of the main entrance
           doors.

           Type                        Year   Cost               Priority
           Barrier Free Access Upgrade 2007   $3,210             Medium

           Updated: February 16 2006

K4010.03 Barrier Free Interior Circulation

There is a wheelchair stair lift in the 1951 section only. The school has a multitude of levels and stairs and there is no
barrier free access to the second floor of the 1968 section.
Rating                         Installed Design Life Updated
2 - Poor                           0           0         NOV-05


Event:     Provide an elevator, 3 wheelchair stair lifts and 3
           ramps to make the school wheelchair accessible.

           Concern:
           The majority of the school is not wheelchair accessible.
           Recommendation:
           Provide an elevator in the 1968 section, three wheelchair stair
           lifts in, and from, the 1925 section, and provide three interior
           ramps at smaller changes in floor level.

           Type                        Year   Cost               Priority
           Barrier Free Access Upgrade 2007   $321,000           Medium

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                         Page 50 of 51
                                                     Edmonton - Our Lady Of Mount Carmel School (B3227A)

K4010.04 Barrier Free Washrooms

There is a barrier free washroom in the 1951 section. It is inaccessible to the rest of the school.
Rating                         Installed Design Life Updated
2 - Poor                           0           0         NOV-05


Event:     Provide a barrier fee washroom in the girls and
           boys washrooms on each floor of the 1968 section.

           Concern:
           There is a barrier free washroom in the 1951 section only. This
           section is wheelchair inaccessible to the rest of the school.
           Recommendation:
           Provide barrier free washrooms to both levels of the 1968
           section. This will allow the majority of the school to have
           access to barrier free washrooms.

           Type                        Year   Cost              Priority
           Barrier Free Access Upgrade 2007   $8,560            Medium

           Updated: February 16 2006




 Report run on: May 10, 2006 2:26 PM                                                                  Page 51 of 51
                       RECAPP Facility Evaluation Report




                              Our Lady Of Mount Carmel School
                                          S3227
                                         Edmonton




Report run on: May 10, 2006 2:48 PM
                                                           Edmonton - Our Lady Of Mount Carmel School (S3227)
                     Facility Details                                                   Evaluation Details
   Building Name: Our Lady Of Mount Carmel S                       Evaluation Company:
          Address:                                                       Evaluation Date: November 4 2005
         Location: Edmonton
                                                                         Evaluator Name:
       Building Id: S3227
 Gross Area (sq. m): 0.00
 Replacement Cost:   $0
  Construction Year: 0                                                      Total Maintenance Events Next 5 years:                    $57,245
                                                                            5 year Facility Condition Index (FCI):                        0%

General Summary:
The site is generally flat with a small rise in grade from the street to the original entrance of the 1925 section. There are
ornamental lawns to the south and east of the building. The west and north is asphalt surfaced for play areas and
parking. There are mature deciduous and evergreen trees, and some treated wood planters with shrubs. The inner
courtyard is concrete surfaced. There are some grading issues between the original 1925 building and the 1968 addition
which cannot be resolved because of the respective floor elevations. There are concrete sidewalks which are cracked and
uneven. The site is generally in acceptable condition.

Structural Summary:



Envelope Summary:



Interior Summary:



Mechanical Summary:


Electrical Summary:


                                                                    Rating Guide
  Condition Rating    Performance
      1 - Critical    Unsafe, high risk of injury or critical system failure.
       2 - Poor       Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs.
    3 - Marginal      Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs.
   4 - Acceptable     Meets present requirements, minor deficiencies. Average operating/maintenance costs.
       5 - Good       Meets all present requirements. No deficiencies.
    6 - Excellent     As new/state of the art, meets present and foreseeable requirements.




Report run on: May 10, 2006 2:48 PM                                                                                                   Page 2 of 6
                                                         Edmonton - Our Lady Of Mount Carmel School (S3227)
S7 SITE
G2020.02.02 Flexible Paving Parking Lots(Asphalt)**

Asphalt parking lot.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2020.06.02 Parking Bumpers*

Wood parking rails on steel H-section posts.
Rating                           Installed Design Life Updated
5 - Good                            0           0          NOV-05

G2020.06.03 Parking Lot Signs*

Painted stall signs on wood rail.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2020.06.04 Pavement Markings*

Painted parking stall lines.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2030.04 Rigid Pedestrian Pavement (Concrete)**

Concrete sidewalks.
Rating                           Installed Design Life Updated
2 - Poor                            0           0          NOV-05


Event:     Replace concrete sidewalks.

           Concern:
           Concrete sidewalks are cracked and uneven.
           Recommendation:
           Remove cracked and uneven concrete sidewalks and provide
           new concrete sidewalks. 100 sq.m.

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $14,445           High

           Updated: February 22 2006

G2030.06 Exterior Steps and Ramps*

Cast-in-place concrete steps to basement mechanical room in 1948 section.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05




 Report run on: May 10, 2006 2:48 PM                                                                Page 3 of 6
                                                         Edmonton - Our Lady Of Mount Carmel School (S3227)

G2040.02 Fences and Gates**

Chain link fence to perimeter of sports fields, city owned and maintained. Ornamental fence to south and west of original
1925 building. Pipe rail fence to east of school.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2040.03 Athletic and Recreational Surfaces**

Grassed sports fields owned and maintained by the city of Edmonton. Asphalt play surface to north of school with exterior
basketball backstops. Interior courtyard, concrete surface.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2040.06 Exterior Signs*

Freestanding wooden school sign adjacent to entrance. School name mounted to brick wall with individual cast aluminum
letters, adjacent to main entrance.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2040.08 Flagpoles*

Steel flagpole adjacent to original entrance in 1925 building.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05

G2040.11 Retaining Walls*

Concrete retaining wall at side of steps leading to basement mechanical room in 1951 section.
Rating                           Installed Design Life Updated
2 - Poor                            0           0          NOV-05


Event:     Provide new cast-in-place concrete retaining wall
           to 1951 basement mechanical room.

           Concern:
           Retaining wall is leaning over.
           Recommendation:
           Remove existing concrete retaining wall, provide new concrete
           retaining wall and repair asphalt play surface where disturbed
           by work.

           Type                         Year   Cost              Priority
           Failure Replacement          2007   $21,400           Medium

           Updated: February 22 2006

G2050.04 Lawns and Grasses*

Ornamental lawns to south and east of school.
Rating                           Installed Design Life Updated
4 - Acceptable                      0           0          NOV-05




 Report run on: May 10, 2006 2:48 PM                                                                          Page 4 of 6
                                                        Edmonton - Our Lady Of Mount Carmel School (S3227)

G2050.05 Trees, Plants and Ground Covers*

Mature deciduous and evergreen trees. Some shrubs and junipers.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           0          NOV-05

G2050.07 Planting Accessories*

Treated wood planters.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           0          NOV-05

G3010.02 Site Domestic Water Distribution*

100mm domestic line to 1968 addition, connected to city main. 50mm domestic line to original building, connected to city
main.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           0          NOV-05

G3010.03 Site Fire Protection Water Distribution*

Fire hydrant not located within 45m of main entrance.
Rating                         Installed Design Life Updated
2 - Poor                           0           0          NOV-05


Event:     Provide fire hydrant within 45m of main entrance.

           Concern:
           There is no fire hydrant within 45m of main entrance.
           Recommendation:
           Provide a fire hydrant within 45m of main entrance.

           Type                        Year   Cost                 Priority
           Code Upgrade                2007   $26,750              High

           Updated: February 22 2006

G3020.01 Sanitary Sewage Collection*

150mm sanitary sewer from 1968 addition, connected to city main. Assumed combined sanitary and storm from original
building and other additions.
Rating                         Installed Design Life Updated
4 - Acceptable                     0           0          NOV-05




 Report run on: May 10, 2006 2:48 PM                                                                         Page 5 of 6
                                                           Edmonton - Our Lady Of Mount Carmel School (S3227)

G3030.01 Storm Water Collection*

Flat top catchbasins in parking lot and interior courtyard. 250mm storm from 1968 addition connected to city main.
Assumed combined storm and sanitary from original building and other additions.
Rating                           Installed Design Life Updated
3 - Marginal                          0           0          NOV-05


Event:     Replace underground storm lines from 1925
           original building.

           Concern:
           Underground storm lines from roof collectors appears to be
           deteriorated and storm water enters the basement area.
           Recommendation:
           Replace underground storm lines.

           Type                           Year   Cost             Priority
           Failure Replacement            2007   $21,400          High

           Updated: February 22 2006

G3060.01 Gas Distribution*

Natural gas line to interior meter.
Rating                           Installed Design Life Updated
5 - Good                              0           0          NOV-05

G4010.04 Car Plugs-ins*

There are twp parking areas with stalls that have plug-ins. The area to the north side of the building has sixteen stalls with
plug-ins, consisting of eight weatherproof duplex receptacles mounted on the parking rail. These plug-ins are contactor
controlled.
The area on the south side of the building has nine stalls with plug-ins, consisting of six weatherproof duplex receptacles
mounted on an ornamental metal fence. These receptacles are not controlled.
Rating                           Installed Design Life Updated
4 - Acceptable                        0           0          NOV-05

G4020.01 Area Lighting*

Incandescent, HPS and LPS wall mounted perimeter entry lighting. There are pole mounted area light fixtures. Strret lighting
fixtures arfe located close enough to the school property to contribute light to the parking area.
Rating                           Installed Design Life Updated
4 - Acceptable                        0           0          NOV-05




 Report run on: May 10, 2006 2:48 PM                                                                              Page 6 of 6

				