                                                  STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION                                       700-010-14

                                                ENGINEER'S WEEKLY SUMMARY                                                         CONSTRUCTION
                                                                                                                                          11/00




                              ENGINEER'S WEEKLY SUMMARY OF EVENTS, OBSERVATIONS AND REMARKS

     SR 9 (I-95) From North of PGA Blvd To the Palm Beach/Martin County Line
     ACTIVITIES PERFORMED FOR THE WEEK OF 03/17/03 to 03/23/03
     A) PRIME CONTRACTOR - RANGER CONSTRUCTION INDUSTRIES, INC.
     Placed asphalt structure, level "D", from south 2 miles of Indiantown Road to Martin County Line along Northbound
     I-95, lane (R3). RCI continued to maintain MOT devices in support of the pavement operation.
     B) SUB CONTRACTORS
     Protection Services:
     Furnished/installed MOT devices in support of the milling and resurfacing operation from, south 2 miles of Indiantown
     Road to Martin County Line along Northbound I-95, lane (R3).
     Mill-It Corporation:
     Milled existing asphalt along Northbound I-95 mainline and shoulder from, south 2 miles of Indiantown Road to Martin
     County Line along Northbound I-95, lane (R3).
     Gene's Striping:
     Placed temporary striping in support of the paving operation from, south 2 miles of Indiantown Road to Martin County
     Line along Northbound I-95, lane (R3).
     Design Traffic Installation:
     Installed End Anchorage Assemblies guardrail along I-95 at Donald Ross Road.




                          CLICK HERE IF YOU NEED ADDITIONAL SPACE TO TYPE THE WEEKLY SUMMARY




                 ENGINEER IN CHARGE (signature)


                  John M Sassine, PLS                                                            The Corradino Group
         ENGINEER IN CHARGE (PRINT NAME AND RANK)                                            DOT OFFICE OR CONSULTANT C.E.I.


         FIN PROJECT NUMBER         FED AID PROJECT NO.                           CONTRACTOR                           CONTRACT NUMBER

     403614-1-52-01              0951 573 I                Ranger Construction Industries, Inc.
                                                                                                                      21564

            WEEK ENDING                  COUNTY                          JOB PROGRESS                             ELAPSED TIME

                                PALM BEACH             6 $ 371,078.01            = 7.25              % 21.00           = 7.24               %
     3/23/2003
                                                       6 $ 5,118,530.00                                290.00

    CONTRACT DAYS USED         21                 PROGRESS SCHEDULE SHOWS           7.24          % COMPLETED AFTER   21             DAYS
    THIS FORM SUMMARIZES THE INFORMATION ON DAILY REPORT OF CONSTRUCTION FROM MONDAY THROUGH SUNDAY. AFTER COMPLETION,
    ATTACH THIS FORM TO THE TOP OF THE WEEK'S DAILY REPORT OF CONSTRUCTION FORMS PRIOR TO DISTRIBUTION.

    DISTRIBUTION:   ORIGINAL COPY PROJECT FILE
                    COPY TO CONTRACTOR (AS REQUESTED)
                                                                                                                                   Prev Next
              SAVE FORM                        PRINT                          CLEAR                Zoom 100% 6   Goto Page    6    Page Page
                                                                                                                        700-010-14
                                                                                                                 CONSTRUCTION
     RETURN TO PG. 1                      Fields at top of page will link from page 1                                      11/00
                                                       when completed.                                            Attachment Page

 FIN PROJECT NUMBER       FED AID PROJECT NO.                          CONTRACTOR                       CONTRACT NUMBER

403614-1-52-01           0951 573 I              Ranger Construction Industries, Inc.
                                                                                                      21564


C) ANTICIPATED ACTIVITIES FOR NEXT WEEK:
Continue milling and placement of asphalt structure, level "D" for mailine and shoulder, between Martin County Line
and PGA Boulevard, along Southbound I-95, lane (L3). RCI will continue to maintain MOT devices and temporary
striping in support of the pavement operation. DTI will continue installation of guardrail throughout the project, at
various locations along Southbound and Northbound I-95.
D) ENGINEER'S COMMENTS:
Two rain days were granted this week due to adverse weather condition, on (03/17/03), and on (03/23/03).


   Uneven pavement construction signs, to be mounted at both sides of highway, along Northbound I-95 as follows:
Between PGA Blvd. and Donald Ross Road at station 55 +/- 00 and station 70 +/- 00; between Donald Ross Road and
Indiantown road, at station 220 +/- 00 and station 300 +/- 00; also, between Indiantown Road and Martin County
Line, station 400 +/- 00 and station 475 +/- 00. (When RCI starts Southbound paving operation, contractor will be
required to place the uneven pavement signs accordingly, in similar locations to Northbound stationing).


   RCI to place warning construction signs at both sides of highway Northbound I-95: "Road Work next 8 miles" at
station 70 +/- 00; "Road Work next 5 miles" at station 220 +/- 00, and another "Road Work next 1 mile" at station
432 +/- 00. Southbound I-95: "Road Work next 11 miles" at station 432 +/- 00; "Road Work next 7 miles" at station
220 +/- 00, and another "Road Work next 4 miles" at station 70 +/- 00. (Project # 7's miles are included along
Southbound I-95).
   In order to protect the workers, RCI needs to utilize the Truck Mounted Attenuator, (TMA) and shall be placed in
the lane closure which the workers are occupying, and shall move accordingly, (see Traffic Control General notes,
Sheet No. 74, Note # 10).


   Speed Limit regulatory signs, to be changed to reflect 55 Mile/Hr in lieu of the five (5) existing 70 Mile/ Hr signs
along Northbound I-95, (three signs), and along Southbound I-95, (two signs); also, the VMS and the work zone's
regulatory speed limit signs in support of the lane closure, also need to reflect, 55 Mile/Hr.


   RCI to provide lighting during night operations as per, Traffic Control General notes, Sheet No. 74, Note # 17. RCI
and TCG agreed to place one lighting plant approximately 1500 Ft. from beginning of lane closure, and another at half
way distance within the same lane closure.

								