					Architectural Plan
Note: this project plan was exported from Project KickStart directly to Excel.

     Quick Links
     1. Download Free Trial                          3. Project KickStart Product Page       5. Project KickStart Templates
     2. Buy Project KickStart                        4. Project KickStart Tour               6. Contact Project KickStart (800) 678-7008

 # Tasks                                    Days           Start      Finish %       Cost Assignments                              Notes
 1 ARCHITECTURAL PLAN                         163       3/1/2010   10/13/2010    0   $0.00
 2   PHASE 0: Preliminaries                    46       3/1/2010     5/3/2010    0   $0.00
 3     Complete Client Preliminary Tasks       45       3/1/2010    4/30/2010    0   $0.00
       TBD
 4     DELIVERABLE: Notice to Proceed            0      5/3/2010     5/3/2010    0   $0.00

 5     Architectural Preliminaries            117       5/4/2010   10/13/2010    0   $0.00
 6       Assemble Consultant Contracts        105       5/4/2010    9/27/2010    0   $0.00
 7           Associate Architect(s)            21       5/4/2010     6/1/2010    0   $0.00
 8           Structures                        21       6/2/2010    6/30/2010    0   $0.00
 9           Landscaping                       21       7/1/2010    7/29/2010    0   $0.00
10           Cost Estimating                   21      7/30/2010    8/27/2010    0   $0.00
11           Consultants                       21      8/30/2010    9/27/2010    0   $0.00
12       Review Consultant Contracts            5      9/28/2010    10/4/2010    0   $0.00
13       Negotiate Consultant Contracts         4      10/5/2010    10/8/2010    0   $0.00

14        DELIVERABLE: Signed Contracts          0    10/11/2010   10/11/2010    0   $0.00

15      DELIVERABLE: Project Plan                0    10/12/2010   10/12/2010    0   $0.00
16      DELIVERABLE: Cost Estimate               0    10/13/2010   10/13/2010    0   $0.00
17 PHASE 1: Program Evaluation                  26    10/14/2010   11/18/2010    0   $0.00
18   Review Program                              4    10/14/2010   10/19/2010    0   $0.00
19      Review Cost Estimate                     4    10/14/2010   10/19/2010    0   $0.00
20   Conduct Interviews                          2    10/20/2010   10/21/2010    0   $0.00
21   Prepare Presentation                        1    10/22/2010   10/22/2010    0   $0.00
22   Make Presentation                           1    10/25/2010   10/25/2010    0   $0.00
23   Review by Agency                           10    10/26/2010    11/8/2010    0   $0.00
24   Receive Comments                            1     11/9/2010    11/9/2010    0   $0.00
25   Add Changes                                 6    11/10/2010   11/17/2010    0   $0.00
26   DELIVERABLE: Space Plans                    0    11/18/2010   11/18/2010    0   $0.00
27 PHASE 2: Schematic Design                    43    11/19/2010    1/18/2011    0   $0.00
28   Prepare Initial Schematic                   5    11/19/2010   11/25/2010    0   $0.00
29   Present Schematic                           1    11/26/2010   11/26/2010    0   $0.00
30   Review by Agency 1                          8    11/29/2010    12/8/2010    0   $0.00
31   Meet for Feedback 1                         1     12/9/2010    12/9/2010    0   $0.00
32   Revise Schematic 1                          4    12/10/2010   12/15/2010    0   $0.00
33   Review by Agency 2                          8    12/16/2010   12/27/2010    0   $0.00
34   Meet for Feedback 2                         1    12/28/2010   12/28/2010    0   $0.00
35   Revise Schematic 2                          4    12/29/2010     1/3/2011    0   $0.00
36   Presentation/Q&A                            1      1/4/2011     1/4/2011    0   $0.00
37   Review by Agency (Final)                    8      1/5/2011    1/14/2011    0   $0.00
38   DELIVERABLE: Schematics Signed-Off          0     1/17/2011    1/17/2011    0   $0.00

39   DELIVERABLE: Preliminary Cost               0     1/18/2011    1/18/2011    0   $0.00
     Estimate
40 PHASE 3: Design Development                  63     1/19/2011    4/15/2011    0   $0.00
41   In-house kick-off meeting                   1     1/19/2011    1/19/2011    0   $0.00
                                                                                                 Free Trial available at
     7/15/2011, 026e4761-a18d-4d98-af57-f91f43ce19cf.xls                                       www.ProjectKickStart.com                    1 of 3
Architectural Plan
Note: this project plan was exported from Project KickStart directly to Excel.

     Quick Links
     1. Download Free Trial                          3. Project KickStart Product Page       5. Project KickStart Templates
     2. Buy Project KickStart                        4. Project KickStart Tour               6. Contact Project KickStart (800) 678-7008

 # Tasks                                      Days         Start      Finish %       Cost Assignments                              Notes
42     Consultant Kick-Off Meeting               1     1/20/2011    1/20/2011    0   $0.00
43     100% Design Development                  60     1/21/2011    4/14/2011    0   $0.00
       Submittal
44       Designs TBD                            60     1/21/2011    4/14/2011    0   $0.00
45     DELIVERABLES: Designs Signed-Off          0     4/15/2011    4/15/2011    0   $0.00

46 PHASE 4: Construction Documents              65     4/18/2011    7/15/2011    0   $0.00
47   In-house Kick-Off Meeting                   1     4/18/2011    4/18/2011    0   $0.00
48   Consultant Kick-Off Meeting                 1     4/19/2011    4/19/2011    0   $0.00
49   90% Construction Documents                 60     4/20/2011    7/12/2011    0   $0.00
50      Documents TBD                           60     4/20/2011    7/12/2011    0   $0.00
51   DELIVERABLE: C.D.s for Plan Check /         0     7/13/2011    7/13/2011    0   $0.00
     Permit / Review
52   DELIVERABLE: 100% Cost Estimate             0     7/14/2011    7/14/2011    0   $0.00

53   DELIVERABLE: Owner Approval of              0     7/15/2011    7/15/2011    0   $0.00
     C.D.s
54 PHASE 5: Building / Planning Review          47     7/18/2011    9/20/2011    0   $0.00

55     Public Project Review                    10     7/18/2011    7/29/2011    0   $0.00
56     Building Permit Process / Plan Check     35      8/1/2011    9/16/2011    0   $0.00

57     DELIVERABLE: Deliverable:                 0     9/19/2011    9/19/2011    0   $0.00
       Documents to Design Consultants

58   DELIVERABLE: Building Permit                0     9/20/2011    9/20/2011    0   $0.00
59 PHASE 6: Bidding                             22     9/21/2011   10/20/2011    0   $0.00
60   Assemble Bids                              10     9/21/2011    10/4/2011    0   $0.00
61   Answer Questions                            5     10/5/2011   10/11/2011    0   $0.00
62   Receive Bids                                0    10/12/2011   10/12/2011    0   $0.00
63   Review Bids                                 5    10/13/2011   10/19/2011    0   $0.00
64   Award Contract                              0    10/20/2011   10/20/2011    0   $0.00
65 PHASE 7: Contract Administration            182    10/21/2011     7/2/2012    0   $0.00
66   Prepare In-House CA                         8    10/21/2011    11/1/2011    0   $0.00
67      TBD                                      8    10/21/2011    11/1/2011    0   $0.00
68   Project Construction                      180    10/24/2011    6/29/2012    0   $0.00
69      (See Construction Plan Details)        180    10/24/2011    6/29/2012    0   $0.00

70     DELIVERABLE: Notice of Completion         1      7/2/2012     7/2/2012    0   $0.00

71 PHASE 8: Owner Occupancy                     20      7/3/2012    7/30/2012    0   $0.00
72   DELIVERABLE: Happy Client                  20      7/3/2012    7/30/2012    0   $0.00



     Next Steps
     1. Download Free Trial                          3. Project KickStart Product Page       5. Project KickStart Templates
                                                                                                   Free Trial available at
     7/15/2011, 026e4761-a18d-4d98-af57-f91f43ce19cf.xls                                        www.ProjectKickStart.com                   2 of 3
Architectural Plan
Note: this project plan was exported from Project KickStart directly to Excel.

    Quick Links
    1. Download Free Trial                         3. Project KickStart Product Page   5. Project KickStart Templates
    2. Buy Project KickStart                       4. Project KickStart Tour           6. Contact Project KickStart (800) 678-7008

 # Tasks                                    Days         Start     Finish %       Cost Assignments                             Notes
   2. Buy Project KickStart                        4. Project KickStart Tour           6. Contact Project KickStart (800) 678-7008




                                                                                            Free Trial available at
     7/15/2011, 026e4761-a18d-4d98-af57-f91f43ce19cf.xls                                  www.ProjectKickStart.com                     3 of 3

				
DOCUMENT INFO
Description: Project Kick Start document sample