Eng_conditions_of_amended_planseng_app_LH_2126227
Document Sample


ENGINEERING APPRAISAL
MEMORANDUM
FILE REF
TO Owen Taylor
COPY TO Siva Sivapalan, Peter Nagels
FROM Ann Rammo
DATE 28-Nov-2007 (amended 22/01/09)
SUBJECT RESOURCE CONSENT APPLICATION: LH-
2126227, 83 Hinemoa Street / Birkenhead for New Residential
Units 2 or more, Proposal to construct two commercial units
and 20 residential units
As requested, I have assessed the application (and the amended plans and
information attached to the letter from SFH Consultants Ltd in their letter dated 07
November 2008) against Council‟s relevant engineering policies. These include:
Geotechnical Issues
The site is steeper than 1:4
Geotechnical Engineering report for the site done by Tonkin and Taylor
Ltd entitled Apartment Development -83 Hinemoa Street Birkenhead
Geotechnical Investigation dated 16 November 2007 reference 25059.
Stability issues have been identified in T&T report and a suitable condition
has been drafted to protect the adjacent public road and ensure that the final
design is compliant with the requirement of the above report.
An addendum report from Tonkin & Taylor dated 16 December 2008
(reference 25059.001) has also been reviewed and is considered to support
the amended application generally as required by the Infrastructure Design
Standards. While the proposed excavations are deeper, the original
boreholes and dynamic probes remain of sufficient depth to support the
review by Tonkin & Taylor.
A further report at building consent stage remains required as a condition –
the Infrastructure Design Standards allow for such a circumstance. As well
condition 10 is amended in regard to methodologies (to address excavations
for tanks) and an Advice Note in respect of the existing crib wall, which on
email advice of Tonkin & Taylor should be reviewed as maintenance or
remediation will be difficult after construction of the proposed buildings
PIR entries have been made in respect of both reports.
Wastewater
Z:\temp\LAP\00665713.DOC
New 100 mm in 180 mm sleeve as in MSC plans
New sewer pipe replacement confirmed by owner letter 23/11/07
Stormwater
SMA2
ARC consent for discharge
Peter Nagels comments on 05/07/07 and January 2009
3 detention tanks, 2 *25m3 each ( one for re use , the other for detention)
another one 12m3 for the car park, as in MSC plan 25905 RC.01 Revision E
New 150mm SW line as in MSC report drains to #85 Hinemoa Street (SW
outfall).
Also OFP flows near the rear of the site
Enviro pod filter to be fitted in the car park as stated in MSC report.
New storm water pipe replacement confirmed by owner letter 23/11/07
New CCC is issued on 26/11/07
Water Supply
Siva „s advice applies
EW major for water connection for sprinklers supply
One FH fire hydrant
Two FH is required to achieve the min flow as in NSCC standards
Transportation
Get rid of the existing vehicle crossing and replace it with new ordinary one
Other matters
As part of this assessment, a site visit to the subject site was carried out on 03/
Augest/2007.
The proposed access is clear of the existing street trees.
Having assessed the application, I recommend that, subject to the following
conditions the consent can be granted from an engineering perspective.
Design Drawings
1. The consent holder must ensure complete engineering drawings, accompanied
with a design certificate in the form of Schedule 1A of NZS 4404:2004, detailing
proposed new or altered public assets including details of proposed silt
detention measures, are prepared and submitted as an Engineering Works
Application (Major) for assessment and written approval by the Environmental
Services Development Engineer before the commencement of any works
unless otherwise specified within this consent.
Advice Note:
i) All designs shall be in accordance with the council‟s “Infrastructure
Design Standards” manual Issue 10.
Z:\temp\LAP\00665713.DOC
2. The consent holder must arrange for inspections in accordance with the “North
Shore City Council‟s Environmental Services Quality Assurance Manual” to be
carried out by a suitably qualified person during construction of all works on the
site to ensure that those works are constructed in accordance with the
approved engineering drawings or any approved amendments to those
drawings, Council‟s standard requirements for the construction of land
development projects, and sound engineering practice.
3. The consent holder must ensure that inspections undertaken in accordance
with condition 2 above are recorded in the "North Shore City Council's
Environmental Services Quality Assurance Manual”. The manual, including the
Certificate of Practical Completion, is to be completed and forwarded to
Environmental Services at the completion of construction of all works.
4. Accurate as-built plans must be submitted for all Public Services, including
Roading, and water supply, in accordance with the North Shore City Asset Data
Standards Manual. The as-built plans must be approved by Data Bureau prior
to the public service becoming operational.
Earthworks, Erosion and Sediment Control, Dust and Noise
5. The consent holder must comply with the approved Erosion and Sediment
Control Plan prior to the commencement of earthworks.
The consent holder must ensure all necessary measures proposed in the Plan
approved by Council have been implemented and provide a certificate of
establishment to Council prior to the commencement of any construction works.
All site works including any bulk earthworks shall be carried out in
accordance with the approved engineering drawings, any Erosion and
Sediment Control Plan and in accordance with Section 9 of the North Shore
City Operative District Plan. The work must take full account of the
geotechnical report dated 16 November, by Tonkin and Taylor
Ltd, entitled Apartment Development -83 Hinemoa Street Birkenhead
Geotechnical Investigation, reference 25059.
6. All personnel working on the site shall be made aware of the „Erosion and
Sediment Control Plan‟ and its requirements. The approved „Erosion and
Sediment Control Plan‟ shall be kept on site for inspection by Council‟s
Compliance Officer.
7. The consent holder shall institute appropriate measures to control or mitigate
any potential dust nuisance. All such measures initiated shall be maintained
throughout the entire duration of the construction period.
8. The consent holder shall implement, to the satisfaction of Council‟s
Development Engineer, suitable measures to prevent depositing of earth on
surrounding streets by trucks moving fill and other materials to and from the
site. In the event that any material is deposited on the street, the consent
Z:\temp\LAP\00665713.DOC
holder shall take immediate action, at their expense, to clean the street. The
loading of earth, fill and other materials shall be confined to the subject site.
Geotechnical
9 All earthworks, retaining walls and foundations shall be designed in accordance
with the recommendations of Geotechnical Engineering report for the site done
by Tonkin and Taylor Ltd dated 16 November 2007 reference 25059 and the
addendum reference 25059.001 dated 16 December 2008 entitled “Apartment
Development – 83 Hinemoa Street Birkenhead Geotechnical review for lower
basement”.
10 The consent holder shall engage Tonkin and Taylor Ltd to review the final
building and the temporary work designs, providing a supplementary
investigation report generally meeting the requirements of the IDS Phase 3
Table 2.1 under clause 2.1 . A monitoring plan shall also be provided and
reviewed by Tonkin and Taylor Ltd at the time of building consent application.
Review of methodologies shall include consideration of temporary or permanent
works needed in respect to the placement of detention tanks. A geotechnical
engineer who is a member of the IPENZ geotechnical Practice College shall be
engaged to monitor and control the excavation and related temporary and
permanent earthworks.
Advice Note
As access to the existing crib wall will be restricted post-construction of the
proposed buildings, Tonkin & Taylor have pointed out that the crib wall should
be reviewed with respect to the affects of the proposed construction and the
ongoing stability and maintenance of the crib wall. Any remediation
requirements and methodologies to protect or remediate the crib wall should
therefore be considered in the supplementary investigation report to be
provided to support any building consent application and any remediation
integrated into the building consent drawings to be submitted.
Vehicular Access / Works within public road
DE to delete as required
9. The consent holder must design and construct vehicular accessways and any
associated retaining walls that are required in compliance with the
Infrastructure Design Standards of Council, making adequate provision for the
drainage of surface water.
10. The consent holder must design the roading and vehicular accessways and
replace the existing at Marintime Terrace removing the existing one and
reinstate the kerbs and construction of new one at Hinemoa Street in
compliance with the Infrastructure Design Standards of Council, making
adequate provision for the drainage of surface water and submit drawings for
engineering works approval. A building consent application must also be made
for any associated retaining walls. The accessway shall be constructed in
accordance with the approved drawings. On completion a certificate of
practical completion shall be provided to Council as set out in the North Shore
City Council Quality Assurance Manual Issue 6 Appendix 6
Z:\temp\LAP\00665713.DOC
Advice Note
A RON application must be made in respect of the removal of the old vehicle
crossing and construction of new one or any temporary crossing.
11. The vehicular accessway is to be lit over the entire length in accordance with
AS/1158.3:1999, Lighting Category P5, Luminaire classification Type 4 with
upward waste light ratio not exceeding 6%.
12. The Consent holder must provide complete engineering drawings as part of the
engineering works application detailing all proposed construction works
affecting the public road carriageway or berm and submit to Environmental
Services for approval.
Advice Note
Maximum driveway gradient is 1 in 5, Maximum driveway gradient where
vehicles are required to turn off the driveway to a parking garaging or
manoeuvring area is 1 in 8. No cut or fill is permitted on the road reserve.
Due allowance must be made for vertical curves, maximum recommended
crossfall is 6%.
Noise Limitations
13. The consent holder is to note the provisions of the Proposed District Plan,
which limits the hours of all noise related activity on and emitting from the site
Construction activity shall occur on the site in accordance with the following
limits:
Weekdays
6.30am - 7.30am less than an L10 level of 60 dBA
7.30am - 6pm less than an L10 level of 75 dBA
6pm - 8pm less than an L10 level of 70 dBA
Saturdays
7.30am - 6pm less than an L10 level of 75 dBA
Sunday, Public Holidays and all other times
No noise permitted on site above the normal background level, ie. no heavy
machinery or noise producing equipment.
Where the L10 is a noise level that is equalled or exceeded for 10% of any 15
minute measurement period.
Z:\temp\LAP\00665713.DOC
The site is to comply with NZS 6803P at all times.
Note: The intent of the standard is that all noisy construction work will take
place between 7.30am and 6pm, Monday to Saturday.
Stormwater, Wastewater and Water Supply
14. The consent holder shall provide a stormwater drainage and on-site stormwater
management system, the design of which shall be presented to Council for
approval with the building consent application.
At the end of the defects liability period for all the stormwater system evidence
shall be provided that the process to transfer the ARC stormwater discharge
consent to Council has been initiated.
15. The consent holder shall take note of any existing overland flows on the
proposed development site provide suitable means to eliminate, control or
mitigate these flows to the satisfaction of the Council‟s Development Engineer,
the designs of which shall be presented to the Council with the Building
Consent application.
16. The consent holder shall install all water reticulation for the development, the
design of which shall be presented to Council for approval with the building
consent application, or, if public, as an Engineering Works application. This
reticulation system shall be designed and installed in accordance with Council‟s
Infrastructure Design Standards (including fire fighting) such that service and
pressure levels are not compromised. The relevant engineering plans shall be
submitted as an Engineering Works application to Environmental Services for
approval prior to any construction commencing. The consent holder shall carry
out all tests required by the New Zealand Fire Service and Council in regard to
water pressure and flow testing. This testing shall be done at the consent
holder‟s expense
Advice Note(s)
Resource consents, particularly for earthworks and stormwater discharge
approval may be required from the Auckland Regional Council. Please
contact the Auckland Regional Council Land and Water Section on (09) 366-
2000 for advice in this regard.
An operation and maintenance manual will be required for all stormwater
management devices as part of building consent or engineering works
approval conditions and an entry in the Property Information Register of
Council will be made regarding the stormwater device and the manual.
Watermeter banks for all units may be installed in the road berm.
Z:\temp\LAP\00665713.DOC
Get documents about "