OVERVIEW
• Client and Organization
• Project Description
• Design Requirements
• Project Approach
• Design Solution
• Conclusion
CLIENT AND ORGANIZATION
• Hunt Construction Group
- Indianapolis, Indiana
- Robert W. Fuller, Construction Manager
PROJECT DESCRIPTION
• Yale University in New Haven, Connecticut
New Haven
PROJECT DESCRIPTION
• Parallel bid process
• Identify missed details
• Discover alternative approaches
• Obtain an understanding of
construction methods and
procedures
CONSTRUCTION MANAGEMENT
• First year a Construction Management
Project offered at Rose-Hulman
• Learning along the way with our professors
• Difficulties fitting
design criteria into
our project
DESIGN REQUIREMENTS
• Constraints These areas include:
KNOT
GARDEN
- No historical
buildings or HISTORIC
MANSIONS
landmarks may
be harmed
SITE
LUCE HALL
DESIGN REQUIREMENTS
• Deliverables
- Project Proposal
- Site Utility Relocation Bid Package
- Excavation Support/Shoring Design
- Excavation Bid Package
- Wall Formwork Selection
- Wall Formwork Bid Package
PROJECT APPROACH
• Design/Assessment of Options
- Utility Relocation
- Current utilities run directly through proposed site
- Utilities relocated and
functioning before excavation begins
PROJECT APPROACH
• Sheeting and Shoring
- Geotechnical report obtained from Hunt
- Considered numerous shoring options
Typical
Soldier
Pile/Lagging
System
PROJECT APPROACH
• Select Wall Formwork System
- Foundation design provided by Hunt Construction
- GPHB will select appropriate formwork system
- Numerous options in consideration
- Criteria of Selection: constructability,
cost efficiency, functionality
PROJECT APPROACH
• Utility Relocation Bid/Excavation &
Formwork Bid
- Guaranteed Maximum Price (GMP) bids
- 2006 RS Means Manual
- Labor Rate Adjustments
- Unit Material Prices
- Bonding, Permits, Fees
PROJECT APPROACH
• Codes & Regulations
- Occupational Safety and Health Administration (OSHA)
- Connecticut State Building Code
- International Building Code (IBC)
- Environmental Protection Agency (EPA)
- Leadership in Energy and Environmental Design (LEED)
- LEED Silver Certification (possibly Gold)
UTILITY RELOCATION
• Assessed multiple routes for utility relocation
• Conducted research for two different
excavation methods
- Open Trenching
- Directional Boring
RECOMMENDATION: OPEN TRENCHING because
directional boring poses many problems with such a
high volume of utilities running beneath Prospect
Street.
PROJECT PROGRESS
NEW
UTILITIES
EXISTING
UTILITIES
NORTH
UTILITY RELOCATION
Utility Relocation Route
Proposed Luce Hall
Building I
1 Existing Utilities Proposed Building II
C-1
UTILITY RELOCATION
Relocation Route Existing Utilities
20’-0”
45’-0”
1
C-1
UTILITY RELOCATION
• Bid Package 1 Quantity Take-Off
- General Conditions/Requirements
- Test Pits
- Demolition and Access
- Sediment and Erosion Control
- Utility Excavation/Installation
$746,000
CONSTRUCTION SEQUENCE
•Place job trailer
•Site Access
•Demolition
•Soldier Piles
•Excavation
•Structural Fill
N
SOLDIER PILE DESIGN
• Soldier Pile / Timber Lagging System
• HP 12x53 sections (90)
• 45’ long
15’
• Embedded 30’ into surface
• 5” timber lagging
30’
SOLDIER PILE DESIGN
REINFORCED CONCRETE WALL
FORMWORK SYSTEM
• Reinforced Cast-in-Place Concrete Wall
• 15 inches thick & 12 feet 8 inches high
• Various Temporary Forming Methods
• Contractor Preference
REINFORCED CONCRETE WALL
FORMWORK SYSTEM
Side View X-Section
REINFORCED CONCRETE WALL
FORMWORK SYSTEM
CONCLUSION/LESSONS LEARNED
• Client satisfied with proposal
• All requested designs complete
• All requested bid packages complete
• Information is difficult to obtain
• Experienced bidders have large advantage (Means)
• Schedule in advance (Everyone is busy)
• Extremely valuable learning experience
QUESTIONS?