; Project Earned Value Report
Documents
Resources
Learning Center
Upload
Plans & pricing Sign in
Sign Out
Your Federal Quarterly Tax Payments are due April 15th Get Help Now >>

Project Earned Value Report

VIEWS: 18 PAGES: 3

Project Earned Value Report document sample

More Info
  • pg 1
									                                           EARNED VALUE STATUS REPORT

        Project Title:                                             Date Prepared:

        Budget at Completion (BAC):                                Overall Status:

                                               Current Reporting    Current Period   Past Period
                                                    Period           Cumulative      Cumulative
        Planned value (PV)
        Earned value (EV)
        Actual cost (AC)

        Schedule variance (SV)
        Cost variance (CV)
        Schedule performance index (SPI)
        Cost performance index (CPI)

        Root Cause of Schedule Variance:




        Impact on Deliverables, Milestones, or Critical Path:



        Root Cause of Cost Variance:




        Impact on Budget, Contingency Funds, or Reserve:




        Percent planned
        Percent earned
        Percent spent

        Estimates at Completion (EAC):
        EAC w/CPI [BAC/CPI]
        EAC w/ CPIxSPI [AC+((BAC-
        EV)/(CPIxSPI))]
        Selected EAC, Justification, and Explanation




        To complete performance index (TCPI)
ed9caa6c-ee8a-4c7a-8e65-4e1debb57802.xls
                            Parametric Estimates
                        Resource
WBS ID     Effort Hours Quantity % available
       1.1          150          2          75%




                                Analogous Estimates
                           Prior
WBS ID      Prior activity Variable Duration

         1.1 Build deck   160 sq. ft. 10 days




                              Three Point Estimates
                         Most
           Optimistic    likely      Pessimistic
WBS ID     estimate      estimate estimate
       1.1            20          25             36
c Estimates
              Performance Duration
              factor        Estimate
                        80%         125




 Estimates
              Current                       Duration
              variable      Multiplier      Estimate

              200 sq. ft.          1.25          12.5




t Estimates
                            Expected
              Weighting     Duration
              factor        Estimate
              (o+4m+p)/6               26

								
To top