					Month      PHASE       Iteration       Task Name                       Task Description
October
           INCEPTION
                       Iteration # 1
                                       Client Meeting                  Weekly meeting with clients
                                       Learning                        Papers on Architecture/Eclipse
                                       Client Meeting                  Weekly meeting with clients
                                       Use Cases                       Team will work on high level Use
                                       Client Meeting                  Weekly meeting with clients
                                       Learning                        Eclipse plug in architecture
                                       Artifact - Vision Document      Vision 1.0 version is out
                                       Use cases for the features      Requirement manager will lead
                                       Use case workshop               Project manager will coordinate to
                                       Client Meeting                  Weekly meeting with clients
                                       Scheduling a session for        Project manager will coordinate to
                                       Use case workshop follow up     Workshop held last week may
                                       Learning                        Eclipse plug in
                                       Client Meeting                  Weekly meeting with clients
November
                                       Artifact - Statement of Work    SOW version 0.9 will be out, to
                                       Paper Prototyping               Start working on making paper
                                       Detailed use cases              Team needs to make detailed
                                       Client Meeting                  Weekly meeting with clients
                                       Learning                        eclipse plug in architecture
                                       Paper Prototyping               finish making paper prototypes for
                                       Work on building the            Start coding for building a proof of
                                       Client Meeting                  Weekly meeting with clients

                                       Iteration assessment            Assess the iteration
                       Iteration # 2
                                       Work on SOW proposal            - draft the SOW
                                       Work on building the            Coding continues for building the
                                       User manual                     - come up with a structure
                                       Client Meeting                  Weekly meeting with clients
                                       Work on building the            Coding continues for building the
                                       work on User manual             - Use results from prototype for
                                       Client Meeting                  Weekly meeting with clients
December
                                       Work on building the proof of   Coding continues for building the
                                       proof of concept Demo           Prepare Demo for the experiment
                                       Client Meeting                  Weekly meeting with clients
                                       Artifact - SOW, Use case,       Prepare Final draft of SOW, Use
                                       Client Meeting                  Weekly meeting with clients
                                       Iteration assessment            Assess the iteration
                                       Semester end                    Access the findings for the

                                                                       Note:Development team will
December
           INCEPTION
                       Iteration # 3
                                       Make use case and paper         - Utilize the methodology that has
                                       Client Meeting                  Weekly meeting with clients
                                       Risk review meeting             - revisit the risks
                                       Make use case and paper         - Utilize the methodology that has
                                       Client Meeting                  Weekly meeting with clients
                                       Make use case and paper         - Utilize the methodology that has
            Client Meeting         Weekly meeting with clients
            Make user manual       - Follow the user manual structure
            Client Meeting         Weekly meeting with clients
            Iteration assessment   Assess the iteration
INCEPTION   Phase assessment       Assess the AUP phase -
Agenda                                 Duration Start Date   End Date      completion



- Work accomplished                    30 min   3-Oct-2007 3-Oct-2007          100%
                                       7 days   3-Oct-2007 7-Oct-2007          100%
- Work accomplished                    30 min   ######### 10-Oct-2007          100%
                                       7 days   ######### 17-Oct-2007          100.%
- Work accomplished                    60 min   ######### 17-Oct-2007          100%
                                       7 days   ######### 24-Oct-2007          100%
                                       7 days   ######### 24-Oct-2007          100%
                                       7 days   ######### 24-Oct-2007          100%
                                                during the week                100%
- Work accomplished                    60 min   ######### 24-Oct-2007          100%
                                                during the week                100%
                                       7 days   ######### 7-Nov-2007           100%
                                       7 days   ######### 31-Oct-2007          100%
- Work accomplished                    30 min   ######### 31-Oct-2007          100%

                                       7 days   #########     7-Nov-2007        100%
                                       7 days   #########     7-Nov-2007        100%
                                       60 min   #########     7-Nov-2007        100%
- Work accomplished                    30 min   #########     7-Nov-2007        100%
                                       60 min   ?            ?                    0%
                                       7 days   #########    ##########         100%
                                       7 days   #########    ##########          10%
- Work accomplished                    60 min   #########    ##########         100%

- Collect Metrics                      1 days   ######### ##########              0%

                                       7 days   #########    ##########           0%
                                       7 days   #########    ##########           0%
                                       7 days   #########    ##########           0%
- Work accomplished                    30 min   #########    ##########           0%
                                       7 days   #########    ##########           0%
                                       7 days   #########    ##########           0%
- Work accomplished                    30 min   #########    ##########           0%

                                       7 days   #########    ##########           0%
                                       7 days   #########    ##########           0%
- Work accomplished                    30 min   #########     5-Dec-2007          0%
                                       7 days   #########    ##########           0%
- Work accomplished                    30 min   #########    ##########           0%
- Collect Metrics                      1 days   #########    ##########           0%
- Check Status of Required Artifacts   1 days   #########    ##########           0%




                                       2 days   #########    15-Jan-2008          0%
- Work accomplished                    30 min   #########    16-Jan-2008          0%
                                       30 min   #########    18-Jan-2008          0%
                                       7 days   #########    23-Jan-2008          0%
- Work accomplished                    30 min   #########    23-Jan-2008          0%
                                       7 days   #########    29-Jan-2008          0%
- Work accomplished   30 min   #########    30-Jan-2008   0%
                      7 days   #########     5-Feb-2008   0%
- Work accomplished   30 min   6-Feb-2008    6-Feb-2008   0%
- Collect Metrics     1 day    8-Feb-2008    8-Feb-2008   0%
                      1 day    #########    11-Feb-2008   0%
Date changed to 26th




Iteration got moved

				