Joint Industry Electricity Steering Committee Information Request No. 1.18.0(a) Dated: 2 March 2004 BC Hydro Response issued 29 March 2004 British Columbia Hydro & Power Authority Revenue Requirements Application 2004/05 and 2005/06
Page 1
18.0
Reference:
Application, Page 10-5 to 10-8 BC Hydro has based the ROE in the application on the Terasen pre-tax ROE.
1.18.0(a) What was the fiscal period for the Terasen effective income tax rate used in the Application? RESPONSE: The Terasen Gas Inc. effective income tax rate used in the Application pertains to the year 2004, ending December 31, 2004.