					   Customer Based Generation

                              EPA OVERVIEW
The following is a summary only, and has no legal effect. Refer to the Standard EPA for a complete
                        understanding of the EPA terms and conditions.




                                 Customer Based Generation Workshop November 4, 2002                 1
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   2
                   Introduction
n   Thank you all for coming today, it is good to see such an
    overwhelming response to this program.
n   Customer Based Generation represents a very important step for
    BC Hydro in terms of resource acquisition.
n   We want to invite you to participate in today’s workshop by asking
    questions and providing feedback.
n   The structure for today is:
     n about 5 minutes for several burning questions directly after
       each speaker
     n then the remainder of the day for a question and answer session

n   We may not have all the answers
n   Look to this workshop to explain the EPA and move forward


                        Customer Based Generation Workshop November 4, 2002   3
Purpose of Today’s Workshop
n   Review the EPA in detail
n   All material presented today will be available on the
    web site
n   The workshop will be recorded and the Q&A will be
    transcribed, edited for clarity and accuracy with
    respect to the CFT and EPA and posted on the web
    site within 1-2 weeks




                    Customer Based Generation Workshop November 4, 2002   4
        Customer Options for
             Generation
n   Customer Based Generation Call
     n Competitive call with ceiling price

n   BC Hydro Power Smart
     n For self generation load displacement

     n Competitive incentive based

n   Green and Alternative Energy
     n Competitive call with ceiling price

n   Selling to Power Marketer
     n Competitive market based




                       Customer Based Generation Workshop November 4, 2002   5
    CBG Program Objectives
n   Purchase, from our customers, 800 GWh per year with
    Generation on line by 2005 November
n   Transparent process
n   Low transaction cost - standardized EPA
n   Ceiling price to reflect
     n our long term energy price

     n firm energy and associated risks

n   Firm energy and capacity supply to meet domestic load
    growth.



                      Customer Based Generation Workshop November 4, 2002   6
          Energy Acquisition Strategy
                      10000
                                                            (Illustrative)
  Load Growth - GWh    9000
                       8000
                       7000
                       6000
                       5000
                       4000
                       3000
                       2000
                       1000
                         0
                              03-04      04-05      05-06      06-07   07-08    08-09     09-10     10-11     11-12
                              Vanc. Is Generation Project                      New Green
                              Add'l Resource Smart                             Customer Based Generation
                              Energy Demand Growth                             Demand Growth less Planned Power Smart

CBG is a key component of our Energy Acquisition Strategy, which includes
Power Smart, Resource Smart, CBG and Green resources. Current targets (i.e
800 GWh for CBG) are illustrated above.
Factors such as energy and peak demand growth, results of current acquisition
programs will influence timing and size of future CBG/Green resource calls.
                                            Customer Based Generation Workshop November 4, 2002                         7
                     CBG Schedule
                                                                                      Award Purchase
     Qualification          Selection for Tender         Call For Tender
                                                                                        Agreement

Request for qualification
        Period


    RFQ Workshop                Review of                CFT Workshop                    Tender Due
       Jun 21                Submissions and                Nov 4                          Jan 15
                                Selection


                                                         Call For Tender
                                                                                     EPA due - June 6/03
                                                              Period


                                                                                     Tender Evaluation,
                                                                                       Selection and
                                                                                          Signing


May 31 to July 12           July 12 to Sep 6            Sep 6 to Jan 15              Jan 15 to Mar 4
                                                                                      to 2003 June 6



                               Customer Based Generation Workshop November 4, 2002                         8
                  RFQ Response
n   Target of 800 GWh                     8000
    per year
                                          7000

                                          6000




                          GWhs per year
n   Submissions                           5000
    totaling 6800 GWh                     4000
    per year                              3000

                                          2000

n   37 projects                           1000

                                             0

                                                 Target        Submissions




                    Customer Based Generation Workshop November 4, 2002      9
              Call For Tender
n   Target of 800 GWh                      3500
    per year
                                           3000

                                           2500




                           GWhs per year
n   Call for Tenders
                                           2000
    issued to
    proponents of 3100                     1500

    GWh per year                           1000

                                            500

                                              0

                                                  Target          Tenders




                     Customer Based Generation Workshop November 4, 2002    10
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   11
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   12
     CFT Stage: Confirmation
n   Must be Short-Listed at the RFQ Stage                                            Page 2

    Reassess:                                                                        Page 25, 27-31

    n   Customer Eligibility
    n   Project Eligibility
    n   Owner/Operator Experience
    n   Financial Capability
    n   Project Status


*Page numbers in this section reference the Revised CBG/CFT 2002 Call for Tenders Document


                               Customer Based Generation Workshop November 4, 2002              13
           Eligibility: Customer
Review Mandatory Requirements:
  n   Customer class, use for normal operations, period
      of service
  n   Customer involvement, proximity to customer
  n   New or incremental, proven technology
  n   Met the time lines:
       n   Tender submission: 4 PM, Jan. 15, 2003
       n   Target COD on or before: Nov. 1, 2005

                     Customer Based Generation Workshop November 4, 2002   14
     Eligibility: Owners/Operators
Project-Related Requirements:
Must Indicate                                                              Page 16, 25, 31

n   Changes in owner/operators
n   Changes in financial capability

n   If there are significant changes
    provide evidence there is no
    significant impact on ability
    to finance, develop and operate
    the project


                     Customer Based Generation Workshop November 4, 2002                     15
    Project/Seller’s Plant Description
n   Description of the Project                                                Page 32

n   Description of Seller’s Plant
n   Description of Energy Source for Seller’s Plant
n   List key facilities and equipment that will be
    installed or added to Seller’s Plant to complete
    the Project
n   Nameplate capacity for each electrical
    generator within the Seller’s Plant - existing or
    new


                        Customer Based Generation Workshop November 4, 2002             16
        Information Requirements
n   BC Hydro requires information in submission:
     n Declaration of customer involvement                                   Page 36
     n Material changes in project information                               Page 31
       from RFQ
     n Project specific adjustments                                          Page 28
     n Existing generating capacity and energy                               Page 11, 13
     n Electric one-line and steam flow diagram (if                          Page 11, 13
       applicable) for metering
n   Bidder may request information on CFT                                    Page 22
    process: direct all inquiries to BC Hydro
    Purchasing Manager
n   Q&As will be posted on the website

                       Customer Based Generation Workshop November 4, 2002                 17
         Contracted Capacity Table

Make no allowance for outages:                                               Page 26


n   Average Annual Capacity for each year of
    Contract Term (MWh/h)

n   Monthly Percentage of Average Annual
    Contracted Capacity (%)




                       Customer Based Generation Workshop November 4, 2002             18
      Contracted Capacity Selection
                                                                            Other Outages and
                                                                            Plant Operational
               100%
                90%
% Contracted




                80%                                                         Non-Winter Month
  Capacity



                70%                                                         Planned Outage
                60%                           90%
                50%
                        80%
                40%                                                         Transmission
                30%                                                         Constrained
                20%
                10%                                                         Force Majeure
                 0%
                      Average             Average
                       Annual             Monthly
                      Capacity            Capacity                          Hardship Hours

         Minimum % deliveries apply to yellow bars only
          Some ability to mitigate using 110% capacity
                          Customer Based Generation Workshop November 4, 2002                   19
                         Tenders
n   Tender Security submitted with Bid:
    n   $10,000/MW of Contracted Capacity with $5,000                         Page 28
        minimum
n   Will Reject all Tenders containing material                               Page 21
    amendments, modifications or conditions to Tender
    Forms or EPA or do not conform
n   Bid Price envelopes of rejected, non-conforming                           Page 16
    bids will be returned unopened
n   Tenders may not be withdrawn or amended from                              Page 21, 30
    Tender Closing Time to 4 PM, June 30, 2003

                        Customer Based Generation Workshop November 4, 2002             20
               Potential Tender
               Disqualification
Reasons Tenders may be disqualified include:
n Late submission of information                                             Page 6, 12, 13
n Tender submission with non-material                                        Page 21
  amendments, modifications or conditions
n Incomplete or unsigned Tenders                                             Page 8, 12, 13,
                                                                             26, 30
n   No or insufficient Tender Security              Page 28
n   Discrepancy in Green qualification, adjustments Page 12, 13, 15,
    or Generator Baseline between Tender and        20, 25, 26, 41
    those provided by BC Hydro


                       Customer Based Generation Workshop November 4, 2002                     21
                Tender Security
n   In form of cash, bank draft, certified cheque or                            Page 8, 28
    letter of credit
n   Forfeited if bidder is successful and fails to                              Page 8
    execute and deliver EPA
n   Returned if bidder:
    n   Executes and delivers EPA and development                               Page 8
        security
    n   Bid is unsuccessful and no EPA is awarded                               Page 6




                          Customer Based Generation Workshop November 4, 2002                22
    Other Tender Requirements
n   Contracted Capacity Information                                            Page 33, 34
n   Confirmation of Customer Involvement                                       Page 16
n   Adjusted Bid Price: must be less than the ceiling                          Page 17, 18
    price
n   Agree to Adhere to BC Hydro’s Code of Conduct                              Page 20, 27
    Guidelines Applicable to 2002 CBG Call for
    Tenders




                         Customer Based Generation Workshop November 4, 2002                 23
             Tender Selection
n   Tender must be signed by a person who                                 Page 7, 8,
                                                                          30
    has authority to bind
n   Once through Part I, EPAs will be                                     Page 27-29,
                                                                          38
    awarded based on lowest Bid Price
    adjusted for ranking purposes


n   Selection of successful Tenders will be                               Page 6

    March 4, 2003



                    Customer Based Generation Workshop November 4, 2002                 24
                                 EPA Options
n   Can bid flat, increasing or decreasing Contracted Capacity                                Page 9, 26
    over contract term :
                       30
                       25
                       20
            MWh/hour




                       15
                       10
                        5
                        0
                Year        1      2    3    4      5    6      7     8     9    10
                                Increasing       Decreasing         Recall 1       Recall 2

n   One time, irrevocable option to recall 20% of Contracted                                  Page 9, 11, 26
    Capacity - price reduction of $2.00/MWh adjusted by 50%
    of CPI on subsequent deliveries to BC Hydro

                                        Customer Based Generation Workshop November 4, 2002                25
                        EPA Price
Price paid by BC Hydro:
n   Bid Price with adjustments for:
    n   Delivery time
    n   Non-compliance with the Green Criteria (if applicable)
    n   Recall option (if exercised) and
    n   Inflation


    Pages 7, 9-11, 13-14, 18-21, 28-29, 38, 120



                          Customer Based Generation Workshop November 4, 2002   26
                      EPA Signing
n   EPA Awards will be made March 4, 2003                                        Page 6
n   If EPA unsigned by expiration date (June 6, 2003), Page 19
    BCH may offer EPA:
    n   To successful bidders with unbid capacity
    n   To unsuccessful bidders:
         n   In each case starting with lowest cost Tender
         n   Tenders must be less than the ceiling price
         n   Bidder may accept or reject the offer
n   If project is terminated on or before end of Initial                         Page 19
    Period, BCH may offer EPA as above


                           Customer Based Generation Workshop November 4, 2002             27
         CFT Pricing Examples and
         EPA Terms & Conditions
To be addressed by subsequent speakers:
n   Pricing Examples: qualifying vs non-qualifying bid prices,
    ranking
n   Specific Terms & Conditions of the EPA including:
    n   Development and Operating Security
    n   LDs
    n   Delivery priorities
    n   Metering



                         Customer Based Generation Workshop November 4, 2002   28
    Other Calls for Proposals
n   Bidders may also submit the same project to the                          Page 21
    October Green RFQ if they meet qualifying
    criteria


n   If awarded an EPA under the CBG Tender                                   Page 21
    process, same project to the Green Call will be
    automatically withdrawn by BC Hydro and
    Green Call Tender Security Refunded




                       Customer Based Generation Workshop November 4, 2002             29
         Electricity Supply
Future Electricity Supply:
n BC Hydro increasingly dependent on independent
  generators for capacity and firm energy
n BC Hydro bears market risk if non delivery

n BC Hydro has a continuing obligation to serve

n Therefore contracted energy must deliver be delivered




                  Customer Based Generation Workshop November 4, 2002   30
 Objectives of the CBG EPA
Objectives of the EPA for the CBG Program:
n Move towards more commercial terms

n Ensure a degree of reliability while allowing for
  events beyond the Seller’s control:
   n Force Majeure Provisions

   n Hardship and Hydrology Limitation Provisions

   n Recall Option

   n 80% / 90% Capacity Factor Provisions




                   Customer Based Generation Workshop November 4, 2002   31
            EPA Flexibility
Provide flexibility for the Seller:
n Split Bid

n Flat, Increasing or Decreasing Capacity Profile by
  year and a monthly profile
n Recall Option

n 10 - 20 Year Contract Term

n Green or Non-Green




                  Customer Based Generation Workshop November 4, 2002   32
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   33
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   34
              EPA Introduction
n   Move towards a more commercial contract
         n Tender Process

         n Delivery commitment and risk sharing in the form of:

             n Liquidated Damages for non-delivery

             n 90% and 80% month/annual “thresholds”

             n Economic Hardship recognition

             n Force Majeure recognition

n   A longer, more complex document
         n Standard form for all projects

             n reduced transaction costs

         n Options / Flexibility

             n capacity profile

             n recall option

             n ability to sell to multiple Buyers

             n Green or not Green

                          Customer Based Generation Workshop November 4, 2002   35
              EPA Schedule
Issue CFT                                                   September 06, 2002
Issue EPA                                                   October 4, 2002
Bidders apply for Interconnection                           October 18, 2002
Bidders Meeting                                             November 04, 2002
Bidders submit Green Evidence                               December 02, 2002
BCH provides Green/GHG/GBL Info                             December, 17, 2002
BCH provides Interconnection Estimate
   and Area Locations Adjustments                           December 17, 2002
Bidders submit Tender                                       January 15, 2003
BC Hydro announces successful Tenders                       March 04, 2003
Bidders return signed EPA                                   June 06, 2003

                   Customer Based Generation Workshop November 4, 2002           36
              Term / Quantity
Parties:    BC Hydro as Buyer
            Customer or IPP as Seller
Term:       10 to 20 years from COD (Appendix 5), as bid by
            Seller
            Target COD not subject to change for any reason
Quantity:   Contracted Capacity (CC), which may be:
            n Fixed for term

            n Variable over term, but minimum CC must be not less
              than 50% of maximum CC
            n Entire project capacity (Cp)

            n Part only, with balance committed to a self generation
              hosting facility or third party purchase (Split Bid)

                       Customer Based Generation Workshop November 4, 2002   37
                 Quantity cont’d
Recall Option:

n   Seller has one-time irrevocable option to reduce CC by 20%
n   365 days notice required
n   No Recall prior to COD
n   $2.00/MWh (adjusted by 50% of CPI) price reduction
    effective on Recall




                      Customer Based Generation Workshop November 4, 2002   38
    Definitions / Key Terms                                                     (Appendix 1)


n   Contracted Capacity (CC): The quantity of electricity the Seller
    commits to deliver on an hourly basis, as bid by the Seller

n   Eligible Electricty (EE): The quantity of electricity the Buyer is
    obliged to accept and pay for on an hourly basis– generally a
    maximum of 110% of CC

n   Metered Electrity (Mg): The quantity of eletricity metered at the
    generator




                          Customer Based Generation Workshop November 4, 2002              39
        Definitions / Key Terms
n   Generator Baseline (GBL): Existing plant capacity, if any,
    determined during tender period based on nameplate capacity
    and historical generation

n   Plant Capacity (PC): The total capacity of the generating plant
    (including existing GBL capacity and new capacity resulting from
    the project)

n   Project Capacity (CP): New or incremental capacity (I.E.
    excluding generator baseline)



                         Customer Based Generation Workshop November 4, 2002   40
                 Definitions cont’d
n   Initial Period: 180 days (extendible to 270 days) after EPA
    signing– time permitted for fulfillment of specified conditions
    subsequent

n   COD: Commercial Operation Date (as per Appendix 5)




                          Customer Based Generation Workshop November 4, 2002   41
                 Definitions cont’d
n   Force Majeure: Usual events of Force Majeure – beyond the
    control of parties (excluding Economic Hardship)

n   Hardship Event To be addressed later in the presentation




                         Customer Based Generation Workshop November 4, 2002   42
     Conditions Subsequent                                                     (Section 3)




n   Mutual right of termination for failure of conditions subsequent
    within Initial Period (180 days after Term commencement):
     n Permits

     n Land Tenure

     n Regulatory Exemption - not a “public utility”

     n Interconnection & Facilities Agreements (Seller may waive)

     n Financing (Seller may waive)

     n Seller confirms the above




                         Customer Based Generation Workshop November 4, 2002                 43
    Conditions Subsequent cont’d
                                    (Section 3)


n   Seller must use commercially reasonable efforts to satisfy the
    conditions
n   Initial Period - 90 day extension possible
n   Mutual right of termination for adverse regulatory intervention
    during initial period
n   Development security (Cash or L/C) refunded if, despite Seller’s
    reasonable commercial efforts, the EPA is terminated
n   If reasonable prospect of meeting conditions




                         Customer Based Generation Workshop November 4, 2002   44
           Delivery/Acceptance
n   From COD Seller obligated to deliver uninterrupted hourly
    Contracted Capacity (CC) subject to:
    n   Force Majeure
    n   Hardship event
    n   Transmission constraint
    n   Hydrology limitation (Hydro projects that elect inclusion of
        limitation only)




                         Customer Based Generation Workshop November 4, 2002   45
     Delivery/Acceptance cont'd
n   From COD Buyer must accept and pay for Eligible Electricity
    (EE) subject to:
     n Force Majeure

     n Transmission constraint, which cannot be relieved by
       Buyer’s reasonable management of demand, supply and
       transmission access rights
     n Disconnection of Seller’s Plant under the Interconnection
       Agreement
     n Suspension for Seller default (after cure period - 30 days)




                        Customer Based Generation Workshop November 4, 2002   46
              Delivery Priority
                      ("Split Bids" - Section 7.5)

n   e.g. An existing generator (with GBL) is expanded to service
    incremental loads (i.e. above GBL) through sales to BC Hydro
    under EPA and to electricity host and/or third party

n   If Seller cannot meet Contracted Capacity and other
    incremental loads with generation above GBL, then Seller
    must first meet Contracted Capacity, before serving such
    incremental loads, unless constraint is due to:




                       Customer Based Generation Workshop November 4, 2002   47
        Delivery Priority cont'd
    n   Outage (other than prohibited winter planned outage)
    n   Force Majeure
    n   Hardship Event
    n   Transmission constraint


n   In which case incremental loads must be served Pro Rata




                        Customer Based Generation Workshop November 4, 2002   48
            Force Majeure                                             Section 10



n   Usual events of Force Majeure
n   No relief for economic hardship or lack of availability of
    fuel/energy source, including natural hydrology limitations
    (although Hydro projects that elected to be subject to the
    Hydrology Adjustment will be allowed relief for Hydrology
    Limitations - see Appendix 10)




                        Customer Based Generation Workshop November 4, 2002        49
          Hardship Clause                                                     (Section 11)



Hardship Event is defined as:
n   Change in law or policy - Federal, Provincial, Local
n   Fuel shortage or price increase
n   Co-generation host shutdown
n   Electricity host shutdown
    All predicated on the fact that the event is out of the Seller’s control, he has
    acted prudently to mitigate and it has a material adverse economic effect on
    the long-term viability of the operation of the Seller’s Plant.




                             Customer Based Generation Workshop November 4, 2002             50
       Fuel Shortage or Price
              Increase
If the Project includes thermal generation:
n A lack of availability of the Energy Source due to diminished
   supply
n Or an increase in the delivered cost to the Seller of the Energy
   Source
n Including an increase in such delivered cost resulting from an
   inability of the Seller to contract for secure supply of the Energy
   Source over a reasonable term due to a deterioration in the
   creditworthiness of the Seller and/or the Guarantor



                       Customer Based Generation Workshop November 4, 2002   51
Delivery Requirements                                                     (Appendix 4)


Liquidated Damages apply if Seller fails to meet:
n GHG Intensity Factor - fixed target

n Monthly Capacity Factor >90% of CC

   n Excluding Force Majeure hours

   n Excluding Transmission Constraint hours

   n Excluding Planned Outages (non-winter months)

n If Hardship Event relief is in effect, the CC is reduced
  proportionately
n Monthly Capacity Factor LD’s are based on the month’s
  average non-firm hourly weighted Mid-C price and the CFT
  Adjusted Bid Price

                    Customer Based Generation Workshop November 4, 2002                  52
Delivery Requirements cont’d
n   Annual Capacity Factor > 80 % of CCP
     n Excluding Force Majeure hours

     n Excluding Transmission Constraint hours

n   If Hardship Event relief is in effect, the CC is reduced
    proportionately
n   No “double-counting” - i.e. monthly LDs paid are
    deducted from any annual LDs payable
n   LD’s are based on the average of the average monthly at
    Mid-C and the CFT Adjusted Bid Price (Appendix 4 &
    Section 3)

                      Customer Based Generation Workshop November 4, 2002   53
         Security                (Section 13 and Appendices 6 and 7)


n   Development Security: Cash or L/C ($20,000/MW of maximum
    average annual CC) to secure construction of plant

n   Operating Security: Cash, L/C or creditworthy
    covenant/guaranty (determined at COD, and at each
    anniversary, as $2,000/MW of average annual CC times
    number of years remaining in term) to secure operating
    performance

n   One time test at EPA signing for creditworthiness of Seller or
    Guarantor


                        Customer Based Generation Workshop November 4, 2002   54
               Termination                                       (Section 15)

n   Buyer may terminate for:
     n Failure to commence construction by target COD

     n Delay in COD by 365 days, extendible to 730 day for Force
       Majeure
     n Seller becoming regulated as a "Public Utility" with material
       adverse effect on Buyer
     n Prolonged Seller Force Majeure (365 days)

     n Prolonged Hardship Event (730 days) or

     n Seller defaults (with cure period)

n   Seller Liable for:
     n Seller liable for "Mark to Market" termination payment if

       Buyer terminates for delay in commencement of construction
       or in COD or for Seller default
                         Customer Based Generation Workshop November 4, 2002    55
             Termination                                       (Section 15)




n   Seller may terminate for:
     n Prolonged Buyer Force Majeure (365 days), or

     n Buyer default (with cure period)



n   Buyer liable for "Mark to Market" termination payment if
    Seller terminates for Buyer default




                       Customer Based Generation Workshop November 4, 2002    56
                Other Terms
Other terms and conditions reflecting CBG program (most are
normal for long-term Electricity Purchase Agreements) including
those pertaining to:

    n 5 year minimum customer involvement
    n Determination of COD

    n Operating standards

    n Reporting / scheduling

    n Restriction in planned winter maintenance

    n Metering


                     Customer Based Generation Workshop November 4, 2002   57
           Other Terms cont'd

n   Payment terms
n   Insurance
n   Assignment
n   Confidentiality and
n   Law and dispute resolutions




                      Customer Based Generation Workshop November 4, 2002   58
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   59
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   60
 Type and Operating Condition

                          n    Separate Generator
                          n    Existing Generator - upgraded
   Type of plant          n    All output to BC Hydro
    Split or not          n    Output to BC Hydro and others


                          n    Normal
                          n    Hardship
                          n    Force Majeure
Operating condition       n    Outage: Forced, Maintenance, Planned
                          n    Voluntary Turndown
                          n    Increased Steam Use by host coupled with
                               decreased Electricity Generation



                   Customer Based Generation Workshop November 4, 2002    61
                No Existing Generation
                                     Example No. 1
            Seller’s Plant   110 % = 44 MW
                                                               Maximum of 40 MW + 10% = 44 MW

                                                       Cp = PC = CC = 40 MW
                             90 % = 36 MW

                                            Project Capacity = Plant Capacity = Contracted Capacity




 Project
Capacity        40 MW                    For 0 < Metered Generation (Mg ) <= 40 MW
(Cp) = 40

                                                         Eligible Electricity is Mg




                             Customer Based Generation Workshop November 4, 2002                 62
                   Existing Generation
                  Example No. 2        All output sold to BC Hydro

           Seller’s Plant   110 % = 25.5 MW
                                                            Maximum of 5 MW + 10% = 5.5 MW

                                                      PC = 25 MW
                            90 % = 24.5 MW           Cp = CC = 5MW
                                                             For (Mg - 20) <= 5.5 MW
 Project
Capacity       5 MW                                                                 Eligible
(Cp) = 5                                                                          Electricity is
                                                                                     Mg - 20

                                                       GBL = 20 MW




              20 MW
                            Existing Generation
              Existing      cannot be sold under
             Generation       the CBG - EPA


                            Customer Based Generation Workshop November 4, 2002                    63
                      Existing Generation
                              Example No. 3            Split Bid Project

           Seller’s Plant                                         Maximum of 3 MW + 10% = 3.3 MW

                                                              PC = 25 MW
             110 % = 3.3 MW
                                                              CC = 3 MW
 Project     90 % = 2.7 MW
Capacity                                                                   For ( Mg - 20) <= 3.3
(Cp) = 5
                3 MW                                                       Eligible Electricity is Mg - 20


                                                              GBL = 20 MW




               20 MW
                                  Existing Generation
              Existing            cannot be sold under
             Generation             the CBG - EPA


                                  Customer Based Generation Workshop November 4, 2002                        64
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   65
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   66
            EPA Price and Examples
This Presentation will Cover the Following:
n   CFT Adjusted Bid Price
      n   Ceiling Price
      n   Adjustments for Ranking

n   Price Paid to Seller for Electricity
        n   Inflation Indexing
        n   Adjustments

n   Illustrative Examples
        n   Pricing
        n   Liquidated Damages
                        Customer Based Generation Workshop November 4, 2002   67
                Pricing Overview
Two Price Related Concepts:

i)   CFT Adjusted Bid Price

        n   Used to comparatively assess bids

        n   Adjustments applied to rank bids (do not effect price
            paid if successful bidder)

ii) Price Paid for Eligible Electricity

        n   Bid Price identified on Tender

        n   Some adjustments are applicable

                      Customer Based Generation Workshop November 4, 2002   68
         Bid Price Ranking Adjustments

                                                                                                                             Green = Less $ 5.00
Seller's Bid Price                                                                                      Green
                     Hydrology Adjustment              GHG Intensity
   (From CFT)                                                                                         Adjustment
                                                                                                                          Not Green = No Adjustment



                     Applicable = Add $ 3.50
                                                   Reduce Bid Price By Up                            Area Location           Depends on Generator
                      Not Applicable = No                To $ 3.00                                    Adjustment       Interconnection Preliminary Study
                          Adjustment




                                                                             Location Adjustments
                                                                                                       System                Depends on Generator
                                                                                                      Adjustment       Interconnection Preliminary Study




                                                                                                                       Per Location Adjustment Tables in
                                                                                                     Bulk Location
                                                                                                                                     CFT
                                                                                                      Adjustment
                                                                                                                               (Pages 17 & 18)




                                                                                                    CFT Adjusted Bid
                                                                                                         Price




                                               Customer Based Generation Workshop November 4, 2002                                                         69
                      Ceiling Price
n   CFT Adjusted Bid Price is then compared to Ceiling
    Price of $55 per MWh (2003 CAD)
        n   If greater than Ceiling Price Bid is rejected
n   The Ceiling Price is based on BC Hydro’s long-term
    electricity price forecast for firm energy
n   Methodology for developing this price forecast has been
    posted to the CBG website
n   2005 to 2020 natural gas price at Sumas is forecast at
    about USD$3.00 per MMBtu




                         Customer Based Generation Workshop November 4, 2002   70
                            CGG Pricing Example: CFT Bid Price Adjustments

                                                     Proponent 1              Proponent 2          Proponent 3

Location                                                     Tofino              Kamloops            Squamish
Green Criteria Qualified & Elected Green?                       Yes                       No               Yes
GHG Intensity Offsets Qualified?                 Yes, at 3 $/MWh          Yes, at 1 $/MWh       Yes, at 3 $/MWh
Bid Price                                                  $ 60.00                  $ 50.00            $ 64.00


Adjustments:
 Hydrology                                                 + $ 3.50
 GHG Intensity                                             - $ 3.00                 - $ 1.00            - $ 3.00
 Green Criteria                                            - $ 5.00                                     - $ 5.00
 Area Location                                             - $ 1.80                 + $ 3.50           + $ 0.50
 System                                                                                                + $ 1.00
 Bulk Location                                             - $ 0.50                 + $ 2.40
CFT Adjusted Bid Price                                     $ 53.20                  $ 54.90            $ 57.50
Ranked Price < Ceiling Price                                    Yes                       Yes               No
Ranking                                                        First                Second            Rejected




                                    Customer Based Generation Workshop November 4, 2002                            71
      Payment Price Adjustments
n   Price paid to seller is the Bid Price adjusted for:
        n Price inflation at 50% of CPI


        n Delivery Time (Per Schedule on Page 10 of CFT)


     n And if applicable:

        n Green Criteria non-performance


        n Recall adjustment




                    Customer Based Generation Workshop November 4, 2002   72
   Price Paid to Seller
                     Seller's Bid Price
                       (From CFT)




                                                 Yes = Less $ 2.00
                    Recall Adjustment
                        Amount
                                                No = No Adjustment
  Inflation
Adjustment
 (1/2 CPI)
                                                 Yes = Less $ 5.00
                      Failure to Meet
                      Green Criteria
                                                No = No Adjustment



                      Delivery Time           Delivery Time Adjustment
                       (Month and              Schedule in Appendix 3
                        HLH/LLH)                     Section 3.3




                       Price Paid to
                           Seller




              Customer Based Generation Workshop November 4, 2002        73
                               CGG Pricing Example: Post COD Payment Adjustments

                                                                                       Proponent 1            Proponent 2

Location                                                                                         Tofino          Kamloops
Failure to Meet Specified Green Criteria                                                           Yes                 No
Proponent Exercised Recall Option                                                                   No                 Yes
Bid Price                                                                                   $ 60.00               $ 50.00


Green Criteria Non-Performance Adjustment                                                    -$ 5.00
Recall Option Adjustment                                                                                           -$ 2.00

Adjusted Bid Price Prior to Delivery Time Adjustment                                        $ 55.00               $ 48.00


Project Generation Profile                                                                  Variable      Flat Annual Block


                                                                               First Year Payment Price (CAD Per MWh)


                                                  January    HLH     117%                        64.35               56.16
                                                             LLH      98%                        53.90               47.04
                                                             …


                                                                      …




                                                                                                    …




                                                                                                                       …
                                               December      HLH     116%                        63.80               55.68
                                                             LLH     93%                         51.15               44.64

Effective Price Received                                                                    $ 53.50               $ 48.00



                                           Customer Based Generation Workshop November 4, 2002                                74
            Liquidated Damages

n   Three types of Liquidated Damages described in
    EPA:
     n   Annual GHG Intensity LDs
     n   Monthly Capacity Factor LDs
     n   Annual Capacity Factor LDs
n   Examples of Annual GHG Intensity LDs and
    Monthly Capacity Factor LDs follow



                   Customer Based Generation Workshop November 4, 2002   75
                    GHG Intensity LDs
                                                     Units


     [A]   Annual Eligible Electricity               MWh                                 160,000


     [B]   Actual GHG Intensity              MT CO e Per MWh
                                                  2                                         0.29
     [C]   Target GHG Intensity                         "                                   0.18
     [D]   Difference                                   "                    [B] - [C]      0.11


     [E]   GHG Intensity Factor                 CAD Per MWh                                 1.50




n   GHG Intensity LDs are [A] times the lesser of $8.33 times [D] or
    [E]
n   In this case the LDs are calculated to be $0.92 per MWh, and
    $147,200 for the year
                                  Customer Based Generation Workshop November 4, 2002              76
                           CBG Example: Monthly Capacity Factor Liquidated Damages


1. Calculating Amount of Electricity


 [A]    Monthly Contracted Capacity                                                                MW        40.0
 [B]    Hours in Month                                                                             Hours    720.0
 [C]    Force Majeure Hours in Month                                                               Hours     24.0
 [D]    Transmission Constraint Hours in Month                                                     Hours      1.0
 [E]    Planned Outage Hours in Month (non-winter only)                                            Hours     24.0

 [F]    Monthly Contracted Electricity                            A x (B - C - D - E)              MWh     26,840
 [G]    Times 90% Tolerance                                                                                  90%

 [H]    Adjusted Monthly Contracted Electricity                         (F X G)                            24,156
  [I]   Actual Monthly Delivered Energy                                                            MWh     21,600

 [J]    Difference                                                       (H - I)                   MWh      2,556




                                             Customer Based Generation Workshop November 4, 2002               77
                      CBG Example: Monthly Capacity Factor Liquidated Damages cont.

2. Calculating "LD Factor" and Liquidated Damages


 [K]   Hourly Weighted Mid-C Index Price                                                   USD Per   MWh           45.00
 [L]   Wheeling Rate Mid-C to BC                                                           USD Per   MWh            3.58
 [M]   Transmission Losses Mid-C to BC                                                          %                   1.9%
 [N]   Ancillary Services Mid-C to BC                                                      USD Per   MWh             -
 [O]   Other Transmission Charges Mid-C to BC                                              USD Per   MWh             -
 [P]   Average Monthly Bank of Canada Exchange "noon rates"                                CAD Per USD              1.55

 [Q]   Delivery Adjusted Index Price                           (K + L + N + O) x P         CAD Per MWh     $       76.76
                                                                      (1 - M)


 [R]   CFT Adjusted Bid Price                                                              CAD Per MWh             48.00

 [S]   Liquidated Damages Factor                                  Max (0, Q - R)           CAD Per MWh             28.76
 [J]   Difference                                                                                MWh               2,556


 [T]   Monthly Capacity Factor Liquidated Damages                     (S x J)                    CAD             73,504



       Note: Revenues for Energy Delivered in Month                                              CAD           1,036,800




                                           Customer Based Generation Workshop November 4, 2002                        78
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   79
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   80
              Green Overview

n   Green in EPA
n   Green and GHG timeline
n   Submission requirements
n   Replies on Green Elements
n   Link with next Green call
n   Questions




                     Customer Based Generation Workshop November 4, 2002   81
              Green In The EPA
                    (Section 7.10, 7.12 and Appendix 11)


n   All off-site emission reduction rights are property of BC Hydro
n   All on-site emission reduction rights are property of Seller
n   All Green rights are property of Seller, and may be transferred to
    BC Hydro (Section 7.12)
n   GHG LDs apply for failure to achieve GHG intensity target




                          Customer Based Generation Workshop November 4, 2002   82
      Green In The EPA (cont’d)
                             (Appendix 11)



n   Applies to projects that elect to be Green
n   Includes Green Criteria - low impact and socially
    responsible
n   Outlines alternative dispute resolution process
n   Defines construction environmental management plan
    and operations environmental management system




                     Customer Based Generation Workshop November 4, 2002   83
                       Green Timeline
                                          Sept 6 - Jan 15


      Sept 6 - Green Info
          Provided


               Dec 2 - Bidders Prepare and
                  Submit Green & GHG


                               BCH responds to Bidders
                               regarding Green - Dec 17



                                                       Jan15 - Deadline for Bid




Post EPA Period: Remaining Green evidence received and evaluated
                    under EPA contract terms.


                               Customer Based Generation Workshop November 4, 2002   84
     Green Mandatory Submission
            Requirements
Customer must provide:
   n A description of the facility

   n A commitment to meet the Criteria (low impact & social)

   n A confirmation of the Project type (by technology)

   n A confirmation of the New project




                      Customer Based Generation Workshop November 4, 2002   85
      New Project Confirmation

New Project is defined as:
n Began generating electricity on or after April 2001

n Repowered on or after April 2001

n Separable improvement or separable enhancement to an
  existing facility - construction of improvement or
  enhancement on or after April 2001
       n contractually available and metered separately

         (energy or steam)




                    Customer Based Generation Workshop November 4, 2002   86
Project Type Requirements-Biomass

n   Biomass - woodwaste, agricultural by-products, dedicated
    energy crops or liquid fuels as described in CBG Green
    Criteria
n   Describe of the contents and source of the fuel
n   Typically <=3% fossil fuel usage




                      Customer Based Generation Workshop November 4, 2002   87
Project Type Requirements- Hydro

n   Maintenance of the upstream ecosystem
n   Expert confirmation the projects meets one of the defined
    types:
     n Run of river - less than 24 hours

     n No existing generation, natural storage used

     n No existing generation, existing storage




                       Customer Based Generation Workshop November 4, 2002   88
            Green EPA Submission
                Requirements
n   Customer to provide as much evidence as possible for these
    requirements
n   Expert confirmation required as noted
     n Reputable scientist, professional engineer, hydrologist,
       agricultural specialist or other
n   Provide as many studies as possible
n   All evidence must be provided by the end of the Initial Period
    for Green confirmation




                        Customer Based Generation Workshop November 4, 2002   89
         Responses from BC Hydro

Assessment of:
   n Facility description

   n GHG intensity factor and GHG adjustment

   n Newness of project

   n Qualification for the CBG Green adjustment

      n High likelihood - adjustment confirmed


      n Maybe with additional evidence - adjustment non

        confirmed but can be applied if chosen by customer
      n No based on evidence submitted - adjustment does not

        apply

                       Customer Based Generation Workshop November 4, 2002   90
Green Power Generation Call RFQ

n   RFQ for Green Power Generation (GPG) was issued October
    30, 2002
n   Separate call with different rules
n   CBG projects can be submitted to the Green call
n   Once a project is offered a contract in one process it is
    automatically removed from the other




                      Customer Based Generation Workshop November 4, 2002   91
     GHG Intensity Adjustment

n   Bid prices to be adjusted for evaluation purposes only
n   Sliding scale relative to a combined cycle gas turbine
n   Adjustment in (C$/MWh) = greater of
    n   zero or
    n   (3.00 - 8.333 * Project GHG Intensity)




                         Customer Based Generation Workshop November 4, 2002   92
    Calculating Project GHG
            Intensity
1. Start with total annual fuel input.
2. If plant cogenerates electricity and steam, estimate annual fuel
   input attributable to electricity production.
    n difference between total fuel input and the fuel input that

       would be required for equivalent volume of steam in a non-
       cogen configuration
3. Calculate annual GHG associated with fuel input attributable to
   electricity production, in tonnes CO2e.
    n GHGs include CO2, CH4 and N2O

    n use Environment Canada emission factors

       http://www.ec.gc.ca/pdb/ghg/ghg_docs/Emission_Factors.pdf
                        Customer Based Generation Workshop November 4, 2002   93
       Calculating Project GHG
            Intensity cont’d
   n   if you need to convert between units, provide assumptions and
       references
        n   conversion factors available in Annex B of
            www.nrcan.gc.ca/es/ceo/outlook.pdf
   n  note that biomass is CO2 neutral for GHG accounting
      purposes
    n convert CH4 and N 2O to CO2e using Global Warming

      Potential factors provided
4. Estimate total annual electricity production, whether consumed
   onsite or sold to BC Hydro or others, in MWh
5. Calculate Project GHG Intensity, in tonnes CO2e/MWh

                              Customer Based Generation Workshop November 4, 2002   94
2002 CBG Greenhouse Gas Intensity Adjustment Form
BC Hydro Customer-Based Generation Program – 2002

Applicant Information

Project Name: Example
Contact Name for this Form:                                                Company Name:
Phone:                                                                     Address:
Fax:                                                                       City:
E-mail:                                                                    Province:
                                                                           Postal Code:
           (a)          Brief Description of the Project and Fuel Use

Hypothetical 40 MW gas-fired cogeneration facility



Project GHG Intensity Calculation

Fuel type(s) (if more than one, include percentages): Natural gas
Total annual fuel input, by fuel: 2.5 million GJ                                                   Units: GJ
                                                                                                                          3
If a cogeneration plant, annual fuel input attributable to                                         Units: GJ and m
                                                                                           3
electricity production, by fuel: 1.8 million GJ = 48 million m                                 @
                 3
37.23 MJ/m         (from Canada’s Emission Outlook: An Update,
December 1999, page B-3)
                                                                                                                 3
Emission factors, by                     CO 2 :                1,880                               Units: g/m
fuel:
                                                                                                                 3
                                         CH 4 :                0.048                               Units: g/m
                                                                                                                 3
                                         N 2 0:                         0.02                       Units: g/m
Annual emissions:                                    Tonnes             Global Warming                     Tonnes CO          2   e
                                                                            Potential
                                                                             Factors
                                        CO      2:   90,240                     x1                              90,240
                                         CH     4:       2                         x 21                              42
                                         N 2 0:          1                         x 310                          310
                                        Total            --                          --                         90,592
Total annual electricity production: 300,000                                                       MWh
Project GHG intensity (PGI): 0.302                                                                 Tonnes CO2e/MWh
           (b)         GHG Intensity Adjustment (round to whole cents)
3.00 – 8.333 * PGI = 0.42                                        $/MWh
Greater of zero or above value = 0.42                               $/MWh


                                   Customer Based Generation Workshop November 4, 2002                                                95
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   96
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   97
           Interconnections
n   Interconnection Application
n   Interconnection Process and Study Objective
n   Study Components and Costs
n   Preliminary Study Deliverables
n   Revenue Metering




                  Customer Based Generation Workshop November 4, 2002   98
    Interconnection Application
n   All proponents were required to submit a Preliminary
    Interconnection Application Form to the Office of Generator
    Interconnections
n   Bidders will be provided with reliable cost interconnection cost
    estimate and consistently calculated interconnection related
    adjustments for bid comparison
n   16 applications received by 18 October 2002 deadline
n   17 December 2002: Delivery of Interconnection Cost Estimate and
    Area Transmission Location Adjustments




                         Customer Based Generation Workshop November 4, 2002   99
BC Hydro’s Generator Interconnection Process
CBG Preliminary                                                 18 Oct 2002 to 17 Dec 2002
Interconnection
  Application



                                                                                  Preliminary
Customer Inquiry                                                                   Study and
 and/or Initial                                                                       ALA
    Meeting


Interconnection     Interconnection        $10k - $25k Cost
  Application        Impact Study           8 to 15 weeks

                                                                                                Total Process Timeframe
                                                                                                Typically 12 to 24 Months

                       Project                 Interconnection       $10k - $40k Cost
                   Interconnection             Facilities Study       8 to 15 weeks
                    Requirements


                                                                          Construction of          Typical:
                                                   Facilities             Interconnection         >$100k Cost
                                                  Agreement                  Facilities



                   Interconnection                                                                    Commissioning
                     Agreement                                                                              and
                                                                                                      Interconnection




                                     Customer Based Generation Workshop November 4, 2002                                    100
      Interconnection Objective
n   Interconnection is more than specifying the equipment
    at the physical point of interconnection
n   Interconnection study determines what is required to
    ensure the BCH transmission system reliability is
    maintained after interconnection (“protection and
    control”)
n   Cost estimate will be guaranteed to not exceed 130% of
    the estimate (NEW!!)


                      Customer Based Generation Workshop November 4, 2002   101
                Study Components
n   Several inter-related planning depts involved
    n   Area Planning - acceptability, islanding issues
    n   Network Planning - stability impacts
    n   Station Planning - station capacity
    n   Protection Planning - protection and control requirements
    n   Telecontrol Planning - communication needed for protection to work
    n   Project Management review - completeness of scope
n   Largest variable in interconnection cost is due to
    protection requirements - not correlated to generation
    project size

                             Customer Based Generation Workshop November 4, 2002   102
                   Study Costs
n   A standard cost approach was used to prepare estimate
     n 8 week time period does not allow time to estimate

       individual study requirements
     n $15 K for projects impacting transmission system

     n $3-5 K for projects on distribution system

n   Unique circumstances are being reviewed
n   Upon completion, we will review overall study costs and
    provide refunds if standard cost estimate was too high


                      Customer Based Generation Workshop November 4, 2002   103
                  Deliverables
Preliminary Interconnection Study Deliverables:
n Interconnection cost estimate

n Adjustments for bid comparison

   n Bulk Location Adjustment ( i.e. transmission capacity

     impact)
   n Area Location Adjustment ( i.e. line loss impact)

   n System Upgrade Adjustment ( i.e. impact of costs borne by

     BCH)
n Bidders project must comply with BCH Interconnection
  Requirements regarding equipment on their side of the POI


                      Customer Based Generation Workshop November 4, 2002   104
               Revenue Metering
n   Costs of revenue metering is not included in estimate:
    n   Revenue Metering is required per Section 7.11 of EPA
    n   Revenue metering is not required for interconnection
    n   Will vary depending on project configuration
    n   Largest cost is Voltage Transformers and Current
        Transformers
n   Provision of revenue meters and equipment by BCH can be
    added to Facilities Agreement scope

                        Customer Based Generation Workshop November 4, 2002   105
   Revenue Metering
Approximate Costs                                                    (Section 7.11a)


138 kV VTs and CTs                                         $70 K
25 kV Meter Kit                                            $30 K
25 kV VTs and CTs                                          $25 K
600 V VTs and CTs                                          $15 k
Load Profile Meter                                         $6 k




               Customer Based Generation Workshop November 4, 2002                     106
QUESTIONS?




Customer Based Generation Workshop November 4, 2002   107
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   108
                             AGENDA
         Topic                                             Presenter
n   Introduction & Welcome                                Bev Van Ruyven

n   CFT Process Selection                                 Terry McCullough

n   Break

n   EPA Terms & Conditions                                Myran Wallace

n   Eligible Electricity Examples                         Al Boldt

n   Lunch

n   EPA Price & Examples                                  Greg Simmons

n   Green Criteria & GHG Estimating                       Jim Scouras

n   Interconnection Process/Issues                        Ken Miyazaki

n   Break

n   Q&A                                                   Panel

n   Closing Remarks                                       Bob Elton

                                    Customer Based Generation Workshop November 4, 2002   109