Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
• Lower Whatshan River Fish Habitat Enhancement Physical and Biological Effectiveness Monitoring • Reservoir Vegetation Monitoring • Reservoir Wildlife Monitoring • First Nations Heritage and Archaeology Monitoring • Habitat Complexing Assessment and Enhancement Structures • Inonoaklin Recreation Site Boat Launch Extension For Water Licences 120711 and 120712
31 July 2006
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
BC Hydro Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
1 Introduction
This document represents a summary of the status and the results of the Whatshan Water Use Plan (WUP) monitoring programs and physical works to 31 May 2006, as per the Whatshan Order under the Water Act, dated 14 July 2005. There are four monitoring programs and two physical works including: a) Lower Whatshan River Fish Habitat Enhancement Physical and Biological Effectiveness Monitoring b) Reservoir Vegetation Monitoring c) Reservoir Wildlife Monitoring d) First Nations Heritage and Archaeology Monitoring e) Habitat Complexing Assessment and Enhancement Structures f) Inonoaklin Recreation Site Boat Launch Extension
2
Background
The water use planning process for BC Hydro’s Whatshan project was initiated in May 2002 and completed in May 2003. The conditions proposed in the WUP for the operation of the project reflect the October 2003 recommendations of the WUP Consultative Committee. In August 2003, the Whatshan WUP was submitted to the Comptroller of Water Rights (Comptroller). On 14 July 2005, BC Hydro was ordered to implement the conditions proposed in the Whatshan WUP and prepare the monitoring programs and physical works terms of reference (TOR). On 14 November 2005, the Whatshan WUP monitoring programs and physical works TOR were submitted to the Comptroller for review and approval. On 15 February 2006, the TOR for the Lower Whatshan River Fish Habitat Enhancement Physical and Biological Effectiveness Monitoring, Reservoir Vegetation Monitoring and Reservoir Wildlife Monitoring programs and the physical works TOR were accepted by the Comptroller. As requested by the Comptroller, BC Hydro will revise the TOR to reflect work not requiring a permit under the BC Heritage Conservation Act to include a non-intrusive archaeological overview assessment of the drawdown zones of Whatshan Lake Reservoir. BC Hydro will work with the First Nations to develop a plan to meet the obligations required under the BC Heritage Conservation Act.
BC Hydro
Page 1
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
On 12 June 2006, revised Whatshan WUP physical works TOR were submitted to the Comptroller for review and approval. To date, these TOR have not been accepted by the Comptroller. As outlined in the Whatshan WUP, BC Hydro will review the results of the monitoring programs five years after implementation of the WUP. A formal review of the WUP is recommended in ten years. A review could be triggered sooner if significant risks are identified through the analysis of monitoring results.
3
Status
The following table outlines the status and schedule for the Whatshan WUP monitoring programs and physical works.
Table 3-1: Status of Whatshan WUP Monitoring Programs and Physical Works Implementation
2006 Monitoring Programs
WLR YR1
2007
WLR YR2
2008
WLR YR3
2009
WLR YR4
2010
WLR YR5 Interim Review
2011
WLR YR6
2012
WLR YR7
2013
WLR YR8
2014
WLR YR9
2015
WLR YR10 Final Review ■ ■
Lower Whatshan River Fish Habitat Enhancement Physical and Biological Effectiveness Monitoring Reservoir Vegetation Monitoring Reservoir Wildlife Monitoring First Nations Heritage and Archaeology Monitoring
■ ■ ■
■
■ ■
■
■
■
■
■
■
■
■
■
■
Physical Works
Habitat Complexing Assessment and Enhancement Structures Inonoaklin Recreation Site Boat Launch Extension Legend: ■ u/w = = = ■ ■ ■ ■
Program to be undertaken/initiated in identified year Project is underway Program completed for the year
4
Whatshan WUP Monitoring Programs
This section outlines the status of the Whatshan WUP monitoring programs as per the Order under the Water Act, dated 14 July 2005.
4.1 4.1.1
Lower Whatshan River Fish Habitat Enhancement Physical and Biological Effectiveness Monitoring Overview The objective of this monitoring program is to evaluate the general ecological and specific fish and fish habitat benefits expected from the physical works habitat enhancement structures installed in Reach W3 of the lower Whatshan River. The Whatshan WUP Consultative Committee expressed concern that low flows in the lower Whatshan River from the Whatshan Dam to Arrow Lake may affect fish habitat and fish populations. To benefit rainbow trout in Reach W3, the Consultative Committee agreed to examine the feasibility and, if feasible, install 15 to 20 habitat
BC Hydro
Page 2
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
enhancement structures in reach W3 in lieu of a minimum flow release from the dam (see Section 5.1 below for construction of enhancement structures). The TOR describe a monitoring program that will evaluate the benefits of these structures to fish habitat and, consequently, to fish abundance in Reach W3 of the lower Whatshan River. Monitoring indicators will include measures of: a) Physical habitat. b) Fish abundance and biological characteristics. These indicators will be measured prior to and following installation of the habitat structures to evaluate the benefits of the structures. This monitoring program includes two major components: monitoring physical habitat and longevity of structures; and monitoring biological response with a before-after approach. 4.1.2 Status This monitoring program was initiated in May 2006 and will be carried out over ten years, occurring in years 1, 2, 4, 7 and 10. The first program report is expected in April 2007. 4.1.3 Interpretation of Data At this time there is no data to interpret for this monitoring program. 4.2 4.2.1 Reservoir Vegetation Overview The objective of this monitoring program is to reduce uncertainty related to the effects of reservoir operations on reservoir vegetation in the Whatshan Lake Reservoir. The Whatshan WUP Consultative Committee expressed concern that changes to the operation of the Whatshan Lake Reservoir would affect emergent and submergent vegetation in the drawdown zone of the reservoir. Reservoir vegetation is sensitive to the frequency and duration of inundation such that vegetation communities present at various elevations in the drawdown zone are determined by historic reservoir operations. Changes to reservoir operations recommended in the WUP were designed to benefit recreation and fish in the reservoir, and include reservoir elevations with approximately 1 m less drawdown during the winter and higher reservoir elevations during May and June. It was hypothesized that WUP operations may reduce the extent of emergent vegetation and increase the extent of submergent vegetation. However, this response was highly uncertain, and the Consultative Committee recommended that reservoir vegetation be monitored.
BC Hydro
Page 3
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
Monitoring indicators will include measures of: a) Emergent and submergent vegetation spatial extent. b) Emergent and submergent vegetation species composition. c) Emergent and submergent vegetation relative productivity. These indicators will be measured using aerial photography both prior to and following implementation of new reservoir operations. This monitoring program involves mapping of vegetation communities from air photos, ground-truthing of the air photo mapping, data entry, and reporting. 4.2.2 Status This monitoring program was initiated in May 2006 and will be carried out over ten years, occurring in years 1, 6, and 10. Efficiencies were realized in the proposal stage around air photo methodologies and additional air photo collection may occur as budgets permit. The first program report is expected in April 2007. 4.2.3 Interpretation of Data At this time there is no data to interpret for this monitoring program. 4.3 4.3.1 Wildlife Monitoring Overview The objective of this monitoring program is to reduce uncertainty in the relationship between wildlife and reservoir vegetation. The Whatshan WUP Consultative Committee expressed concern that changes to the operation of the Whatshan Lake Reservoir might affect wildlife species that use littoral and riparian habitats near the reservoir. During the Whatshan water use planning process, many hypotheses were proposed for the effects of reservoir operations on wildlife. The Consultative Committee recommended that reservoir wildlife be monitored to provide information to help make more informed decisions during future water use planning processes. The wildlife monitoring program is designed to: 1. Provide information on the relationship between reservoir wildlife and aquatic (emergent and submergent) or riparian vegetation; and 2. Infer how wildlife responds to the changes in vegetation, which will be documented by the vegetation monitoring program. Specific monitoring variables will be determined during the program design and pilot survey component in year 1. This monitoring program involves: developing a detailed monitoring program design and associated pilot survey in year 1, annual volunteer surveys in years 2 to 10, and analysis and reporting of monitoring results in year 10.
BC Hydro
Page 4
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
4.3.2
Status This monitoring program is scheduled to be initiated in May 2006 and will be carried out over ten years. The first program report is expected in April 2007.
4.3.3
Interpretation of Data At this time there is no data to interpret for this monitoring program.
4.4 4.4.1
First Nations Heritage and Archaeology Monitoring Overview As per the Whatshan WUP Order dated 14 July 2005, BC Hydro submitted a monitoring program TOR for acceptance by the Comptroller outlining the details of a study to locate archaeological sites within the reservoir between the elevations of 634.4 and 641.3 metres. The objective of the archaeological inventory is to identify and record archaeological resources in the drawdown zone of the Whatshan Lake Reservoir and to describe the archaeological significance and elevations of these sites relative to the reservoir operation range. During the Whatshan water use planning process, a preliminary assessment of archaeological resources in the Whatshan area was completed (Choquette, 2002)1. Whatshan Lake Reservoir was created well before any systematic archaeological investigations were required for developments such as hydroelectric reservoirs. Therefore, the archaeological values of the original lakeshore and riverbank settings along with the adjacent terrain were never identified, recorded, or subject to salvage data retrieval. The report prepared by Choquette concluded that based on available information no operational changes were necessary to address archaeological concerns. However, this conclusion is based on an incomplete understanding drawn from historic information from unauthorized relic collectors and a very brief survey of the uppermost part of the drawdown zone. Choquette further recommended that a systematic survey of the reservoir drawdown area be completed when the reservoir is at its lowest elevation in order to properly inventory the archaeological resources in the drawdown zone. This information would be used in future water use planning processes to inform the assessment of options for operations of the reservoir.
4.4.2
Status This monitoring program is on hold pending approvals and clarification. As requested by the Comptroller, BC Hydro will revise the TOR to reflect work not requiring a permit under the BC Heritage Conservation Act to include a non-intrusive archaeological overview assessment of the drawdown zones of Whatshan Lake
1
Choquette, Wayne. 2002. Archaeological Component, Input to the Water Use Planning Process for the Whatshan Reservoir.
BC Hydro
Page 5
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
Reservoir. BC Hydro will work with the First Nations to develop a plan to meet the obligations required under the BC Heritage Conservation Act. 4.4.3 Interpretation of Results At this time there is no data to interpret for this monitoring program.
5
Whatshan WUP Physical Works
This section outlines the status of the Whatshan WUP physical works as per the Order under the Water Act, dated 14 July 2005.
5.1 5.1.1
Habitat Complexing Assessment and Enhancement Structures Overview The objective of this physical work is to achieve effective river habitat in the lower Whatshan River. During the Whatshan water use planning process it was noted that effective river habitat in the lower Whatshan River could be achieved through changes in operation of the Whatshan Reservoir Lake but that such changes would be costly. In lieu of the operational changes, it was determined that equivalent benefits to fish habitat could be achieved with the addition of about 15 to 20 complexing structures in Reach 3 of the river. The Consultative Committee recommended construction of physical works in Reach 3. Prior to the complexing structures being designed and installed, an assessment of habitat complexing potential and rainbow trout population monitoring in the Reach is to be undertaken. It is expected that this assessment and monitoring work will take two years to complete. Design of the structures will follow the assessment work. Upon approval of these designs by the Comptroller, BC Hydro will proceed with construction of the habitat complexing structures.
5.1.2
Status This physical work was initiated in May 2006 and will be carried out over three years. The first physical work report is expected as part of the Lower Whatshan River Fish Habitat Enhancement Physical and Biological Effectiveness Monitoring report in April 2007. On 12 June 2006, the Habitat Complexing Assessment and Enhancement Structures TOR were revised to reflect a modification to the implementation schedule and were submitted to the Comptroller for review and approval. To date, this TOR has not been accepted by the Comptroller.
5.1.3
Interpretation of Data At this time there is no data to interpret for this physical work.
BC Hydro
Page 6
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
5.2 5.2.1
Inonoaklin Recreation Site Boat Launch Extension Overview The objective of the boat launch extension was to enable boat access to the reservoir when the reservoir is as low as 636.5 m.
5.2.2
Status For the Inonoaklin Recreation Site Boat Launch Extension, the scope of the original TOR was to extend the existing boat launch from elevation 638.1 m to deeper water to facilitate launching at a wider range of reservoir operations. BC Hydro received environmental approvals for the original project from the Department of Fisheries and Oceans (DFO) in March 2006. On 1 March 2006, BC Hydro requested permission from the Comptroller for a one time special drawdown to 635 m for the boat ramp installation. Permission was received that day. On 7 March 2006, during the site visit for prospective tenders for the ramp installation contract, it was found that the reservoir floor immediately below the lower end of the existing boat ramp was too shallow to allow an extension of the ramp. Based on discussions with the Inonoaklin Recreation Commission who manage the site for BC Parks (the boat launch is located on a BC Parks Reserve) a new boat ramp located approximately 150 m north of the existing boat launch was deemed suitable. Shortly after the site visit, BC Hydro received permission from the Recreation Commission to construct a boat ramp and associated parking area in this new location. On 7 March 2006, BC Hydro initiated the construction of the new boat ramp given the small window of opportunity to complete this project in the early spring pending the coming freshet. The project was substantially completed on 12 April 2006. Remaining minor works at the top of the ramp, including a barrier gate, signs and nopost-guardrails, will be completed shortly. The Inonoaklin Recreation Site Boat Launch Construction Summary Report was completed. On 12 June 2006, the Inonoaklin Recreation Site Boat Launch Extension TOR were revised to reflect the a new boat ramp located approximately 150 m north of the existing boat launch and were submitted to the Comptroller for review and approval. To date, this TOR has not been accepted by the Comptroller.
6
Whatshan WUP Monitoring Programs and Physical Works Costs
The following table summarizes the Whatshan WUP monitoring programs and physical works costs approved by the Comptroller on 15 February 2006 and the actual costs to 31 May 2006.
BC Hydro
Page 7
Whatshan Project Water Use Plan Monitoring Programs and Physical Works Annual Report: 2006
Table 6-1: Whatshan WUP Monitoring Programs and Physical Works Costs Costs Approved by Comptroller of Water Rights
Direct Management Implementation Direct Management Implementation Direct Management Implementation Direct Management Implementation $48,570 127,900 27,760 134,400 64,321 31,200 TBD TBD
Description
Actual Costs to 31 May 2006
Monitoring Programs
Lower Whatshan River Fish Habitat Effectiveness Monitoring Reservoir Vegetation Monitoring Reservoir Wildlife Monitoring First Nations Heritage and Archaeology Monitoring1 $10,491 0 6,403 0 4,858 0 0 0
Physical Works2
Habitat Complexing Assessment and Enhancement Structures Inonoaklin Recreation Site Boat Launch Extension
1 2
Direct Management Implementation Direct Management Implementation
$43,815 236,400 17,255 51,400
$0 0 2,542 18,552
The First Nations Heritage and Archaeology Monitoring TOR to be revised. On 12 June 2006, the revised Whatshan WUP physical works TOR were submitted to the Comptroller for review and approval. To date, the TOR have not been accepted by the Comptroller.
BC Hydro
Page 8
Whatshan Project Water Use Plan Construction Completion Report:
• Inonoaklin Recreation Site Boat Launch Extension
May 2006
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report
The Inonoaklin Recreation Site at the Whatshan Lake Reservoir is located about 20 km west of the Needles ferry. The previous existing boat launch at the recreation site runs from the reservoir’s normal full level of 641.30 m down to elevation 638.10 m. The existing boat ramp was to be extended but due to insufficient gradient at lower elevations it was not a valid option. Therefore; a second concrete boat launch was constructed within the recreation site 150 m to the left (north) of the existing boat ramp. Appendix 1 contains photos showing the location of the second boat launch. The work was comprised of the excavation for, and placement of, a concrete slab that would be the second boat launch at the Inonoaklin Recreation Site at Whatshan Lake Reservoir. The work included construction of a 3.0 m wide by 100 mm thick reinforced concrete slab that runs from the normal high water level of 641.30 m for Whatshan Lake down to El. 635.50 m. The slab was placed on compacted native gravel. There was no material brought in from other areas for the construction of the boat launch. The construction of the boat launch included the development of a spoil infill area that will be used as a parking area for vehicles/boat trailers. The spoil area is adjacent to the top of the concrete ramp. Whatshan Lake was drafted down to an elevation of 635.0 m to accommodate the construction of the boat launch to ensure all work was conducted in the dry. Construction for the new boat launch began on April 5, 2006 with excavating a rough in grade to determine gradient to the top of the beach. The photos in appendices 1 and 2 show that there was no riparian vegetation removed for the creation of the boat launch. The area in which the boat launch was created was at the edge of the Inonoaklin Recreation Site beach area. Therefore; there was very little vegetation growing in the area. Any vegetation that was removed was for the parking area located at the top of the ramp. Photos located in appendices 2 and 3. Formwork for the concrete began on April 8, 2006 along with pouring 50 ft of cement on the bottom portion of the ramp. There was a berm placed long the bottom edge of the formwork to ensure that concrete runoff would not enter the reservoir. The top portion of the ramp was poured on April 11, 2006. There was a small delay between the two pours due to weather conditions. Appendix 4 contains photos of the concrete formwork and the pouring of the cement. The parking area, beach work and the sloping of the boat launch banks was completed on April 12, 2006. Appendix 5 contains photos showing the finished boat launch and the top parking area. The environmental management plan created for the construction of the Inonoaklin Recreation Site boat launch is located in Appendix 6.
BC Hydro
Page 2
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Appendix 1 Inonoaklin Recreation Site New Boat Launch Location
BC Hydro
Page 3
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 4
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 5
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Appendix 2 Construction of Boat Launch
BC Hydro
Page 6
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 7
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Appendix 3 Parking Area Adjacent to top of Boat Launch
BC Hydro
Page 8
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 9
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 10
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Appendix 4 Concrete Work
BC Hydro
Page 11
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 12
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 13
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 14
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 15
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Appendix 5
Finished Boat Launch and Parking Area
BC Hydro
Page 16
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 17
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
BC Hydro
Page 18
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Appendix 6 Environmental Management Plan
BC Hydro
Page 19
Whatshan Water Use Plan Inonoaklin Recreation Site Boat Launch Construction Summary Report 5 May, 2006
Whatshan Water Use Plan New Boat Launch Ramp at Inonoaklin Recreation Site
Environmental Management Plan
Prepared by: Koreen Morrone BC Hydro
March 22, 2006
BC Hydro
Page 20
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
Table of Contents
Table of Contents.................................................................................................................. 21 1. PROJECT DESCRIPTION ............................................................................................ 22 2. ENVIRONMENTAL MANAGEMENT............................................................................. 22 2.1 Purpose of the EMP .............................................................................................. 22 2.2 Emergency Contact Information ............................................................................ 23 3. SUMMARY OF ENVIRONMENTAL IMPACTS AND MITIGATION .............................. 23 4. ENVIRONMENTAL MONITORING ............................................................................... 24 5. ENVIRONMENTAL IMPACTS AND MITIGATION........................................................ 24 5.1 Concrete Work ...................................................................................................... 25 5.2 Watercourse and Water Quality Protection ........................................................... 25 5.3 Oil and Fuel ........................................................................................................... 26 5.4 Waste Disposal...................................................................................................... 27 Appendix A – Contractor Environmental Orientation Record................................................ 28 Appendix B - Oil and Chemical Spill Emergency Response Plan......................................... 30 Appendix C - Spill Response Equipment Suppliers .............................................................. 33 Appendix D - Vehicle Spill Kit Contents ................................................................................ 35
BC Hydro
Page 21
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
1.
PROJECT DESCRIPTION
The Inonoaklin Recreation Site at the Whatshan Lake Reservoir is located about 20 km west of the Needles ferry. The existing boat launch at the recreation site is 3.05 m wide and is constructed from horizontal concrete strips (3.05 m long by 0.36 m wide) that are hooked together. The ramp has a constant grade (slope) of 15%. The existing ramp runs from the reservoir’s normal full level of 641.30 m down to elevation 638.10 m. The existing boat ramp was to be extended but due to insufficient gradient at lower elevations it is not a valid option. Therefore; a second concrete boat ramp is to be constructed within the recreation site 150 m to the left (north) of the existing boat ramp. The work is comprised of the excavation for, and placement of, a concrete slab that will be a second boat ramp at the Inonoaklin Recreation Site at Whatshan Lake Reservoir. The work includes construction of a 3.0 m wide by 100 mm thick reinforced concrete slab that will run form the normal high water level of 641.30 m for Whatshan Lake down to El. 635.50 m. The overall length of the slab, as measured along the surface of the slab will be about 40 m. Apart from the uppermost 1 m of ramp the ramp will be at a constant grade of 15%. The top 1 m of ramp will be at about 10% to allow a smooth transition onto the ramp. There will be no cross fall across the width of the ramp. The slab is to be placed on compacted native gravel. The completed slab will not follow the fall line of the existing bank but will be angled left in a straight line. Also included in the work is the development of a spoil infill area that will be used as a parking area for vehicles/boat trailers. The spoil area is adjacent to the top of the concrete ramp constructed under this contract. Excess native materials from the boat ramp excavation are to be placed in the spoil area, compacted and left level, in a neat and tidy manner.
2. 2.1
ENVIRONMENTAL MANAGEMENT Purpose of the EMP
The purpose of this Environmental Management Plan is to identify any elements of the project that could present a hazard to the environment. The plan describes how those risks can be mitigated through proper work management and in the event of an accident, procedures that will contain and limit impacts to the environment. The EMP shall be used as a guide to ensure the use of best management practices; contractors and employees shall follow its intent. Steps will be taken to ensure no deleterious substances enter watercourses that flow into adjacent fish habitat. Any condition which has resulted from operations of this project, which constitutes, or could result in unnecessary damage or disturbance to property and the environment, will be corrected to the satisfaction of BC Hydro environmental staff and the applicable government authorities.
BC Hydro
Page 22
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
2.2
Emergency Contact Information
Contact Name Dave Percell Hamling Lakes Construction Bob Essery Koreen Morrone 250-814-6660 1-800-663-3456 604-666-3500 Joanne Starchuck Jeff Walker 604-590-7571 604-528-1620 Office # 250-814-6626 Cellular / Pager # 250-837-8618
Project Manager Contractor Site Foreman/ Construction Officer Environmental Monitor Provincial Emergency Program (PEP) DFO Spill Reporting line MMBU Environmental Specialist BC Hydro Waste Management Support
3.
SUMMARY OF ENVIRONMENTAL IMPACTS AND MITIGATION
Long term environmental impacts resulting from this project are not expected. Shortterm impacts related to construction are expected to be minimal and easily avoided/mitigated. The environmental concern of this project is the potential for the introduction of harmful or polluting substances into the soil or nearby waterways as a result of activities on site, also for the potential for harmful alteration, disruption or destruction of fish habitat. In particular for the boat launch creation the primary impacts that could arise are introduction of sediment into the aquatic environment during and shortly after excavations and placement of gravel and general fill, fuel and oil spills, or the introduction of concrete or concrete wash water into the aquatic environment. To accommodate the construction of the second boat launch at the Inonoaklin recreation site the Whatshan Reservoir will be drafted down to an elevation of 635.0 m. This allows all the work to be conducted in the dry.
BC Hydro
Page 23
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
Work Area Inappropriate treatment of concrete washwater Deposition of sediment into waters frequented by fish
•
Impact Release of toxic concrete washwater into water body
-
Mitigation Concrete washwater management
EMP Section(s) Section 5.1
•
Fuel handing and oil/fuel filled equipment
Excavation in and around a waterbody causing direct deposition of sediment into the waterbody • Exposure of erodible soils that upon exposure to runoff or precipitation release sediment into adjacent waterbody Spills and/or leaks of: • Fuel, lubricating oil and coolants associated with the operation of heavy machinery and equipment during construction. • Equipment oil and hazardous materials, which can result in soil and water contamination and impact the receiving environment. • • Shipping special or dangerous waste in a non-compliant manner Storage of waste inappropriately
-
Suitable sediment and erosion control techniques
Section 5.2
-
Spill Containment Spill Response Spill Kits
Section 5.3
Inappropriate disposal of waste
-
Adherence to waste management and shipping regulations
Section 5.4
4.
ENVIRONMENTAL MONITORING
The Project Manager and Site supervisor will ensure that the EMP is followed. The Environmental Monitor (BC Hydro environmental staff) will visit the site, when necessary to supervise the environmentally sensitive aspects of the project. The monitor will conduct a site visit prior to the commencement of the project, during the shutdown stages of the project and as required during any of the key stages of the project. The environmental monitor (B.C. Hydro technical/professional staff and/or contractor) will have the authority to order the shut-down of the operation if environmental protection is compromised.
5.
ENVIRONMENTAL IMPACTS AND MITIGATION
This section provides proposed measures to prevent or mitigate adverse environmental effects of the project including identification of measures to prevent equipment malfunction, spills, or accidents. References are made to BC Hydro work procedures contained in the Appendices. Throughout this project, BC Hydro and its contractors will limit disturbance to the environment by abiding by the following practices. Hydro’s Representative or EO will ensure compliance with the requirements identified in this section.
BC Hydro
Page 24
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
5.1
Concrete Work
Any concrete work must be conducted so that wash water and excess concrete slurry from the site and equipment do not contaminate the reservoir drainage waters. Forming procedures will be of the highest standards to ensure that concrete does not leak into the reservoir. All equipment shall be washed off site, unless provided with an on board wash bucket. The contractor shall find an appropriate wash location away from the construction site that allows for filtration of sediment so as to not discharge directly into fish-bearing water bodies or storm sewers directly connected to fish-bearing water bodies. Concrete finishing tools shall not be cleaned in Whatshan Lake reservoir or any other water courses. Water used for cleaning concrete finishing tools and equipment shall be disposed of in the designated waste area as specified above.
5.2
Watercourse and Water Quality Protection
Disturbance to the banks of the reservoir will be minimized and will be confined entirely within the boat launch ramp boarders. No riparian vegetation will be affected other than that within the boarders of the boat launch. No further material will be placed within the drawdown zone of the reservoir other than granular fill as required to stabilize the sub grade. Only native material or clean granular fill will be utilized. No fill will be placed outside of the boarders of the boat launch. The project will not cause debris of any kind to be placed within the reservoir or the drawdown zone of the reservoir. Excavated material that is removed from within the drawdown zone will be placed within the designated spoil area located adjacent to the top of the new ramp. Runoff from the construction sites will not be allowed to enter any established watercourse (this includes seasonably dry water channels and ditches) unless it meets aquatic life criteria specified in the BC Water Quality Guidelines (Criteria): 1998 Edition and the CCME Canadian Water Quality Guidelines. In accordance with these guidelines BC Hydro and its contractor shall perform in a manner that ensures water exiting the work site meets the following parameters.
Parameter Suspended Solids
Maximum Allowable • 25 mg/l above background when background is between 25 and 250 • 10% when background is ≥ 250 mg/l
No oil or grease will be permitted to escape into adjacent drainages and natural watercourses. In the case of a spill, the BC Hydro Oil and Chemical Spill Emergency Response Plan (Appendix 1) must be followed such that no release to watercourses occurs. BC Hydro will periodically monitor water quality parameters. BC Hydro’s EM retains the right and responsibility to suspend site work and to take corrective action if water quality parameters are not in compliance with allowable levels. Work will be suspended until adequate corrective measures have been implemented to the satisfaction of Hydro’s Representative.
BC Hydro
Page 25
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
5.3
Oil and Fuel
Spills and leaks of oils and fuels can adversely effect terrestrial and aquatic environments if not managed properly. In addition to absorbent materials required to cleanup drips, leaks and minor spills, a fully stocked spill kit must be located on site to deal with any emergency spill situations. Spill kits shall be available where oil filled equipment will be working, and staff and contractors on site will be trained in the proper use of spill kits. Due to the risk of spill and fire, fuels and/or other petroleum or combustible products will not be stored in any large quantity on site. Only small fuel containers, such as approved safety containers or Tidy Tanks properly mounted in trucks will be allowed on site for any extended period of time. All containers must be labelled with appropriate TDG, WHMIS and safety markings. To reduce the risk and the impact of spills: 1. Implement the oil spill response plan (Appendix B). 2. No equipment will enter the wetted portion of the reservoir or any watercourse at any time. 3. All machinery will be serviced and maintained well above the high water line of the reservoir or any watercourse to prevent leaks of fuel or lubricants from entering the reservoir or any watercourse. All equipment will be inspected for leaks and worn hoses and fittings prior to access onto the site and daily thereafter. 4. Place oil sorbent sheets and/or containers under vehicles and equipment parked in high-risk areas (i.e., adjacent to watercourses) for longer than 2 hours or immediately under any vehicle or equipment that is leaking. Leaking equipment must be immediately shut down and repaired. 5. Provide adequate containment for fuel and oil products. 6. Ensure that all fuel, oil handling, storage and containment meet the requirements of BC Fire Code (1998) and A Field Guide to Fuel Handling, Transportation & Storage 3rd Edition, February 2002 (Ministry of Water, Land and Air Protection). 7. Ensure that any employees and/or contractors transferring fluids and fuelling equipment understand the environmental risks of the area, equipped with adequate spill prevention and response measures, have appropriate training, and are following fuelling practices deemed acceptable by BC Hydro. At a minimum, all refuelling activities must be conducted at least 15 m away from any water body. 8. Ensure that the operator is in attendance during all fuel transfers. 9. Locate emergency spill response kits in areas where oil filled equipment will be working and provide additional spill response materials in sufficient quantities on site to catch drips, minor leaks and spills (Suggested suppliers for this type of equipment and minimum spill kit contents are found in Appendixes C and D) NOTE: the spill response kits should only be used in the event of a spill incident and not for day to day equipment/tool management.
BC Hydro
Page 26
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
5.4
Waste Disposal
Special wastes and hazardous materials are not anticipated for this project. However, it should be noted that absorbent materials or soils saturated with oil or gasoline are classified as special waste. Soils and/or other materials contaminated by petroleum products, chemicals, or other undesirable materials will be transported and disposed of in accordance with the BC Transportation of Dangerous Goods Act, BC Contaminated Sites Regulation, BC Special Waste Regulations and Waste Management Act. Contaminated soils will be excavated, treated on-site, or hauled off-site to an accepted treatment/disposal area. All legislation with respect to storage, land filling, and disposal of materials, will have to be adhered to by BC Hydro employees and its Contractors. BC Hydro and its Contractors shall monitor all work areas and perform a final cleanup, as necessary, upon completion of the project.
BC Hydro
Page 27
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
APPENDIX A – CONTRACTOR ENVIRONMENTAL ORIENTATION RECORD
The Contractor Environmental Orientation Record (CEOR) shall be completed for all contract work involving an environmental component, as specified by Generation’s Environmental Management System Procedure 3.6 Contractor and Supplier Management. The Project Manager is responsible for ensuring that the environmental requirements of the work are reviewed with the Contractor before work is started, and that a record of the discussion is documented on the CEOR. The form must be signed by both the BC Hydro Representative and the Contractor. By signing the CEOR, the Contractor indicates he/she has been advised of the environmental requirements of the contract. In field situations, compete two (2) copies of the form (one for the Contractor and one for BC Hydro records) or photocopy the form. The CEOR shall be filed with the Contract documents.
Date: 1 Project Information Project Title – Project Description Project Location – 2 Contractor Information (if applicable) Company Name Company Address Facility PH OR SY
Site Contact/Representative Name Tel. # 3 Fax # E-mail
Environmental Management Plan / Environmental Practices Review the environmental issues and requirements of the work as specified in the Environmental Management Plan (EMP) or Environmental Practices (EP). Is there an EMP or EP for the work? Have the environmental requirements been reviewed with the contractor and the contractor’s staff? (Use the checklist below to guide discussion) Yes Yes NA NA
Environmental Issues Soil erosion / compaction Vegetation disturbance or removal Generation and disposal of hazardous substances Generation and disposal of waste Spill of hazardous substances Fuel and flammable storage Dust generation / other air emissions Water quality – erosion and siltation
Environmental Protection Requirements
Discuss ed
Yes Yes Yes Yes Yes Yes Yes Yes
NA
NA NA NA NA NA NA NA NA
BC Hydro
Page 28
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
Fish and Aquatic - Habitat alteration, disturbance or loss Wildlife and Bird – Habitat Alteration, Disturbance or Loss Disturbance to Heritage Resources / Archaeological Sites Visual Impacts / Noise Concerns Property Considerations Disruption of Recreation Use Public Safety Concerns Do the tools and equipment meet the requirements? 4
Yes Yes Yes Yes Yes Yes Yes Yes
NA NA NA NA NA NA NA NA
Permits and Approvals Information: Ensure the necessary environmental permits and approvals relating to the work have been obtained prior to starting work.
Are environmental notifications, permits, licenses or approvals required? List applicable regulatory requirements and permit reference numbers. .
Yes NA
5
Have the permits, licenses and approvals obtained and / or checked? Emergency Response Plan / Oil and Chemical Spill Response Plan Has the Emergency Response Plan been discussed?
Has the Oil and Chemical Spill Response Plan been discussed? Are there spill kits available on location? Where are the spill kits located?
Yes
NA
Yes Yes Yes
NA NA NA
6
Environmental Incident Reporting
Ensure Contractor is aware of BCH EIR system.
Yes NA
Environmental Incident Reporting Procedures discussed?
The undersigned has been briefed on the environmental requirements of the work as detailed above.
Signed: Contractor BC Hydro Contract Representative Date:
Counter-signed: Additional Comments:
Date:
BC Hydro
Page 29
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
APPENDIX B - OIL AND CHEMICAL SPILL EMERGENCY RESPONSE PLAN
If a spill of fuel, oils, lubricants or other harmful substances occurs, the following procedures will be implemented. B.C. Hydro Spill Response Steps 1. 2. 3. 4. 5. 6. Ensure Safety Stop the Flow (When Possible) Secure the Area Contain the Spill Notify/Report (PEP 1-800-663-3456) Clean-Up (circumstances may dictate another sequence of events)
1.
Ensure Safety
• • • • • Ensure personal/public, electrical and environmental safety Wear appropriate Personal Protective Equipment (PPE) Never rush in, always determine the product spilled before taking action Warn people in immediate vicinity Ensure no ignition sources if spill is of a flammable material Act quickly to reduce the risk of environmental impacts Close valves, shut off pumps or plug holes/leaks, set containers upright Stop the flow of the spill at its source Limit access to spill area Prevent unauthorized entry onto site Block off and protect drains and culverts Prevent spilled material from entering drainage structures (ditches, culverts, drains) Use spill sorbent material to contain spill If necessary, use a dike or any other method to prevent any discharge off site Make every effort to minimize contamination Contain as close to the source as possible Notify appropriate Site Supervisor or alternate of incident (provide spill details) When necessary the first external call should be made to (see spill reporting requirements): Provincial Emergency Program (PEP) 1-800-663-3456 (24 hour) Provide necessary spill details to other external agencies (see spill reporting requirements)
2.
Stop the Flow (when possible)
• • •
3.
Secure the Area
• •
4.
Contain the Spill
• • • • • •
5.
Notify/Report
• • •
BC Hydro
Page 30
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
•
Complete a BC Hydro Environmental Incident Report (EIR) available on the BC Hydro Intranet site (http://w3.bchydro.bc.ca/env_incident_rpt/index.htm).
BC Hydro Spill Reporting Notification Chart
Spill Observer
Facility Manager or Delegate
all spills to water
all spills off Hydro property
oil spills >100 litres on land
oil spills <100 litres on land
PEP 1-800-663-3456 DFO (604) 666-3500 submit EIR
PEP (spills > 100 litres) 1-800-663-3456 BC MWLAP submit EIR
PEP (spills > 100 litres) 1-800-663-3456 submit EIR
submit EIR
Table 1: List of externally reportable quantities for commonly used substances Product Class 2.1 – flammable gas (e.g., propane) Class 2.2 - non flammable gas (e.g., SF6, CO2) Class 3 - flammable liquids Class 8 - corrosive liquid acids and caustics (e.g., battery acid) Class 9 – environmentally hazardous (e.g., PCB's, used ethylene glycol) Oil & Waste Oil Other Substances (e.g., new antifreeze, power-wash water) Pesticides & Herbicides Quantity 10 kg or 10 min. 10 kg or 10 min. 100 litres 5 kg or litres 1 kg or litre 100 litres 200 kg or litres 1 kg or litre
Note: All spills to water are reportable. If in doubt as to whether or not to report a spill, err on the side of caution and report the spill.
BC Hydro
Page 31
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
6.
Clean-Up
Technical assistance is available from Generation Sustainability on clean-up procedures and residue sampling. • All equipment and/or material used in clean-up (e.g. used sorbents, oil containment materials etc.) must be disposed of in accordance with BC Ministry of Water, Land and Air Protection (MWLAP) requirements. Generation Sustainability will assist in compliance with federal and provincial legislation. − Accidental spills may produce special wastes (e.g., material with > 3% oil) and contaminated soil. All waste disposal must comply with the BC Special Waste Regulations (BC Reg. 63/88) and the BC Waste Management Act ([RSBC 1996] Chapter 482). Compliance with these regulations generally requires: − Classification of the waste − Packaging requirements (proper labeling and suitable storage containers) − Transportation documentation − All transporters must be properly trained − Disposal in accordance with the regulations at an appropriate facility − Spill reporting requirements must also be followed Waste sorbent material may not be disposed of in a landfill without prior approval from MWLAP and the landfill operator. Contaminated soil must be treated and dealt with as required on a sitespecific basis and must comply with the requirements of the BC Contaminated Sites and Special Waste Regulations (B.C. Reg. 375/96). At a minimum, the contractor must consider soil relocation agreement standards and obtain soil relocation agreements as required.
− −
BC Hydro
Page 32
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
APPENDIX C - SPILL RESPONSE EQUIPMENT SUPPLIERS
Please note: sorbent materials are designed for specific uses and purposes (e.g., oil only sorbents vs. general sorbents). Ensure that the appropriate materials are ordered for the project. • • All standard spill response equipment including standard kits can be ordered as a regular BC Hydro stores requisition. Contact Store 1: (604) 590-7572 or (47572). Use form 60320.
Spill containment booms, sorbent sweeps and pads are also available from the companies listed below. Custom made kits and supplies are also available upon request. Company Acklands-Grainger Inc.1,2,3,5 Address #200 & #205, 31136 Peardonville Rd Abbotsford, BC V2S 5W6 2475 Douglas Rd Burnaby, BC V5C 5A9 1620 Island Hwy Campbell River, BC V9W 2E5 #1, 725 Industrial Rd Cranbrook, BC V1C 4C7 10208 - 94th Ave Fort St John, BC V1J 4X3 3407-3rd Ave, PO Box 578 Port Alberni, BC V9Y 4E4 155 George Hills Way Prince Rupert, BC V8J 3R2 #222, Hwy 23 North PO Box 1530 Revelstoke, BC V0E 2S0 3010 Highway Drive Trail, BC V1R 2T3 2015 Government Street Victoria, BC V8T 4N9 Unit #203, 1305 Welch Street North Vancouver, B.C. V7P 1B3 212- 590 Ebury Pl. Annacis Island, B.C. 8980 Oak Street Vancouver, B.C. 5052 Hartway Drive Prince George, BC V2K 5B7 2950 Highway Drive Trail, BC V1R 2T3 5508 Dorset Burnaby, B.C. Phone Number 604- 854-6664 604-879-5764 250-287-9215 250-426-3335 250-785-8135 250-724-0181 250-624-9195 250-837-5161
250-364-1277 250-384-1111 604-980-4899
Aquaguard1,2,4,5 Canadian West Wiper2,4 CG Industrial Specialties Ltd.
2,3
604-522-5650 604-263-1671 (after hours) 604942-5739 250-962-8261 250-364-2510 1-800-648-5166 604-435-6671
Columbia Environmental Services7 Enviro-Guard Products Ltd.
1,2,5
BC Hydro
Page 33
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
Company Hazco Canada Inc. 2,7
Hazmasters Environmental Controls Inc. 2 Industrial Equipment Company Ltd. 5 Infra-Tech Polymers Inc. 1,2,3 Nilex Inc. 6
Address #160 - 13511 Vulcan Way Richmond, BC V6V 1K4 2478 Fawn Terrace Mill Bay, BC V0R 2P0 3131 Underhill Avenue Burnaby, B.C. V5A 3C8 2243 - 6th Avenue Castlegar, BC V1N 2W1 Unit #4, 1947 Telegraph Trail Langley, B.C. V3A 4P8 3963 Phillips Avenue Burnaby, BC V5A 3K4 1015 Great St. Prince George, BC V2N 2K8 109 - 3840 Jacombs Richmond, B.C. 11940 Kingfisher Drive Richmond, BC V7E 3X6 Falkland, B.C. V0E 1W0 Nelson, BC 20333 - 102B Ave Langley, B.C.
Phone Number 604-214-7000 1-800-361-3201 250-743-3946 1-800-667-0444 604-420-0025 (after hours) 604443-9908 250-365-7767 604-888-8808 1-800-567-4888 604-420-6433 1-800-663-0478 250-563-9898 604-273-2236 604-275-1346 1-800-677-4556 250-379-2212 250-505-3806 1-877-455-5336 604-513-9009 (after hours) 604685-5036 604-682-6678 1-866-887-8627 604-254-3952 604-271-7500 1-877-925-7500
Pigmalion Environmental Products1,2,3 Rocky Mountain Environmental Ltd. 1,2,3,4,5 Spill-Check Environmental Products1, 2,3 SpilKleen (Division of Agra max Inc) 1,2,3,4,5 StanChem Inc. 3
Sumas Environmental Services7 Tech-Power Industrial Supplies Ltd. 1,2,3 Versatech Products Inc. 2,4,5 Note:
4623 Byrne Road Burnaby, BC V5J 3H6 745 Clark Vancouver, B.C. 11951 Forge Place Richmond, B.C. The suppliers noted above provide: 1 Cellulose treated sorbent booms, pads and socks 2 Polypropylene sorbent booms and pads 3 Particulate sorbents (floor drying materials) 4 Containment boom 5 Spill containment products; storage 6 Geotextiles, silt fences/curtains, drainage 7 Spill cleanup equipment and services
BC Hydro
Page 34
Whatshan Water Use Plan Physical Works Terms of Reference
5 May, 2006
APPENDIX D - VEHICLE SPILL KIT CONTENTS
VEHICLE EMERGENCY SPILL RESPONSE KIT CONTENTS
Quantity
Description Spill Response Kit (Complete kit) 10’ Oil Only Socks Polypropylene sorbent pads (Oil only) 18”X18”X3/8” Neoprene Mat (Drain Cover) 48”X48”X1/8” PCB Test Kit – (Not Required) 250ml Glass Sampling Jar with Lid and Eye Dropper 25ml Amber Bottle with Lid – (Not Required) Sample Jar Labels and Chain of Custody Doc. 10 Quart Cellulose Sorbent Material, Oil Only Barrier Ribbon, Yellow “Caution Do Not Enter” Poly Disposal Bags (45 Gal. Drum size, minimum 6 mil)) Blank Labels for plastic bags Plastic Bag Tie Epoxy Plug Compound (Hydrocarbon Compatible) Spill Kit Container Marked “Spill Response Kit” Spill Response Card List of Kit Contents
Stock Numbers 154-0017 154-0018 154-0019 154-0804 154-0016 154-0816 154-0829 Stores 1 154-0020 154-0805 113-0015 Stores 1 388-4072 154-0021 154-0835 Print Shop D98-19 Print Shop D98-7
2 each 15 each 1 each 1 each 1 each 1 each 2 each 2 each 1 each 1 each 1 each 1 each 1 each 1 each 1 each 1 each
ATTENTION
** IMMEDIATE REPLACEMENT OF ANY CONTENTS USED IS ESSENTIAL ** REFER TO BC HYDRO WASTE MANAGEMENT STANDARD WM-110 (SPILL RESPONSE)
BC Hydro
Page 35