									    Streamlining Solar in NYC

Con Edison Interconnection Process
            August 6, 2010




                                    1

                                ON IT
       Some Helpful Con Edison Websites

                           coned.com/energyefficiency
coned.com/dg




www.coned.com/es




                                                            2

                                                        ON IT
Web Based Application
•   Registration

     •   Customer and Contractor (carefully – cannot be
         changed!)

•   Contact Information

•   Application ‘paperwork’

•   Upload drawings, etc.

•   Application tracking
     – Milestones
     – Status and Responsibility
                                                              3

                                                          ON IT
          Applications Requirements
• Authorization letter
• Application Form
• Standardized Contract
• Three Line Diagram
• Inverter Certification to UL1741
• Verification Test Procedure

                                          4

                                      ON IT
Three Line Diagram - Sample


                                 Correct Customer
                                          Voltage
                   Inverter
                                     New/existing
                                       equipment
                                     Title Block,
                ConEd Meter
                                 Drawing Number
               Service Voltage        & Revision




                                          ON IT
Net Metering Eligibility – State Legislation

 Photovoltaic and wind eligibility expanded
     • Residential up to 25 kW
     • Commercial up to 2 MW

 –   Adds Micro-CHP and fuel cells to 10 kW
 –   Customer pays any additional interconnection costs
     needed to accommodate larger installation
 –   AC Disconnect not required for systems up to 25kW.
 –   Inverter must meet UL 1741
     –PSC Certified Equipment listing on PSC website



                                                          ON IT
Application Process Steps
Application review
     –   Whether complete

     –   Whether meets requirements of the Standardized Interconnections
         Requirements (SIR) and the Utility

System Installation

•   Meter installed once installation is complete

Verification Test

•   Utility option to witness

Final Acceptance Letter

•   Issued once verification test is complete and approved

                                                                               7

                                                                           ON IT
Most Common Issues with Applications
Job completed prior to paperwork being submitted – or field changes differ from
  submitted – may require paperwork or field changes after the fact leading to
  delays and frustration.

Labeling in field

• Breaker position – 52IT
• Disconnect – 89L
• Post 3 line diagram
Nits:

• Use Con Edison Service address and customer name (as on bill)
• Appendix A and Contract – ‘Company’ should be ‘Con Edison’
• Need to submit a separate application and agreement for each account

                                                                                     8

                                                                                 ON IT
               Question?

              Thank you!

    Streamlining Solar in NYC
Con Edison Interconnection Process
               August 6, 2010


         Margarett Jolly – DG Manager
      jollym@coned.com     212-460-3328       9