King’s Cross Countdown




 March    1 July   29 July     July &      September   November
                             August 2011
 2011     2011      2011                      2011       2011
Move Planning Timetable
              Building work        Removals          Furniture &
                                                     equipment

Autumn term   Complete major       •Outline removal programme scheduled
              construction &       •CSM confirms furniture & equipment
              commission           needed (old and new)
              services
Spring term   Commence fit out     Detailed removal planning with CSM
                                   move representatives


Summer term   Complete fit out     New furniture and equipment procured
              for priority areas
              e.g. workshops
Summer        Handover of        Equipment and furniture relocated,
holidays      completed building delivered and installed
Move Plan will …
Plan and manage the relocation from our current sites

Work with CSM move representatives to co-ordinate packing, removal
and unpacking

Provide detailed information packs and other communications about the
move

Co-ordinate any specialist removals e.g. workshop machinery, museum
collection, library

Manage the removals company and the actual removals

Co-ordinate the delivery of equipment, furniture and materials
Central Saint Martins
Central Saint Martins




To book email your details to:


kingscross@csm.arts.ac.uk

						
Related docs
Other docs by chenmeixiu
MILLER COLLEGE OF BUSINESS
Views: 247  |  Downloads: 0
Climate Change Assessment of Development Options
Views: 154  |  Downloads: 0
cu
Views: 174  |  Downloads: 0
by BARRY TYLER
Views: 257  |  Downloads: 0