									                               Scrapers in the SPS
                                making clean scraping

•   Tests made in 2003

•   H and V scrapers at 51459 (from ISR)

•   2 stage collimation system:
      primary collimators at 51699 (V) and 51702 (H) at 90° from scrapers
      secondary collimators at 51932(V) and 51931 (H) at 90° from primaries
      2 jaws (IN/OUT or UP/DOWN) per collimator

•   2 preparation tests,
      first one on P2 to set-up equipment,
      the second one during long MD to adjust the scraper timing on the flat top.




                                  C.Fischer - SLI 01/04/2004
                             Scrapers in the SPS
                               making clean scraping
•   Actual test performed in October 2003
             one batch of 28.1011 protons
             10% of the current removed
             V scraper sweeping at 0.3 mm
             in the second half of flat top


•   Collimator adjusted in order to concentrate the losses at their location.




                                C.Fischer - SLI 01/04/2004
Scrapers in the SPS
  making clean scraping
No collimation - no scraping – signal from BLMs




    C.Fischer - SLI 01/04/2004
                 Scrapers in the SPS
                 making clean scraping
Collimators IN     primary: H ± 14 mm, V ± 17 mm: -   with V scraping
                   secondary: H: ± 15 mm, V ± 18 mm




                                                       LSS5




                   C.Fischer - SLI 01/04/2004
Scrapers in the SPS
making clean scraping




                              Scraping&collimation
                                     in LSS5




 C.Fischer - SLI 01/04/2004
                         Scrapers in the SPS
                          making clean scraping

                                 However

•   LSS5 must be kept clean – lots of instrumentation

•   The whole set of scrapers & collimators must be relocated elsewhere (2005)

•   Looks difficult in sextants 1 2 3

•   LSS6 possible candidate but not straightforward



• A solution must still be found



                             C.Fischer - SLI 01/04/2004
                           Scrapers in the SPS
                            making clean scraping


•   Cost: 12 k CHF (cables + transport) + 10 k CHF if VME crate needed

•   Cooling needed in the future

•   Scrapers 30 years old (ISR) ⇉ exceed their MTBF
         ⇉ need probably to be rejuvenated for reliable daily operation

•   New components, new study : ≃ 15 k CHF




                              C.Fischer - SLI 01/04/2004
                       Scrapers in the SPS
                        making clean scraping



Planning for 2004

•   check the effectiveness of scraping with BIPMV and BSRT

•   Cross- calibrate/compare BLMs and Scintillators signal




                           C.Fischer - SLI 01/04/2004
 Scrapers in the SPS
making scraping operational
     Present scraper & collimator control




    C.Fischer - SLI 01/04/2004
                            Scrapers in the SPS
                          making scraping operational


•   At the moment works on P2 events only

•   Timing adjustments (experts) required to scrape on P1 (long MDs)

•   New software for scrapers being prepared (G. Crockford- J.J. Gras)
          problem should be solved

•   Collimators , scintillators to be incorporated ?




                                C.Fischer - SLI 01/04/2004
    Costs and hardware implications for another scraper

•    One scraper associated with 4 collimators ?
           H & V primary and H & V secondary

•    2 scraper mechanisms in reserve,
           one available for installation, one kept as a spare

•    3 collimators in reserve,

•    4 (radioactive) other ones stored in ISR tunnel, some handling is required to looked
     at them;
•    one of them easily accessible, 38 mSv, W, Cu oxydation to be checked, vacuum
     tests to be performed ?


•    motorisation available, to be incorporated



                                  C.Fischer - SLI 01/04/2004
     Costs and hardware implications for another scraper

•   Scraper preparation              ≃                      15-20 k CHF
•   New tank                                                10 k CHF
•   New control                                             10 k CHF
•   Installation of 1 scraper and 4 collimators             25 k CHF
            cabling, cooling , crate, transport


•   APPROX. TOTAL COST                                      65 k CHF



• location: where ?