					                                                   Ministry of Provincial Councils & Local Government
Loan
   Implementing Agency               Project         Agreement                                                           Amount in mn            In US$ mn
                                                    Date/Closing
                                                                   Donor            Main activities          Currency   Total    Dis. up to   Total   Dis. up to                 Current Status
                                                        Date
                                                                                                                        loan     31/03/05     loan    31/03/05

M / Provincial Councils &      Provincial Road     26.03.2003      Japan   Rehabilitation and upgrading of   JPK           5.8          0.3    56.2          2.9 as at 31.12.2004
Local Government               Improvement Project 31.12.2008              secondary roads and bridges in                                                        Appointment of Project Implementation
                                                                           the Sabaragamuwa and Central                                                          Consultant - The Consultants have been
Contact Person                                                             Provinces and consultancy                                                             mobilized.
Project Mr. Wijekoon                                                       services for construction                                                             Procurement of Project Vehicles, Office
Tel : 672734 , Fax: 673077                                                 supervision                                                                           Equipment & Furniture - completed
e-mail : jbicprip@sltnet.lk                                                                                                                                      Road Organizations of the two Provincial
       npdprip@sltnet.lk                                                                                                                                         Councils - set up and awaiting the approval of
                                                                                                                                                                 respective Governors
ERD : Mr. Indika Premaratna,                                                                                                                                     Fixing Road Boundary on Project Roads -
AD                                                                                                                                                               Contracts for the survey work have been
   Tel :2484711, Fax:                                                                                                                                            awarded and work commenced in the Central &
2447633                                                                                                                                                          Sabaragamuwa Provinces. 90 % of the road
 e-mail : indika@erd.gov.lk                                                                                                                                      boundary survey for Phase 1 in Sabaragamuwa
                                                                                                                                                                 has been completed by Survey Department.
                                                                                                                                                                 Establishment of Metal Quarries and Borrow
                                                                                                                                                                 Pits - few metal quarries have been identified
                                                                                                                                                                 and samples of them have been handed over to
                                                                                                                                                                 University of Peradeniya for testing

                           Southern Provincial    19.01.1998       ADB     Rehabilitation of about 616 km C, SDR          22.0         20.4    33.3         30.9 . Phase I - IV civil works contracts are
Contact Person             Road Improvement       31.12.2003               D & E class roads and                                                                 completed; PMU is in the process of issuing
Project Dir. Mr.Ranjith    Project                                         construction of 11 bridges in the                                                     completion certificates and verifying final
Premasiri                                                                  Southern Province. Improve                                                            payments. Phase V civil works are almost
Tel :09-23845 Fax:09-41595                                                 capacity of Southern RDA to                                                           completed except SPRDA head office building,
                                                                           manage the road network                                                               which should be completed before 15 June
ERD- Mr.Alexi                                                              efficiently.                                                                          2004. The capacity building component is
Gunasekera,AD                                                                                                                                                    substantially complete; all other outstanding
Tel: 2484726 Fax: 2447633                                                                                                                                        matters to be finalized before end May 2004.
e-mail: alexi@erd.gov.lk                                                                                                                                         The loan was closed on 30th June 2004. Civil
                                                                                                                                                                 works have been completed and finalizing in the
                                                                                                                                                                 accounts are in progress.
   Implementing Agency               Project         Agreement                                                            Amount in mn            In US$ mn
                                                    Date/Closing
                                                                   Donor            Main activities           Currency   Total    Dis. up to   Total    Dis. up to                 Current Status
                                                        Date
                                                                                                                         loan     31/03/05     loan     31/03/05

Road Agencies in Western, Road Sector            10.02.2003        ADB     National highways                   SDR         42.8          6.4    64.6           9.6 Project Implementation consultancy contract
North Western, North Central Development Project 30.06.2008                -Provincial roads                                                                       was awarded in February 2004.
and UVA                                                                    Rehabilitation of 980 km of C,D &
RDA                                                                        E class roads. Capacity building of
Contact Person                                                             road agencies in provincials and
Project Dir : D G S                                                        private sector contractors.There
Chandralal,                                                                will be 52 roads and 17 bridges
Tel :2885490                                                               contracts.
RW R Premasiri : Tel :
2672732

ERD - Mr Alexi
Gunasekera,AD
Tel : 2484727, Fax:2447633
e-mail:alexi@erd.gov.lk


M/Provincial Council & Local   Road Sector         21.08.2003      OPEC Upgrading 980 km. of provincial      USD            8.5          1.1      8.5          1.1 as at 31.12.2004
Government                     Development Project 31.12.2007           roads by widening to 6.7 m 2.                                                              1. 96% of civil work contract package in phase 1
Contact Person                 (co-financing with                       Repairing of provincial bridges,                                                           have been awarded.
Mr. R.W.R.                     ADB)                                     culverts & drainage structures 3.                                                          2. Tender have been called and Tender
Premasiri,Project Director                                              Rehabilitation of 40 km. of                                                                Technical Evaluation is processing for civil work
T.P. 011-2672731                                                        community access roads with a                                                              phase II
    011-2672732                                                         modified grael surface
ERD: Contact person Mr.
T.M.J. Bandara Tel: 94-11-
2484791 Fax: 2447633
e-mail:
jayarathne@erd.gov.lk
   Implementing Agency                Project           Agreement                                                             Amount in mn            In US$ mn
                                                       Date/Closing
                                                                      Donor            Main activities            Currency   Total    Dis. up to   Total   Dis. up to                  Current Status
                                                           Date
                                                                                                                             loan     31/03/05     loan    31/03/05

M / Provincial Council and      Conflict Affected     14.01.2004      ADB     Project is to rehabilitate and       SDR         35.0          0.7    52.9          1.1 The project is progressing satisfactorily.
Local Government                Area Rehabilitation   30.06.2008              reconstruct essential infrastructure                                                    Component
RDA                             Project                                       & restoration of community                                                              A: Roads Rehabilitation: Tender documents
CEB                                                                           livelihoods in the affected district                                                    have been approved by ADB Component
NWS&DB                                                                        of North and East and in conflict-                                                      B: Power Sector: Subprojects/villages for Rural
Project Directors:                                                            affected divisions of the four                                                          Electrification has been identified and
Electrification -Mrs.B.                                                       adjacent districts of Puttalam,                                                         procurement has begun.
Jayaweera 2335922                                                             Polonnaruwa, Anuradhapura &                                                             C: Community Development: The project has
Roads -mr. S. Meihandan                                                       Moneragala.                                                                             identified and approved 153 subprojects
2865122                                                                       Rehabilitation of about 500 km of                                                       covering all eight districts. Procurement for over
Community Development -                                                       national roads                                                                          90 subprojects have been awarded during 2nd
Mr. T. Lankaneson                                                             Rehabilitation of power                                                                 quarter 2004.
0262227434/435                                                                transmission, distribution & rural                                                      D: Feasibility Study Jaffna Water Supply:
ERD: Mr. Alexi Gunasekera,                                                    electrification                                                                         Technical evaluation of consultants has
AD                                                                            Smaller scale community                                                                 completed. Staffing for the project office has
Tel 248726, Fax: 2447633                                                      infrastructure rehabilitation and                                                       been approved by the ministry, but recruitment
e-mail: alexi@erd.gov.lk                                                      activities such as schools, water                                                       has not started.
                                                                              supplies, health centres, minor
                                                                              roads, renewable energy
                                                                              Undertake a feasibility study for
                                                                              water supply & sanitation systems
                                                                              for Jaffna peninsula




North East Provincial Council   North East          01.11.2001        ADB     To contribute government overall SDR             19.7          9.1    29.7         13.9 1. Total funds allocated for anchor sub projects
Project Director : Mr.          Community           30.06.2007                releaf and rehabilitation program                                                       committed. OPEC loan is utilized for financing of
T.Lankaneson                    Restroation &                                 for the North East. By improveing                                                       15.8% of the toatl cost of the anchor sub
Tel: 0262227434/435             Development Project                           the living conditions and well-                                                         projects.
ERD: Mr. Alexi Gunasekera,                                                    being of communities that have
AD                                                                            been affected complete.
Tel 248726, Fax: 2447633
e-mail: alexi@erd.gov.lk
   Implementing Agency              Project           Agreement                                                       Amount in mn            In US$ mn
                                                     Date/Closing
                                                                    Donor          Main activities        Currency   Total    Dis. up to   Total    Dis. up to                 Current Status
                                                         Date
                                                                                                                     loan     31/03/05     loan     31/03/05

M/ Provincial Council & Local North East            16.05.2002      OPEC The Project consists two parts    USD          4.0          1.9      4.0          1.9 as at 31.12.2004
Government North East         Community             30.05.2007           1. Larger scale sub projects                                                          1. Funds committed for 494 sub projects
Provincial Council            Restoration Project                         a) Reconstruction of small scale                                                     completed
Contact Person                (co-financing with                         infrastructure                                                                        2. contracts for 437 sub projects awarded
Mr. T. Lankanneson            ADB)                                        b) Provision of equipment,                                                           3. 202 sub projects completed
Project Director-                                                        furniture, vehicles, training,                                                        4. 14 village rehabilitation plans in progress
T.P. : 026-2227434-5                                                     shelter, agriculture inputs for
ERD: Contact person                                                      resettled/relocated people
Mr.T.M.J. Bandara Tel: 94-11-                                            2. smaller scale community based
2484791 Fax: 2447633                                                     development sub-project
e-mail:
jayarathne@erd.gov.lk
   Implementing Agency            Project           Agreement                                                                Amount in mn           In US$ mn
                                                   Date/Closing
                                                                  Donor             Main activities              Currency   Total   Dis. up to   Total   Dis. up to                  Current Status
                                                       Date
                                                                                                                            loan    31/03/05     loan    31/03/05

M / Provincial Councils &   North East Irrigated    21.12.1999    WB      Rehabilitation of 400 small              XDR      19.6      17.2       29.6          26.0 1. Livelihood Support Activities (LSAs) - DCA
Local Government            Agricultural Project    30.06.2005            irrigation schemes with area of                                                           has been amended to facilitate LSA in January
                                                                          16,000 ha.                                                                                2003, I LSAs are managed by Women Rural
Contact Person:                                                           NGO support for Social                                                                    Development Societies(WRDS) - Repayable
Project Dir: Mr.                                                          Mobilization                                                                              small scale grants have been provided for
P.Ramanathan                                                              Community level small                                                                     15504 projects. These are small scale funds for
Tel: 026-22468 Fax: 026-                                                  construction and training of                                                              income generating activities. (Target 18781
24006                                                                     beneficiaries and staff                                                                   projects) A good number of WRDSs have
    026- 24005                                                            Rehabilitation of 1200 Km of rural                                                        completed the first round of lending repayments
e-mail: neiap@sltnet.lk                                                   roads.                                                                                    have begun, and second round of lending too
                                                                          Construction of 300 nos. drinking                                                         has started.
ERD- Ms.R.A.Champika, AD                                                  water wells.                                                                              2. Sustainability
Tel: 484793 Fax: 447633                                                   Feasibility study for rehabilitation                                                      Most of the tanks have been rehabilitated and
e-mail:                                                                   of 10 selected major/medium                                                               handed over to FOs wells and community
champika@erd.gov.lk                                                       irrigation schemes                                                                        buildings etc. constructed have been taken over
                                                                                                                                                                    by RDSs and WRDSs.
                                                                                                                                                                    Institutional arrangements for maintenance of
                                                                                                                                                                    rural roads (Class 1) & E is a grey area.
                                                                                                                                                                    Responsibility lies with Pradesiya Sabas but
                                                                                                                                                                    fiscal and technical constraints are there.
                                                                                                                                                                    3. Civil Works
                                                                                                                                                                    Most of the projects civil works completed by
                                                                                                                                                                    Dec. 31, 2004. A few activities including repairs
                                                                                                                                                                    to Giant tank remains but could be completed in
                                                                                                                                                                    the 1st from month of 2005.
   Implementing Agency                Project           Agreement                                                                 Amount in mn             In US$ mn
                                                       Date/Closing
                                                                       Donor            Main activities           Currency    Total      Dis. up to   Total      Dis. up to                    Current Status
                                                           Date
                                                                                                                              loan       31/03/05     loan       31/03/05

North/East Provincial Council   North/East                Part Z :   WB        Assist NEPC in carrying out a      USD        31                       31                      1. Total project cost of US$ 36 mn is provided
Contact Person:                 Emergency             04.12.2992 N/E           programme in affected areas                                                                    from the Unutilzed funds transferred from 3 IDA
Project Dir: Mr. S. Rangaraja   Reconstruction        Reconstruction           assistance to IDPs, development                                                                Projects-PSIDC US$ 26 mn MRRP- US$ 5 mn,
Tel: 026-22012 Fax: 026-        Programme              Agreement :             of health, water sectors and                                                                   CBSL US$ 5mn. Amended the DCA on
20000                                                   12.12.2002             capacity building at in NEPC are                                                               30/08/2004 in order to include the vehicle
e-mail: nepcso@sltnet.lk                                                       considered.                                                                                    maintenance under incremental operating costs.
                                                                                                                                                                              2. Extended the project period upto 30/06/2005.
ERD- Ms.R.A.Champika, AD                                                                                                                                                      3. Proposed to utilize savings of SDR vs Dollar
Tel: 484793 Fax: 447633                                                                                                                                                       appreciation for the Cancer Hospital Tellipalai
e-mail:                                                                                                                                                                       and for the living quarters and transport facilities
champika@erd.gov.lk                                                                                                                                                           for Cancer Hospital Staff.
                                                                                                                                                                              4. 85% of the civil worked have been completed.




Grant
   Implementing Agency                Project           Agreement                                                              Amount in mn              In US$ mn
                                                       Date/Closing                                                           Total Dis. up to        Total Dis. up to
                                                           Date        Donor            Main activities           Currency    grant 31/03/05          grant 31/03/05                           Current Status


M / Provincial Councils &       Improvement of        30.06.2001      German Improve the service delevery of      EUR              2.6          1.4        3.3          1.8 13 Underserved settelements have been
Local Government Contact        Infrastructure and    31.12.2007      y (gtz) CMC to the underserved                                                                        selected based on the Poverty Profile Report
Person                          Service Delivery in                           settlements with community                                                                    prepared by CMC. Community modules have
Project Dir : Mr. N. S.         Underserved                                   participation                                                                                 been prepared with the purpose of building a
Jayasundara, Deputy             Settlements of                                                                                                                              sound partnership between CMC and CBOs.
Municipal Commissionr           Colombo                                                                                                                                     Distric teams were establised.
Tel :268 1198
Fax : 267 1282

ERD : Mr S M Piyatissa, AD
Tel : 2484788 ,
Fax : 2447633
e-mail : piyatissa@erd.gov.lk

				