									    PROJECT STATUS REPORT EXAMPLE

    LMT/PEL LIMS DEPLOYMENT PROJECT

    Table 1. Progress Report

Project Name: LMT/PEL LIMS Deployment Project

Project Manager: Mary Smith

Report Date: December 15, 2006


Project Start Date: 2/6/2006

Original Planned Completion: January 2008

Revised Completion Date: December 2008


Project Summary Information
       ● The transition of LMT data from the FINCH system to the LIMS module developed by Group A is
           nearly complete. Although the data has not completely loaded into the LIMS for final testing,
           operationally, the LIM system is stable.
       ● Documentation for the LMT LIMS developed by Group A is expected to be delivered at the end of
           January 2007 at which time, transition of the LIMS to Group B will be considered complete.
       ● Development of the caBIG compliant LMT LIMS is proceeding as planned although some tasks
           had to be accomplished in a different sequence than originally planned. While this did not affect
           the completion of the project, funding issues affected planned recruitment and, therefore, the
           overall project schedule.
       ● Recruitment of the Programmer 3 position has begun; candidate to be interviewed Jan 2007.


2007 Project Budget: $285,945

       Labor: $********
       Equipment: Hardware, Software: $5,500
       Travel: $10,000 (LIMS Meetings)

       2007 Cost to date: $*****.***


Executive Summary:

       ●    The expertise of the LIMS Integrator in developing LMT caBIG compliant LIM systems has been
            vital to the success of the current project.
       ●    Transition of the caLIMS from group A is proceeding well.
       ●    Funding issues delayed recruitment of the second and third programmers and consequently, the
            schedule.
       ●    The second programmer being recruited; a qualified applicant has been found.
       ●    Recruitment for the Helpdesk support will begin in February.



                                                -1-
    PROJECT STATUS REPORT EXAMPLE




   Table 2. Project Activity
  Deliverable/ Activity      Scheduled        Planned       Actual      Revised          Rationale
                               Start         Completion      Start        Com-
                                                                         pletion
LMT Phase I                  Sep 2006        Jan 2008     Sep 2006      May         Assembly model was
                                                                        2007        required for
                                                                                    integration with
                                                                                    caLIMS for transition
                                                                                    to Group B
LMT Phase II                 May 2007        Nov 2007
LMT Phase III                Dec 2007        May 2008
LMT Phase IV                 Jun 2008        Aug 2008
PEL Phase I                  Feb 2007        Sep 2007                               Delayed start due to
                                                                                    lack of resources
PEL Phase II                 Sep 2007        Apr 2008
PEL Phase III                Apr 2008        Dec 2008


    Table 3. Risk Update
    New Risk Identified        Probability      Impact    Response      Owner        Status/ Outcome
                                                           Strategy

Scarcity of qualified LIMS    High            High        Broaden       Group      Qualified application
programmer applicants                                     recruitment   B          received; to be
                                                          venues to                interviewed early Jan
                                                          include                  2007
                                                          LIMS
                                                          websites.