PROJECT STATUS REPORT EXAMPLE

Reviews
PROJECT STATUS REPORT EXAMPLE LMT/PEL LIMS DEPLOYMENT PROJECT Table 1. Progress Report Project Name: LMT/PEL LIMS Deployment Project Project Manager: Mary Smith Report Date: December 15, 2006 Project Start Date: 2/6/2006 Original Planned Completion: January 2008 Revised Completion Date: December 2008 Project Summary Information ● The transition of LMT data from the FINCH system to the LIMS module developed by Group A is nearly complete. Although the data has not completely loaded into the LIMS for final testing, operationally, the LIM system is stable. ● Documentation for the LMT LIMS developed by Group A is expected to be delivered at the end of January 2007 at which time, transition of the LIMS to Group B will be considered complete. ● Development of the caBIG compliant LMT LIMS is proceeding as planned although some tasks had to be accomplished in a different sequence than originally planned. While this did not affect the completion of the project, funding issues affected planned recruitment and, therefore, the overall project schedule. ● Recruitment of the Programmer 3 position has begun; candidate to be interviewed Jan 2007. 2007 Project Budget: $285,945 Labor: $******** Equipment: Hardware, Software: $5,500 Travel: $10,000 (LIMS Meetings) 2007 Cost to date: $*****.*** Executive Summary: ● ● ● ● ● The expertise of the LIMS Integrator in developing LMT caBIG compliant LIM systems has been vital to the success of the current project. Transition of the caLIMS from group A is proceeding well. Funding issues delayed recruitment of the second and third programmers and consequently, the schedule. The second programmer being recruited; a qualified applicant has been found. Recruitment for the Helpdesk support will begin in February. -1- PROJECT STATUS REPORT EXAMPLE Table 2. Project Activity Deliverable/ Activity Scheduled Start LMT Phase I Sep 2006 Planned Completion Jan 2008 Actual Start Sep 2006 Revised Completion May 2007 Rationale Assembly model was required for integration with caLIMS for transition to Group B LMT Phase II LMT Phase III LMT Phase IV PEL Phase I PEL Phase II PEL Phase III May 2007 Dec 2007 Jun 2008 Feb 2007 Sep 2007 Apr 2008 Nov 2007 May 2008 Aug 2008 Sep 2007 Apr 2008 Dec 2008 Delayed start due to lack of resources Table 3. Risk Update New Risk Identified Probability Impact Response Strategy Broaden recruitment venues to include LIMS websites. Owner Status/ Outcome Scarcity of qualified LIMS programmer applicants High High Group B Qualified application received; to be interviewed early Jan 2007 -2-

Related docs
status report example
Views: 642  |  Downloads: 20
Project Status Report
Views: 194  |  Downloads: 39
status report
Views: 1231  |  Downloads: 43
STATUS QUO REPORT
Views: 15  |  Downloads: 2
Status Report example
Views: 929  |  Downloads: 152
Weekly Status Report
Views: 168  |  Downloads: 19
Status report of the ANTARES project
Views: 6  |  Downloads: 0
Project Status Report
Views: 580  |  Downloads: 4
SCITITPWG26 AIMS Project Status Report
Views: 0  |  Downloads: 0
Example Species Status Summary
Views: 4  |  Downloads: 0
Status Report of the
Views: 9  |  Downloads: 0
Other docs by LeesRadford