									STScI HST Servicing Mission 4
  Delta Readiness Review

           April 21, 2009

  Space Telescope Science Institute
     John N. Bahcall Auditorium
                          Agenda (1)
1. Introduction and Summary          Helmut Jenkner        30’
    a) Agenda
    b) Purpose and Scope
    c) Proposal Processing
    d) Long Range Plan
    e) Data Management Systems
    f) Freeze Plan
    g) Data Release Policy
    h) NICMOS Readiness
    i) Operational Readiness
    j) SM4 Support
    k) SMOV Management and Reporting
    l) OPO Readiness




April 21, 2009          STScI SM4 Delta Readiness Review         2
                              Agenda (2)
2.      SMOV Program                            Carl Biagetti           20’
3.      Planning and Scheduling                 Merle Reinhart          15’
4.      Commanding                              Alan Welty              10’
5.      Calibration Pipeline                    Warren Hack             10’
6.      WFC3 Readiness                          John MacKenty           20’
7.      COS and STIS Readiness                  Alessandra Aloisi       25’
8.      ACS Readiness                           Linda Smith             15’
9.      FGS and OTA Readiness                   Ed Nelan / Matt Lallo   10’
10.     ERO Readiness                           Keith Noll              10’
11.     Infrastructure                          Doris McClure           10’
12.     DRR Action Item Review                  Ken Sembach             10’




April 21, 2009              STScI SM4 Delta Readiness Review                  3
Introduction and Summary

      Helmut Jenkner
                            Purpose and Scope

    Purpose: Demonstrate STScI Readiness for SM4.
    Scope: This is a Delta Readiness Review:
          Builds on SM4 Readiness Review held on September 9
           and 10, 2008:
                Presentations available at
                 http://www.stsci.edu/institute/org/hstmo/sm4/readinessreview
                All action items from that review have been closed (see list in
                 backup charts).
          Concentrates on updates, changes and new items,
           including new work done.
          Areas with only small changes are summarized in this
           initial presentation.


April 21, 2009                    STScI SM4 Delta Readiness Review                 5
Proposal Processing

    Denise Taylor
                      SMOV Proposals

    150 proposals (not including ERO and withdrawn props)

    35 COS props (164 ext. orb., 111 int. orb.) - All ready.
    31 ACS props (38 ext. orb., 493 int. orb.) – All ready
    42 WFC3 props (163 ext. orb., 370 int. orb.) - All ready
    25 STIS props (21 ext. orb., 174 int. orb.) - All ready
    12 NIC props (34 ext. orb., 136 int. orb.) - All ready
     3 PCS props (41 ext. orb.) - All ready
     2 FGS props (22 ext. orb.) - All ready




April 21, 2009           STScI SM4 Delta Readiness Review       7
                      ERO Proposals

    8 ERO proposals to be executed after SM4 for 89
     orbits (ERO proposal 11500 executed 3 orbits on
     Eta Carina in September 2008 with WFPC2.)

    All ERO proposals are ready for flight:
          Three WFC3 ERO
          One STIS ERO
          One ACS ERO
          Three COS ERO




April 21, 2009         STScI SM4 Delta Readiness Review   8
                 Cycle 17 Proposal Pool (1)

    197 GO proposals including those from HST Cycle 17 TAC,
     Chandra TAC, and previous HST TACs, for 3627 orbits.
    16 SNAP proposals, for 1417 orbits.
    24 GTO/COS proposals for 291 orbits.
    3 GTO/ACS proposals for 24 orbits.
    2 ERS proposals for 214 orbits.
    3 GO/PAR proposals for 410 orbits.

    103 Calibration proposals for 1088 external orbits, 7069
     internal orbits.




April 21, 2009          STScI SM4 Delta Readiness Review        9
                 Cycle 17 Proposal Pool (2)
    Program Coordinators (PCs) are processing observations in the pool: ~
     7000 external and ~7000 internal orbits. Eight calibration proposals still
     to be submitted.
    Instrument teams have been reviewing these observations and will
     have most done before SM4. Remaining will be done according to Long
     Range Plan schedule.
    Final processing steps will wait until after SM4, when the ground system
     is reconfigured for 3 gyro mode.
    Time-critical Cycle 17 GO observations have been executing in 2-gyro
     mode since October 2008 (96 orbits so far).
    After SM4, all remaining Cycle 15, 16 proposals will be re-worked for 3-
     gyro mode.
    Remaining NICMOS observations are being switched to another
     existing or future instrument, when possible to reach scientific goals
     without NICMOS.


April 21, 2009               STScI SM4 Delta Readiness Review                10
Cycle 17 Long Range Plan

        David Adler
                                     Cycle 17 Long Range Plan

                     Cycle 17 Long Range Plan has been rebuilt.
                     Distribution is mostly smooth, with some minor
                      resource conflicts being worked:
                              End of SMOV:                                      End of Cycle 17
                              Aug 17, 2009                                      Aug 31, 2010




                     SM4, SMOV                                                             Cycle 17 “tail”
                     (not in plan)
orbits/day




         11
             0


                 April 21, 2009              STScI SM4 Delta Readiness Review                                12
                     Cycle 17 Plan: Numbers
    SMOV, EROs (not included in Cycle 17): ~500 orbits.

Cycle 17 Statistics:
 380 days in length (8/17/09 - end of SMOV - to 8/31/10).
 Cycle 17 GO, GTO, cals, etc: ~4550 orbits (100 NIC).
 Cycle 15/16 carryover: ~600 orbits (500 NIC).
 Total C15/16/17: ~5150 orbits.
 Planned Cycle 17 “tail:” ~650 orbits.

Expected subscription:
 4500 orbits/380 days = 11.8 orb/day ~ 82.6 orbits/week.
 Slightly above the anticipated rate of 80 orbits/week.
          Some science may come forward into SMOV if space allows.
          Some orbits may be dropped if NIC restart is unsuccessful.

LRPG is ready for SMOV and Cycle 17.


April 21, 2009                  STScI SM4 Delta Readiness Review        13
Data Management Systems

    Al Holm, Lisa Gardner
                     SM4-Related Deliveries
                     Since September 2008
    DMS 2008.4 was delivered on October 7, 2008
          13 PRs for COS, 4 PRs for ACS, 1 PR for Fastrak
    DMS 2008.5 was delivered on November 13, 2008
          2 PRs for COS and 1 PR for ACS
    DMS 2009.1 was delivered on March 9, 2009
          18 PRs for COS, 3 PRs for ACS, and 1 PR for WFC3
    DMS 2009.2 was delivered on April 14, 2009
          16 PRs for COS, 2 PRs for WFC3, 1 PR for both COS and WFC3,
           and 1 PR for STIS
    STSDAS deliveries were delivered with each of these
     builds and included a total of 55 PRs for COS, 25 PRs for
     WFC3, and 2 PRs for ACS

April 21, 2009               STScI SM4 Delta Readiness Review            15
                 Outstanding SM4-Critical PRs
    The following Problem Reports are planned to be
     quick-fixed before SMOV
          OPUS 62322 "COS images with subarrays are not being
           populated correctly”
          STSDAS 62336 "CALACS crashes with floating-point
           CCDGAIN in _raw files”
    Both PRs have been tested and are ready to go




April 21, 2009           STScI SM4 Delta Readiness Review    16
Freeze Plans

   HSTMO
                          SM4 Freeze Plans
    HSTP Level Freeze
          Started on April 13.
          Extends into SMOV (~few weeks) at discretion of HST Operations
           Project Manager.
          Requires HSTP approval for installations while freeze is in effect.
    HSTMO Level Freeze
          Started on April 13.
          Extends into SMOV (~few weeks) at discretion of HSTMO.
          Requires HSTMO approval for installations while freeze is in effect.
          Generally will be discussed and approved at SMOV meetings, or via
           email.
    Some systems will not be affected
          Must protect systems essential for SM4 and SMOV4…
          But allow other work to proceed efficiently.


April 21, 2009                 STScI SM4 Delta Readiness Review                  18
                          HSTP Level Freeze

    Software covered:
          SPSS
                Commanding
                SRT
                GSSS, POPS, POMS, etc.
          PASS
          PRD
    Hardware covered:
          PASS servers
          SPSS servers
          Network switches and routers


April 21, 2009                STScI SM4 Delta Readiness Review   19
                            HSTMO Level Freeze
    Software covered:
          APT and TRANS (HST operational versions)
                Assist
                SPIKE elements used in APT
          OPUS, including operational pipeline versions of:
                CALxxx
                MultiDrizzle
                CDBS
                OMS
          DADS
          STSDAS
          Infrastructure and operating systems for above systems
    Hardware covered:
          “SOGS” network
          DMS hardware (Sunfire 15K, EMC, safestore devices, etc.)


April 21, 2009                   STScI SM4 Delta Readiness Review     20
                    Other HST Systems

    Unaffected by freezes:
          HLA
          GMS
          ETCs
          SPIKE
          PROMPT




April 21, 2009        STScI SM4 Delta Readiness Review   21
  Data Release Policy

HSTMO, Science Policies Group
                      Data Release Policy
                      Implementation (1)
    OPB has set initial proprietary period to one year
     for proposals using either new SIs or serviced
     modes.
          ERO and ERS data will remain proprietary until their
           press release.
          SMOV and calibration data for COS, WFC3, and the
           serviced modes will remain proprietary until ERO press
           release.




April 21, 2009             STScI SM4 Delta Readiness Review         23
                      Data Release Policy
                      Implementation (2)
    Manual process for shortening release dates will
     continue
          based on proposal ID, not visit or SI mode
    GO data taken with new SIs and with serviced
     modes will be embargoed
          authorization to access data from proposal will be
           withheld until the PI agrees not to discuss or present the
           data publicly until after ERO press releases




April 21, 2009              STScI SM4 Delta Readiness Review        24
                     Embargo Agreement Text
                                  (as revised per STScI RR AI04)


  Because NASA has not yet made the first Early Release Observations (EROs) public for the new
  and serviced instruments, the STScI requires that you agree to abide by the restrictions below
  before we can make your data accessible to you for retrieval. Once we receive an email reply
  with your acceptance of these restrictions, we will allow you access to your Cycle 17 data.

  All Guest Observers requesting access to their Cycle 17 data from new and serviced instruments
  before the NASA ERO press release date must agree to refuse any public discussion or display of
  these data and/or any scientific results derived from them until after the official NASA ERO press
  conference. Public discussions include seminars, colloquia, press conferences, lectures,
  conference posters, website postings, mass media interviews, and journal publications. Do you
  agree to these terms?

  Before you distribute these data further to co-investigators or other collaborators working with
  you on these data, they must agree to these terms also.

  Matt Mountain
  Director, Space Telescope Science Institute




April 21, 2009                       STScI SM4 Delta Readiness Review                                  25
   NICMOS Readiness

Tommy Wiklind, Anton Koekemoer
                 NICMOS SMOV4 Readiness

    NCS re-start attempt during the first week of
     SMOV:
          Detailed re-start procedure is being defined.
          Nominal cool-down time is estimated to be four weeks
           (previously two weeks).
          The NICMOS SMOV4 program remains the same as of
           September 2008.
          Coronagraphic programs placed at the end of the SMOV
           period.
          Photometric and grism calibrations will be done as part
           of a Special Cycle 17 Calibration program.
    If this NCS re-start attempt is unsuccessful, stand
     down from all NICMOS activities during SMOV.

April 21, 2009             STScI SM4 Delta Readiness Review      27
                 NICMOS SMOV4 Proposals
                    Team & Assignments




April 21, 2009       STScI SM4 Delta Readiness Review   28
                      NICMOS SMOV4 Calibration
                              Timeline
  Week 1
       NCS re-start *
  Week 1 - 4
       NCS cooling *
  Week 5 (4 external orbits)
       NICMOS SAFE to OPER *
       DC Transfer Test *
       Filter Wheel Test *
       Focus/Tilt I Check *
  Week 6 (4 external orbits)
       Focus/Tilt II (FSW updates if necessary) *
       FOM Functional (possibly FSW updates) *
       Start of Darks/Read Noise
       Start of Thermal background characterization
  Week 8 (10 external orbits)
       Aperture Locations (for SIAF update) *
       Optical Plate Scale (FSW update if necessary)
       NICMOS ERS enabled
  Week 12 - 14 (21 external orbits)
       (Coronagraphic Verification/Characterization)
       NICMOS Coronagraphic enabled
       Geometric stability                                           *) Time critical activities

April 21, 2009                     STScI SM4 Delta Readiness Review                                 29
DMS Operational Readiness

          Al Holm
                 Successful Test Activity

    Processed science data received from PACOR via
     the backup CD-R method.
    Tested destination directories for all fast track data.
    Supported data processing and delivery for the
     ACS-R Optimization Campaign Dry Run.
    Supported data processing and delivery for the SI
     C&DH SMGT.
    Supported data processing and delivery for
     SR4.2a.
    Conducted acceptance tests of DMS 2008.4,
     2008.5, 2009.1, and 2009.2, and supported their
     installation.

April 21, 2009         STScI SM4 Delta Readiness Review    31
SM4 Support

Chris Long et al.
                            Observatory Support Team
                           Project/JSC       Project/GSFC             STOCC            STScI                   STScI
    Orbit                  Mountain          Jenkner                  C. Long          Blades                  GSFC
                                                                                                                JSC
    Planning               Hauser            Sembach                  Wheeler          Biagetti                 IDT


                       WFC3                         COS                      STIS                            ACS
               GSFC              STScI       GSFC         STScI       GSFC          STScI         GSFC             STScI
 Orbit            Hartig                    Lennon                   Kaiser                       L. Smith       Cox
                  Petro                     Sahnow                   Oliveira                      Lucas        Platais
                                            J. Green                Woodgate                                   Gonzaga
                                             Penton
                                            McPhate


Analysis    MacKenty            Baggett      Keyes        Ake       Goudfrooij     Lennon       Golimowski     Maybhate
            Bushouse            Hilbert    Friedman       York       Proffitt       Wolfe        Mutchler      Chiaberge
                                           Osterman     Beland        Gull                          Lim        Desjardins
                                                        Froning      Linder



                                              FGS               Lallo/ Nelan
                                            NICMOS           Koekemoer / Wiklind
                                          Commanding          Welty / Dashevsky


 April 21, 2009                               STScI SM4 Delta Readiness Review                                              33
                 SM4 Science Schedule




April 21, 2009       STScI SM4 Delta Readiness Review   34
SMOV Management and Reporting

       Carl Biagetti, HSTMO
                      SMOV-Related Meetings
    SMOV Status and Planning Meeting (“Morning Meeting”):
          Daily (7 days/week) for first ~4 weeks, 3 days/week thereafter; 8:30 a.m.
          STScI Board Room, audio (video?) tie-in with GSFC.
          Lead: Biagetti; backup: Burley.
    SMOV Weekly Management Meeting:
          Time/venue TBD.
          HSTP Management, HSTMO, Biagetti, Burley.
    HST Mission Status Reviews (MSRs):
          3rd Tuesday of each month.
          Topics as required.
    SMOV Telescope Time Review Board (TTRB):
          Reviews changes to SMOV proposals and timeline.
          Biagetti, Burley, Niedner, Sembach, D. C. Taylor.
    SMOV Closure Review (~November 2009):
          Formal team reports.
          Trace-back to SMOV requirements.


April 21, 2009                   STScI SM4 Delta Readiness Review                      36
                   SMOV-Related Reporting

    Minutes from SMOV Status and Planning Meetings
     (Biagetti, Burley).
    HST Weekly Reports:
          Highlights only; links to Minutes.
    SMOV Closure Report:
          Following SMOV Closure Review.




April 21, 2009              STScI SM4 Delta Readiness Review   37
   OPO Readiness

Stratis Kakadelis, Mario Livio
                 OPO SM4 Readiness
All OPO SM4 products/services are
ready for launch
   News: newsroom support at KSC & JSC –
    daily video updates
   Education: specialized content for students
    & educators on Amazing Space – special
    SM4-themed museum shows distributed
    through ViewSpace network
   Online: partnership with NASA web portal for
    content & videos complete – SM4 portal page
    on HubbleSite
   Origins: SM4 info feed to International Year
    of Astronomy websites and amateur groups
April 21, 2009         STScI SM4 Delta Readiness Review   39
Backup Charts
                 Action Items from September
                 Readiness Review - Day 1 (1)
    A01: SMOV TTRB membership needs to be defined (Biagetti)

    A02: Provide recommendation for whether or not a SMOV replanning exercise is
     necessary (Biagetti, in consult with Burley and HSTMO)

    A03: Provide information about SNAP program to K. Kalinowski (Sembach)

    A04: Revise wording for Data Release Policy to include collaborators and Co-Is
     requesting access (Holm)

    A05: Provide recommendation for whether or not a Fastrack test using existing dataset
     (e.g., NICMOS or ACS O-scope mode) is needed (Holm)

    A06: Secure shipping/receiving entrance so visitors must use front entrance) (Schnader /
     Director’s Office)




April 21, 2009                   STScI SM4 Delta Readiness Review                            41
                 Action Items from September
                 Readiness Review - Day 1 (2)
    A07: Assess options for identifying persons entering building with attention to what must
     be implemented both for permanent staff and for short/long-term visitors during SM4 and
     SMOV (Schnader / Director’s Office)

    A08: Notify HSTMO when ACS Oscilloscope Mode data flow has been fully tested,
     including OPUS and Fastrack paths (Sirianni)

    A09: Provide HSTMO with WFC3 soft-safing description (MacKenty / Welty)

    A10: Provide Burley with summary chart of SM4 readiness dates for instruments / data
     systems / commanding / P&S / etc... (Sembach)

    A11: Provide Directorate with weekly description of SM4 preparedness and critical path
     items / dates (Doxsey)

    A12: Check with instrument and operations teams to make sure key personnel have
     GSFC badges in case long-term internet and/or power outage require relocation to
     GSFC (Sembach / Long / Workman)

    A13: Provide HSTMO with list/description of the 12 CALCOS modules that have not
     been verified by the COS PVT (Aloisi)

April 21, 2009                    STScI SM4 Delta Readiness Review                            42
                 Action Items from September
                  Readiness Review - Day 2
    B13: Provide HSTMO with hardcopy images of WFC3 detector illumination for various
     CSM positions to use during SM4 FT assessment (MacKenty)

    B14: Identify key SMOV alignment/focus instrument activities and times for which
     George Hartig is needed (Biagetti)

    B15: Provide HSTMO with target completion dates for SMOV Analysis Plans (Team
     Leads)

    B16: Review ACS SMOV decision points and responsible parties with HSTMO and
     Biagetti (Smith)

    B17: Provide focus decision tree, in consult with HSTMO (Lallo)

    B18: Finalize analysis strategy/personnel for EROs in consultation with instrument
     teams. Provide final list to HSTMO. (Noll)

    B19: Finalize strategy for which ERO observations are executed if SMOV schedule slips
     or decision is made to show results from less than nominal 9 EROs at AAS (Noll)

    B20: Provide updated Fastrack and real-time contact request list to Burley for SMOV
     planning (Biagetti)

April 21, 2009                   STScI SM4 Delta Readiness Review                          43
SMOV4 PLANNING READINESS

STScI SM4 DELTA READINESS REVIEW
           21 APR. 2009
            Carl Biagetti
                     SMOV4 PLAN
                  CHANGES TO DRIVERS

    ERO schedule is no longer driven by AAS
     schedule
          Therefore moved from weeks 7 & 8 to weeks 9 & 10

    All other drivers remain the same
          See 09Sep08 Readiness Review




April 21, 2009            STScI SM4 Delta Readiness Review    45
                      SMOV4 PLAN
                 CHANGES TO CONSTRAINTS


    No changes to SMOV planning constraints
          See 09Sep08 Readiness Review




April 21, 2009           STScI SM4 Delta Readiness Review   46
                         SMOV4 PLAN
                 PRIORITIZATION OF ACTIVITIES



    SMOV4 Plan prioritizes SMOV activities to allow
     schedule flexibility and proper sequencing
          No changes in prioritizations
          See 09Sep08 Readiness Review




April 21, 2009           STScI SM4 Delta Readiness Review   47
                               COS PLAN CHANGES
                                 SINCE SEP 2008
            Several recent Target Acq problems have surfaced
             and have been addressed
                    Subarray specifications
                    PSA/BOA reference points
                    Corrections to target placements in detector frame

            Proposal impacts
                    20 proposals needed to be updated (complete)
                       to address above problems
                       for mid-2009 targets

            Timeline Impacts
                    Additional uplink requirements
                    In-line commanding (PMDB) updates identified
                       Updates need to be submitted for upcoming SMSs
                    Several changes in activity dependencies
                    Several time-dependent targets (CVZ, etc.)

April 21, 2009                      STScI SM4 Delta Readiness Review      48
                            WFC3 PLAN CHANGES
                              SINCE SEP 2008
    SMOV transition from PROTECT to Nominal state
          Dave Hickey’s testing is complete
                resulted in some adjustments to r/t commanding for bench thermal
                 management
                Otherwise transparent to SMOV timeline
    Proposal impacts
          None
    Timeline Impacts
          None




April 21, 2009                     STScI SM4 Delta Readiness Review                 49
                           ACS PLAN CHANGES
                             SINCE SEP 2008

         Optimization Campaign (OC) Dry Run
          encountered several problems
                ground and flight sw configurations
                being worked or already solved
                analysis time between iterations needs to increase
      Proposal impacts
        Additional CTE/Cross-Talk check during OC
         Timeline Impacts
                Sixteen additional days for OC (total = 37 days)
                  may be mitigated by potential for early completion of test
                  Causes downstream delays to ACS CCD science/EROs

April 21, 2009                   STScI SM4 Delta Readiness Review               50
                               FGS PLAN CHANGES
                                 SINCE SEP 2008
    Mini-OFAD and FGS alignment (5 orbits ea.) moved to Cycle 17 Cal Plan
       FGS2 alignment wrt FGS 1&3 will be unstable in early SMOV

          New FGS will not be used as dominant guider in SMOV timeframe
          Therefore Proposals 11459 (Alignment) & 11460 (mini-OFAD) are deferred to
           Cycle 17
             Waiver of SMOV Requirements L.10.4.7.3.3 & L.10.4.7.3.


    Near Term Monitor of FGS2R2 Stability (4 orbits) moved to C17 Cal Plan
       Prop 11464 - relies on M35 which is not available in mid-2009
       Therefore deferred to Cycle 17 (Proposals 11874 & 11875)
                Waiver of SMOV Requirement L.10.4.7.3.8

    FGS1R & FGS3 Recommissioning (2 orbits) moved to C17 Cal Plan
       Prop 11463 - relies on M35 which is not available in mid-2009

       Therefore deferred to Cycle 17 (Proposal 11871)
                Waiver of SMOV Requirement L.10.4.7.3.7




April 21, 2009                        STScI SM4 Delta Readiness Review             51
                            FGS PLAN CHANGES
                          SINCE SEP 2008 – CONT’D

    FGS2R2 AMA Adjustment Activity
          Proposal 11458 will be scheduled starting in SMOV Week 2 instead of Week 1
             Lessens the effect of outgassing on the measurement results
             Allows additional pre-look visits in Week 1 for target determination for Week 2 AMA
               adjustments and some scale and coarse alignment information

    Proposal impacts from FGS changes
          Nelan/Reinhart have updated SMOV proposals
             11457, 11458, 11459, 11462



    Timeline Impacts from FGS changes
          Several SMOV days are gained by the deferrals to Cycle 17
          Gains are offset by decision to move AMA activities from Week 1 to Week 2
          FGS2R2 commissioning for guiding
             Remains at ~ SMOV Day 42

          These timeline adjustments were worked out in the GSWG and SMOVWG




April 21, 2009                        STScI SM4 Delta Readiness Review                              52
                      DMS PLAN CHANGES
                    SINCE SEP 2008 – CONT’D
    Proposal for special BEA attitude to test Bay 10 (SI
     C&DH) thermal model
          Feasible in early BEA period
          => New SMOV thermal requirement

    Proposal impacts
          None, only SMS-level changes

    Timeline Impacts
          None




April 21, 2009              STScI SM4 Delta Readiness Review   53
                         NICMOS PLAN CHANGES
                         SINCE SEP 2008 – CONT’D
    No recent changes

    Awaiting Project WG recommendation on NICMOS SMOV Plan

    Proposal impacts
          None
          Target updates for mid-2009 SMOV have been postponed
                Pending successful NCS reactivation and cooldown

    Timeline Impacts
          Current SMOV timeline includes nominal NICMOS plan on “non-
           interference” basis




April 21, 2009                     STScI SM4 Delta Readiness Review      54
                   SMOV4 MILESTONES
                       VEHICLE


AS OF 08DEC08                     AS OF                     AS OF    DELTA
                                 08DEC08                   21APR09   (DAYS)

 HST RELEASE = SMOV START         20 MAY                   20 MAY      0
 BEA PERIOD COMPLETES             10 JUNE                  10 JUN      0
 FGS2R2 ENABLED FOR GUIDING       02 JUL                   29 JUN     -3




April 21, 2009          STScI SM4 Delta Readiness Review                      55
                      SMOV4 MILESTONES
                  GO SCIENCE ENABLE POINTS

                                                                           DELTA
                           AS OF 08DEC08            AS OF 21APR09          (DAYS)

      FGS1R                        22 JUN                     10 JUN         -12

      STIS CCD                     09 JUN                     10 JUN          +1
      STIS NUV/FUV                 12 JUN                     17 JUN          +5
      STIS SMOV COMPLETE           25 JUN                     26 JUN          +1

      ACS SBC                      10 JUN                     12 JUN          +2
      ACS WFC                      27 JUN                     13 JUL         +16
      ACS HRC                      28 JUN                     13 JUL         +15
      ACS CORONAGRAPH              14 JUL                     30 JUL         +16
      ACS SMOV COMPLETE            14 JUL                     31 JUL         +17

      NICMOS IMAGING               TBD 24 JUL                 TBD 05 AUG     +12
      NICMOS CORONAGRAPHY          TBD 30 AUG                 TBD 28 AUG      -2
      NICMOS SMOV COMPLETE         TBD 06 SEP                 TBD 04 SEP      -2




April 21, 2009             STScI SM4 Delta Readiness Review                         56
                      SMOV4 MILESTONES
                 GO SCIENCE ENABLE POINTS (2)
                                 AS OF                   AS OF       DELTA
                                08DEC08                 21APR09      (DAYS)
    WFC3
          UVIS EASY             07 JUL                     01 JUL     -6
          IR EASY               07 JUL                     13 JUL     +6
          UVIS HARD             11 AUG                     12 AUG     +1
          IR HARD               14 AUG                     14 AUG      0
          SMOV COMPLETE         14 AUG                     14 AUG      0
    COS
          FUV              18 JUL                          27 JUL     +9
          NUV IMAGING      11 AUG                          08 AUG     -3
          NUV SPECTROSCOPY 31 JUL                          13 AUG     +13
          COS SMOV COMPLETE 11 AUG                         30 AUG     +19



April 21, 2009           STScI SM4 Delta Readiness Review                     57
                          SMOV4 MILESTONES
                         ERO ENABLE POINTS
                  (Not necessarily the execution dates)
                                     AS OF                 AS OF        DELTA
                                    08DEC08                21APR09      (DAYS)
    STIS
          CCD                      09 JUN                     10 JUN   +1
          NUV/FUV (N/A)            22 JUN                     17 JUN   - 5
    ACS
          WFC                      27 JUN                     13 JUL   +16
          HRC                      28 JUN                     13 JUL   +15
    WFC3
          UVIS                     04 JUL                     06 JUL   + 2
          IR                       06 JUL                     12 JUL   + 6
    COS
          FUV                      03 JUL                     20 JUL   +17
    NICMOS
          IMAGING                  TBD 08 JUL                 27 JUL   +19

April 21, 2009              STScI SM4 Delta Readiness Review                     58
                                                 WFC3 UVIS/IR “HARD “SCI ENABLE,
                         FGS2R2                  COS NUV SCI ENABLE
                         GUIDING
                      ACS HRC SCI          COS FUV SCI ENABLE, NIC SCIENCE ENABLE (TBD)
ACS SBC SCI
ENABLE                UVIS“EASY” SCI
                                         WFC3 IR “EASY” SCI ENABLE

STIS SCIENCE ENABLE        ACS WFC SCI ENABLE,
 April 21, 2009                        STScI SM4 Delta Readiness Review                   59
                 Critical Operations and Operational
                          Challenges in SMOV
    HV Ramp-ups for STIS and COS
          Unchanged since Sep 2008
    Focus & Alignments for COS & WFC3
          Iterative processes for each SI in the same weeks
          Unchanged since Sep 2008
    Realtime Commanding
          GENSLEWs (Use Offsets), Table uploads, Event flag mgmt, etc.
          Unchanged since Sep 2008
    Fast Data Turnaround (FASTRACK)
          Needed in several places for in-line analyses
    Command Instructions
          COS SMOV Plan has introduced in-line commanding (pmdb)
           updates
    ACS Optimization Campaign
          Intensive, in-line analyses, instruction changes, sms updates, r/t
           commanding

April 21, 2009                 STScI SM4 Delta Readiness Review                 60
               Critical Operations and Operational Challenges in SMOV Weeks 1-7

                                              Yellow indicate times of high activity
                                   FTn = Fastrack data delivery requested by n proposals
   WEEK
               1               2                3               4                5                6              7
SYSTEM
               20 MAY          01 JUNE          08 JUNE         15 JUNE          22 JUNE          29 JUNE        06 JULY
S/C & FGS      BEA, VDT, AMA   BEA              BEA                              VDT
               ADJ, FT1        AMA ADJ, FT2



WFC3           OUTGAS          OUTGAS, SDB      OUTGAS          INIT UVIS        INIT UVIS        UVIS/IR FINE   IR FINE ALIGN,
                               CHK                              ALIGN, INIT IR   ALIGN, INIT IR   ALIGN, FT2     FT1
                                                                ALIGN, FT2       ALIGN, UVIS
                                                                                 FINE ALIGN,
                                                                                 FT3

COS            OUTGAS, SDB     OUTGAS           FUV HV,         FUV HV, NUV      NUV              FUV            COS NUV
               CHK                              COS/FGS         ALIGN/FOCUS,     ALIGN/FOCUS,     SENSITIVITY,   SPECTRO
                                                ALIGN, NUV      FUV SENS, FT2    EXT.             COS WL         SENSITIVITY
                                                ALIGN, FT2                       SPECTRO.         SCALES         FUV ALIGN
                                                                                 PERF., FT1                      /FOCUS,, FT2


ACS            SDB CHK,        WFC OC, FT1      WFC OC, FT4     WFC OC, CCD      WFC OC           WFC OC
               TEMP SET PNT,                                    X-TALK, FT4
               WFC OC, FT1

STIS           SDB CHK                          FT1             EROs




NICMOS         COOLDOWN        COOLDOWN         COOLDOWN        COOLDOWN         FW TEST,
                                                                                 FOCUS/PAM
                                                                                 ADJ, FT2


   April 21, 2009                             STScI SM4 Delta Readiness Review                                            61
                           SMOV PROPOSAL IMPLEMENTATION TEAM (PIT)
                                 EARNED VALUE (EV) as of 17Apr09
         10 EV points/proposal                    165 SMOV4 PROPOSALS = 1650 total EV points
          3 pts for prop submit                   - 165 PROPOSALS PIT-APPROVED
          2 pts for 1st PIT mtg                   PIT PROGRESS
          2 pts for 2nd PIT mtg
                                                   - 100 % PLANNED EARNED VALUE for Apr 15
          3 pts for prop complete
                                                   - 100 % ACTUAL EARNED VALUE as of Apr 17




April 21, 2009                       STScI SM4 Delta Readiness Review                           62
                   SMOV4 READINESS


    SMOV PLAN
          COMPLETE

    SMOV PROPOSAL DATABASE
          COMPLETE

    SMOV TEAM
          READY



April 21, 2009        STScI SM4 Delta Readiness Review   63
Planning and Scheduling

       Merle Reinhart
                              Database
                         NSSC-1 Flight Software
                NSSC-1 FSW updates are required to support
                 SM4

                NSSC-1 8.6 supports full complement of SIs
                 during SM4
                    Installed Sep. 10 during SMS 252 (SMS 254 was first
                     use)
                    Avoids software changes during SM4

                NSSC-1 9.0 removes support for COSTAR and
                 WFPCII
                    This will be installed immediately after SM4 during the
                     H&S SMS


April 21, 2009                    STScI SM4 Delta Readiness Review             65
                                    Database
                                  PRD/SCIOPSDB
          OPSPRD 7.1 has been deployed to SMS 110
          Planned updates after SM4 rendezvous, prior to deploy
                PRD PRs
                    60663: PLCP PJSAFHLD for ACS safing recovery including TEC commanding
                    60739: AGCF and SCHF parameters for switch to 3-gyro mode
                    60742: Table ODB for NSSC-1 9.0 FSW
                SCIOPSDB PRs
                    57951: Initial creation of T-Mode database records
                    59227: Update ACS Boot to Operate recon command_time
                    59975: Update ACS recons for SM4 - 10.2 rules
                    60611: Change to ACS SBC states to allow WFC/SBC for long durations during
                     early SMOV4
                    60647: Update ACS recon timing for repair
                    60635: Remove WFPC2, COSTAR, add WFC3, COS RTCS' from DEFAULT.CSE
                     for SM4
                    60726: Update DBDF - Mods SMS Syntax for Multi-Gyro Operation
                    60822: Add COS FUV and NUV for bright object checking
                    62426: Restrict sa_eps_parms maximum incidence for post-SM4 low-power time


          A Freeze Waiver will be requested for all of the above


April 21, 2009                        STScI SM4 Delta Readiness Review                            66
                          Database
                 SMOV Preparation Environment
   SMOV4 development utilizes the same methodology that was
    successfully used for all previous Servicing Missions.
   Use a separate database and disk space from Operations, but the same
    machines/servers.
         spss_sm4 database for SMOV4 development
         spss database for current SPSS Operations
   Uses the operational software and tools, but utilizes different
    PRD/SCIOPSDB and SMS Instructions
         Allows simultaneous Flight Operations and SMOV development
         Two environments are isolated
   The spss_sm4 database is managed in the same way as the SPSS
    Operations database.
   This SMOV4 environment is used to:
         Prepare the SMOV proposals for execution
         Create the SMGT products
         Create the SMOV4 representative products
         Post-SM4 DRM Planning and Scheduling exercise

April 21, 2009                 STScI SM4 Delta Readiness Review        67
                          Database
                          The Merge
    SMOV environment, spss_sm4 database, gets merged into
     the Operations environment, spss database, after
     rendezvous and berthing occurs.

    PRD/SCIOPSDB group will audit the merged spss
     database for correctness

    OPS will audit the proposals for correctness

    End-to-end process generally takes about 2 days.

    This Merge process was successfully tested on September
     15th.

April 21, 2009          STScI SM4 Delta Readiness Review       68
                             Database
                       PASS Configuration Files
    These are files used by the PASS software and
     configuration controlled by the P&S Operations group.
    Mission Scheduler Basefile change to enable the solar
     array maximum incidence check
          Old: USE_CALC_SA_ANGLE = 'N’
          New: USE_CALC_SA_ANGLE = ’Y'
    Command Loader Basefile changes to disable WFPC2 and
     COSTAR and enable WFC3 and COS (or the appropriate
     combination).
          In the CLBASE Namelist
                Old: NS_SINAME = 'ACS ', 'NIC ', 'STIS', 'CSTR', 'WFII’
                New: NS_SINAME = 'ACS ', 'NIC ', 'STIS', 'COS ', 'WFC3’
                Old: NSREDUNDV = 'A', 'A', 'A', 'B', 'A', 'A’
                New: NSREDUNDV = 'A', 'A', 'A', 'B', 'A', 'B’
                Old: NSSHPSI = '_NSSHPS4’
                New: NSSHPSI = '_NSSHPS5'

April 21, 2009                    STScI SM4 Delta Readiness Review         69
                          Database
                 PASS Configuration Files (cont)
    MEGG initialization file changes to swap in the
     appropriate new instruments.
          Old:                                      – New:
             WFPC standby                                 WFC3 hold
             COSTAR hold                                  COS hold
             STIS operate                                 STIS operate
             NICMOS saa_oper                              NICMOS saa_oper
             ACS hold                                     ACS hold
             NCS CPL_hold                                 NCS CPL_hold
                                                          COS_NUV hold
                                                          COS_FUV hold




April 21, 2009                 STScI SM4 Delta Readiness Review             70
                           Planning and Scheduling
                                 Procedures
                The procedures are written, configured descriptions of a particular
                 process workflow that describes the tools and actions that should
                 be performed to accomplish that particular workflow.
                Procedures that need modification to support post-SM4
                   None of these updated procedures will be put into place until
                    after the database merge is complete.
                          3.2.01 - Scheduling Unit Selection
                            • Remove the WFPC2 decon references and add in the
                              WFC3/ACS/STIS Anneal proposals
                          3.2.02 - Flight Calendar Preparation
                            • Add the STIS Low Voltage management (STISLs) back in
                          3.2.03 - Flight Calendar Building
                            • Remove the special checks for non-functional ACS/STIS
                              detectors
                     The following procedures were modified and installed
                          3.2.17 - Science Instrument Safe Mode Recovery
                            • Add WFC3/COS and post_SM4 ACS
                            • All Visits are ready for use

April 21, 2009                          STScI SM4 Delta Readiness Review               71
                           Planning and Scheduling
                                    Tools
   The tools are configured programs or scripts that are used to perform
    certain actions called out in the Procedures used for building the weekly
    flight calendars.
         ccl_gsselect
                Selects the guidestars used in the SMS
                Don’t allow FGS2R2 to be used as the dominant guider
         su_gaps.sqr
                Calendar Visit summary report
                Add COS/WFC3
         gimme_snaps.py
                Builds the lists of what to schedule on a particular week
                Change the default for SI/configs to exclude back to nothing
         Calendar/SMS checklists
                Checks correctness of flight calendars and SMS’s
                Updates for the new Sis
         pass_prod_xfer.py
                Add Bay 10 incidence column to the pointing profile section of delivery letter
   All of these tools will be put into place operationally after the database merge is
    complete.


April 21, 2009                             STScI SM4 Delta Readiness Review                       72
                        Rendezvous
          Transitioning HST to Servicing Mission 4

        Objective: prepare HST for rendezvous with the Space Shuttle
         while maximizing the science content of the launch week SMS

        Methodology: utilize the nominal P&S Intercept capability
                A primary science SMS with “transition” visits
                A pre-planned intercept SMS with Gyro-4 test and rendezvous attitude
                 maintenance
                Post-launch switch from science to intercept
                TDRS Schedule rework

        Testing:
                Previously used for SM3B
                Tested during the System Readiness 4.2 and 4.2a SMGTs
                     Intercept loaded and executing but stopped prior to Gyro-4 test and
                      rendezvous attitude maintenance to reduce test duration

April 21, 2009                          STScI SM4 Delta Readiness Review                    73
                           Rendezvous


     Science SMS

                                     Rndz             Rndz
                 science                     science                 science
                                    attitude         attitude

09.131                                                                     09.138
                                           load breaks
    Intercept SMS

                                     Rndz
                 science                             G4 Tests   Rndz Att Maint
                                    attitude


April 21, 2009
                             = execution path if launch occurs
                           STScI SM4 Delta Readiness Review                      74
                              Deploy SMS Process
                          Firing Up an Improved HST
                The deploy SMS is a Health & Safety SMS generated using
                 the nominal H&S generation process
                    3-Gyro Onboard Attitude Determination (OBAD) = “T”mode
                    Built using NSSC-1 FSW 9.0
                    36 hour duration
                    BEA compliant initial attitude provided by PCS
                    Contains no SI commanding
                         Allows installation of NSSC-1 FSW 9.0 and COS FSW
                           • Removes support for COSTAR and WFPC2
                           • Fixes a COS Lamp startup failure issue
                         Allows real-time commanding to configure HST for use
                Tested during the System Readiness 4.2 and 4.2a SMGTs
                First Science SMS
                    NSSC-1 cold-start due to FSW install in previous SMS
                    Begin SMOV activities
                    Based upon preliminary SMOV template calendar

April 21, 2009                         STScI SM4 Delta Readiness Review          75
                 SMOV4 Calendar/SMS Builds

   Construct representative SMOV products assuming a nominal mission
    and a nominal SMOV
   Products will cover the first 4-6 weeks of SMOV
         Determines the scheduling feasibility of the SMOV Plan
         Finds any inconsistencies between the different SMOV Proposals
   These products will be widely distributed for review
         Ensures we haven’t missed or misinterpreted something
   Will be the starting point for building the templates the Flight Calendar
    Builders will use for flight.
   Templates will be started by ~T-14 days and handed to the Flight
    Calendar Builder by their nominal T-11d build start.

   Currently have the first 3 weeks built and delivered for review.
         Week 4 is nearly complete and expected to be delivered for review later this
          week.



April 21, 2009                   STScI SM4 Delta Readiness Review                    76
                        P&S Team SM4 Readiness
                          Operations Support
                P&S staff will be on-site at STScI to cover critical activities
                 as necessary
                     Launch to update TDRS schedule
                     Pre and Post reboost ephem processing
                     Post-Deploy ephem
                     HST Attitude from PCS and H&S SMS creation
                     Follow-on Science SMS creation

                Post-deploy scheduling
                     Resume normal SMS build and delivery schedule for SMOV
                      following post-deploy H&S and first Science SMS

              P&S Team ready for SM4, SMOV and Cycle 17 operations



April 21, 2009                     STScI SM4 Delta Readiness Review                77
                       Items Still in Work

    Update Flight Rendezvous/Transition Visits
          Complete by April 30 after April 27 ephem received
    Rework SMOV Weeks as necessary based upon
     review feedback received.
          Complete by May 6
    Rework SMOV Weeks 2-4 as a result of ACS O-
     Mode changes
          Complete by May 6
    Finish building Representative SMOV Weeks out
     to at least 5
          Attempt to complete by May 6, no later than May 18

April 21, 2009             STScI SM4 Delta Readiness Review     78
   Commanding

      Alan Welty
Commanding Branch - OED
                              Regression Testing1
    Bit Validation Status
          ACS
                Done
          NICMOS
                Done (revalidation not requested)
          STIS
                Done
          COS
                Done
          WFC3
                Done




April 21, 2009                     STScI SM4 Delta Readiness Review   80
                              Regression Testing2
    Certification Status
          ACS-R
                Last: 27-Jan-09; Up to date
          NICMOS
                Last: 09-Apr-09; Up to date
          STIS
                Last: 05-Feb-09; Up to date
          COS
                Last: 02-Apr-09; Up to date
          WFC3
                Last: 27-Jan-09; Up to date
          FGS
                Last: 23-Mar-09; Up to date




April 21, 2009                    STScI SM4 Delta Readiness Review   81
                           Commanding Changes1

                General
                    Standardize TEXT blocks
                    Facilitate more complete searches of Instructions & PDB tables
                     & groups
                    Standardize SI event flag management instructions
                ACS
                    Address SBC turn-on timing problem
                    60 sec delay after WFC gain or readout mode change
                    Eliminate possibility of commanding on side 2
                    Include SCIHDR in ASIC diagnostics special commanding
                    Update WFC Optimization special instruction EJCCDBIASR –
                     will require bench test & freeze waiver
                NICMOS
                    Special commanding to Enable FW motion




April 21, 2009                     STScI SM4 Delta Readiness Review                   82
                           Commanding Changes2

                STIS
                    Restore MAMA Recovery special commanding
                COS
                    Updates to prevent associations from sharing auto-wavecals
                    Update Target Acq subarrays & FSW patchable constants
                    Implement FUV Recovery special commanding
                WFC3
                    Implement Safing Recovery instructions
                    Update Operate to Boot regarding TEC event flags
                FGS
                    Add support for Maintenance Slews
                    Add support for specifying LOCOUNT on proposal




April 21, 2009                     STScI SM4 Delta Readiness Review               83
                                               Other Work
          Instruction Audit
                SPSS_SM4/IMDB comparison completed 09-Apr-09
          COS & WFC FSW Patchable Constants
                WFC3 verification nearing completion (target: 4/24/09)
                COS verification started (target: launch on best effort basis)
                  • Target Acq constants done
          Documentation
                ACS DM-05 delivered Dec 2008
                COS & WFC3 DM-05 minor updates will be made before SM4
                COS & WFC3 OP-01 updates TBD
          SMS Review Tool
                Necessary code is complete; some input data updates are TBD (related to tracking info, not
                 SMS checking); will be done before launch
                To be installed during SM4 (some updates are not appropriate for pre-SM4 operation of ACS;
                 Freeze waiver needed)




April 21, 2009                           STScI SM4 Delta Readiness Review                                84
                          Conclusion

    STScI Commanding software (IM, PDB tables &
     groups, and the SRT) is ready for SMOV
          Bench test needed for EJCCDBIASR
          SRT not to be delivered until SM4
    DM-05 docs will be ready by SM4
    OP-01 docs will be updated as soon as we can,
     but likely not before SM4




April 21, 2009           STScI SM4 Delta Readiness Review   85
 Calibration Pipeline:
SSB Software for SMOV
        Warren Hack
         SSB/OED
                       Calibration Pipeline: SSB
   STIS:
         OPRs 60326 (zero-exposure time) and 60327 (sc2dcorr fix) have been addressed.
         CALSTIS is ready to support SMOV activities when needed.

   NICMOS
         OPRs 61686 (pipeline update for BEPCORR and SAACORR) and 62269 (SAACLEAN) have
          been addressed.
         An update to CALNICB will be delivered as a quick-fix for 2009.2 to address OPR 61187
          (exposure-time related keywords).
         Otherwise, NICMOS pipeline calibration software is ready to fully support NICMOS SMOV
          activities

   ACS:
         OPRs 62104 (time-dependent distortion keywords) addressed and installed in OPUS 2009.2.
         CALACS should be ready to support SMOV activities when OPR 62336 has been addressed with
          the quick-fix to OPUS 2009.2. This OPR corrects a problem with CALACS crashing with floating -
          point CCDGAIN values in the headers of RAW (_raw.fits) ACS files.

   MultiDrizzle:
         Updates, primarily to support reprocessing, included: recognizing WFPC2 DQ images in MEF and
          waiver-FITS format, getting full 64-bit support working under Solaris, processing data in native
          units or electrons, and fixing a bug processing ACS/WFC data in OTFR.
         MultiDrizzle remains ready to fully support all ACS data processing needs during SMOV and can
          be used to test WFC3 distortion calibrations in off-line processing as needed.

April 21, 2009                        STScI SM4 Delta Readiness Review                                  87
                     Calibration Pipeline: WFC3
   19 OPRs for CALWF3 itself were addressed since the last review.

   In addition, 7 additional algorithmic changes were also implemented that had no impact
    on pipeline calibration operations.

   Highlights of these fixes include:
         NICMOS CR rejection algorithms now 'tuned' for WFC3 use
         UVIS calibrations now more robust for use with subarrays and L-FLATS

   Summary:
         No issues remain for SMOV pipeline to fully support WFC3 SMOV activities




April 21, 2009                       STScI SM4 Delta Readiness Review                        88
                     Calibration Pipeline: COS
   50 OPRs for CALCOS itself have been addressed since the last review.

   Highlights of these fixes include (but not limited to):
         Implementation of CSUM file generation by CALCOS
         Improvements to wavecal processing
         Proper handling of images with no data, including background regions of subarrays
         Support of imaging wavecals
         Improvements to finding a wavecal spectrum

   Summary:
         A couple of modes remain unsupported in the pipeline: ACQ image data will not be
          calibrated yet, wavelength calibration for NUV data needs improvement, and imaging
          wavecal for TIME-TAG TAGFLASH data in direct imaging mode can not be used to
          compensate for mirror/mechanism drift yet.
         A version of CALCOS will be available for off-line use by the COS team during SMOV
          that will support ACQ image calibration and include improved NUV wavelength
          calibration.
         All other modes required for SMOV support have been implemented, tested by the
          COS team and delivered for use in the pipeline.



April 21, 2009                    STScI SM4 Delta Readiness Review                            89
                         Calibration Pipeline:
                          Software Versions
   Software versions installed in OPUS for use during SMOV:


          Instrument        Version OPUS Build Notes
          CALCOS            2.8a            2009.2                 Installed
          CALWF3            1.4             2009.2                 Installed
          CALACS            5.0.5           2009.2a                Quick-fix

          CALNICA           4.4.0           2009.2                 Installed
          CALNICB           2.6.2           2009.2a                Quick-fix
          CALSTIS           2.27            2009.1                 Installed

April 21, 2009                  STScI SM4 Delta Readiness Review               90
                   Calibration Pipeline: COS OPRs
    61075 - CALCOS should use different Doppler keywords.                    61511 - CALCOS should accept acq f iles as input.
    61076 - CALCOS should not write MAXDQ or AVGDQ columns in x1d            61783 - CALCOS changes f or version 2.7
     tables.                                                                  61953 - CALCOS should check f or no counts within active area.
    61077 - CALCOS should add comments to the jnk primary header.            61954 - Bug in CALCOS test f or no data.
    61078 -CALCOS should align spectra by wavelength when averaging.         61955 - CALCOS should not increase image size f or imaging
    61093 - CALCOS should use separate keywords for slopes of spectra.        data.
    61162 -Modify calcos to write a calcos sum (csum) image.                 61957 - CALCOS should not test f or missing column using
    61214 -CALCOS must update exptime local variable                          try/except block.
    61215 - CALCOS should use the product name in the jnk file.              62060 - CALCOS roundof f error when computing indices.
    61216 - Miscellaneous changes to CALCOS.
                                                                              62061 - CALCOS error in computing count rate.
    61218 - COS TDSCORR calibration step changes                             62062 - CALCOS should populate photometric keywords f or
                                                                               imaging data.
    61286 - Changes to CALCOS wavecal processing.                            62063 - CALCOS should not just copy an x1d f ile to x1dsum.
    61293 - Change PSHIFT keywords to SHIFT1 in CALCOS.                      62064 - CALCOS should copy subarray keywords to the csum
    61294 - CALCOS should shift ACCUM images by the wavecal offsets           primary header.
    61296 - CALCOS should set bad regions to zero in ACCUM images.           62065 - CALCOS should print the numpy and pyf its version
    61297 - CALCOS should correct for bad data in background regions.         strings
    61299 - Remove dependence on keyword DOPPMAG in CALCOS.                  62066 - CALCOS should exclude background regions outside
                                                                               subarrays.
    61300 - CALCOS should apply TEMPCORR and GEOCORR to the DQ
     array.                                                                   62067 - Add the option to CALCOS to use two dif f erent
    61301 - CALCOS has the wrong sign for flat field Doppler shift for        background heights.
     ACCUM.                                                                   62068 - CALCOS should check f or DQ_WGT being all zero.
    61302 - CALCOS should use the TDSCORR keyword.                           62069 - CALCOS should check f or exptime = 0 when computing
                                                                               error array.
    61303 - CALCOS should smear the DQ extension by the range of
     wavecal offsets.                                                         62070 - CALCOS should check whether xd_range is too large.
    61304 - CALCOS made a new reference rather than a copy.                  62080 - CALCOS uninitialized variable len_raw
    61305 - CALCOS should add a DQ column to x1d tables.                     62091 - CALCOS should process imaging wavecals.
    61307 - CALCOS should append to the trailer file for each exposure.      62092 - CALCOS needs additional tests f or no data.
    61334 - CALCOS should copy segment-specific keywords.                    62137 - Change to CALCOS code f or f inding a wavecal spectrum.
    61394 - CALCOS should update wavelengths in x1d tables for wavecal       62153 - CALCOS should read countrate keywords f rom the f irst
     exposures                                                                 extension header.
    61461 - Changes to COSUTIL                                               62233 - Problems with f lagging out of bounds in CALCOS.
                                                                              62270 - CALCOS must update ASN_MTYP when copying x1d to
                                                                               x1dsum



April 21, 2009                                       STScI SM4 Delta Readiness Review                                                      91
                 Calibration Pipeline: WFC3 OPRs
    60727 - CALWF3 wf3rej not using correct UVIS readnoise values
    60833 - Calwf3 UVIS blevcorr influenced by CR hits in parallel overscan
    60930 - CALWF3 isn't completing EXPSCORR processing
    60988 - calwf3 should convert IR image units to electrons
    60990 - calwf3 UVIS flatcorr step could apply gain correction twice
    60997 - calwf3 wf3rej skysub=mode doesn't work well for flats
    61138 - CALWF3 UVIS photcorr should compute PHOTFNU keyword value
    61164 - CALWF3 throws an IRAF segv on missing input file
    61347 - CALWF3 IR zsigcorr uses wrong sampzero time for subarrays
    61425 - CALWF3 IR DQ flag for cosmic ray not propagated to all subsequent groups
    61428 - CALWF3 IR flatcorr crashes when processing subarray images
    61436 - CALWF3 IR dqicorr needs to allow for optional BPIXTAB columns
    61497 - CALWF3 PHOTCORR needs to use different PHOTMODE construction
    61608 - CALWF3 UVIS processing needs to verify matching reference file parameters
    61698 - CALWF3 BLEVCORR crashing for some UVIS SMGT datasets
    61741 - CALWF3 DQ flag assignments need to be updated
    61785 - CALWF3 UVIS FLATCORR crashes applying L-FLAT
    61819 - CALWF3 wf3rej is propagating CR flags for one input image to all following images
    62005 - CALWF3 wf3rej routine not flagging all rejected input image pixels
    Trac 352 - CALWF3 IR crcorr should get parameters from CRREJ reference table
    Trac 365 - Fix CALWF3 IR crcorr early saturation logic
    Trac 376 - CALWF3 IR crcorr outputs zeros for pixels with one good sample
    Trac 377 - CALWF3 IR crcorr yielding incorrect output SAMP and TIME values
    Trac 378 - CALWF3 UVIS biascorr sometimes uses incorrect subarray offsets
    Trac 381 - Changes to CALWF3 IR CRCORR DQ flagging
    Trac 391 - CALWF3 wf3rej is giving different sky values on different platforms when skysub=mean
    SSB Trac system: https://www.stsci.edu/trac/ssb/stsci_python

April 21, 2009                            STScI SM4 Delta Readiness Review                             92
Wide Field Camera 3 Readiness

         John MacKenty
                           WFC3 Highlights

    Development of Cycle 17 Calibration Proposals
    Extensive testing of CALWF3 pipeline
          Both of these activities were optimized to provide training and
           integration into the WFC3 team of new staff
    Published WFC3 Data Handbook
    Second delivery of pre-launch CDBS Reference Files
    Ongoing TV3 analysis
          16 Instrument Science Reports since Sept 2008 SMOV review
          Support for DCL activities on Bowtie and IR Linearity issues
    Studies and simulations of astrometry and Multi-drizzle
    Review of remaining NICMOS proposals to support transfer
     to WFC3 where appropriate

April 21, 2009                 STScI SM4 Delta Readiness Review              94
                              WFC3 Team Role
         WFC3 team at STScI has responsibility for all aspects of instrument
          commissioning (no separate IDT)
         Engineering support from STScI and WFC3 Project at GSFC
            

        Randy Kimble will provide part time Science IPT support in SMOV

        GSFC/DCL retains some detector experiment and analysis resources

        ERO team responsible for conduct of ERO program

        WFC3 SOC responsible for Early Release Science (feedback on
         calibrations)
        ESA/ECF responsible via MOU for GRISM support and calibration

      WFC3 team is organized into “tasks” with individual task leads and
          matrixed team members supporting each task.
                Most team members have extensive experience with WFC3 ground
                 testing
                Resources planned to accommodate work peaks
                Evolving model to incorporate 3-4 FTE growth in Sept/Oct timeframe



April 21, 2009                    STScI SM4 Delta Readiness Review                    95
                 Team Organization, Leads, Members
         Group Tasks:
                SM4 Support: Larry Petro
                SMOV: Susana Deustua (Andre Martel  JWST/CSA)
                TV3 Analysis: Howard Bushouse
                Cycle 17 Calibration: Susana Deustua
         Process Tasks:
                Calibration Products: Sylvia Baggett
                Software and Data Processing: Howard Bushouse
                User Support: Cheryl Pavlovsky
                Documentation: (Jessica Kim Quijano)
                Operations Support: Larry Petro
         Analysis Tasks:
                Imaging: Linda Dressel
                Photometry: Jason Klirai and Elena Sabbi (Tom Brown  JWST)
                Detectors: Peter McCullough
                Grisms: ECF with Howard Bushouse as interface
         Other team members:
                Tiffany Borders, Michael Dulude, George Hartig, Bryan Hilbert,
                 Brian McLean, Vera Platias, Abhijith Rajan, Adam Riess, Michael
                 Wong
April 21, 2009                    STScI SM4 Delta Readiness Review                 96
                     Team Member Changes

    New team members (since TV3)
          Tiffany Borders, Michael Dulude, Abhi Rajan – RIA new hires
          Jason Kalirai – AURA astronomer
          Brian McLean – loan from OED, astrometric support
          Adam Riess – shared with JHU (works WFC3 2nd half of year)
          Elena Sabbi – ESA astronomer
          Michael Wong – visiting Scientist from UC Berkeley

    Departing team members
          Tom Brown (JWST MO, will analyze LOS SMOV proposal)
          Andre Martel (JWST/CSA, will analyze SMOV data)
          Jessica Kim Quijano



April 21, 2009               STScI SM4 Delta Readiness Review            97
                 SM4 Support from STScI/WFC3
    UNCHANGED since Sept 2008
    Larry Petro (STScI WFC3 group) is responsible for
     organization of Sci IPT support and training, FT science
     contents, software tool development for FT analysis, and
     science performance assessment
    Orbit Shift @ GSFC
          Larry Petro on SI Console monitoring AT
          George Hartig in Science room
    Planning Shift @ GSFC
          Howard Bushouse on SI Console monitoring FT
                Conducts FT analysis in Science room
          John MacKenty in Science room to assess Science Pass/Fail
    Planning Shift @ STScI
          Sylvia Baggett and Bryan Hilbert in STRESS to provide independent
           analysis of FT data

April 21, 2009                   STScI SM4 Delta Readiness Review         98
                     SMOV Development Status
         Susana Deustua is responsible for WFC3 SMOV coordination
                Replaced Andre Martel who moved to JWST/CSA
         Proposal PI’s mostly based on Thermal Vac activity leads
                Observing strategy combination of TV and ACS/NICMOS
                Analysis strategy follows TV (quicklook, ISR, products)
         Considerable synergy achieved between TV3 analysis, SMOV,
          Cycle 17 calibration proposal planning, and CDBS produce
          generation: well defined individuals or teams identified for each
          activity.
         Launch delay resulted in three target changes
                11450 UVIS Photometric Zero Points and 11451 IR Photometric Zero
                 points change to photometric standard star GD153
                11426 UVIS SMOV Contamination Monitor uses star GRW+70D5824
                11441 IR Pointing Stability uses MESSIER-75
         We have also transitioned reponsibility for 11450 and 11451 from
          Tom Brown to Jason Kalirai
         Current plan remains at ~160 external orbits


April 21, 2009                    STScI SM4 Delta Readiness Review                  99
                         WFC3 SMOV Strategy
         WFC3 schedule paced by 21 day detector venting and
          Bright Earth avoidance periods prior to cooling
          detectors.
         SMOV4 designed to avoid linkage between UVIS and IR
          channels
         Commissioning Sequence
                Provide operational integrity of instrument (mechs, memory,
                 etc).
                Establish operating conditions (e.g. thermal setpoints for
                 detectors)
                Optical Alignment
                ERO Science
                Initial SMOV calibrations
                “Easy” Science enabled
                Science Oversight Committee Early Release Science starts
                Remainder of SMOV calibrations
                “Hard” Science enabled
April 21, 2009                   STScI SM4 Delta Readiness Review              100
                           WFC3 SMOV Timeline (1)
 Weeks Activities           Milestones                                Comments
 1-3   1,2,3                FT re-run, Memory and Databuffer          During 21 day BEA and
                            Checks                                    Detector outgas periods
 4               4,5,6,7    UVIS and IR Detector cooldown             PI approval
                            and functional tests
 4               8,9,10     CSM, SOFA, FSM, W Cal lamp
 4&5             16,17      UVIS and IR TEC performance               Assess thermal state
 5               14,15      UVIS Shutter, D2 lamp                     PI approval
 5&6             11,12      UVIS and IR initial alignment             Multiple uplinks
 7&8             21,22      UVIS and IR fine alignment
 5+              13,44      UV contam and bowtie monitors
 6               18         CCD Hot Pixel Anneal                      Start monthly cadence
 7               29,30      UVIS and IR to FGS alignment              Enables ERO & EASY
 10              29,30      SIAF update
 12-13                      SMOV complete                             Enables HARD



April 21, 2009                     STScI SM4 Delta Readiness Review                             101
                         WFC3 SMOV Timeline (2)
 Weeks Activities Milestones                                        Comments
 11,12           23,24     UVIS and IR Image Quality

 11              43        UVIS PSF Core Modulation                 Shutter jitter test
 12,13           25,26     UVIS and IR PSF Wings                    tests saturation
                                                                    residuals
 5-11            19,33,35 UVIS Int Flats, Dark/RN/CTE, SAA
 5-12            20,34,36 IR Int Flats, Dark/RN/Bckgnd, SAA
 7               37,39,31 UVIS Photometry Zero Points, Flat EASY GO Science
                          Uniformity, Plate Scale           start
 8-9             38,40,32 IR Photometry Zero Points, Flat   EASY GO Science
                          Uniformity, Plate Scale           start
 9               42       IR Grism Test
 10              27,28    UVIS and IR Pointing Stability




April 21, 2009                   STScI SM4 Delta Readiness Review                         102
                   CALWF3 Testing and Updates
    CALWF3 pipeline improved and received additional testing
          CALWF3 v1.0 delivered Sept 2008 (DMS/OPUS 2008.3)
          CALWF3 v1.1 delivered Dec 2008 (DMS/OPUS 2008.4)
                Stacking code (UVIS image combination) for reference file generation
          CALWF3 v1.2 delivered Feb 2009 (DMS/OPUS 2009.1)
                Bug fixed from testing campaign in Dec 2008
          CALWF3 v1.3 delivered Mar 2009 (DMS/OPUS 2009.2)
                IR up the ramp fitting improvements
                UVIS subarray bias subtraction bug fix
                Keyword modifications: removed ground test keywords, fixed EXPSTART and
                 EXPEND time values
    8 testers followed detailed plan to test every calibration step
          Each step tested with full-frame, sub-array, unbinned, and binned images
          Also served to train new team members in use of CALWF3
    Current Issues (no impact on SMOV; non-critical for GO science):
          Seven WFC3 telemetry mnemonics have multiple raw-to-physical
           conversion equations in the PRD--all of which are temperature monitors
           (#62237 and 62344)
                Different conversions are for Side 1 vs. Side 2, and for normal ops vs. anneal
          IMAGETYP header keyword currently set to “EXT” for IR darks (#62405)
April 21, 2009                        STScI SM4 Delta Readiness Review                            103
                  Improved Pre-launch CDBS
         Generation-1 completed Fall 2008
             - based on TV3 data
             - reference files covering all primary supported UVIS/IR modes (>100
          files)
             - files checked, delivered, in archive available for use

         Generation-2
           - based on TV3 data but now with improved software (reffile & calwf3)
           - nearly complete (>80 files)
           - UVIS flatfields and IR subarray darks in progress, installed by early May
           - includes revision to CDBS selection and expansion rules (to improve
                application of bias files for UVIS subarrays)
     
         CDBS WWW pages ready
            - maintained by INS CDBS group with input from INS WFC3 team
              -
          http://www.stsci.edu/hst/observatory/cdbs/SIfileInfo/WFC3/reftablequer
          yindex

April 21, 2009                  STScI SM4 Delta Readiness Review                     104
Snapshot of
main WFC3
reference file
WWW page

  Link to more
  description of
  each file type


                                                              Files
  Link to page                                                needed
  tabulating                                                  by calwf3,
  available files                                             prior to
  as function of                                              drizzle
  observing
  mode and
  recommended
  useafter date

April 21, 2009             … continued Review
                    STScI SM4 Delta Readinesson next   page          105
                 … continued from previous page




                                                               Needed
                                                               for drizzle




                                                               Not needed
                                                               by calwf3
                                                               at this time

April 21, 2009              STScI SM4 Delta Readiness Review           106
                                      MultiDrizzle
         Multidrizzle important for WFC3 science and archive
                WFC3 has greater geometric distortion than prior instruments
                     IR channel is 123 x 139 arc seconds FOV onto square detector
                Users have become expert with image combination techniques
         WFC3 pipeline designed to produce outputs ready for Multidrizzle
          (very similar to ACS)
         WFC3 support for Multidrizzle led by Linda Dressel with Platais,
          McLean, Dulude, and Petro.
         Calibration
                SMOV provides initial geometric distortion and SI location data
                Stability of these calibrations to be determined during SMOV/Cy17
         Testing
                Thermal vac did not measure plate scale or distortion
                Pre-launch database loaded with optical model derived data
                Simulated WFC3 data successfully run in Multidrizzle
                Full-up testing awaits on-orbit operations



April 21, 2009                       STScI SM4 Delta Readiness Review                107
                 WFC3 Data Handbook
                                           Launch delay provided
                                            opportunity to
                                            complete and release
                                            version 1.0 of the
                                            WFC3 Data Handbook
                                           Kudos to Jessica Kim
                                            Quijano, Howard
                                            Bushouse, Susana
                                            Deustua, and the
                                            entire team for this
                                            book.



April 21, 2009      STScI SM4 Delta Readiness Review           108
                               Cycle 17 Calibration
        Cycle 17 Calibration plan (Susana Deustua as lead)
                Based upon
                     Instrument Handbook promised calibrations
                     Needs of Cycle 17 GO and ERS science programs (from CS reviews)
                Primary plan (36 proposals/255 external orbits)
                     Phase 1’s reviewed in February by HSTMO
                     Phase 2’s submitted for all proposals
                Internal orbits stress system
                     5 largest programs tested for 2 week scheduling interval
                Delta plan to be developed in late 2009 based on SMOV outcomes
        Entire team involved in Cycle 17 Calibration plan development and
         execution
                Each proposal has a lead and multiple co-I’s
                Entire team conducted “peer reviews” of every proposal
                Extensive discussion (including other SI teams) of photometric plan
                ISRs (white papers) on Photometric standards, Cluster fields, and
                 Detector monitoring strategies being written

April 21, 2009                        STScI SM4 Delta Readiness Review                  109
                        Cycle 17 Calibration Plan (1/4)
Wfc3    Cy17                                                 Scheduling     Accuracy
                     Proposal Title             No. Orbits                                                          Notes
 ID      ID                            Freq                   Required        Goal
                           PI                   Ext   Int

wfc3_   11903      UVIS Zero points.    10x     46           Monthly at     2% W,        Measure zero points and m onitor sensitivity
01                 J. Kalirai                                f irst         5% M, N      (throughput).

wfc3_   11905      UVIS Daily Mon      1/day          956                   0.1 e-       Build daily, weekly superbias & superdark reference files.
02                 T. Borders                                               readnoise    Avoid periods just before and after annealing.

wfc3_   11906      UVIS CCD Gain.       3x             18    Months 4, 8,   <1% per      Calculate absolute gain per am plifier at nom inal
03                 C. Pavlovsky                              12             quadrant     tem perature.

wfc3_   11907      UVIS Bowtie         1/ two         231    Every other    <1%          Minim ize and neutralize "bowtie" effect. Every other
04                 S. Baggett           day                  day                         day. 10 m in visits

wfc3_   11908      UVIS Contam Mon     1/wk     37     37    Weekly than    2%           Monitor contam ination by m easuring throughput in a
05                 S. Baggett                                bi-weekly                   subset of key filters using stars.

wfc3_   11912      UVIS Int Flats.      5x             90    Quarterly      < 5%         Assess stability of flat field structure
06                 A. Rajan

wfc3_   11911      UVIS L-Flats and     2x      30           Early in                    Build L-flats using star field.
07                 Geo Distortion.                           cycle
                   E. Sabbi
wfc3_   11918      UVIS Im age Qual     3x      9            SMOV + 3,                   Im age stability assessment
08                 L. Dressel                                6, 9 months
wfc3_   11919      UVIS PSF Wings.      1x      7            Mid Cycle      >5arcsec     Evaluate PSF stability at 5 field points, in two filters.
09                 L. Dressel                                               radius
wfc3_   11913      UVIS Filter Wedge    1x      3            Early in       0.5 pixels   Verify UVIS filters positions for im age displacement
11                 J. MacKenty                               cycle          at 633 nm.
wfc3_   11938      UVIS Stray Light.    1x      4            Af ter SMOV    10%          Characterize stray light from bright sources outside
12                 L. Petro                                                              the UVIS FOV.

wfc3_   11925      UVIS Linearity       1x      2      3     1st Quarter    <5%          Measure linear response, well depth at non-linearity
13                 S. Deustua                                               corrected    onset, and, response curve in key filter subsets.
                                                                            to < 0.3%

  April 21, 2009                                 STScI SM4 Delta Readiness Review                                                            110
                                             Cy17 Cal Plan (2/4)
wfc       Cy17          Proposal Title                 No. Orbits   Scheduling      Accuracy                             Notes
3ID        ID                                                        Required         Goal
                                             Freq.

                               PI                     Ext    Int


wfc      11924    UVIS CTE Monitoring         3x       6      24    4,8,12        <1% phot,         Monitor CTE effects on photometry and
3_1               V. Platais                                        months        1% pixel shif t   astrom etry, using standard star field.
4
wfc      11922    UVIS Fringing               1x       3            Any           <1%               Monitor fringing in red UVIS filters, check
3_1               E. Sabbi                                                                          fringing m odel.
5
wfc      11904    UVIS Droplets               3x       9       3    1st Quarter   <1%               Characterize and m onitor effect of droplets
3_1               J. Kalirai                                                                        on photometry. Repeat visits 6,12 m onths.
6
wfc      11909    UVIS Hot Pixel Anneal.      15x            105    Monthly       < 0.1 e/pix,      Fix hot pixels.
3_1               S. Baggett                                                      dark 0.01/hr
7
wfc      11914    UVIS Earth Flats            1x              50    Late in       1% relative       Determ ine pixel to pixel flat field of
3_1               Pathfinder P. McCullough                          Cycle                           WFC3+OTA.
8
wfc      11926    IR Zero points.             14x     28            Monthly       2% W,             Measure and m onitor IR zero points and
3_1               S. Deustua                                                      5% M & N          sensitivity curves in all IR filters.
9
wfc      11929    IR Dark Monitor.           m any           423    Weekly        0.1 e-            Monitor IR dark current and read noise.
3_2               B. Hilbert                                                                        Creat superdarks.
0
wfc      11930    IR Gain.                    3x               8    Early, Mid-   5% per            Determ ine effective electronic gain of MCT
3_2               B. Hilbert                                        Cycle         iteration         array through internal flats.
1

wf c3    11931    IR Count Linearity.         3x       6       9    Every 4       <5%, correct      Quantif y non-linear behavior of IR detector,
_22               B. Hilbert                                        months        to < 0.3%         and determine corrections.



      April 21, 2009                                 STScI SM4 Delta Readiness Review                                                         111
                                             Cy17 Cal Plan (3/4)
wfc3I   Cy17                                                          Scheduling      Accuracy
                        Proposal Title                   No. Orbits                                                      Notes
 D       ID                                                            Required         Goal
                                                 Freq.
                              PI                         Ext   Int


wfc3_   11915   IR Internal Flats.                3x           110    Every 4         < 5%        Monitor IR flat stability
23              P. McCullough                                         months

wfc3_   11928   IR L- Flat and Geo Distortion.    3x     18           Every 4         1%          Build L-flats using star field. Third iteration can
24              V. Platais                                            months                      be closer to end of cycle.

wfc3_   11920   IR Im age Quality.                3x     6            SMOV + 4,       20 stars    Asses overall im age performance and stability
25              L. Dressel                                            8, 12 months                during Cycle 17. Measure FGS-IR alignm ent.

wfc3_   11921   IR PSF Wings.                     1x     5            Late in cycle   >5arcsec    Evaluate PSF stability at 5 field points, in two
26              L. Dressel                                                            radius      filters.

wfc3_   11913   IR Filter Wedge Check.            1x     2            Early to mid    0.5 pixel   Verify IR filters m eet CEI spec. for im age
27              J. MacKenty                                           cycle                       displacement

wfc3_   11932   IR Stray Light.                   1x     4            Af ter SMOV     10%         Characterize stray light from bright sources
28              L. Petro                                                                          outside the IR FOV

wfc3_   11916   IR Intrapixel Sensitivity         1x     2            Early in        <0.2%       Measure IPSV of array
29              Variation. M. Wong                                    cycle           rms

wfc3_   11933   IR Rate Dependent Non-            1x     9            mid-cycle       1%          Characterize rate dependent non-linearity by
30              linearity. A. Riess                                                               observing star cluster with variable backgnd.

wfc3_   11927   IR Persistence.                   1x     6      18    SMOV + 6,                   Measure and m onitor persistence through
31              S. Deustua                                                                        observations of sparse star fields.

wfc3_   11917   IR Earth Flats Pathfinder.        1x            50    anytime         1%          Determ ine pixel to pixel flat field of WFC3+OTA.
32              P. McCullough                                                         relative




    April 21, 2009                                  STScI SM4 Delta Readiness Review                                                        112
                                               Cy17 Cal Plan (4/4)
                                                                     Schedulin
wfc3I     Cy17                                                                    Accuracy
                         Proposal Title                 No. Orbits      g                                           Notes
 D         ID                                                                       Goal
                                                Freq.                Required
                                PI                      Ext   Int


wfc3_    11934    UVIS G280 Flux Calibration.    1x      1           early in    <10% in      Establish flux calibration for G280 grism s, wrt
33                H. Bushouse                                        cycle       1st orders   spatial position in FOV

wfc3_    11935    UVIS G280 Wavelength           1x      1           early in    14           Establish G280 wavelength calibration over
34                Calibration.                                       cycle       angstroms    FOV wrt position.
                  H. Bushouse


wfc3_    11936    IR Grism Flux Calibration.     2x      4           early in    <5% in 1st   Establish flux calibration for both IR grism s ,
35                H. Bushouse                                        cycle       order        wrt spatial position in FOV


wfc3_    11937    IR Grism Wavelength            1x      2           early in    1 pixel in   Establish wavelength calibration over FOV wrt
36                Calibration.                                       cycle       1st orders   position for both IR grism s
                  H. Bushouse



        Cycle 17 Orbit Totals

                                                        255   2135




    April 21, 2009                                 STScI SM4 Delta Readiness Review                                                    113
                                        Conclusions
      WFC3 team is ready for SMOV
      Team and Ground system is ready to support SM4
            FT analysis well practiced with realistic data from ground testing
            Redundant analysis paths exist and have been tested
      Team and Ground system is ready to support SMOV
            Augmentations completed for central data store
            Team well versed in processing WFC3 data from TV experience
            Launch delay permitted training of new staff, improvements to pipeline and
             CDBS
      Team and Ground system is ready for Cycle 17 science operations
            Robust Cycle 17 Science Calibration plan developed
            Ground testing of geometric distortion and multi-drizzle limited in scope
                    Significant work post SM4 to obtain distortion calibration (schedule driver)
                    Multi-drizzle leverages ACS experience and is tested with WFC3 datasets
            Future enhancements for efficiency are Cycle 18 issues (no Cy17
             development)


April 21, 2009                          STScI SM4 Delta Readiness Review                            114
COS & STIS Readiness
     Alessandra Aloisi (INS)
(with input from Tony Keyes & Charles Proffitt)
                                  COS+STIS Team
                         Alessandra Aloisi  Danny Lennon
                                (Acting Team Lead during SMOV)

   COS                                              STIS
   Tom Ake (COS Flat Fields)                        Charles Proffitt (STIS Tech & SMOV Lead)
   Van Dixon (COS IHB)                              Mike Wolfe (STIS IHB, monitors & ref files)
   Parviz Ghavamian                                 Wei Zheng
   Tony Keyes (COS Tech & SMOV Lead)
   Derck Massa (COS DHB & F calibration)
   Sami Niemi
   Cristina Oliveira (COS ETCs &  calibration)     COS+STIS
   Dave Sahnow (COS detectors & PVT)                Rossy Diaz (Pipeline Lead)
   Ed Smith                                         Paul Goudfrooij
   Dave Soderblom (COS TAs)                         Rachel Osten (C17 Cal Lead)
   Brian York                                       Nolan Walborn (User Support Lead)



     Currently 19 team members (including 4 JHU contracts)
                 Departed  Shaw, Lennon (except for acting lead period)
                 Arrived  Dixon, Niemi, York

April 21, 2009                      STScI SM4 Delta Readiness Review                              116
                 COS SM4 Science Support (EVA3)


            Start of Orbit Shift through COS AT
                 Dave Sahnow, Alessandra Aloisi  Danny Lennon
                 John McPhate, Jim Green
            COS FT and data analysis through end of Planning Shift
                 Scott Friedman, Tony Keyes
                 Steve Osterman, Jim Green, Stephane Beland
            Back-up data analysis at STScI
                 Tom Ake, Brittany Shaw  Brian York
                 Cynthia Froning, Steve Penton
            STScI Engineering Support
                 Tom Wheeler, Chris Long




April 21, 2009                  STScI SM4 Delta Readiness Review     117
                                               COS SMOV NUV Sequence
                                                                           Internal pressure                                                   FUV SMOV
   HST release           MAMA LV on                                                              24h
                                                                           <20 micro-Torr                                                       sequence
                                                                                                 data
            COS-01                 COS-02 11353           COS-03 11354          COS-04 11355
         Recovery f rom              Onboard              Science Data          NUV Initial HV                                                         Require
             SAFE                  Memory Check           Buf f er Check       Turn-on/Ramp-up                                                       Wavelength
                                                                                                                             COS-16 11476            Scale Update
                                                                                                                               NUV Ext.
                                                   Internal pressure                                                          Spectr. Perf .
                                                    <10 micro-Torr                                                              Part 1             COS-17 11477
       COS-06 11467
                          COS-07 11355 v5                              COS-05 11466                                                                  NUV Ext.
        NUV Internal                                                                           Wavelength
                               NUV                                         NUV                                                                      Spectr. Perf .
       Functionality &                                                                         Ranges OK                Enable Wavecal-
                             Fold Test                                 Dark Measure                                                                   Part 2
         Operation                                                                                                         dependent
                                                                                                    SIAF update
                                BEA Complete                                                                            NUV Calibration          COS-19 11479 v2-n
                                                                                                    available
                         24h                                                                                              and Science              NUV Spectr.
                         data COS-08 11468                COS-10 11496            COS-15 11475 Wavelength                                           Sensitivity
                                  OTA to FGS               Internal NUV            Internal NUV                                                                      REF
                                                                                                 Ranges
                                Alignment (NUV)          Wavelength Meas           Wavelength   Not OK                                            COS-20 11480
24h                                                       & Grating Ef f .             Verif y
data                                 Uplink              Vis 1, 3 – lamp 2       REF             24h                         COS-21 11481         NUV Structural
                         24h                                                                     data                        NUV High S/N          & Thermal
                         data                                                                                                 Verif ication         Stability
ERO                              COS-09 11469                                  24h      Uplink
                                   NUV Optical                                 data              REF
SCI                             Alignment /Focus                                  COS-14 11474
             Alignment
                                     visit 1-6                                   NUV Int/External
REF
              Not OK
                                                                                Wavelength Scales
                                 Uplink
IHB
                         24h                                                              Uplink
                         data COS-09 11469                 24h                   24h
                                                           data                  data                         COS-11 11471       COS-12 11472
                               NUV Optical                                                                    NUV Imaging        NUV Dispersed     Uplink
                                                           COS-19 11479 v1        COS-10 11470
                            Alignment vis 7-12                                                                 Acq Verif y         Acq Verif y
                                                             NUV Spectr.           Internal NUV
         External                                          Sensitivity Quick       Wavelength
         Observations                                                                  Meas             REF                                    REF     Do NOT
                                          Uplink
                                                                                                              COS-18 11478       COS-13 11473          Require
         May require wait                                                                                         NUV            NUV Imaging         Wavelength
                                                           Alignment OK        Uplink                          Flat Fields       Perf ormance        Scale Update
        April 21, 2009                     SIAF update            STScI SM4 Delta Readiness Review                                                               118
                                           start
                                              COS SMOV FUV Sequence
                                                        Outgassing
                             XDL at OPER                Concern?                                                   24h
                                                                                                                   data
                                 Internal
        COS-01                   Pressure             COS-22                  Internal            COS-23 11356
HST     COS-02 11353                                FUV Detector                                  FUV Initial HV
release COS-03 11354             <100 micro-                                  Pressure
                                                     Door Open                                   Turn-on/Ramp-up
                                 Torr                                                                                     COS-31 11489
                                                                              <10 micro-                                                                 COS-32 11490
                                                                              Torr                                          FUV Ext.
                                                                                                                                                           FUV Ext.
        NUV SMOV                                                                                                           Spectr. Perf .
                                                                                                                                                          Spectr. Perf .
         sequence                                                                  Pressure Gauge OFF                        Part 1
                                                          COS-25 11483                                                                                      Part 2
                                   COS-24 11482
                                                           FUV Internal                         Wavelength
24h                                    FUV
data COS-08 11468                                         Functionality &                       Ranges OK                 Enable Wavecal-
                                   Dark Measure                                                                                                          COS-33 11491
                                                            Operation                                                        dependent
      NUV Optical                                                                                  SIAF update                                               FUV
   Alignment /Focus                                                                                available              FUV Calibration                 Flat Fields
                                     BEA Complete                                   REF                                                                                    REF
                                                                                                                            and Science
                        uplink                              COS-27 11496
24h                                                                                       COS-30 11488 Wavelength
data                                                         Internal FUV                  Internal NUV     Ranges
                                  COS-34 11492 v1                                                                                                      COS-34 11492 v2-4
    COS-09 11469                                           Wavelength Meas                 Wavelength       Not OK
                                    FUV Spectr.                                                                           COS-36 11494                   FUV Spectr.
      NUV Optical                                           Vis 2 – lamp 2                     Verif y
                                  Sensitivity - Quick                                                   24h               FUV High S/N                    Sensitivity
   Alignment /Focus                                                                                  data                                                                  REF
                            24h                                             Uplink                                         Verif ication
                            data
              Uplink               Uplink                                                                                                     COS-35 11493
                                                             COS-27 11485                             REF
                                                   24h
       SIAF update                                 data                               COS-29 11487                                            FUV Structural
                                                              Internal FUV
       start                      COS-26 11484                                        FUV Int/External                                         & Thermal
                                                              Wavelength
                                    FUV Optical                                      Wavelength Scales                                          Stability
                                                              Meas – Vis 1                                                  Require
                                 Alignment /Focus                                                     24h
                                                                            24h                       data                Wavelength
                                      visit 1-4                             data
                                                                                                                          Scale Update
                                   Uplink                                            COS-28 11486
                                  COS-26 11484                                       FUV Dispersed
                                                          Alignment OK                                                     24h
                                    FUV Optical                                        Acq Verif y                         data    Rapid data turnaround required
                                                                                                               Enable
         External                Alignment /Focus
                                                                                                              FUV ERO
         Observations             Verif . – visit 5-6                                Does NOT Require                      ERO     Required to enable ERO
                                                                                                             No wavecal
                                                                                     Wavelength Scale
         May require wait                                                                 Update                            SCI    Required to enable science

                                                                                                                           REF     Analysis produces reference file

        April 21, 2009                                             STScI SM4 Delta Readiness Review                                                                    119
                                                                                                                           IHB     Results reported in IHB
                              COS SMOV Timeline

  May 12: SM4 Launch
  May 19: COS installation (EVA3)
  May 23 – Jul 6: Beginning COS SMOV engineering and alignment activities
         Engineering Check-out and Detector Turn-on (NUV: May 23 - Jun 4, FUV: Jun 5-15)
              Fast turnaround of turn-on visits
         Initial Detector verifications (NUV: Jun 4-8, FUV: Jun 16-20)
         Optical Alignments (Jun 11 - Jul 10) Fast turnaround of each visit
  Jul 20: COS EROs enabled (EROs executed week of July 20)
  Jul 30: COS science observations enabled in FUV
  Aug 13: COS science observations enabled in NUV
  Jul 6 - Aug 30: General Science Calibration Verification
         TA Verification (FUV: Jul 27, NUV: Aug 8-13)
         Imaging Verification (Jul 27)
         Wavelength Calibration (FUV: Jul 11-25, NUV: Jul 6-23) Fast turnaround of each visit
         Flux Calibration (FUV: Jul 27-30, NUV: Aug 4-6) Fast turnaround of quick-look visits
         Internal and External Flat Fields (NUV: Aug 7-11, FUV: Aug 10-11)
         High S/N Verification (FUV: Aug 16-17, NUV: Aug 14-15)
         Spectroscopic Performance (FUV: Aug 2-11, NUV: Aug 3-15)
         Thermal Stability (FUV: Jul 20, NUV: Jul 19, Aug 30)

      (Critical calibration programs for C17 & C18 updates are in boldface)

April 21, 2009                      STScI SM4 Delta Readiness Review                            120
                           COS SMOV Personnel
                 STScI               COS/STIS Team                       COS IDT
                   Cox                     (Aloisi)                       Beland
                  Hartig                     Ake                          Froning
                  Lallo                     Bohlin                        Penton
                 Wheeler                    Dixon                          Burgh
                  Welty                   Ghavamian                       France
            (involvement < 5%)           (Goudfrooij)           (2 persons rotating at STScI)
                                            Keyes
                                            Massa
                 BALL                       Niemi
                                                                          Green
                 Harguth                                                 Osterman
                                           Oliveira
                  Delker                                                 McPhate
                                            Osten
                                           Sahnow                    (for consultation)
                 GSFC                       Smith
                 Serrano                  Soderblom
                                             York


             SMOV divided 50-50 between COS/STIS team and COS IDT

April 21, 2009                   STScI SM4 Delta Readiness Review                               121
                             COS SMOV Re-Planning
   19/34 Phase II programs re-submitted after launch slip
          Target changes needed for 5 programs (visibility & guide star issues)
          Other structural changes needed for remaining programs
                 Revisions following TA review to better infer on-orbit TA quantities
                 Revisions to use revised TA strategies
                 Revisions following added capability to flash lamp in imaging mode
                 Revisions due to identification of new observation windows to achieve SMOV goals
                   (e.g., new CVZ or maximum Doppler effect opportunities)
   PIT reviews and CS/BOP reviews of re-submitted programs completed
   Analysis plans revised in light of recent Phase II changes
   Development/adaptation of software to handle COS SMOV data and
      testing of analysis procedures under completion
          ~ 40% of programs have 100% of the software complete
          ~ 35% of programs have at least 80% of the software complete
          ~ 25% of programs have at least 50% of the software complete

                     All COS SMOV programs are flight-ready
                     Analysis plan document delivered to HMO
         All software scripts to be finalized and tested by launch (May 12)
April 21, 2009                          STScI SM4 Delta Readiness Review                            122
                        COS Cycle 17 Calibration

Part I of C17 calibration plan approved by HST-MO in Sep 2008
Total of 10 programs, 103 external & 457 internal orbits
All Phase II programs submitted by the deadline (Mar 13, 2009)
      1 program merged with other 2 programs, for a total of 9 programs submitted
      6 external orbits not used
C17 cal program 11997 added later for FUV wavelength monitoring (12 orbits)
CS reviews of programs with external targets underway
      5 programs & 20 BOP targets
      Targeted launch date (May 12) at the latest for completion
Additional C17 cal programs may be identified after SMOV (Fall 2009)




April 21, 2009                   STScI SM4 Delta Readiness Review                   123
                 COS Ground System: Front-End

            Issues worked with A. Welty and others in OED
     Already implemented into TRANS/commanding and APT 17.2.7

  Removal of LRC for lamp flashes in tagflash mode
  Changes in rules for shared wavecals
         Needed to avoid problems during archiving
         Some existing SMGT data (3%) will still require back-end workaround
  Lamp flash in COS NUV imaging mode
  New lamp-flash durations in tagflash mode to support single-
    stripe cross-correlation in NUV wavelength calibration
  Anomalous recovery procedure for COS FUV detector
  Updates to TA commanding to handle
         different offsets between WCA and science apertures (PSA/BOA)
         grating-specific spectral location, subarray, & cross-dispersion plate scale


April 21, 2009                  STScI SM4 Delta Readiness Review                        124
                     COS Ground System: Back-End
   Header keywords and tables
          Joint COS/DPAS/DSB bi-weekly meetings continue (Fraquelli)
          A lot of critical items completed as part of OPUS 2009.1 & 2009.2
          Test version of software for COS cumulative image and pulse-height histogram to
              be delivered for SMOV (and later in OPUS 2009.3)
          One SMOV critical PR (proper population of subarray for ACQ/IMAGE) to be
              installed as quick fix after OPUS 2009.2
   CALCOS
          Modules tested and verification completed by end of Feb 2009
          All critical changes included in CALCOS 2.8 (OPUS 2009.2)
          CALCOS 2.8 to be considered baseline version of COS pipeline
          Some additional improvements to be implemented in test version of CALCOS for
              SMOV (and later in CALCOS 2.9)
                 Improved NUV wavelength calibration
                 Capabilities for creation of COS cumulative image and pulse-height histogram
                 Processing of ACQ/IMAGE TA images
   Non-pipeline analysis tools (not tied to OPUS; part of STSDAS/Phython)
          First performance assessment completed (Dixon)
          Improvements to be implemented but lower priority compared to additional
             CALCOS improvements (Hodge)
          Targeted Summer 2009 for implementation & Fall 2009 for public release

April 21, 2009                         STScI SM4 Delta Readiness Review                         125
                   STIS SM4 Science Support (EVA4)


        Start of Orbit Shift through STIS-R AT
                 Mary Beth Kaiser, Cristina Oliveira
                 Bruce Woodgate
        STIS-R FT and data analysis through end of Planning Shift
                 Charles Proffitt, Alessandra Aloisi  Paul Goudfrooij
                 Ted Gull, Don Lindler
        Back-up data analysis at STScI
                 Danny Lennon, Mike Wolfe
        STScI Engineering Support
                 Tom Wheeler, Chris Long




April 21, 2009                      STScI SM4 Delta Readiness Review     126
                                         STIS SMOV Sequence

        STIS recovered     STIS-02          STIS-03            STIS-04            MAMA HV wait 4+ days af ter release & 3+ days af ter LV on.
         CCD TEC &       Memory Load      Science Data        Mechanism
         MAMA LV on       And Dump        Buf f er Check      Functional
         22 May           22 May          24 May              25 May




          STIS-05           STIS-06       Start STIS-07             STIS-19            STIS-17                   STIS-18         Start STIS-20
         CCD Anneal          CCD          CCD Dark &              FUV MAMA           FUV MAMA                  NUV MAMA          NUV MAMA
         Repeat 28d        Functional     Bias Monitor            Dark Measure       HV Recovery               HV Recovery       Dark Monitor
         27-28 May        28 May          Daily from 29 May      3 Jun & 24 Jun     27 May to 1 Jun            2 Jun to 6 Jun    4/wk start 7 Jun


           STIS-14          STIS-08                              STIS-10               STIS-21                   STIS-22
          CCD CTI          Aper Wheel                          CCD Optical            FUV Optical              NUV Optical
         Measurement      & Lamp tests                         Format Verif y        Format Verif y            Format Verif y
         29 May           28 May                               29 May                3 Jun                     8 Jun
Eng.

Al.                         STIS-09                                               Af ter BEA end (9 Jun)
CCD                       STIS to FGS       STIS-12               STIS-13
                                                                                       STIS-23                   STIS-24
                           Alignment      Contingency          CCD Spectro
FUV                                                                                   FUV Image                 NUV Image
                         29 May           Corrector &           Image Qual
                                                                                        Quality                   Quality
NUV                      Update SIAF?     Focus Adjust         & ACQ tests                                                      ERO and GO
                                                               29 May                11 Jun                    11 Jun
                                                                                                                                observations
ERO                                                                                                                               enabled.
                           STIS-11
                         STIS External                           STIS-15                             STIS-25                    10 Jun (CCD)
        External         Focus Check                           CCD Spectro                        MAMA Spectro                  17 Jun(MAMAs)
        Observations                                           Throughputs                         Throughputs
                          29 May
        Internal                                               10 Jun                                 11 Jun
        Observations
                                                                 STIS-16                            STIS-26
                                                               CCD Stability                      MAMA Stability
       April 21, 2009                              STScI SM4 Delta Readiness Review                                                         127
                                                               9 Jun                                  12 Jun
                           STIS SMOV Timeline

   May 12: SM4 Launch
   May 20: STIS-R executed (EVA4)
   May 22 - Jun 24: STIS SMOV
          Engineering check-out, including mechanism mini-functional (May 22-25)
          MAMAs HV Recovery (May 27-Jun 6) Fast turnaround of each visit
          CCD Anneal & Functional (May 27-28)
          Aperture Wheel & Lamp tests (May 28)
          STIS-to-FGS alignment and focus check (May 29)
          CCD checks, including dark & bias monitor, CTI, throughputs, format
               verification, image quality & stability (May 29 - Jun 10)
          MAMA checks, including darks, throughputs, format verification, image
               quality & stability (Jun 3 - Jun 12)
   Jun 10: STIS science observations enabled with CCD
   Jun 17: STIS science observations enabled with MAMAs
   Jun 10-17: STIS EROs

      (Critical calibration programs for C17 & C18 updates are in boldface)




April 21, 2009                   STScI SM4 Delta Readiness Review                  128
                           STIS SMOV Personnel


                 STScI               COS/STIS Team                  STIS IDT
                  Lallo                     (Diaz)                  Feggans
                  Long                   Goudfrooij                   Gull
                 Makidon                  (Lennon)                   Lindler
                 Wheeler                   Proffitt                 Woodgate
                                            Wolfe
            (involvement < 5%)             Zheng

                                            GSFC
                                           Serrano




            SMOV divided 80-20 between COS/STIS team and STIS IDT



April 21, 2009                   STScI SM4 Delta Readiness Review              129
                        STIS SMOV Re-Planning

      Total of 25+1 (focus contingency) programs
      Target changes made for 5 programs
             BEA & guide star issues
      Phase II of these 5 programs re-submitted
      CS/BOP reviews performed

                  All STIS SMOV programs are flight ready
                  Analysis plan document delivered to HMO
                 All software development/testing completed




April 21, 2009                STScI SM4 Delta Readiness Review   130
                           STIS Additional Updates

STIS Cycle 17 Calibration
     Approved by HST-MO in Aug 2008
     Total of 24 programs, 52 external & 2169 internal orbits
     All Phase II programs submitted by the deadline (Mar 13, 2009)
     C17 cal program 11999 added later for HST-JWST cross-calibration (13 orbits)
     CS reviews of programs with external targets underway
            5 programs & 17 BOP targets
            Targeted launch date (May 12) at the latest for completion
     Additional C17 cal programs may be identified after SMOV (Fall 2009)
Cumulative Image for STIS MAMAs
     STIS requirements delivered together with COS requirements
     To be part of OPUS build 2009.3
CALSTIS
     Couple of minor changes delivered for OPUS 2009.1
     Fix to bug affecting post-pipeline processing of prism wavecals to be delivered
        later


 April 21, 2009                     STScI SM4 Delta Readiness Review                   131
                          COS/STIS User Support
Documentation
     COS Data Handbook v 1.0 published on March 16 (Shaw et al.)
     COS IHB updates that do not require SMOV input in progress (Dixon et al.)
User Support Software
     Pysynphot support for COS/STIS fully implemented
     ETC Support
            Testing of numerous COS and a few STIS PRs for ETC 17.4 underway
            Pysynphot conversion of STIS ETC for ETC 18.1 underway
     APT/BOT Support
            Changes to implementation of STIS FUV MAMA repeller wire offset (APT 18.1 ?)
            Quick fix to implementation of STIS MAMA long-slit aperture
                  (work on correct implementation in progress, APT 18.1 ?)
     Moving Target BOP software
            Fixed software for ACS; added capability to do field BOP check for COS & STIS
CS Reviews of COS & STIS GO/GTO/DD programs currently underway
     98 programs for a total of 503 BOP targets
     ~ 37% of programs and ~ 23% of BOP reviews completed
     Targeted launch date (12 May 2009) for 50% completion
     Remaining 50% to be completed in May/June 2009 timeframe
April 21, 2009                    STScI SM4 Delta Readiness Review                          132
ACS Readiness
  Linda Smith
ACS Team Lead
             Revisions/New Work

Personnel  changes - SM4 + SMOV Team
Dry Run for Optimization Campaign
      - led to revisions to OC + FT
Minor revisions to SMOV proposals
ACS Repair - will now support FT in EVA 3
                 SMOV+SM4 Staff List (18)

   Linda Smith                       Norman Grogin
   Luigi Bedin                       Pey-Lian Lim
   Ralph Bohlin                      Ray Lucas
   Colin Cox                         Jennifer Mack
   Marco Chiaberge                   Aparna Maybhate
                                      Gerhardt Meurer (ACS/GTO JHU)
   Tyler Desjardins
                                      Max Mutchler
   Andy Fruchter
                                      Anatoly Suchkov (ACS/GTO JHU)
   David Golimowski                  Alan Welty
   Shireen Gonzaga (SM4 only)




April 21, 2009           STScI SM4 Delta Readiness Review              135
                          Staff: EVA 3

                                   Orbital                    Linda Smith
                                    Shift                      Ray Lucas

                 GSFC
                                                            David Golimowski
                                 Planning
                                                             Max Mutchler
                                   Shift
                                                             Pey-Lian Lim*


                                                                Colin Cox
                                   Orbital
                                                            Tyler Desjardins*
                                    Shift
                                                            Shireen Gonzaga

                STScI
                                                            Marco Chiaberge
                                 Planning
                                                            Aparna Maybhate*
                                   Shift
                                                             Norman Grogin*
April 21, 2009           STScI SM4 Delta Readiness Review    * new team member   136
                 ACS Team Organization




April 21, 2009     STScI SM4 Delta Readiness Review   137
                      Optimization Campaign Team

    Oversight, report and contact point for DCL/Teledyne and SMOV team
          David Golimowski (OC Lead)
          Linda Smith (ACS/SMOV Lead)
          Aparna Maybhate (OC Lead Backup)
    Scientists for data analysis
          Norman Grogin (CTE-internal, Cross talk)
          Marco Chiaberge (CTE – external)
          Anatoly Suchkov (Cross-talk)
    Research Instrument Analysts and Research Instrument Scientists for
     data analysis
          Pey-Lian Lim
          Tyler Desjardins
          Max Mutchler
          Ray Lucas




April 21, 2009                    STScI SM4 Delta Readiness Review         138
                   OC Dry Run: Objectives

 Verify OC  operational processes using SMSs, real-time commanding
 Test all data flow paths and communications
 Rehearse data reduction and analysis using custom scripts
 Exercise decision making process
 Determine timing for analysis, decision making, and producing Ops
 Requests
 Verify SMS products for each iteration




•GSFC, Teledyne and STScI participated
•GSFC configured EM-3 unit (CEB-R and LVPS-R) and Build-5 WFC in ESTIF
•Only first 4 of 8 iterations of the OC were simulated + FT as iter 0
•Dry Run took place Feb 9 - March 17

April 21, 2009           STScI SM4 Delta Readiness Review             139
                           Summary of Results
    Run was vital for testing analysis software, training analysts, verifying
• Dry
 communication and data flow, and exposing problems

• Weverified that we can optimize the parameters by detecting differences in
 images with different parameter offsets

• Werehearsed our decision making process by declaring that only 4 iterations were
 necessary to meet the goals of the OC

• Issues raised and fixed by Dry Run:
• - analysis software has been revised/new tasks added
•          - incorrect OPUS keyword issues fixed
• - Phase II proposal typos and commanding issues fixed
• - iterations 5 and 6 swapped to allow a full set of visits if we stop early
• - OC timeline has been extended to allow extra thinking time and to        make
  better use of SMS boundaries



 April 21, 2009                STScI SM4 Delta Readiness Review                     140
                         Revised OC Timeline




  •OC now runs for 37 days compared to original 24 days (Oct launch)
  •Timeline has been extended to provide extra thinking time and to make effective use of SMS boundaries

April 21, 2009                      STScI SM4 Delta Readiness Review                                 141
                           OC Documentation



•       TIR 2008-03: ACS-R SMOV Optimization Plan - I. Rationale
        and Strategy (Cheng)
•       TIR 2009-01: ACS-R SMOV Optimization Plan - II.
        Implementation and Data Analysis (Sirianni et al.)
•              - to be released this week
•       TIR 2008-04: ACS-R Multi-Parameter Optimization
        Constraints (Gilliland et al.)




    April 21, 2009        STScI SM4 Delta Readiness Review     142
                              Functional Test


     •    FT was run as iteration 0 to provide starting point for OC
     •    Few issues were discovered - these have now been corrected and FT
          has been run successfully (review at GSFC on March 18)

     •    Issues addressed:
     •    Gain change from 2 to 1
     •    1 minute settling time added
     •    Subarray Y size changed from odd to even number


            We will hold final rehearsal for FT next week (April 29th) using data
          from Dry Run




April 21, 2009                  STScI SM4 Delta Readiness Review                     143
                                  Decision points
         These are the main decision points we will need to pass during
          the first few weeks of SMOV:

                5/24 FPGA data transfer rate

                6/18 Removal of last 4 iterations of optimization campaign

                At end of optimization campaign
                   Clamp and Sample vs Dual slope for SMOV and Science

                     Decision based on overall performance




April 21, 2009                       STScI SM4 Delta Readiness Review         144
                 If difficulties arise:
WFC readout   noise is higher than expected at end of OC:
Plans in place to review affected ACS Cycle 17 proposals
(have been identified by Phase II reviewers)
Consider introducing half-speed readout mode in Cycle 18


HRC   does not function:
All HRC and WFC activities are either separate SMOV
proposals or visits - minimal disruption to SMOV plan.
Affected Cycle 17 proposals will be reviewed to determine if
the science can be executed with other instruments.




April 21, 2009        STScI SM4 Delta Readiness Review       145
                          Summary
         Dry Run has provided excellent test of
          complex Optimization Campaign and allowed
          us to detect and resolve various issues
         We now have all data analysis tools in place
          to conduct OC, make necessary decisions,
          and communicate results
         Data analysis tools are also in place for all
          the other ACS SMOV proposals

             Conclusion: The ACS team is ready to
                         support SM4 and SMOV

April 21, 2009           STScI SM4 Delta Readiness Review   146
  FGS SMOV4 -FRR

               E. Nelan
               04/21/09

changes to previous plan are highlighted in
                   red
                            FGS: Same Team
    STScI (plan development, target selections, phase2 proposals, PDB updates , FGS
     astrometry commanding updates )
          E. Nelan
          M. Lallo
          M. Reinhart
          G. Chapman

    Goodrich (AMA adjustments to optimize FGS2)
          L. A-Reed
          K. Chisholm

    GSFC (FGS-FGS alignment, FGS distortion calibration, PDB updates, general
     engineering support)
          E. Kimmer
          M. Wenz
          A. Bradley

    And the Guide Star Acquisition Working Group



April 21, 2009                  STScI SM4 Delta Readiness Review                       148
                             FGS: Same Objectives
    Verify FGS1 and FGS3 operations
          guide star acquisition test shortly after Health & Safety SMS.
          post SMOV4 observations of M35 calibration star field
                M35 in Solar Avoidance until mid-August
                Migrate these proposals & observations to Cycle 17 Calibration Plan
          verifies FGS1r for astrometry

    Commission FGS2 for operations
          AMA adjustment to optimize performance
          distortion and alignment calibration
                Change: alignment and plate scale calibration only in SMOV4
                distortion calibration deferred until Cycle 17, after monitoring program indicates FGS2 has
                 become sufficiently stable
          update ground system to support use of FGS2 as a guider
          guide star acquisition test with FGS2 (~6 weeks after release)
          expedite process to reduce use of FGS3.

    All (=2) FGS2 Monitoring Proposals have been migrated to Cycle 17 Calibration
     Plan, using M35.

April 21, 2009                           STScI SM4 Delta Readiness Review                                      149
                    SM4/FGS <--> CAL/AST Proposals
     AD          SM4 ID   Cyc17 ID                           Title                            Analysis

   FGS08         11462       -        FGS1r, FGS2r, FGS3 Pre-SM4 Performance                   STScI

   FGS03         11457       -        Guide Star Acquisition with FGS1 & FGS3              GSFC & STScI
                                      Optimizing FGS2 with the AMA (includes                Goodrich &
   FGS04         11458       -
                                      FGS2 alignment and plate scale calibration).            STScI
   FGS05         11459     11876      Post SMOV4 FGS2-FGS Alignment                        GSFC & STScI

   FGS06         11460     12002      FGS2 Mini-OFAD                                       GSFC & STScI
                           11871
   FGS09         11463                Recommissioning FGS1 & FGS3 After SM4                    STScI
                           11872
   FGS07         11457       -        Verify Guide Star Acquisition with FGS2              GSFC & STScI
                           11874
   FGS10         11464                Near Term Monitoring of FGS2 After SM4                   STScI
                           11875

     FGS11,12,13 are satisfied by analysis using data gathered by commissioning and verification proposals

                             grey indicates execution prior to SMOV

         red indicates activity has been migrated to the Cycle 17 FGS Calibration Plan

April 21, 2009                          STScI SM4 Delta Readiness Review                                     150
                             FGS/SM4: Plan Timeline
      Prior to SMOV4, FGS2 target acquisition parameters have been updated
                    KB = 0.9
                    KD = 0.065
                    K5 = 300

      Verify guide star acquisition with FGS1 and FGS3 in week-1
      Verify these K-factors during week-1 with a post-release ITS observation

      Observe the three candidate “AMA stars” with FGS1r in Transfer mode (week -1)
            Determine which stars are point sources
            Find best star to use for the 15 point-of-light test (which executes early in week-3)

      Optimize FGS2 with the AMA, weeks - 2 & 3
      Execute observations for the FGS2-FGS Alignment and Plate Scale Calibrations
            BEA target field near the Galactic Bulge, part of the AMA proposal.

      Ground System Updates (week-5) and FGS2 Guide Star Acquisition Test (week-6)

      FGS1 & FGS3 verifications migrated to Cycle 17 Calibration Plan
      FGS2 monitoring & final calibrations migrated to Cycle 17 Calibration Plan


April 21, 2009                        STScI SM4 Delta Readiness Review                               151
                 FGS SMOV4 Readiness Status



    Ready
          For a May 12 - 14 launch


    If launch is delayed beyond May 14, new BEA-compliant targets for
     AMA and FGS alignment calibrations will be needed.
    These will be “swapped in” to the existing proposal.




April 21, 2009                  STScI SM4 Delta Readiness Review         152
 Early Release Observations

STScI SM4 DELTA READINESS REVIEW
           21 APR. 2009
             Keith Noll
                                  Targets

    Nine unique targets in ERO plan
          includes one parallel field
    Three targets changed:
          two targets are substitutions of identical target type
          one substitution is a return to first-choice target
          one extragalactic target changed from galaxy to galaxy
           cluster
          one parallel field dropped
    Target mix remains diverse



April 21, 2009              STScI SM4 Delta Readiness Review        154
                          Instruments

    New and repaired instruments utilized
          3 WFC3 prime, 2 supporting
          3 COS prime
          1 STIS prime, 1 supporting
          1 ACS prime, 1 parallel

    WFPC2 archival observations will support STIS
     target
    No NICMOS use planned for ERO



April 21, 2009            STScI SM4 Delta Readiness Review   155
                     Instrument Modes

    WFC3: UVIS & IR
          F438W, F555W, F606W, F814W, F140W
          F280N, F373N, F469N, F502N, F656N, F657N, F658N,
           F665N, F673N, F680N, F126N, F164N
    COS
          G130M, G160M
    ACS: WFC
          F475W, F550M, F625W, F814W
          F502N, F658N
    STIS
          G430M, G750M


April 21, 2009            STScI SM4 Delta Readiness Review   156
                    Phase 2 status

    All proposals passed PIT
    Guide star issue for one proposal to be resolved
     (as of 4/13).




April 21, 2009       STScI SM4 Delta Readiness Review   157
                            Orbit Total

    Orbit total reduced by 11 orbits from previous plan
Propid           Orbits           Comment
11501            19               more efficient orient
11502            24
11503            5
11504            9                smaller mosaic
11505            5
11506            3
11507            6
11508            4

TOTAL            75


April 21, 2009            STScI SM4 Delta Readiness Review   158
                  Data Acquisition Dates

    WFC3        weeks 9-10
    COS         week 10
    ACS         weeks 7-8, 9-10 (par)
    STIS        weeks 4, 10

    No anticipated need for fast track data with current
     schedule




April 21, 2009          STScI SM4 Delta Readiness Review   159
                                   Schedule

    EROs have reduced risk
          COS EROs now after SIAF update
    ERO press release not tied to any specific events
          increases flexibility
    August is a “slow” news month
          press release in September
    Current schedule allows for adequate processing
     time




April 21, 2009               STScI SM4 Delta Readiness Review   160
                                     Analysis
    Initial data analysis by instrument-related teams
          COS = IDT (Froning, ), STScI (Keyes)
          WFC3 = STScI (Anderson, Bushouse, Noll, RIA/RIS)
          STIS = former IDT (Gull +), STScI (Proffitt)
          ACS = STScI (IS, RIA/RIS)
          estimate 1 week processing time for COS, STIS, ACS; 1.5 weeks for WFC3
           (includes mosaicking)
    WFC3 Team will produce enhanced science-quality data products for
     the archive after the ERO release
    Image production
          OPO (Levay, Frattare, Noll, Livio)
          estimate 3 days per image (total = 21 days)
    Graphics
          OPO (Bacon, Feild, +)
          1 day per spectrum
          some graphics prepared in advance


April 21, 2009                  STScI SM4 Delta Readiness Review               161
                          Contingencies

    Targets now span full year
          small launch delays have no impact
          long delays (months) impact targets and orients
    2 gyro contingency:
          loss of minutes on all targets
          loss of one WFC3 target altogether
          one target with narrow July window
          six targets have moderate to minimal changes in
           schedulability (gaps of ~2 weeks or less)




April 21, 2009             STScI SM4 Delta Readiness Review   162
                        Summary

    EROs are ready to go!
    EROs will give us some of the first looks at the new
     and repaired instruments in a wide array of filters
     and observing modes.




April 21, 2009       STScI SM4 Delta Readiness Review   163
Infrastructure Contingency Planning

              Doris McClure,
           IT Services Division
              Val Schnader,
        Business Resource Center
                               Topics Covered

    Facilities readiness and failover capabilities
          Backup power
          Building security
    Essential computer equipment
          Planning and scheduling systems
          Data Management Systems
          Science instrument support systems
          Visiting instrument teams
          Infrastructure: central storage, network, email
          Off-hours support during SM4 and SMOV
    Internet access/data transfer



April 21, 2009                 STScI SM4 Delta Readiness Review   165
                       Backup Power Capabilities

    All essential network equipment, servers, and storage are
     located in computer rooms connected to an UPS
     (uninterruptible power supply)
          Provides 30-45 minutes of backup power
    In addition, critical servers and core network switches are
     attached to power generator
          Provides unlimited backup power
          Covers Planning and Scheduling systems and Data Management
           System
    The power generator was successfully tested in March
     2009




April 21, 2009               STScI SM4 Delta Readiness Review           166
                              Building Security – Muller Bldg.

    Normal operating procedures
          Guard stationed at building entrance 24x7
          Building open from 7am to 6pm, all visitors must sign in
          Access card for entry to building is required outside these hours
    Changes since last review
          Access card is now required inside Muller 24x7
                The only internal access allowed without a card is to the Cafeteria, Cafeteria Conference
                 Room, Auditorium, and Lobby (addresses Action A06)
          Short/long-term visitors during SM4 and SMOV are being provided access cards for
           that period (addresses Action A07).
    Plans during SM4
          Access through front door will continue to be from 7am to 6pm
          First floor access will continue be controlled 24x7 per change indicated above




April 21, 2009                           STScI SM4 Delta Readiness Review                                    167
                               Essential Computer Systems - 1



         Planning and Scheduling systems
                P&S network switch is single point of failure. Maintenance agreement only
                 guarantees next day replacement.
                     Spare network switch in process of being procured; expect delivery prior to launch
                Servers protected against power outages by both UPS and power generator
                Desktop systems protected against power outages by UPS
                Distributed model ensures that failure of any one system should not affect
                 operations
                If entire site (STScI) becomes unusable, STScI can move this function to
                 GSFC where offsite backup servers are in place
                     Last successful test was performed 10 April 2009
         Data Management Systems – no changes
                Servers and storage are protected against power outages by both UPS and
                 power generator
                No backup/offsite capabilities exist




April 21, 2009                           STScI SM4 Delta Readiness Review                                  168
                               Essential Computer Systems - 2

    Science instrument support systems
          Systems are primarily individual desktop/laptop systems
          Protection against power failures
                Systems in 4th floor South offices and new offices in 4th floor Center are protected by UPS
                 and power generator
                Other offices are not protected
                Alternative locations exist (e.g. Rm 111 “Fishbowl”) that are protected by UPS and power
                 generator in the event of power failure
    Visiting instrument teams – no changes
          Space set up in 135 and N409
          Procedure in place to certify visitor systems prior to attaching them to the STScI
           network
          No protection against power failure
                Can use Rm 111 in the event of power failure




April 21, 2009                           STScI SM4 Delta Readiness Review                                      169
                                 Essential Computer Systems - 3



         Network equipment and central storage system
                Critical network equipment (core switches and routers) and the central storage system
                 are protected against power failures by UPS and the power generator
                Core switches and routers have failover capability to backup switch/router
                     Procurement of spare switch for SOGS in progress; expect it to be in house by 12 May
                Central storage system has new areas dedicated to SM4/SMOV configured in highly
                 available (RAID6) configuration. Two disks can fail and the storage will continue to
                 function.
                     Waiver request filed 4/15 to add ~12 TB prior to launch; work scheduled for 4/27
         Email server – no changes
                The email server is also connected to the UPS and generator
                There is no backup server available, however alternatives will be in place:
                     Use of STScI Information Channel (SIC) via web
                     Contact list includes alternate email addresses for all essential staff




April 21, 2009                               STScI SM4 Delta Readiness Review                                170
                          Essential Computer Systems - 4


    Off-hours support – no changes
          On site support is provided from approximately 7am to
           6pm, Monday through Friday
          During mission, extra support will be on site as required
           for quick turn around items
          On-call procedures in place for unanticipated failures of
           essential computer systems
                ITSD management will be point of contact and on call 24x7
                 throughout SM4 and SMOV
                Essential IT personnel will be on call and will respond to
                 emergencies




April 21, 2009                   STScI SM4 Delta Readiness Review             171
                                   Internet Access/Data Transfer

    Internet access is required to:
          Send/receive all data between STScI and GSFC
    No backup capability exists at STScI
    Plans in event of unanticipated, extended failure
          Potential use of visitor network (now on Verizon) for certain data transfers
          Data from PACOR would need to be transferred via media (e.g. tape)
          Planning and Scheduling operations move to GSFC
          Science instrument support staff can go to GSFC
                Laptops are certified and HSTnet ready
                Room 3/144 at GSFC will be available through 8/31
    Plans to address outages – no changes
          Scheduled outages: NISN sends notices of planned outages well in advance, usually 1-2 weeks.
           If timing is bad, we will reschedule with GSFC/NISN.
          Unscheduled outages: STScI will contact GSFC (Simrall) and/or NISN Help Desk in the event of
           an unplanned outage and work to resolve as quickly as possible.




April 21, 2009                             STScI SM4 Delta Readiness Review                          172

								