EL PASO COUNTY FINANCIAL AND CONTRACT SERVICES DIVISION BID TABULATION SHEET
SUBJECT:
Crushing & Screening of Used Concrete and Asphalt Materials Transportation BUYER: Brenda Gordon
DEPT:
BID NO.: IFB 09-028
TIME: 11:00 AM ASSISTANT: Norma Ingalls
BID OPENING: May 5, 2009
KILLION Fort Collins, CO RESPONSE CHECKLIST Yes Unit Price (per Ton) Mobilization included
RECYCLED MATERIALS CO Arvada, CO Yes Unit Price (per Ton) Mobilization included
RUBBLE INC. Parker, CO Yes Unit Price (per Ton) Mobilization included
ELK CREEK SAND & GRAVEL Yes Unit Price (per Ton) Mobilization included
OVERLOOK MINE LLC Winter Park, CO Yes Unit Price (per Ton) Mobilization included
LANGSTON CONCRETE Canon City, CO YES Unit Price (per Ton) Mobilization included
PELINO EXCAVATION Buena Vista, CO YES Unit Price (per Ton) Mobilization included
RECYCLED AGGREGATE PRODUCTS YES Unit Price (per Ton) Mobilization included
QTY Old Asphalt Materials, Yard Old Concrete Materials, Yard 2 Akers CY Akers CY
UNIT 14,000 19,000
1
$3.25 $3.25
Material processed with track hoe & hammer attachment, then loaded by a wheel loader into impact crusher. Finished product then transferred from the crusher & stockpiled by radial stackers. The tons crushed will be verified by a certified scale located on a conveyor belt where finished material will transfer for stockpiling. June 1, 2009
$3.90 $4.75
Retek Mobile Crusher & Screen
$4.24 $4.14
Preprocess, load to crusher, screen, recirculate oversized. Finish material will run up stackiing conveyor
$4.70 $3.50
Carefully, using veritical shaft impactor load with hoe, demolition head to scalp and remove excess steel
$3.15 $3.52
1) CAT 320 Excavator 2) METSO 1213 Impactor 3) 966 CAT Loader
$3.34 $3.23
Hammer hoe concrete into smaller chunks then crush, using CAT 988 loaders, Komatsu PC200 excavator, crushing plant, plant conveyor w/scale.
$4.61 $5.24
Impact crusher & Tele Stackerbelt
$3.65 $3.65
Metso 12135 Track Crusher
3 Describe how crushing & screening
will be done, with what type of equipment
4 Describe how you will verify the
amount of tons crushed
Load Rite System on Loader
Loader Bucket Scale
Certified belt scale
1) Certified "beltway Scale on Impactor 2) Certified "load rite" scale on loader both w/printers
Certified Belt Scale
Conveyor Scales Calibrated at Setup
Bucket Scale on loader
5 6 7
Availability: When can you start Response Time: How long after call from County can you be on County site, ready to crush) Describe approximately how long it will take to process the estimated materials card May 2009 after July 1, 2009
anywhere from mid-May contingent upon schedule
May 29, 2009
Immediately
per your schedule
July 2009
7 days
5 working days
30 days
between 15-30 days
7 calendar days
3 days
7 to 14 days
30 days
30-40 days yes
2000 tons per day yes
35 working days yes
29 working days yes
30 days +/NO
19 working days or less NO
165 working hours or 3 weeks YES
1000 to 2000 tons per day Yes
8 Will you accept payment by credit
If Yes, indicate if there is a cost to the County and note the cost amount
no add'l cost blank
no cost see options
add 3% to invoice blank
9
Options
amount pending add'l mobilization will be charged extra
no add'l fees N/A N/A 2nd & 3rd year contract at same price per ton blank