Application of Project Simulation to Optimize Ares I–X Upper Stage Simulator Project Implementation
APPEL PM Challenge Conference February 2008
Vince Bilardo NASA Glenn Research Center Chuck Sander ePM George Culver SAIC
Ares I-X Mission – First Ares I Test Flight!
Glenn Research Center
CM/LAS Simulator USS to CM\LAS Interface
Spacecraft Adapter and Service Module Simulators Upper Stage
Upper Stage Simulator
RoCS USS to RoCS Interface Frustum USS to FS Interface Avionics (internal) Forward Skirts Simulated fifth segment
FS Four-segment motor
PMC 2008
Ares I-X Upper Stage Simulator Team
Glenn Research Center
PMC 2008
Ares I-X Upper Stage Simulator Team
3
Purpose of Analysis
Glenn Research Center
1. SAIC and ePM were tasked to investigate the Upper Stage Simulator manufacturing processes.
a. ePM looked organizationally across entire manufacturing process. b. SAIC focused on manufacturing process details in GRC’s Ares Manufacturing Facility (AMF).
2. Following approach was used by both teams to conduct analysis:
a. Solicited and received process flow and resource use data from customer (NASA USS Project Team). b. Used Simulation techniques to model process execution.
1) ePM used organizational simulation techniques with NASA SimVision® . 2) SAIC used SIMUL8 Discrete Event Simulation (DES) software.
c. Iteratively revised models as process matured.
1) NASA SimVision informing the DES model and vice versa. 2) Modeling workshops informed the project team and the modelers.
PMC 2008
Ares I-X Upper Stage Simulator Team
4
DES Model of USS Manufacturing Process
Glenn Research Center
Segment manufacturing process modeled with SIMUL8 DES software.
Resources
Flange Mfg Processes
Segment Build Processes
Skin Mfg Processes
Painting and Secdry Struct Install
PMC 2008
Ares I-X Upper Stage Simulator Team
5
Results: Sensitivity to Number of Workers
Glenn Research Center
1. Process is highly sensitive to changes in number of both fabricators and welders. 2. To meet deadline with minimum personnel, data suggests good baseline with:
a. 8 Fabricators per shift b. 6 Welders per shift
Fabricators 10 8 6 10 8 6 10 8 6
Welders
Charge Duration (days) 56.6 57.9 61.7 58.4 59.6 64.8 61.4 62.4 68.0
6 6 6 5 5 5 4 4 4
Each Charge duration reflects average of 50 independent trials
PMC 2008
Ares I-X Upper Stage Simulator Team
6
Investigation of Non-Destructive Inspection
Glenn Research Center
Mandatory Inspection Points (MIPs) highlighted.
PMC 2008
Ares I-X Upper Stage Simulator Team
7
Results: NDE Inspection Sensitivities
Glenn Research Center
1. This sensitivity analysis assesses NDE defect rate, NDE repair time per defect, and NDE Inspection time.
a. Subsequent charts show specific sensitivities for each factor.
2. Following results are average of 50 trials each of 72 cases obtained varying:
a. NDE defect rate between 0.1% and 10%. b. NDE repair time at 1, 2, 4, or 10 hours. c. NDE inspection time at 8, 24 or 40 hours.
3. Aggregate results indicate Defect Rate is driving factor.
a. Tornado Plot below indicates Defect Rate has higher relative importance. b. Model-Fit of all data indicates Defect Rate has highest coefficient.
Relative Effect of Inputs on System Duration
Pareto Plot of Estimates
Term NDEDefectRate NDERepairTime NDEInspectTime t Ratio 10.702772 7.211215 2.517328
1. System Duration is 1,193 hrs
+ 159 hrs per defect percent + 106 hrs per NDE repair hour + 10 hrs per NDE inspection hour
2. Defect rate affects the system duration more than the other variables.
PMC 2008
Ares I-X Upper Stage Simulator Team
8
Result: NDE Sensitivities to Baseline
Glenn Research Center
Duration (hours)
1. These charts show impact of changing each NDE factor and holding others factors constant to their baseline. 2. Model Baseline includes:
a. b. c. d. NDE Defect Rate = 5% NDE Inspection = 8 hrs NDE Repair per Defect = 4 hrs Baseline shown with markers in each chart
NDE Repair Time Sensitivity
4000 3500
NDE Defect Rate Sensitivity
3500 3000 2500 2000 1500 1000 500 0 0% 2% 4% 6% 8% 10% 12%
NDE Defect Rate Total Duration Inspect Duration Repair Duration
NDE Inspection Time Sensitivity
3000 2500
Duration (hours)
Duration (hours)
0 2 4 6 8 10 12
3000 2500 2000 1500 1000 500 0
2000 1500 1000 500 0 0 5 10 15 20 25 30 35 40 45
NDE Repair Time per Defect (hours) Total Duration Inspect Duration Repair Duration
Inspection Time (hours) Total Duration Inspect Duration Repair Duration
PMC 2008
Ares I-X Upper Stage Simulator Team
9
DES Results and Conclusions
Glenn Research Center
1. Process is sensitive to number of fabricators and welders.
a. Suggested baseline using 8 fabricators and 6 welders per shift.
2. Flanges, Gussets, & Lugs process matches closely to planned schedule when two full shifts are used. 3. Segment manufacturing Charges match closely to planned schedule when two full shifts are used. 4. Previous analysis has shown process is sensitive to NDE defect rate, NDE repair time, and NDE inspection time.
a. Each percent of NDE defect rate adds 159 hours to process duration. b. NDE Repair time increasing by 1 hour adds 106 hours to process duration. c. NDE Inspection time increasing by 1 hour adds 10 hours to process duration.
PMC 2008
Ares I-X Upper Stage Simulator Team
10
What SimVision® Does
Glenn Research Center
Inputs
Milestones
Model Simulation
Predictions
Critical Path Project schedule Cost (Work, rework, wait, communication) Quality Risks (Work, communication) Position and people work load
Activities and Activity Characteristics Activity Dependencies Position Characteristics Organization Task Assignment Meetings Decision-Making Policy Communication Policy Organizational Dynamics
• Individual behavior • Organization theory • Performance measures • Discrete event simulation
SimVision permits effective front loaded project design by facilitating planning and organizational design with meaningful scenario analysis.
PMC 2008
Ares I-X Upper Stage Simulator Team
11
NASA SimVision® Model of USS Project
Glenn Research Center
Design and Fabricate Flight Test Article 1
Element Control Board (Tues 1 - 3 pm) Technical ntegration Meeting (Wed 9:00 - 11:00 am) Project Management Staff Meeting (Mon 11-12 pm) Interstage ntegration Meeting Thurs 9:30 - 11 am)
ARES I-1 USS Element Manager
Ground Processing Manager
Technical Review Board (TRB) (Thurs 1 - 3 pm)
CLV US Fit Test Article Manager
GSE & Logistics Lead
Structural / Mechanical Design Lead
Fabrication Stand Up Meeting (Daily 9-9:30 am)
Manufacturing Lead
Element Test & Integration Lead
Procurement
GSE Design Team
UDAC Design Teams
Segment Design Team
Fabricators
Welders
Inspectors
Stand Aplha
Stand Beta
Stand Gamma
Stand Delta
Clock / Mate Space
B-333 Team
Plumbrook
B-333 Test
Q4 2006 UDACs
SRR
Q1 2007
Q2 2007
Q3 2007
Q4 2007
Q1 2008
Q2 2008
Q3 2008
UDAC-2 (9/3 - 11/30 2006) UDAC-3 (11/26/06 - 3/19/07)
UDAC-4 (2/28 - 5/22 2007)
PF 2 PF-2 Beta Occupied
PF-2
UDAC-5 (6/25 - 9/04 2007)
PF-2
ainting
PF-2 Design and Procure
Design & Proc Comple te
PF-2 Parts Fab
PF-2 anges
PF-2 Rolling PF-2 all Fit F-2 Top Flange -2 Final Welding PF-2 2nd Structure
Assmbly Complete
PF-1 / PF-2 SS Stack & luation Trial 1 (Bldg 50)
PF-1 / PF-2 SS Stack & luation Trial 2 (Bldg 50)
PF-1 / PF-2 SS Stack & luation Trial 3 (Bldg 50)
PF-1/2 Trial Stack Complete
DIS-2 Delta Occupied DIS 2
DIS-2
DIS-2 Assmbly Complete
DIS 2 Xport B50 to Plum Brook
Pathfinders
DIS-2 Design and Procure
Design & Proc Complete
DIS-2 Parts Fab
DIS-2 anges
DIS-2 Rolling DIS-2 all Fit DIS-2 Top Flng -2 Final Weld IS-2 2nd Structure
ainting
DIS-1
DIS-1 Assmbly Complete
DIS 1 Xport B50 to Plum Brook
DIS-1 Alpha Occupied DIS 1
ainting IS-1 2nd Struct
DIS-1 Design and Procure
Design & Proc Complete
DIS-1 Parts Fab
DIS-1 anges
DIS-1 Rolling DIS-1 all Fit
DIS-1 T Flng
S-1 Fin Weld
Inte rnal Access ther 2nd
Internal Access Fab
Fab Complete
BDM Mounting Fab
Structure Complete
BDN Mounting
Other 2nd Structure Fab
Fab Complete
US-6 Beta Occupied US 6
US-6 Segment
US-6 Prelim Des GRC
Proc Data Dwg
US-6
S-6 Flange
US-6 Final Des GRC
Mfg Dwg
US-6 Parts Fab
S-6 Rolling
Welding 6 Wall Fit
S-6 Top Flange Final Welding
US-6 6 2nd Structure Painting -6 to US-5 LT, C&M
US 6 Complete - Arrive Bldg 333 SS-3 Stacking
US-7 Gamma Occupied US 7
-6 to US-7 LT, C&M
US-7 Segment
US-7 Prelim Des GRC
Proc Data Dwg
US-7
S-7 Flange
US 7
S-7 Rolling S-7 Top Flange 7 Wall Fit US-7 to SA LT, C&M Final Welding 7 2nd Structure US-7 Painting
US-7 Final Des GRC
Mfg Dwg
US-7 Parts Fab
Welding
Complete - Arrive Bldg 333
SA Aplha Occupied SA
SA
A 2nd Structure
SA Segment
Proc
SA
Comple te
A Painting
SA Flange
SA Prelim Des GRC
Data Dwg
SA Final Des GRC
Mfg Dwg
SA Parts Fab
Welding
SA Rolling
SA Top Flange
- Arrive Bldg 333
o SM LT, C&M
Final Welding
A Wall Fit
SM Beta Occupied SM
SM Complete
M 2nd Structure M Painting
mple te SS-3 Stack
SM Segment
SM Prelim Des GRC
Proc Data Dwg
SM
SS-3 Stacked
erSeg-3 Install and Checkout
M Flange
SM Final Des GRC
Mfg Dwg
SM Parts Fab
Welding
SM Rolling
SM Top Flange inal Welding
- Arrive Bldg 333
Destack and Ship to Hangar
Wall Fit
SS-3 Avionics Delivered
Basis
US-5 Delta Occupied US 5
US-5 Segment
US-5 Prelim Des GRC
Proc Data Dwg
US-5
S-5 Flng
US-5 Rolling US-5 all Fit US-5 T Flng S-5 Fin Weld 5 2nd Structure US-5 Painting -5 to US-4 LT, C&M
US-5 Final Des GRC
Mfg Dwg
US-5 Parts Fab
US 5 Complete - Arrive Bldg 333 SS-2 Stacking
Weld
US 4
US-4 Gamma Occupied US-4
US-4 Segment
US-4 Prelim Des GRC
Proc Data Dwg
US-4 Final Des GRC
Mfg Dwg
US-4 Parts Fab
S-4 Flng Weld
US-4 Rolling US-4 all Fit US-4 T Flng S-4 Fin Weld US-4 2nd Structure S-4 Painting to US-3 LT, C&M
US 4 omplete Arrive Bldg 333
♦ Ares GRC Sch 06Oct31.mpp ♦ USS Resource Loading_2006-11-08.xls
US 3
to US-2 LT, S-3 Painting C&M
US 3
US-3 Delta Occupied US-3
S-3 Flng
US-3 Segment
US-3 Prelim Des GRC
Proc Data Dwg
US-3 Final Des GRC
Mfg Dwg
US-3 Rolling US-3 all Fit US-3 T Flng S-3 Fin Weld US-3 2nd Structure
US-3 Parts Fab
omplete Arrive Bldg 333
Weld
US 2
US-2 Alpha Occupied US-2 US 2
S-2 Flng US-2 Rolling US-2 all Fit US-2 T Flng S-2 Fin Weld US-2 2nd Structure S-2 Painting
US-2 Segment
US-2 Prelim Des GRC
Proc Data Dwg
US-2 Final Des GRC
Mfg Dwg
US-2 Parts Fab
to US-1 LT, C&M
omplete Arrive Bldg 333
Complete SS-2 Stack
SS-2 Stacke d
Weld
SuperSeg-2 Install and CHeckout
S-2 Destack and Ship to Hangar
SS-2 Avionics Delive red
SSR Gamma Occupied SSR
SSR
SSR Painting
SSR Segment
SSR Prelim Des GRC
Proc Data Dwg
SSR
omplete Arrive Bldg 333
SS-1 Stacking
SSR Flng
SSR Rolling SSR all Fit SSR T Flng SSR Fin Weld
SSR Final Des GRC
Mfg Dwg
SSR Parts Fab
Weld
US 1
US-1 Beta Occupied US-1
S-1 Flng US-1 Rolling US-1 all Fit US-1 T Flng S-1 Fin Weld
US 1
US-1 2nd Structure S-1 Painting -1 to IS-2 LT, C&M
US-1 Segment
US-1 Prelim Des GRC
Proc Data Dwg
omplete Arrive Bldg 333
US-1 Final Des GRC
Mfg Dwg
US-1 Parts Fab
Weld
IS 2
IS-2 Delta Occupied IS-2
o IS-1 LT, -2 Flng IS-2 Rolling IS-2 all Fit IS-2 T Flng S-2 Fin Weld S-2 2nd Structure 2 Painting
IS 2 omplete Arrive Bldg 333
C&M
IS-2 Segment
IS-2 Prelim Des GRC
Proc Data Dwg
IS-2 Final Des GRC
Mfg Dwg
IS-2 Parts Fab
Weld
( (FJ-1 / FTA1-0) Gamma Occupied
SR Flng
(FJ-1 / FTA1-0)
TSR Painting
FTA1-0) Transport om B50 to Plum Brook
TSR Parts Fab
TSR ng-Btm
R Wall
TSR ing-Top
R Wall Fit-Top
TSR Segment
ward FTA 0 / FJ-1 and FTA-1/ FJ-2 Contract
Weld
Delivery Bldg 50
it-Btm
FJ-2 / FTA1-1) Gamma Occupied
SR Flng SR ng-Btm R Wall it-Btm SR ing-Top R Wall Fit-Top SR Painting
SR (FJ 2 FTA-1) Deliv ery - Bldg 4
SR Segment
IS-1 Alpha Occupied IS-1
SR Parts Fab
Weld
( FTA-1) Delivery - Bldg 333
IS 1
IS-1 Segment
IS-1 Prelim Des GRC
Proc Data Dwg
IS 1
IS-1 Final Des GRC
Mfg Dwg
IS-1 Parts Fab
-1 Flng Weld
IS-1 Rolling IS-1 all Fit S-1 T Flng S-1 Fin Weld S-1 2nd Structure 1 Painting
omplete Arrive Bldg 333
Complete S-1 SSR Temp Stack
SS-1 Temp Stacked
SuperSeg-1 Install and Checkout
S-1 Destack for SR Integration
SS-1 SR / FTA-1 (FJ-1) Assy
SR Inte gration and nstrall & Check Out
SS-1 Stacked
SS-1 Destack and Ship to Hangar
SS-1 Av ionics De livered
GSE Design - CM Interface GSE CM Interface Fab GSE Stand Design Beta Fixture Fab Beta Fixture Assy Beta Fixture Complete Gamma Fixture Assy Delta Fixture Fab Gamma Fixture Complete Delta Fixture Assy Delta Fixture Complete GSE Local Cart Design Local Cart 1 - Fabrication Local Cart 1 - Assembly Local Cart 1 Complete
GSE Design - 1st Stage
GSE 1st Stage Fab
SE Fnl Assy Fixture Design
B333 Uno - Fabrication
B333 Uno - Assembly
B333 Uno Complete B333 Dos - Assembly B333 Dos Complete B333 Tres - Assembly B333 Tres Complete
Ship Segements to KSC
Ground Support Equipment
Gamma Fixture Fab
B333 Dos - Fabrication
B333 Tres - Fabrication
PMC 2008
Ares I-X Upper Stage Simulator Team
12
Results: Baseline Simulation Case
Glenn Research Center
1. Critical Path
a. Ship to KSC Date: March 2009 – six months late! b. PF’s / DIS’s miss completion dates. c. Preliminary Segment Designs are showing schedule pressure. d. Final Segment Designs show float.
Critical Path flows through “middle” segments
2. Organizational Impacts
a. Coordination effort is significant for integrative tasks (Rolling, Seg Fitup). b. Space/Stand competition drives schedule delays. c. Welding tasks present an opportunity to compress/recover schedule. d. Welders and Fabricators experience > 1 month backlog (up to 6 welders and 16 fabricators required during peak periods).
Stand Backlogs
Welding Backlog
Conclusions
a. Accelerate Preliminary Designs and Final Designs for early Segments (e.g., US-2/3/4/6/7). b. Delay designs for later segments to provide resources to critical path. PMC 2008 Ares I-X Upper Stage Simulator Team
13
Results: Manufacturing Skills and Processes
Glenn Research Center
1. Case Summary
a. Ship to KSC Date: October 10 2008. b. Welder experience increases over time. c. Utilize Weld Machines for critical welds. d. WIP space / move tasks off stands.
2. Organizational Impacts
a. Manufacturing resource backlogs are < 2 weeks (less errors, faster work). b. Reduced facility competition increases pressure on assembly resources. c. Facility competition drives > 30 days work backlog.
CP shifts to early segments
40% reduction in errors
Conclusions
a. Crew based assembly reduces schedule delay by ~4 months. Task (PF-2 b. Weld Machines further improve delay by Final Weld) Errors ~1 month. Baseline 4.8 c. Weld Machines alone reduce schedule Weld pressure by ~3 months. Machine 3 d. Provide WIP space; move Secondary Structure Assembly, Painting, and Clock and Mate to Bldg 333 (saves ~30 days of schedule delay). PMC 2008 Ares I-X Upper Stage Simulator Team
Ignored 0.7 0.3
Corrected 1.5 1.1
Reworked 2.6 1.6
14
Manufacturing Organizational Requirements
Glenn Research Center
1. Case Summary
a. Ship to KSC Date: September 1 2008. b. Crew based segment manufacture. c. Utilize Weld Machines for critical welds. d. Increase Manufacturing and Inspection resources.
Improved welding performance drives decision wait increases for inspection tasks as errors are produced over a shorter period.
2. Organizational Impacts
a. Increased Welder (+4) and Fabricator (+2) resources reduces schedule. b. Stand competition is reduced but still an issue for Beta and Alpha as schedule compresses. c. Decision Wait and Coordination volume due to inspection delays drives schedule.
Streamlined Inspection process and increased Inspection resources reduce backlog by more than 1 month.
Conclusions
a. Increase Fabricators (Total = 14) and Implement Crew Based Fabrication and Assembly Welders (Total = 8), or • 4 dedicated high skill/experience Welders using Weld b. Dedicate engineer to reduce decision Machines (Bldg 50) • 12 Fabricators (8-12 Bldg 50, 0-4 Bldg 333) cycle time to 24 hours, resource 1 Accelerate Inspection Process inspector/stand and improve approval • 1 dedicated inspection engineer process. • 24 hour review process for NDE 15 PMC 2008 Ares I-X Upper Stage Simulator Team
Communication and Work Flow Sensitivities
Glenn Research Center
Conclusions
a. Improved coordination reduces schedule pressure by 2 weeks. b. Focusing on early segment design while permitting fabrication of low risk items does not delay final delivery date to KSC.
Manufacturing Dashboard reduces Coordination risks and requirements by ~30%
Delay of Segment Fabrication to July 1, 2007 permits PF’s, DIS’s and other Fabrication (e.g., GSE) steps to proceed with reduced competition for resources.
PMC 2008
Ares I-X Upper Stage Simulator Team
16
Summary of SimVision Findings
Glenn Research Center
1. Resource backlogs and facility competition drive schedule delays. 2. Early design backlogs pressure start of fabrication for early segments. 3. Solving the facility and process issues shifts the bottleneck risk to the organization.
a. Centralized decision making and formalized communication increases risk of delays and need for coordination. b. Coordination and communication risks rise as facility bottlenecks are removed.
4. Specializing resources and tying them to tasks reduces Schedule pressure but increases need for Coordination.
a. Competition for facilities (stands and floor space) will put stress (overtime, rework, quality issues) on the organization to maintain schedule. b. System must be developed to coordinate the required highly choreographed manufacturing flow.
PMC 2008
Ares I-X Upper Stage Simulator Team
17
Summary of SimVision Recommendations
Glenn Research Center
1. Accelerate designs for Pathfinder-2 and early Segments (e.g., US2/3/4/6/7). 2. Delay designs for later segments to provide resources to critical path. 3. Operate a crew based manufacturing organization.
− 4 Welders with Weld Machines (1 additional Weld Machine dedicated to rolling machine). − 12 Fabricators (distributed across fabrication and assembly in Bldg 50 and 333). − 4 Segment Assemblers (Bldg 333 super segment assembly). − Increase welding skills (all critical welds made by weld machines) and develop welding experience (crew based assembly).
4. Begin fabrication of low risk items as early as possible (> 2 weeks). 5. Plan for in process holding space for parts (2 weeks), flanges (8) and segments (1). 6. Plan to relocate Clock and Mate tasks for middle and late segments to Bldg 333. 7. Dedicate 1 engineer (on site), resource 1 inspector/stand and improve approval process (<24 hrs) to minimize schedule impact of inspection tasks.
PMC 2008
Ares I-X Upper Stage Simulator Team
18
Project’s Take Away Recommendations
Glenn Research Center
1. Adopt mechanized welding approach with goal of minimizing weld defects and subsequent rework. • Project Response: Accepted. Agrees with EWI recommendations. Mechanized MIG welding now baselined for Skin-Skin and Flange-Skin welds. 2. Shift design resources to finish common segment design ASAP. • Project Response: Accepted. Common Segments US-2, 3, 4, 6, 7 focus of first incremental USS Critical Design Review. Three serial CDR’s planned out. 3. Adopt crew based approach to maximize crew skill level. • Project Response: Accepted. Professional welders obtained via support contract. 4. Implement schedule dashboard to increase visibility of segment manufacturing flow to team and labor on floor. • Project Response: Accepted. Dashboard one of several metrics used to communicate and track schedule. Daily Standup and Material Review Board (MRB) meetings setup. 5. Implement flange storage recommendations. • Project Response: Accepted. Lay down area in west end of AMF to be utilized. 6. Study moving clock/mate/match drill and secondary structure to Building 333. • Project Response: Partially accepted. Mate space carved out in AMF, plus additional processing (painting, internal access structure installation) required after clock/mate/match drill that is better suited for AMF.
PMC 2008
Ares I-X Upper Stage Simulator Team
19
A Look Backward: Benchmarking Simulation Against Reality
Glenn Research Center
Simulation Prediction
Optimum Staffing: 4-6 welders, 8-12 fabricators Two shift operation required to meet schedule. Accelerate early Common Segment design and delay Complex Segment design. Increase welding skills and experience, utilize mechanized welding to minimize defect rate. Plan for in process holding area for machined parts (flanges, tangs, lugs). Dedicate staff to improve AMF floor coordination and reduce rework decision making time to 24 hrs max.
PMC 2008
Actual Result
Validated: Steady State Staffing (Per Shift) 6 welders, 9 fabricators Validated: Project implemented two shift ops from outset. Validated: Three serial critical design cycles/reviews implemented, to feed three serial manufacturing Charges. Validated: Had to contract out to obtain welders with sufficient skill. Once obtained, mechanized welding was no longer needed! Validated: Need for more floor space drove set up of Temp Storage Facility. Validated: Floor Director position created per shift; Segment Lead Engineer positions created; MRB set up to meet daily.
Ares I-X Upper Stage Simulator Team